1 GENERAL 2 DESIGN 3 CONCRETE 4 REINFORCING STEEL

THESE NOTES SHOULD BE READ IN CONJUNCTION WITH THE "LTA CIVIL DESIGN 3.1 BLINDING CONCRETE 4.1 REINFORCEMENT SHALL BE HIGH YIELD DEFORMED BAR CLASS B, WITH A
1.1 2.1 DESIGN CODES CHARACTERISTIC STRENGTH OF 500 MPa UNLESS NOTED OTHERWISE.
CRITERIA, MATERIAL AND WORKMANSHIP SPECIFICATION". ANY DISCREPANCY
UNLESS OTHERWISE STATED, A 75mm BLINDING CONCRETE (GRADE C16/20) LAYER SHALL
SHALL BE CLARIFIED WITH THE QUALIFIED PERSON (DESIGN) (QPD). 4.2 REINFORCEMENT SHALL BE UNCOATED UNLESS NOTED OTHERWISE.
WHERE APPLICABLE ALL MATERIALS AND WORKMANSHIP SHALL CONFORM TO BE PROVIDED ON ALL SOIL SURFACES FORMING THE UNDERSIDE OF ANY
THE LATEST ISSUE OF THE RELEVANT LTA MATERIALS AND WORKMANSHIP SPECIFICIATIONS, REINFORCED CONCRETE BEAMS, SLABS, RAFTS, PILECAPS OR DRAINS. THE
PARTICULAR SPECIFICATION AND TO THE FOLLOWING SINGAPORE/EUROCODE STANDARDS. THICKNESS AND STRENGTH OF BLINDING CONCRETE MAY NEED TO BE 4.3 UNLESS STATED OTHERWISE, ALL STEEL REINFORCEMENT BARS AND MESH
ANY OTHER RELEVANT CODES OF PRACTICE SHALL BE REFERRED TO, AS AND INCREASED DEPENDING ON THE SOFTNESS AND IRREGULARITY OF THE SOIL SHALL COMPLY WITH THE REQUIREMENTS OF SS 560 AND SS 561
1.2 SITE VERIFICATION OF DIMENSIONS WHEN NECESSARY. RESPECTIVELY. STEEL REINFORCEMENT BARS SHALL BE CUT AND BENT TO
BS 8666
a) CONTRACTOR SHALL FIELD MEASURE AND VERIFY POSITION OF ALL GRID 3.2 STRUCTURAL CONCRETE
LINES, EXISTING STRUCTURES AND FEATURES RELEVANT TO THE SS EN 1990 EUROCODE 0: BASIS OF STRUCTURAL DESIGN 4.4 ALL LAP LENGTHS SHALL COMPLY WITH THE REQUIREMENTS OF SS EN 1992 -1 AS
CONSTRUCTION PRIOR TO COMMENCING CONSTRUCTION GIVEN IN CLAUSE 5 OF THIS DRAWING
3.2.1 UNLESS NOTED OTHERWISE, FOLLOWING CONCRETE GRADES SHALL BE
SS EN 1991 EUROCODE 1: ACTIONS ON STRUCTURES USED
ALL DISCREPANCIES SHALL BE CLARIFIED WITH THE QPD BEFORE
4.5 CRANKING OF COLUMN BARS SHALL NOT EXCEED A SLOPE OF 1:10
BEGINNING WORK.
SS EN 1992 EUROCODE 2: DESIGN OF CONCRETE STRUCTURES 4.6 UNLESS NOTED OTHERWISE, NOMINAL COVER TO ALL REINFORCEMENT
CYLINDER STRENGTH INCLUDING LINKS SHALL BE AS FOLLOWS :
b) THE CONTRACTOR SHALL CHECK,VERIFY AND CONFIRM ALL DIMENSIONS GRADE
MATERIAL ELEMENTS 2

AND LEVELS ON SITE WITH THE RELEVANT ARCHITECTURAL, STRUCTURAL, (N/mm )


SS EN 1993 EUROCODE 3: DESIGN OF STEEL STRUCTURES
AND E&M. THE CONTRACTOR SHALL HIGHLIGHT AND SEEK
C45/55 PRESTRESSED PRECAST GIRDER 45 COVER FOR COVER FOR
CLARIFICATION WITH THE QPD ON ANY DISCREPANCIES IN THE DIMENSION STRUCTURAL EXPOSURE FACILITY
EXTERNAL INTERNAL
OR LEVELS PRIOR TO ORDER OF MATERIAL AND THE COMMENCEMENT OF SS EN 1994 EUROCODE 4: DESIGN OF COMPOSITE STEEL AND CONCRETE STRUCTURES C32/40 ELEMENT BUILDING
ALL ELEMENTS UNLESS NOTED OTHERWISE 32 FACE/(mm) FACE/(mm)
CONSTRUCTION OF THE RELEVANT WORKS.
CONCRETE C20/25 CROSS WALLS 20
SS EN 1997 EUROCODE 7: GEOTECHNICAL DESIGN (BELOW GROUND) CLASS C min C nom C min C nom C min C nom
C16/20 MASS CONCRETE FILL 16
SS EN 1998 EUROCODE 8: SEISMIC DESIGN PILE, PILECAP XD2 40 90 - - - -
GROUT G40 GROUTED MICROPILES TO POB 40
1.3 DRAWINGS
DWALL XD2 40 90 40 90
SS EN 12620: SPECIFICATION FOR AGGREGATES FOR CONCRETE
a) LEVELS AND DIMENSIONS SHOWN ON THE DRAWINGS ARE THOSE REQUIRED
CAST INSITU XC3 (INTERNAL) ONAL EN
I
IN THE COMPLETED STRUCTURAL WORKS UNLESS OTHERWISE STATED. DUE 3.2.3 CONCRETE MIX: 40 50 35 60 S G
EXTERNAL WALL
XC4 (EXTERNAL) S

FE
ALLOWANCE SHALL BE MADE FOR CONSTRUCTION TOLERANCE, VERTICALITY SS EN 13791: ASSESMENT OF CONCRETE COMPRESSIVE STRENGTH IN

IN
PRO

EE
AND ELASTIC DEFORMATION OF THE FORMWORK WHEN SETTING OUT STRUCTURES
XC3 (INTERNAL)
MAXIMUM AGGREGATE SIZE SHALL BE 20mm; BASE SLAB XC4 (EXTERNAL) 40 50 35 60

R
STRUCTURE FORMWORK. GEOTECHNICAL
REFER TO LTA'S M&W SPECIFICATION FOR CONCRETE MIX REQUIREMENT
XC3 (INTERNAL)
ROOF SLAB 40 50 35 60
SS 560: SPECIFICATION FOR STEEL FOR THE REINFORCEMENT XC4 (EXTERNAL)
NG CHEW CHIAT
b) ALL EXISTING LEVELS SHALL BE BASED ON THE LATEST APPROVED SURVEY
MIN. CEMENT RECOMMENDED CEMENT /
DRAWINGS. OF CONCRETE STRUCTURAL
CONTENT MAX W/C COMBINATION TYPE (SS 544 INTERNAL SLAB, 4334
ELEMENTS XC3 35 45 35 45
c) DIMENSIONS ARE NOT TO BE SCALED. (kg/m3) - 1 TABLE A6) BEAM,WALL
S E
IN
SS 561: SPECIFICATION FOR STEEL FABRIC FOR REINFORCEMENT GA POR
d) ALL DIMENSIONS ARE GIVEN IN MILLIMETRES UNLESS NOTED OTHERWISE (UNO). COLUMN XC3 40 60 35 45
OF CONCRETE DIAPHRAGM WALLS
400 0.45 CEM II/B + SR
AND BORED PILES
e) ALL LEVELS ARE GIVEN IN METRES AND ARE DENOTED ON THE DRAWING.
ABOVE GROUND
EN 12345 WELDING MULTILINGUAL TERMS FOR WELDED JOINTS WITH ILLUSTRATIONS EXTERNAL HULL ELEMENTS
(QUALIFIED PERSON STAMP AND SIGNATURE)
OF CAST IN-SITU TUNNEL 360 0.45 CEM II/B + OR
f) THE LATEST REVISIONS IN THE DRAWINGS SHALL BE INCORPORATED IN THE ELEMENTS DATE: 01 FEB 2021
SLAB, BEAM XC3 35 45 35 45 35 45
CONSTRUCTION WORKS. SS EN 206-1 CONCRETE: SPECIFICATION, PERFORMANCE, PRODUCTION AND CONFORMITY
INTERNAL HULL ELEMENTS
ALL IN SS 544 WALL,COLUMN,PIER XC3 35 45 35 45 35 45
OF CAST IN-SITU TUNNEL 340 0.45
SS EN 197-1 CEMENT: COMPOSITION,SPECIFICATION AND CONFORMITY CRITERIA TABLE A6
ELEMENTS
FOR COMMON CEMENTS ONAL EN
I
S G
1.4 INCORPORATION OF M & E REQUIREMENTS IN STRUCTURE S

FE

IN
PRO

EE
SS 544-1 CONCRETE - COMPLEMENTARY SINGAPORE STANDARD TO SS EN 206-1:
ALL MECHANICAL, SANITARY AND ELECTRICAL WORKS, TO BE EMBEDDED IN 3.2.4 CRACK WIDTHS 1. FOR THE INTERNAL ELEMENTS CMIN IS GOVERNED BY BONDING (CMIN,B)

R
THE CONCRETE, OR OPENING FOR PIPE OR DUCT WORK SHALL BE
CIVIL
METHOD OF SPECIFYING AND GUIDANCE FOR THE SPECIFIER
INCORPORATED AND ALL DISCREPANCIES CLARIFIED WITH THE QPD FOR MEMBERS EXPOSED TO EARTH AND/OR WATER, THE CRACK WIDTH ON THE EXTERNAL 2. FOR THE D-WALL, PILE, ROOF AND BASE SLAB CMIN IS GOVERNED BY BOTH DURABILITY SOON WON MOI
BEFORE CONCRETING. FACE SHALL NOT EXCEED 0.25mm WHEN SUBJECTED TO PERMANENT LOAD EFFECTS. (CMIN,DUR) AND BONDING (CMIN,B).
2.2 GROUND LEVEL WATER TABLE
HOWEVER, ON THE EXTERNAL FACE OF SUCH MEMBERS, THE CRACK WIDTH SHALL NOT 3972
FOR DESIGN, GROUND WATER TABLE ASSUMED AT GROUND LEVEL. EXCEED 0.3mm WHEN SUBJECTED TO TRANSIENT LOAD EFFECTS. ON INNER FACES, 3. DEVIATION ALLOWANCE ( C,DEV) IS TAKEN AS 50MM FOR DWALL, 25MM FOR SLABS
S E
CAST AGAINST THE GROUND, AND FOR ALL OTHER STRUCTURES IT IS TAKEN AS 10MM. IN
THE CRACK WIDTH SHALL NOT EXCEED 0.3mm. GA POR
2.3 DESIGN LOADS FLOOD WATER LEVEL 1m ABOVE GROUND LEVEL
LOWEST WATER TABLE LEVEL 5m BELOW GROUND LEVEL
4. COVER FOR INTERNAL ROOF SLAB IS GOVERNED BY THE PS6 REQUIREMENT
2.3.1 SELF WEIGHT : FOLLOWING BULK DENSITIES OF MATERIALS ARE OR THE LOWEST MEASURED GWL 3.2.5 CONCRETE REPAIR
USED FOR LOAD CALCULATIONS
(QUALIFIED PERSON STAMP AND SIGNATURE)
COEFFICENT OF EARTH REFER TO THE M&W SPECIFICATION FOR REQUIREMENTS.
DATE: 01 FEB 2021
MATERIAL TYPE BULK DENSITY (kN/m3) PRESSURE AT REST
Ko 3.2.6 FORMWORK AND SURFACE FINISHES
SATURATED SOIL FILL 19 0.5 4.7 FIRE RATING
FORMWORK AND SURFACE FINISHES SHALL BE CLASS F2 UNLESS NOTED
F2 19 1.0 OTHERWISE. FINISHES OF SURFACES WITH IN ACCORDANCE WITH PARTICULAR SPECIFICATION 6.
WATERPROOFING APPLIED, TO BE COMPATIBLE WITH THE WATERPROOFING MATERIAL. TUNNELS, EXTERNAL HULL: 4 hrs UNO.
16 (ABOVE -10) ESCAPE STAIRS, AIRWELLS, OTHER BELOW GROUND STRUCTURES: 4hrs UNO
M 1.0 ALL CONCRETE CAST ON A SLOPING BASE SHALL COMMENCE AT ABOVE GROUND STRUCTURES: 2hrs UNO.
16.5 (BELOW -10) 3.2.7
THE LOWEST POINT OF THE POUR AND PROCEED UP THE SLOPE
F1 20 0.7 4.8 ALL SPACER BARS, BETWEEN 2 OR MORE LAYERS OF REINFORCEMENT,
3.2.8 CONSTRUCTION AND DETAIL JOINTS SHALL BE H25, OR BAR DIA WHICHEVER IS GREATER AND SHALL BE PLACED AT +1.5m c/c
E 15 1.0
THE LOCATION OF CONSTRUCTION JOINTS AND THE CONCRETE CASTING
OE 20 1.0 4.9 THE ANCHORAGE LENGTH OF LINKS SHALL BE THE MAXIMUM OF 5 TIMES THE BAR
PLAN SHALL BE SUBMITTED FOR THE ACCEPTANCE OF THE QPD. DIAMETER OF LINKS OR 50mm.
OD 20 1.0

5D
TO MINIMISE CRACKING DUE TO SHRINKAGE IN LARGE AREA SLABS
3.2.9

OR
50m
AND WALLS, THE CONTRACTOR SHALL PROVIDE SHRINKAGE JOINTS
OC 20 1.0
(POUR STRIPS) AT APPROPRIATE INTERVALS AS ACCEPTED BY THE QPD.

m
OB 21 1.0

D
3.2.10 CONCRETING OF THICK SECTIONS SHALL BE ON THE RECOMMENDATIONS

5
R R

m
O

O
GIVEN SECTION 11.11 OF LTA M&W SPECIFICATIONS FOR CIVIL AND STRUCTURE

m
OA 21 1.0

0
5

5
WORKS
REINFORCED 5
0

>10m m
>20m m

<50m m
- 25.0 - B ,
CONCRETE U 100, BUT

>1.40
> T

>20
5 > 70mm

>10m m
WATER - 10.0 - 0
m
m
PREMIX - 25.0 -

22
MASS CONCRETE - 24.0 - >070 - 01.02.21 SABJ ISSUED FOR CONSTRUCTION (ST031) JWL KS DW

Rev Date Drawn Description Dsg'd Chk'd App'd


A) 0
B) 0 C) D)
0 0
2.3.2 SUPER-IMPOSED LOADS Client

A) TUNNEL B) FACILITY BUILDING NOTE: FOR C) AND D) THE COVER SHOULD NOT BE LESS THAN EITHER 30 OR 50mm

TYPE OF SUPER-IMPOSED DEAD LOAD MINIMUM LOADING TYPE OF LIVE LOAD THE CLEAR DISTANCE BETWEEN BARS SHALL NOT BE LESS THAN
TYPE OF SUPER-IMPOSED DEAD LOAD MINIMUM LOADING MINIMUM LOADING 100mm, EXCEPT AT LAPS WHERE IT SHALL NOT BE LESS THAN 75mm

FLOOR FINISHES 2.5 kN/m


2
SUPERIMPOSED DEAD LOAD ON ROOF (FINISHED AND 1.9 kN/m
2
GENERAL OFFICE, CAR PARK 5.0 kN/m
2

SCREED - 100mm THICK) 4.10 THE CONTRACTOR SHALL PROVIDE ADEQUATE CHAIRS, SPACING LINKS
TO SUPPORT THE TOP LAYER OF REINFORCEMENT IN THE SLABS AND SPACING LINKS
M&E SERVICES ON ROOF TUNNEL 1.5 kN/m
2
GENERAL M&E ROOM 7.5 kN/m
2

PARTITION WALLS (200mm THICK) 2 SHALL BE PROVIDED TO KEEP VERTICAL WALL REINFORCEMENT IN ITS Contractor
2.0 kN/m
CORRECT ALIGNMENT.
WATER PROOFING ON ROOF TUNNEL 2.0 kN/m
2
TRANSFORMER ROOM 16 kN/m
2

CEILING AND MnE SERVICES 0.5 kN/m


2

SWITCH ROOM 16 kN/m


2

ALL LAPS SHALL BE STAGGERED AS SHOWN BELOW


Engineering & Construction
FLOOR FINISHES 1.9 kN/m
2
4.11
TYPE OF LIVE LOAD MINIMUM LOADING 2
EXCEPT FOR DIAPHRAGM WALLS, BARRETTES PILES & BORED PILES.
GENERATOR ROOM 23 kN/m
FILL MATERIAL 19 kN/m
2

< 50m m
GROUND LEVEL SURCHARGE TEMPORARY 20.0 kN/m
2
2
Design Consultant
MCC 10 kN/m 152 Beach Road
LINE LOADS OF CONCRETE WALLS 2

< 40
2.5 x (THICKNESS OF WALL) x (HEIGHT OF WALL) kN/m
#35-00 Gateway East
GENERAL LEVEL SURCHARGE PERMANENT 25.0 kN/m
2

ALUMINIUM CLADDING 2
LV 10 kN/m
2 >0.3I
o I
o M Singapore 189721
0.2 kN/m Fs
PUBLIC ASSEMBLY AREA LOAD 5.0 kN/m
2

UPS ROOM 21 kN/m


2 Fs
MOTT
M Telephone (65) 62931900
Fax (65) 62931911
WATERPROOFING LOADS 2.0 kN/m
2

MACDONALD E-mail mm@mottmac.sg


SUBSTATION GENERATOR RM

a
2

16.0 kN/m 2 Fs
TVF ROOM 10 kN/m
2.0m THICK SOIL FILL 2
Fs
38 kN/m I Project title
ALL OTHER PLANT ROOM 2 Fs bd
7.5 kN/m

0
2

ALL PLENUM 1.5 kN/m Fs


0.6m THICK SOIL FILL 11.4 kN/m
2

M&E SERVICES ON JET FAN LOCATIONS CONTRACT N101

> 20m m
2

7.5 kN/m CLEAR GAS ROOM 7.5 kN/m


2

I
b

> 20
DAMPER 7.5 kN/m
2 DESIGN AND CONSTRUCTION OF
SUPER IMPOSED DEAD LOAD ADDITIONAL REQUIREMENT ON ROOF AS PER,
LTA CDC 3.3.2.3.1(a) & (b) CONSIDERED
FCC 7.5 kN/m
2
Ibd =DESIGN ANCHORAGE LENGTH NORTH-SOUTH CORRIDOR (TUNNEL)

FIRE ALARM SERVER ROOM 7.5 kN/m


2
I =PROVIDED ANCHORAGE LENGTH BETWEEN ECP AND VICTORIA STREET
b
2.3.3 EQUIPMENT LOADS 2

ITPMS 7.5 kN/m


PLANT AREAS HAVE BEEN DESIGNED FOR A UNIFORM LOAD OF 7.5KPa
2

UNLESS NOTED OTHERWISE IN THE PARTICULAR SPECIFICATION. PUMP ROOM 7.5 kN/m

2 Drawing Title
2.3.4 FAN AND WIND LOADS ACTIVE CARBON FILTER 16 kN/m

COOLING COIL 7.5 kN/m


2

GENERAL NOTES SHEET 1


TYPE OF WIND LOAD LOADING 2

CHILLER PLANT ROOM 7.5 kN/m


2

FAN WIND LOAD ± 3.0 KN/m ESCAPE STAIR CASE AND CORRIDORS 5.0 kN/m
2

ABOVE GROUND STRUCTURES SS EN 1991-1-4:2009, BASIC WIND SPEED=20m/s MOTORCYCLE REST AREA 5.0 kN/m
2

Designed NS 01/02/21 Eng. Chk. KS 15/03/21


2

GENERAL PLANT, MAINTENANCE 7.5 kN/m Drawn JWL 15/03/21 Approved DW 19/03/21

WATER TANKS 30 kN/m Dwg. Chk. JWL 15/03/21 Date 19/03/21


2.3.4 VEHICLE LOADS
HEAVY VEHICLE PARK 2 Scale
Project: 406785
Status
LOADINGS DUE TO VEHICLES SHALL BE ACCORDANCE WITH EURO CODE AND NA TO SS EN 1991-2-2012. 25 kN/m
(VEHICULAR LOAD WITHIN THE BUILDING)
AS SHOWN CAD file:W101CWD-GN0201-.dgn W
CATWALK (FOR INSPECTION) 1.0kN AT 1m CENTERS (CONCENTRATED LOAD)
Drawing no. Rev
15kN AT END ANCHOR
GONDOLA SYSTEM
12kN AT 5m CENTERS FOR INTERMEDIATE HANGER FOR CONSTRUCTION
W/101/CWD/GN/0201 -

"This document is issued for the party which commissioned it and for specific purposes connected with the above captioned project only. It should not be relied upon by any other party or used for any other purpose. We accept no responsibility
for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties."
"This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it."
4.12 ALL LAPS SHOWN ON THE DRAWINGS ARE INDICATIVE ONLY. THE CONTRACTOR
SHALL PREPARE THE SHOP DRAWINGS TO THE QPD'S ACCEPTANCE

4.13 RC STARTER BARS FOR WALLS AND COLUMNS


6.4 BAR POSITION
STARTER BARS FROM THE FLOOR STRUCTURAL SYSTEM FOR RC WALLS
AND COLUMNS SHALL CORRESPOND IN NUMBER AND SIZE TO THE
a) LINKS/HOOKS FOR ROOF SLAB
REINFORCEMENT IN THE WALL OR COLUMN IN WHICH THEY ARE TO BE
EMBEDDED

4.14 STANDARD RADIUS BENDS (MANDREL DIAMETER) 5.2 ASSUMED BOND CONDITIONS
MAIN BAR
A A
A) THE MINIMUM DIAMETER TO WHICH A BAR IS BENT SHALL BE SUCH AS TO
AVOID BEDING CRACKS IN THE BAR, AND AVOID FAILURE OF THE CONCRETE
INSIDE THE BEND OF THE BAR

h
B

CKNESS
ROOF
B) IN ORDER TO AVOID DAMAGE TO THE REINFORCEMENT THE DIAMETER TO

a
h < 250mm

THI
45°< a < 90°FOR ALL VALUES B3 - LAYER

300
OF h (E.G. COLUMNS)
B1 - LAYER
A A ONAL EN
I
S G
4.14.1 FOR BARS AND WIRE : S

FE

IN
ST

PRO

EE
SL

R
h

h
GEOTECHNICAL
BAR MINIMUM MANDREL DIAMETER
ST
DIAMETER FOR BEND, HOOKS AND LOOPS LO NG CHEW CHIAT
NG SL
h > 250mm h > 600mm ITU ION
16mm DI ST CT 4334

250
NA R E
L DI S
DI
RE SE IN E
CT
SL ER GA POR
NOTES: SV
ION AN
A) UNHATCHED ZONE - 'GOOD' BOND CONDITIONS TR
B) HATCHED ZONE - 'POOR' BOND CONDITIONS
C) ADIRECTION OF CONCRETING NOTE: (QUALIFIED PERSON STAMP AND SIGNATURE)

4.14.2 FOR WELDED BENT REINFORCEMENT AND 1. DISTRIBUTION BARS ARE NOT SHOWN DATE: 01 FEB 2021

MESH BENT AFTER WELDING : 2. SHEAR REINFORCEMENTS SHALL BE


5.3 COUPLERS HOOKED AT BOTTOM MAIN REINFORCEMENT B1 AND B3
MINIMUM MANDREL DIAMETER LAYERS ALTERNATIVELY.
ONAL EN
I
S G
S

FE
d

IN
5.3.1 CONTRACTOR TO ALLOW FOR COUPLERS AS REQUIRED TO SUIT

PRO
OR

EE
OR
THE FINAL CONSTRUCTION SEQUENCE.

R
CIVIL
b) LINKS/HOOKS FOR BASE SLAB
SOON WON MOI
5.3.2
TO BE A PROPRIETARY TYPE CAPABLE OF DEVELOPING THE FULL
STRENGTH OF THE PARENT BAR. 3972
S E
IN
5.3.3
THE CONTRACTOR IS TO NOTE THAT DIFFERENT COUPLER TYPES GA POR

5 LAP AND ANCHORAGE LENGTHS FOR CLASS B HIGH YIELD REINFORCEMENT. SHALL BE REQUIRED DEPENDING ON THE FIXING REQUIREMENTS OF MAIN BAR
EACH BARS. E.G. ROTATING OF BARS INTO COUPLERS CAST INTO A
DIAPHRAGM WALL. (QUALIFIED PERSON STAMP AND SIGNATURE)
5.1.1 LAP LENGTHS PROVIDED (FOR NOMINAL BARS, etc.) SHOULD NOT BE LESS THAN 15 TIMES THE BAR
SIZE OR 200mm WHICHEVER IS GREATER. DATE: 01 FEB 2021

CKNESS
6 LEGENDS

BASE
5.1.2 IT IS ASSUMED 100% OF THE BARS ARE LAPPED AT ONE PLACE FOR COLUMNS AND WALLS. SLAB &

THI
BEAM OPTIONS FOR 25%, 33% AND 50% LAPPING AT SAME PLACE ARE ALSO PROVIDED. FOR OTHER
CASES REFERENCES SHALL BE MADE TO SS EN 1992-1-1.
6.1 REINFORCEMENT NOTATION ON THE DRAWINGS :

20 H 25 - (V) - 200 T1 x 12m


5.1.3 BOND CONDITION - THE ULTIMATE BOND STRESS IS RELATED TO THE QUALITY OF THE BOND
CONDITION AND POSITION OF THE BARS AS SHOWN IN SECTION 5.2
NUMBER OF BARS
SL
A. TYPICAL VALUES OF ANCHORAGE AND LAP LENGTHS IN BAR SIZE FOR SLABS : ST
TYPE OF BAR
LO
BOND fck/ fcu fck/ fcu NG SL
BAR DIAMETER IN mm ITU ST ION
CONDITIONS 32/ 40 35/ 45 DI ECT
NA R
L DI
INDICATED ONLY WHEN BAR LENGTH VARIES DI E
FULL TENSION AND GOOD RE SL ST RS
CT
SVE
ION
COMPRESSION AN
POOR BAR SPACING IN mm TR
ANCHORAGE LENGTH, TA
(SEE NOTE C)
BAR POSITION
FULL TENSION AND GOOD NOTE:
COMPRESSION LAP LENGTH OF THE BAR (INDICATE WHEN NECESSARY) 1. DISTRIBUTION BARS ARE NOT SHOWN
POOR
LENGTH, TL
(SEE NOTE C)
WA
LL
c) LINKS/HOOKS FOR WALLS TH
B. TYPICAL VALUES OF ANCHORAGE AND LAP LENGTHS IN BAR SIZE FOR BEAMS : ICK
NE
SS - 01.02.21 SABJ ISSUED FOR CONSTRUCTION (ST031) JWL KS DW
BOND fck/ fcu fck/ fcu
CONDITIONS 32/ 40 35/ 45 Rev Date Drawn Description Dsg'd Chk'd App'd

6.1.1 Client
FULL TENSION AND GOOD
' '
COMPRESSION
POOR
ANCHORAGE LENGTH, TA H13- 300 / 300 HOOKS
(SEE NOTE C)

FULL TENSION AND GOOD TYPE OF BAR


Su
COMPRESSION LAP
POOR LINK/HOOK DIAMETER
LENGTH, TL
(SEE NOTE C)

ON
FOR SLAB: LONGITUDINAL SPACING mm Contractor

RECTI
FOR WALLS: HORIZONTAL SPACING mm
C. TYPICAL VALUES OF ANCHORAGE AND LAP LENGTHS IN BAR SIZE FOR COLUMNS : Su
FOR SLAB: TRANSVERSE SPACING mm
Engineering & Construction

CAL DI
BOND fck/ fcu fck/ fcu
FOR WALLS: VERTICAL SPACING mm MAIN BAR
CONDITIONS 32/ 40 35/ 45

TYPE

VERTI
FULL TENSION AND Su
Design Consultant
COMPRESSION 152 Beach Road
GOOD BAR SHAPE
#35-00 Gateway East
ANCHORAGE LENGTH, TA M Singapore 189721

FULL TENSION AND MOTT


M Telephone (65) 62931900
Fax (65) 62931911
Su E-mail mm@mottmac.sg
COMPRESSION LAP MACDONALD
GOOD
LENGTH, TL
Project title

SH
D. TYPICAL VALUES OF ANCHORAGE AND LAP LENGTHS IN BAR SIZE FOR WALLS/ DWALLS : CONTRACT N101
SH ON DESIGN AND CONSTRUCTION OF
BOND fck/ fcu fck/ fcu
CTI
CONDITIONS 32/ 40 35/ 45 6.2 REINFORCEMENT LAYERING TAGS RE
T1 DI NORTH-SOUTH CORRIDOR (TUNNEL)
SH AL
FULL TENSION AND T2
ONT
Z
RI
BETWEEN ECP AND VICTORIA STREET
COMPRESSION GOOD
HO
ANCHORAGE LENGTH, TA
NOTE:

FULL TENSION AND 1. DISTRIBUTION BARS ARE NOT SHOWN

COMPRESSION LAP GOOD Drawing Title


LENGTH, TL
B2

B1
GENERAL NOTES SHEET 2
NOTE:

1. IT IS ASSUMED NOT MORE THAN 50% OF THE BARS ARE LAPPED AT ONE PLACE FOR BEAMS, 6.3 NOTATION OF SLABS ON THE DRAWINGS :
7 PROTECTION OF EXPOSED REINFORCEMENT
SLABS, COLUMNS AND WALLS. FOR OTHER CASES REFERENCES SHALL BE MADE TO SS EN 1992.1-1.
200 DENOTES SLAB THICKNESS = 200mm
2. FOR BAR SIZES GREATER THAN 32mm THE VALUES GIVEN IN THE TABLES SHALL BE MULTIPLIED
STARTER BARS AND OTHER STEEL BARS WHICH ARE EXPOSED TO THE
Designed NS 01/02/21 Eng. Chk. KS 15/03/21
ENVIROMENT DUE TO DELAY IN CONCRETING OPERATION OR STAGED
3. BOND CONDITION - THE ULTIMATE BOND STRESS IS RELATED TO THE QUALITY OF THE BOND CONSTRUCTION THAT MAY CAUSE CORROSION OF BARS SHALL BE COATED Drawn JWL 15/03/21 Approved DW 19/03/21

CONDITION AND POSITION OF THE BARS ARE SHOWN ON NOTE 5.2. WITH GROUT TO PROTECT THEM AGAINST CORROSION. PRIOR TO CASTING
Dwg. Chk. JWL 15/03/21 Date 19/03/21
OF THE IN-SITU ELEMENT, DRIED CEMENT GROUT SHALL BE REMOVED BY
Scale Status
VIGOROUS WIRE BRUSHING. Project: 406785

AS SHOWN CAD file:W101CWD-GN0202-.dgn W


Drawing no. Rev

FOR CONSTRUCTION
W/101/CWD/GN/0202 -

"This document is issued for the party which commissioned it and for specific purposes connected with the above captioned project only. It should not be relied upon by any other party or used for any other purpose. We accept no responsibility
for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties."
"This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it."
14 GEOTECHNICAL 16. GROUND IMPROVEMENT

1. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH DEEP FOUNDATION ELEMENT DRAWING 1. THE QUALITY OF IMPROVED GROUND SHALL BE CONFIRMED IN ACCORDANCE WITH LTA M&W CHAPTER 7.
2. GROUTING PARAMETERS SHALL BE VERIFIED AND CONFIRMED AFTER TRIAL TESTS. NO INSTALLATION OF GROUND
2. ALL CONCRETE SHALL BE GRADE 32/40 UNLESS OTHERWISE SHOWN IMPROVEMENT SHALL BE CARRIED OUT PRIOR TO SUCCESSFUL COMPLETION OF TRIAL TESTS. THE CONTRACTOR
SHALL SUBMIT DETAILED PROPOSALS FOR CARRYING OUT THE TRIAL TESTS.
3. REINFORCEMENT BAR TO HAVE YIELD STRENGTH AT 500N/mm² 3. THE CONTRACTOR IS TO PROPOSE FOR THE ENGINEER'S ACCEPTANCE AND APPROVAL THE VERIFICATION
METHOD(S) APPRORIATE TO THE LOCATION AND TYPE OF GROUND IMPROVEMENT BEING IMPLEMENTED.
4. THE ESTIMATED EMBEDMENT OF DEEP FOUNDATION ELEMENT (DFE) SHALL BE VERIFIED ACCORDING TO GROUND CONDITIONS
ENCOUNTERED DURING EXCAVATION OR BORING FOR DFE IN ORDER TO ENSURE THAT THE REQUITED GEOTECHNICAL
RESISTANCE IS ATTENDED

5. THE ALLOWABLE DFE SETTLEMENT IS 15mm AND 25mm FOR SHORT AND LONG TERM CONDITIONS RESPECTIVELY

6. THE MAXIMUM DIFFERENTIAL SETTLEMENT SHALL BE LESS THAN 1:1000

7. THE MAXIMUM PERMITTED DEVIATION OF THE CONSTRUCTED DFE FROM THE VERTICAL IS1(H) IN 75(V)

8. THE MAXIMUM PERMITTED DEVIATION OF THE CENTRE OF THE CONSTRUCTED DFE FROM ITS CENTRE SHOWN ON THE DRAWING
SHALL NOT EXCEED 75mm IN ANY DIRECTION ONAL EN
I
S G
9. THE VIBRATION LIMIT FOR THE CONSTRICTION OF DFE IS 15mm/sec PEAK PARTICLE VELOCITY S

FE

IN
PRO

EE
R
10. PRELIMINARY LOAD TEST AND WORKING LOAD TEST SHALL BE UNDERTAKEN TO VERIFY DESIGN PARAMETERS GEOTECHNICAL

NG CHEW CHIAT
11. THE ESTIMATED DFE TOE LEVEL SHALL BE VERIFIED WITH THE RESULT OF THE ULTIMATE LOAD TEST AND ANY NEW BOREHOLE
INFORMATION 4334
S E
12. THE ALLOWABLE GEOTECHNICAL CAPACITY OF THE DFE ARE CALCULATED TO SATISFY THE FOLLOWING FORMULAS IN
GA POR

(QUALIFIED PERSON STAMP AND SIGNATURE)


DATE: 01 FEB 2021
I-COMPRESSION

1. DL + MAX OF (1.11 LL OR NSF) <(Qb/gb+Qs/gs) /(1.35xMF) (EC DA1 - COM 1)


ONAL EN
I
S G
S
2. DL + MAX OF (1.3 LL OR NSF ) < (Qb/gb+Qs/gs) / MF (EC DA1 - COM 2)

FE

IN
M2

PRO

EE
R
3. DL + MAX OF (LL OR NSF) < Qs/1.5 (LTA CDC) CIVIL

SOON WON MOI


4. DL + MAX OF (LL OR NSF) < (Qb + Qs) / 2.5 (LTA CDC)
3972
S E
5. TEMPLOAD< Qs/1.2 (GROUND WATER LEVEL AT THE BOTTOM OF EXCAVATION)(LTA CDC) IN
GA POR

II-TENSION
(QUALIFIED PERSON STAMP AND SIGNATURE)
DATE: 01 FEB 2021
1. TENSION LOAD < Qs g
( sxMF) (EC DA1 - COM 1) & (DA1 - COM 2)
2. TENSION LOAD < Qs/3.5 (LTA CDC)

WHERE DL IS DEAD LOAD

LL IS LIVE LOAD

TEMPLOAD IS TEMPORARY COMPRESSION LOAD DURING CONSTRUCTION

NSF IS NEGATIVE SKIN FRICTION

NSF IS NSF CALCULATED USING M2 PARTIAL FACTOR (APPROXIMATE VALUES IS NSF/1.25)


m2

Qb IS BASE RESISTANCE OF DFE

Qs IS SKIN RESISTANCE OF DFE

- 01.02.21 SABJ ISSUED FOR CONSTRUCTION (ST031) JWL KS DW

MF IS MODAL FACTOR 1.35 (EXPLICIT VERIFICATION OF SLS IS


Rev Date Drawn Description Dsg'd Chk'd App'd
CONDUCTED) OR 1.55 (EXPLICIT VERIFICATION PF SLS IS NOT CONDUCTED)
Client

13. REFER TO TUNNEL DIAPHRAGM WALL SCHEDULE DRAWING 101/TUN/PL/1306 FOR THE
ADOPTED GEOTECHNICAL RESISTANCE DESIGN PARAMETERS.

Contractor

14.ADOPTED GEOTECHNICAL RESISTANCE DESIGN FACTORS Engineering & Construction

Design Consultant
152 Beach Road
#35-00 Gateway East
END BEARING COMBINATION 1 COMBINATION 2
M Singapore 189721
COEFFICIENT
qb(kPa) MOTT
M Telephone (65) 62931900
Fax (65) 62931911
R1 R4 *R4 MACDONALD E-mail mm@mottmac.sg

Project title

BASE gb
1.00 2.00 1.70
CONTRACT N101

SHAFT (COMPRESSION) gs DESIGN AND CONSTRUCTION OF


1.00 1.60 1.40
NORTH-SOUTH CORRIDOR (TUNNEL)
SHAFT (TENSION) gs:t
1.00 2.00 1.70
BETWEEN ECP AND VICTORIA STREET

*R4 MAY BE ADOPTED WHEN EXPLICIT VERIFICATION OF SLS CONDUCTED

Drawing Title

GENERAL NOTES SHEET 3


15.NO DFE SHALL BE CONCRETED UNTIL THE FOUNDATION MATERIAL AND BASE CLEANLINESS HAVE BEEN APPROVED BY THE QP(S)

Designed NS 01/02/21 Eng. Chk. KS


KS 15/03/21

Drawn JWL 15/03/21 Approved DW


DW 19/03/21

Dwg. Chk. JWL 15/03/21 Date 19/03/21

Scale Status
Project: 406785

AS SHOWN CAD file:W101CWD-GN0203-.dgn W


Drawing no. Rev

FOR CONSTRUCTION
W/101/CWD/GN/0203 -

"This document is issued for the party which commissioned it and for specific purposes connected with the above captioned project only. It should not be relied upon by any other party or used for any other purpose. We accept no responsibility
for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties."
"This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it."

You might also like