Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

CAWTHORNE LIGHT (NCTL) METERING SYSTEM

POST DIVESTMENT CRUDE OIL METERING PROJECT


PIPING INSULATION PROJECT
PLANNED SCHEDULE
ID Activity Description Planned Duration Planned Start Planned Finish October November
Wed 10/4 Fri 11/3
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
0
CAWTHORNE LIGHT (NCTL) METERING SYSTEM POST DIVESTMENT CRUDE OIL 38 days Sat 9/30/17 Thu 11/16/17
METERING PROJECT
1
PIPING INSULATION PROJECT 38 days Sat 9/30/17 Thu 11/16/17
2
Perform Site Visitation / Inspection / Assessment 1 day Sat 9/30/17 Sat 9/30/17
3
Issue Materials RFQ to OEM 1 day Mon 10/2/17 Mon 10/2/17
4
Receive Quotation from OEM 1 day Wed 10/4/17 Wed 10/4/17
5
Prepare / Submit Quotation to GCA 1 day Fri 10/6/17 Fri 10/6/17
6
Award of Contract / PO 1 day Sat 10/7/17 Sat 10/7/17
7
Receive Mobilization (as per Contract Terms) from GCA 2 days Mon 10/9/17 Tue 10/10/17
8
Place Order for Materials from OEM 1 day Wed 10/11/17 Wed 10/11/17
9
Receive Materials from OEM (via Air freighting) 3 days Thu 10/12/17 Sat 10/14/17
10
Custom Clearance / Delivery of Materials to OES Fabrication Workshop in 5 days Mon 10/16/17 Fri 10/20/17
Port Harcourt
11
Inspection of Delivered Materials by GCA 1 day Sat 10/21/17 Sat 10/21/17
12
Prefab of Inuslation Materials in OES Fabrication Workshop 12 days Mon 10/23/17 Tue 11/14/17
13
Installation / Fitup of Insulation Materials on Site 12 days Mon 10/30/17 Tue 11/14/17
14
Inspection of Completed insulation on Piping System, by GCA / Aderly 1 day Wed 11/15/17 Wed 11/15/17
15
Project Close Out / WCC Sign Out 1 day Thu 11/16/17 Thu 11/16/17
16
17
18
19
Abbreviations:
20
RFQ: Request for Quotation
21
OEM: Original Equipment Manufacturer
22
GCA: Greg Continental Agency Limited (The Client)
23
PO: Purchase Order
24
OES: Osehu Engineering Services Limited
25
WCC: Work Completion Certificate

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: CAWTHORNE LIGHT (N
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sun 10/1/17
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1

You might also like