ITEM DESCRIPTION UNIT QTY RATE AMOUN


T
1 Fixing of door frames 150mx50mm LM 165 1200 198,000
plugged mahogany frames

2 Motar mix 1:3 steel trowelled internally to SM 2550 300 765,000


walls 200mm thick

3 Plastering with mortar SM 807 300 765,000


Mix1:3 to walls 150mm internally

4 Plastering to soffite of ceiling. (Plastering SM 1,480 300 444,000


below suspended slab)

5 Hacking of floors to receive screeding SM 472 200 94,400


30mm thick screed with mortar mix 1:3

6 Mortar mix 1:3 for screeding 30mm thick SM 472 400 188,800

7 Fixing of door shutters (Panel doors) NO 30 2000 60,000

8 Supply and fix iron mongering as Assa NO 30 4700 141,000


Abloy (Union locks) 2 lever

9 Allow for a sum of Ksh. 300,000 for 300,000


hinges door stoppers and the like

10 Allow for a sum of Ksh.600,000 for steel 600,000


casement windows and steel doors

11 Allow for a sum of Ksh.850,000 for 850,000


plumbing accessories

12 Allow for plumbing of Ksh. 700,000 for 700,000


electrical appliances

13 Ceramic floor tiles on screeded floors SM 470 2,200 1,034,000


with cement paste

14 Ceramic wall tiles to plastered walls SM 180 2,100 378,000


internally with cement paste
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
15 Allow for a sum of Ksh.400,000 for septic 400,000
tank and soak pit
6,395,300
Total

SUMMARY
SUB STRUCTURE (FOUNDATION) 4,324,000

SUPER STRUCTURE 14,114,800

FINISHES 6,395,300

TOTAL 24,834,100