SUB STRUCTURE(FOUNDATION)

ITEM DESCRIPTION UNIT QTY RATE AMOUN


T
1 Dump proof course below all walls SM 86 300 25,800
200mm and150mm thick

2 Super structure walling in mortar mix SM 2,550 2,600 6,630,000


1:3 and reinforced with hoop iron 25mm
at every alternate course

3 Steel reinforcement to columns KG 5,440 200 1,088,000


irrespective of size but assorted in mass
(T16,T12,T8)

4 Form work to columns SM 70 800 56,000

5 Concreting to columns CM 48 13500 648,000


Class 25/20 .Mix 1:1.5:3

6 Formwork to beams SM 780 800 624,000

7 Steel reinforcement to beams KG 5004 200 1,000,000


T20,T16,T12, and T8

8 Concrete class 25/20 to beams CM 56 13,500 756,000

9 Form work to suspended slabs SM 546 800 436,800

10 Steel reinforcement to suspended slab KG 6552 200 1,310,400


T12,T10,T8

11 Concrete class 25/20 to suspended slabs CM 98 13,500 1,323,000


and stair case

12 Masonry walling 1.2m high as parapet SM 90 2,100 189,000


wall

13 Allow for a sum of Ksk.450,000 for 450,000


electrical conduits

14 Allow for a sum of Ksh.600,000 for 600,000


plumbing work

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


15 Allow for a sum of Ksh.300,000 for 300,000
construction of dwarf walls to sinks and
kitchen work tops

14,114,800
Total