Agenda for Progress Review Meeting (PM 054 PRM 034 QRM 025 ESGRM 028)
Name of Project Construction of Piling, Substructure & Superstructure including Part Finishing Works
for Project ‘Sunshine One’, Shriram Grand City, Uttarpara.

Meeting Progress Review Meeting (PM 054 PRM 034 QRM 025 ESGRM 028)

Date and Time 21st June 2022 from 03.00 pm onwards.

Location Site office Conference Room

Attendees Dr. Koushik Bhattacharya – SPLEPL Mr. Nayan Jyoti Bose – SIL
Mr. Madan Bhar – SPLEPL Mr. Kartick Paramanik – SIL
Mr. Abir Sengupta – SPLEPL Mr. Prokash Mitra – SIL
Mr. Chanchal Saha – SPLEPL Mr. Laxmi Kanta Ghosh – SIL
Mr. Ayan Basu Mallik – SPLEPL Any Other Team Member – SIL

Mr. Partha Guha – MDM


Mr. Kalpataru Das - MDM
Mr. Ashis Das – MDM
Mr. Sudip Kr. Ghosh – MDM
Mr. Pradip Basu – MDM
Agenda 1) Review of project HSE Practices and Management status.
2) Review of project Quality Practices and Management status.
3) Review of Simplex’s work progress of all 5 nos. Towers of Sunshine One
vis-à-vis plan for the month of June 2022.
4) Review of current status of manpower availability & Simplex’s plan for
immediate augmentation, Tower-wise.
5) Simplex’s Staff availability and plan for immediate augmentation.
6) Simplex’s plan for commencement of Piling for Tower Crane foundation.
7) Simplex’s plan for mobilisation of essential equipments, dedicated for
Sunshine One.
8) Simplex’s plan to resume concrete production from captive Batching Plant.
9) Status of developing approaches for uninterrupted work progress during
monsoon.
10) Status of strengthening the existing earthen bunds.
11) Simplex’s plan for commencement of Piling at Sunshine Two.
12) Any other relevant points.