Biaya Over Head Project: Rubber Wood Processing Plant Pt. Tiga Mutiara Nusantara

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 126

BIAYA OVER HEAD

PROJECT : RUBBER WOOD PROCESSING PLANT


PT. TIGA MUTIARA NUSANTARA
Resources Duration Unit Price Amount
No. Description
QTY Unit QTY Unit ( Rp ) ( Rp )
I SITE MANAGEMENT
A GAJI
1 Project Manager 1.00 Person 6.00 Months 2,500,000.00 15,000,000.00
2 Engineer 1.00 Person 6.00 Months 1,500,000.00 9,000,000.00
3 Supervisor 1.00 Person 6.00 Months 1,200,000.00 7,200,000.00
4 Surveyor 1.00 Person 6.00 Months 800,000.00 4,800,000.00
5 Logistic 1.00 Person 181.00 Months 50,000.00 9,050,000.00
6 Ass Logistic/ Surveyor 2.00 Persons 181.00 Days 20,000.00 7,240,000.00
7 Site Office Boy 1.00 Person 181.00 Days 20,000.00 3,620,000.00
8 Tenaga Harian (u/ Security dan jaga Malam) 2.00 Persons 6.00 Months 600,000.00 7,200,000.00
9 ETT 1.00 Ls 1.00 Ls 10,000,000.00 10,000,000.00

B MAKAN PERSONIL
1 Personil Management & Staff Pendukung 7.00 Persons 181.00 Days 20,000.00 25,340,000.00
2 Operator Alat Berat 3.00 Persons 90.00 Days 60,000.00 16,200,000.00
3 Tenaga Harian 6.00 Persons 181.00 Days 15,000.00 16,290,000.00

C MOBILISASI / DEMOBILISASI
1 Transport Staff 7.00 Persons 6.00 Times 100,000.00 4,200,000.00
2 Transport Material 25.00 Trips 1.00 Times 350,000.00 8,750,000.00
3 Transport Alat Berat 3.00 Trips 2.00 Times 2,500,000.00 15,000,000.00
SUB TOTAL 158,890,000.00

II BIAYA UMUM
A PEKERJAAN PEMBERSIHAN
1 Pekerjaan Awal
- Babat Rumput 1.00 Ls 1.00 Ls 2,000,000.00 2,000,000.00
- Stripping Top Soil (Buldozer) u/ Bangunan KD 1.00 Ls 16.00 Hours 250,000.00 4,000,000.00
2 Pekerjaan Akhir 1.00 Ls 1.00 Times 1,500,000.00 1,500,000.00

B TEMPORARY FACILITIES
1 Buat Kantor/ Gudang sementara 1.00 Ls 1.00 Ls 15,000,000.00 15,000,000.00
2 Sewa Mess (2 Rumah) 2.00 Unit 6.00 Months 750,000.00 9,000,000.00
3 Pengadaan Air Kerja 1.00 Ls 6.00 Months 500,000.00 3,000,000.00
4 Penerangan/ Lampu/ listrik Kerja (Genset) 1.00 Ls 6.00 Months 3,500,000.00 21,000,000.00
5 Pengukuran awa dan Pematokan 1.00 Ls 1.00 Ls 2,000,000.00 2,000,000.00

C BIAYA MAINTANENCE
1 Alat Kerja 1.00 Ls 1.00 Ls 1,500,000.00 1,500,000.00

D ADMINISTRATION
1 Alat Tulis Kantor dan Foto kopi 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
2 Dokumentasi 1.00 Ls 6.00 Months 250,000.00 1,500,000.00

E KOMUNIKASI
1 Telephone/ Fax/ Internet 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
2 Rekening HP Staff Executive 1.00 Persons 6.00 Months 500,000.00 3,000,000.00
3 Rekening HP Staff 7.00 Persons 6.00 Months 200,000.00 8,400,000.00
4 Expedisi Laporan 1.00 Ls 6.00 Months 100,000.00 600,000.00

G CONTINGENCY & INCIDENTIAL


1 Biaya Kesehatan/ Kecelakaan 1.00 Ls 1.00 Ls 5,000,000.00 5,000,000.00
2 SPSI/ OKP/ Kota Praja dll 1.00 Ls 6.00 Ls 2,000,000.00 12,000,000.00
SUB TOTAL 92,500,000.00

TOTAL 251,390,000.00

1
INFORMASI PROYEK
PROYEK TIGA MUTIARA NUSANTARA

Nama Proyek : RUBBER WOOD PROCESSING PLANT

Pemilik Proyek : PT. TIGA MUTIARA NUSANTARA

Lokasi Proyek : GUNUNG PARA (SERDANG BEDAGAI)

Waktu Pelaksanaan : JANUARY 2005 S/D JULY 2005

Scope Pekerjaan : 1. Bagunan Sipil

2. Bangunan Baja

3. Infrastruktur dan Bangunan Pendukung


RENCANA ANGGARAN BIAYA
PROYEK RUBBER WOOD PROESSING PLANT
PT. TIGA MUTIARA NUSANTARA
Jadwal Pelaksanaan
Start : February 2005
Finish : July 2005
Kontrak : 6.380.857.245,- (Sebelum Margin dan PPN)

Unit Price Amount


No. Description
( Rp ) ( Rp )

1 Rencana Anggaran Biaya 5,226,859,997.04

5,226,859,997.04

2 Over Head Management 251,390,000.00

251,390,000.00

Total 5,478,249,997.04

Dibuat Oleh :

1 H. ARITONANG : ______________
2 ANDY : ______________

Diperiksa Oleh :

1 Z. Pohan : ______________
2 Ruddy : ______________

Disetujui Oleh :

1 Wilbenzs Gosti : ______________


BIAYA OVER HEAD
PROJECT : RUBBER WOOD PROCESSING PLANT
PT. TIGA MUTIARA NUSANTARA
Resources Duration Unit Price Amount
No. Description
QTY Unit QTY Unit ( Rp ) ( Rp )
I SITE MANAGEMENT
A GAJI
1 Project Manager 1.00 Person 6.00 Months 2,500,000.00 15,000,000.00
2 Engineer 1.00 Person 6.00 Months 1,500,000.00 9,000,000.00
3 Administration 1.00 Person 6.00 Months 750,000.00 4,500,000.00
4 Supervisor 1.00 Person 6.00 Months 1,200,000.00 7,200,000.00
5 Surveyor 1.00 Person 6.00 Months 800,000.00 4,800,000.00
6 Drafter 1.00 Person 6.00 Months 750,000.00 4,500,000.00
7 Logistic 1.00 Person 181.00 Months 50,000.00 9,050,000.00
8 Driver 1.00 Person 181.00 Days 25,000.00 4,525,000.00
9 Operator Excavator 1.00 Person 90.00 Days -
10 Operator Compactor 1.00 Person 90.00 Days -
11 Operator Crane 1.00 Person 90.00 Days -
12 Ass Logistic/ Surveyor 2.00 Persons 181.00 Days 20,000.00 7,240,000.00
13 Site Office Boy 1.00 Person 181.00 Days 20,000.00 3,620,000.00
14 Tenaga Harian (u/ pekerjaan baja) 1.00 Person 181.00 Days 40,000.00 7,240,000.00
15 Tenaga Harian (u/ Security dan jaga Malam) 2.00 Persons 6.00 Months 600,000.00 7,200,000.00
16 ETT 1.00 Ls 1.00 Ls 10,000,000.00 10,000,000.00

B MAKAN PERSONIL
1 Personil Management & Staff Pendukung 7.00 Persons 181.00 Days 30,000.00 38,010,000.00
2 Operator Alat Berat 3.00 Persons 90.00 Days 60,000.00 16,200,000.00
3 Tenaga Harian 6.00 Persons 181.00 Days 15,000.00 16,290,000.00

C MOBILISASI / DEMOBILISASI
1 Transport Staff 7.00 Persons 6.00 Times 100,000.00 4,200,000.00
2 Transport Material 20.00 Trips 1.00 Times 2,500,000.00 50,000,000.00
3 Transport Alat Berat 3.00 Trips 2.00 Times 2,500,000.00 15,000,000.00
SUB TOTAL 233,575,000.00

II BIAYA UMUM
A PEKERJAAN PEMBERSIHAN
1 Pekerjaan Awal
- Babat Rumput 1.00 Ls 1.00 Ls 2,000,000.00 2,000,000.00
- Stripping Top Soil (Buldozer) u/ Bangunan KD 1.00 Ls 16.00 Hours 250,000.00 4,000,000.00
2 Pekerjaan Akhir 1.00 Ls 1.00 Times 1,500,000.00 1,500,000.00

B TEMPORARY FACILITIES
1 Buat Kantor/ Gudang sementara 1.00 Ls 1.00 Ls 15,000,000.00 15,000,000.00
2 Sewa Mess (2 Rumah) 2.00 Unit 6.00 Months 750,000.00 9,000,000.00
3 Pengadaan Air Kerja 1.00 Ls 6.00 Months 500,000.00 3,000,000.00
4 Penerangan/ Lampu/ listrik Kerja (Genset) 1.00 Ls 6.00 Months 3,500,000.00 21,000,000.00
5 Pengukuran awa dan Pematokan 1.00 Ls 1.00 Ls 2,000,000.00 2,000,000.00

C BIAYA MENTENENCE
1 Mentenence/ Alat Kerja 1.00 Ls 1.00 Ls 1,500,000.00 1,500,000.00

D ADMINISTRATION
1 Alat Tulis Kantor dan Foto kopi 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
2 Dokumentasi 1.00 Ls 6.00 Months 250,000.00 1,500,000.00

E KOMUNIKASI
1 Telephone/ Fax/ Internet 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
2 Rekening HP Staff Executive 1.00 Persons 6.00 Months 500,000.00 3,000,000.00
3 Rekening HP Staff 7.00 Persons 6.00 Months 200,000.00 8,400,000.00
4 Expedisi Laporan 1.00 Ls 6.00 Months 100,000.00 600,000.00

4
BIAYA OVER HEAD
PROJECT : RUBBER WOOD PROCESSING PLANT
PT. TIGA MUTIARA NUSANTARA
Resources Duration Unit Price Amount
No. Description
QTY Unit QTY Unit ( Rp ) ( Rp )

F PERLENGKAPAN SAFETY DAN P3K


1 Safety Shoes 10.00 Pcs 1.00 Times 200,000.00 2,000,000.00
2 Safety Head 10.00 Pcs 1.00 Times 20,000.00 200,000.00
3 Safety Glass 10.00 Pcs 1.00 Times 15,000.00 150,000.00
4 Safety Gloves 10.00 Pcs 1.00 Times 7,500.00 75,000.00
5 Safety Belt 5.00 Pcs 1.00 Times 150,000.00 750,000.00
6 Kotak P3K 1.00 Pcs 1.00 Times 200,000.00 200,000.00
7 Fire Extinguisier 1.00 Pcs 1.00 Times 1,000,000.00 1,000,000.00

G CONTINGENCY & INCIDENTIAL


1 Biaya Tak Terduga 1.00 Ls 1.00 Ls 10,000,000.00 10,000,000.00
2 Biaya Kesehatan/ Kecelakaan 1.00 Ls 1.00 Ls 5,000,000.00 5,000,000.00
3 SPSI/ OKP/ Kota Praja dll 1.00 Ls 6.00 Ls 2,000,000.00 12,000,000.00
SUB TOTAL 106,875,000.00

TOTAL 340,450,000.00

5
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

I PEKERJAAN PERSIAPAN
10 Pengukuran/ Pematokan & Pemasangan Bowplank m'
Materials
600.00 0.5 Btg Btg - Kayu Sembarang 2".3"
360.00 0.3 Btg Kpg - Papan Sembarang 3/4".8"
30.00 0.025 kg kg - Nails
Labour
1,200.00 1 Ls m' - Vitzet
1,200.00 1 Ls m' - Pasang Bowplank
Equipment
1,200.00 1 Ls - Tools

II BANGUNAN PABRIK uk. 30M x 96M (3 Unit)


A. Pekerjaan Sipil uk. 30m x 96m (3 Unit)
- Pondasi Type F1 = 34 Units
1 Galian Pondasi m3
a. Labour
66.64 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
66.64 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
a. Materials
3.9984 1.20 m3 m3 - Pasir
b. Labour
0.9996 0.30 - Pekerja
0.03332 0.01 - Mandor

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
3.03 0.91 m3 m3 - Batu krikil
15.13 4.54 zak zak - P. Cement
1.80 0.54 m3 m3 - Pasir
b. Labour
3.37 1.01 m3 m3 - Pouring Concrete, Cleaning
Equipment
3.33 1.00 m3 m3 - Lory, timber, ducting etc.

4 Bekesting m2
a Materials
1.65 0.012 m3 m3 - SK Wood
46.82 0.34 pcs Lbr - Triplex 12 mm thick
55.08 0.40 kg kg - Nails
b. Labour
137.70 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
137.70 1.00 m2 m2 - Tools
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

5 Besi Beton Kg
a. Materials
2,092.80 1.03 kg kg - Rebar U32
40.64 0.02 kg kg - Bindraad
b. Labour
2,031.84 1.00 kg kg - Fabricatiom, Installation
2,031.84 1.00 kg kg - Transportation & lifting
c. Equipment
2,031.84 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-225 m3


a. Material
25.14 0.85 m3 m3 - Batu krikil
251.43 8.5 zak zak - P. Cement
16.27 0.55 m3 m3 - Pasir
b. Labour
29.88 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
29.58 1.00 m3 m3 - Lory, timber, ducting etc.

7 Timbunan Kembali Bekas Galian m3


a. Material
36.48 1.2 m3 m3 - Tanah merah
b. Labour
7.60 0.25 - Pekerja
0.30 0.01 - Mandor

- Pondasi Type F2 = 26 Units


1 Galian Pondasi m3
a. Labour
50.96 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
50.96 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
a. Materials
3.0576 1.20 m3 m3 - Pasir
b. Labour
0.7644 0.30 - Pekerja
0.02548 0.01 - Mandor

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
2.32 0.91 m3 m3 - Batu krikil
11.57 4.54 zak zak - P. Cement
1.38 0.54 m3 m3 - Pasir
b. Labour
2.57 1.01 m3 m3 - Pouring Concrete, Cleaning
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

c. Equipment
2.55 1.00 m3 m3 - Lory, timber, ducting etc.

4 Bekesting m2
a Materials
1.23 0.012 m3 m3 - SK Wood
34.83 0.34 pcs Lbr - Triplex 12 mm thick
40.98 0.40 kg kg - Nails
b. Labour
102.44 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
102.44 1.00 m2 m2 - Tools

5 Besi Beton Kg
a. Materials
1,600.37 1.03 kg kg - Rebar U32
31.08 0.02 kg kg - Bindraad
b. Labour
1,553.76 1.00 kg kg - Fabricatiom, Installation
1,553.76 1.00 kg kg - Transportation & lifting
c. Equipment
1,553.76 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-225 m3


a. Material
18.83 0.85 m3 m3 - Batu krikil
188.29 8.5 zak zak - P. Cement
12.18 0.55 m3 m3 - Pasir
b. Labour
22.37 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
22.15 1.00 m3 m3 - Lory, timber, ducting etc.

7 Timbunan Kembali Bekas Galian m3


a. Material
28.45 1.2 m3 m3 - Tanah merah
b. Labour
5.93 0.25 - Pekerja
0.24 0.01 - Mandor

- Pondasi Type F3 = 34 Units


1 Galian Pondasi m3
a. Labour
66.64 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
66.64 1.00 m3 m3 - Excavator
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

2 Pasir Urug t = 5 cm m3
a. Materials
4.00 1.20 m3 m3 - Pasir
b. Labour
1.00 0.30 - Pekerja
0.03 0.01 - Mandor

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
3.03 0.91 m3 m3 - Batu krikil
15.13 4.54 zak zak - P. Cement
1.80 0.54 m3 m3 - Pasir
b. Labour
3.37 1.01 m3 m3 - Pouring Concrete, Cleaning
Equipment
3.33 1.00 m3 m3 - Lory, timber, ducting etc.

4 Bekesting m2
a Materials
1.65 0.012 m3 m3 - SK Wood
46.82 0.34 pcs pcs - Triplex 12 mm thick
55.08 0.40 kg kg - Nails
b. Labour
137.70 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
137.70 1.00 m2 m2 - Tools

5 Besi Beton Kg
a. Materials
2,092.80 1.03 kg kg - Rebar U32
40.64 0.02 kg kg - Bindraad
b. Labour
2,031.84 1.00 kg kg - Fabricatiom, Installation
2,031.84 1.00 kg kg - Transportation & lifting
c. Equipment
2,031.84 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-225 m3


a. Material
25.14 0.85 m3 m3 - Batu krikil
251.43 8.5 zak zak - P. Cement
16.27 0.55 m3 m3 - Pasir
b. Labour
29.88 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
29.58 1.00 m3 m3 - Lory, timber, ducting etc.
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

7 Timbunan Kembali Bekas Galian m3


a. Material
33.17 1.2 m3 m3 - Tanah merah
b. Labour
6.91 0.25 - Pekerja
0.28 0.01 - Mandor

- Saluran Terbuka (Fabrik)


1 Galian m3
a. Labour
121.34 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
121.34 1.00 m3 m3 - Excavator

2 Cor Beton K-175 m3


a. Material
16.58 0.82 m3 m3 - Batu krikil
137.52 6.8 zak zak - P. Cement
10.92 0.54 m3 m3 - Pasir
b. Labour
20.43 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
20.22 1.00 m3 m3 - Lory, timber, ducting etc.

3 Batu Bata m2
1 Materials
18,200.70 63.00 pcs pcs - Brick
4,004.15 13.86 kg kg - Portland Cement
11.56 0.040 m3 m3 - Pasir
2 Labour
288.90 1.00 m2 m2 - Brick Work
3 Equipment
288.90 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

4 Plasteran sisi bagian dalam m2


1 Materials
2,402.49 5.94 kg kg - Portland Cement
8.49 0.021 m3 m3 - Pasir
2 Labours
404.46 1.00 m2 m2 - Cement Plaster
3 Equipment
404.46 1.00 m2 m2 - Supporting Tools

- Bak Kontrol uk. 300 x 400 mm (34 Units)


1 Galian m3
a. Labour
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

11.66 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted


b. Equipment
11.66 1.00 m3 m3 - Excavator

2 Cor Beton K-175 m3


a. Material
16.58 0.82 m3 m3 - Batu krikil
137.52 6.8 zak zak - P. Cement
10.92 0.54 m3 m3 - Pasir
b. Labour
2.12 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
2.10 1.00 m3 m3 - Lory, timber, ducting etc.

3 Batu Bata m2
1 Materials
4,183.20 63.00 pcs pcs - Brick
920.30 13.86 kg kg - Portland Cement
2.66 0.040 m3 m3 - Pasir
2 Labour
66.40 1.00 m2 m2 - Brick Work
3 Equipment
66.40 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

4 Plasteran m2
1 Materials
480.66 5.94 kg kg - Portland Cement
1.70 0.021 m3 m3 - Pasir
2 Labours
80.92 1.00 m2 m2 - Cement Plaster
3 Equipment
80.92 1.00 m2 m2 - Supporting Tools

5 Riol/ Bis Beton dia. 300 mm m'


1 Materials
197.25 1.01 pcs pcs - Riol beton dia. 300 mm
12,303.90 63.00 pcs pcs - Brick
2,706.86 13.86 kg kg - Portland Cement
7.81 0.040 m3 m3 - Pasir
2 Labour
195.30 1.00 m2 m' - Riol Work
3 Equipment
195.30 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

- Sloof uk. 250 x 400 mm


1 Galian m3
a. Labour
130.95 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

130.95 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
a. Materials
15.71 1.20 m3 m3 - Pasir
b. Labour
3.93 0.30 - Pekerja
0.13 0.01 - Mandor

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
11.92 0.91 m3 m3 - Batu krikil
59.45 4.54 zak zak - P. Cement
7.07 0.54 m3 m3 - Pasir
b. Labour
13.23 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
13.10 1.00 m3 m3 - Lory, timber, ducting etc.
-

4 Bekesting m2
a Materials
5.59 0.012 m3 m3 - SK Wood
158.30 0.34 pcs pcs - Triplex 12 mm thick
186.24 0.40 kg kg - Nails
b. Labour
465.60 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
465.60 1.00 m2 m2 - Tools

5 Besi Beton Kg
a. Materials
10,679.38 1.03 kg kg - Rebar U32
207.37 0.02 kg kg - Bindraad
b. Labour
10,368.33 1.00 kg kg - Fabricatiom, Installation
10,368.33 1.00 kg kg - Transportation & lifting
c. Equipment
10,368.33 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-125 m3


a. Material
59.58 0.91 m3 m3 - Batu krikil
297.26 4.54 zak zak - P. Cement
35.36 0.54 m3 m3 - Pasir
b. Labour
66.13 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

65.48 1.00 m3 m3 - Lory, timber, ducting etc.

- Lantai t = 150 mm
1 Pasir Urug t = 5 cm m3
a. Materials
518.40 1.20 m3 m3 - Pasir
b. Labour
129.60 0.30 - Pekerja
4.32 0.01 - Mandor

2 Lantai Kerja K-125 t = 5 cm m3


a. Materials
393.12 0.91 m3 m3 - Batu krikil
1,961.28 4.54 zak zak - P. Cement
233.28 0.54 m3 m3 - Pasir
b. Labour
436.32 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
432.00 1.00 m3 m3 - Lory, timber, ducting etc.
-

3 Wiremesh M-7 ( 1 Layer ) m2


1 Materials
8,812.80 1.02 m2 m2 - BRC Mesh M-7
432.00 0.05 Kg Kg - Chair (Besi Beton dia. 8 mm)
2 Labour Cost
8,640.00 1.00 m2 m2 - Install, Lifting
3 Equipment
8,640.00 1.00 m2 m2 - Supporting Tools

4 Cor beton lantai K-225 m3


a. Material
1,101.60 0.85 m3 m3 - Batu krikil
11,016.00 8.5 zak zak - P. Cement
712.80 0.55 m3 m3 - Pasir
b. Labour
1,308.96 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
1,296.00 1.00 m3 m3 - Lory, timber, ducting etc.

5 Bekesting m2
a Materials
2.67 0.012 m3 m3 - SK Wood
75.74 0.34 pcs pcs - Triplex 12 mm thick
89.10 0.40 kg kg - Nails
b. Labour
222.75 1.00 m2 m2 - Fabrication, Installation, Remove
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

c. Equipment
222.75 1.00 m2 m2 - Tools

B. Bangunan Baja
- Pekerjaan Struktur Baja
1 WF-350x175x7x11 Kg
1 Material
113,617.73 1.01 kg kg - WF-350x175x7x11
1,349.91 0.012 kg kg Welding Electroda
2 Labour
112,492.80 1.00 kg kg - Fabrication, Installation
3 Equipment
112,492.80 1.00 ls kg - Transportation Cost
112,492.80 1.00 ls kg - Steel Structure Tools

2 WF-300x150x6,5x9 Kg
1 Material
22,691.06 1.01 kg kg - WF-300x150x6,5x9
269.60 0.012 kg kg Welding Electroda
2 Labour
22,466.40 1.00 kg kg - Fabrication, Installation
3 Equipment
22,466.40 1.00 ls kg - Transportation Cost
22,466.40 1.00 ls kg - Steel Structure Tools

3 UNP-125x65x6 Kg
1 Material
5,927.89 1.01 kg kg - UNP-125x65x6
70.43 0.012 kg kg Welding Electroda
2 Labour
5,869.20 1.00 kg kg - Fabrication, Installation
3 Equipment
5,869.20 1.00 ls kg - Transportation Cost
5,869.20 1.00 ls kg - Steel Structure Tools

4 CNP-150x50x20x2,3 Kg
1 Material
49,631.60 1.01 kg kg - CNP-150x50x20x2,3
589.68 0.012 kg kg Welding Electroda
2 Labour
49,140.20 1.00 kg kg - Fabrication, Installation
3 Equipment
49,140.20 1.00 ls kg - Transportation Cost
49,140.20 1.00 ls kg - Steel Structure Tools

5 CNP-125x50x20x2,3 Kg
1 Material
2,299.16 1.01 kg kg - CNP-125x50x20x2,3
27.32 0.012 kg kg Welding Electroda
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

2 Labour
2,276.40 1.00 kg kg - Fabrication, Installation
3 Equipment
2,276.40 1.00 ls kg - Transportation Cost
2,276.40 1.00 ls kg - Steel Structure Tools

6 Plat t 15 mm Kg
1 Material
1,166.55 1.01 kg kg - Plat t 15 mm
13.86 0.012 kg kg Welding Electroda
2 Labour
1,155.00 1.00 kg kg - Fabrication, Installation
3 Equipment
1,155.00 1.00 ls kg - Transportation Cost
1,155.00 1.00 ls kg - Steel Structure Tools

7 Plat t 12 mm Kg
1 Material
3,699.02 1.01 kg kg - Plat t 12 mm
43.95 0.012 kg kg Welding Electroda
2 Labour
3,662.40 1.00 kg kg - Fabrication, Installation
3 Equipment
3,662.40 1.00 ls kg - Transportation Cost
3,662.40 1.00 ls kg - Steel Structure Tools

8 Plat t 10 mm Kg
1 Material
5,029.21 1.01 kg kg - Plat t 10 mm
59.75 0.012 kg kg Welding Electroda
2 Labour
4,979.42 1.00 kg kg - Fabrication, Installation
3 Equipment
4,979.42 1.00 ls kg - Transportation Cost
4,979.42 1.00 ls kg - Steel Structure Tools

9 Plat t 8 mm Kg
1 Material
940.41 1.01 kg kg - Plat t 8 mm
11.17 0.012 kg kg Welding Electroda
2 Labour
931.10 1.00 kg kg - Fabrication, Installation
3 Equipment
931.10 1.00 ls kg - Transportation Cost
931.10 1.00 ls kg - Steel Structure Tools

10 Plat t 6 mm Kg
1 Material
2,328.68 1.01 kg kg - Plat t 6 mm
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

27.67 0.012 kg kg Welding Electroda


2 Labour
2,305.63 1.00 kg kg - Fabrication, Installation
3 Equipment
2,305.63 1.00 ls kg - Transportation Cost
2,305.63 1.00 ls kg - Steel Structure Tools

11 L-50x50x5 Kg
1 Material
23,406.75 1.01 kg kg - L-50x50x5
278.10 0.012 kg kg Welding Electroda
2 Labour
23,175.00 1.00 kg kg - Fabrication, Installation
3 Equipment
23,175.00 1.00 ls kg - Transportation Cost
23,175.00 1.00 ls kg - Steel Structure Tools

12 Besi Beton dia. 16 mm Kg


1 Material
3,446.93 1.01 kg kg - Besi Beton dia. 16 mm
40.95 0.012 kg kg Welding Electroda
2 Labour
3,412.80 1.00 kg kg - Fabrication, Installation
3 Equipment
3,412.80 1.00 ls kg - Transportation Cost
3,412.80 1.00 ls kg - Steel Structure Tools

13 Tie Rod dia. 12 mm Pcs


1 Material
2,916.88 1.01 Pcs Pcs - Tie Rod dia. 12 mm
2 Labour
2,859.12 1.00 kg kg - Installation
3 Equipment
2,859.12 1.00 ls kg - Transportation Cost
2,888.00 1.00 ls kg - Steel Structure Tools

14 Anchor Bolt dia. 5/8" Pcs


1 Material
368.00 1.00 pcs pcs - Anchor Bolt dia.16 mm - 50 cm
2 Labour
368.00 1.00 pcs pcs - Setting
3 Equipment
368.00 1.00 pcs pcs - Transportation

15 Turn Bucles dia. 5/8" Pcs


1 Material
80.80 1.01 Pcs Pcs - Turn Bucles dia. 5/8"
3 Equipment
80.00 1.00 ls ls - Steel Structure Tools
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

80.00 1.00 kg kg - Transportation Cost

16 Baut dia. 5/8" Pcs


1 Material
2,969.40 1.01 Pcs Pcs - Baut dia. 5/8"
3 Equipment
2,940.00 1.00 ls ls - Steel Structure Tools
2,940.00 1.00 kg kg - Transportation Cost

17 Baut dia. ½" Pcs


1 Material
9,077.88 1.01 Pcs Pcs - Baut dia. ½"
3 Equipment
8,988.00 1.00 ls ls - Steel Structure Tools
8,988.00 1.00 kg kg - Transportation Cost

18 Baut seng dia. 6 mm Pcs


1 Material
28,104.26 1.01 Pcs Pcs - Baut seng dia. 6 mm
3 Equipment
27,826.00 1.00 ls ls - Steel Structure Tools
27,826.00 1.00 kg kg - Transportation Cost

19 Talang datar galvalume t=0.5 mm m'


1 Material
290.88 1.01 Pcs Pcs - Talang datar galvalume t=0.5 mm
2 Labour
288.00 1.00 kg M' - Installation & Fabrication
3 Equipment
288.00 1.00 ls ls - Tools
288.00 1.00 kg ls - Transportation Cost

20 Atap Primadeck t = 0.45 mm m2


1 Material zincalume 0,45 TCT
10,919.10 1.02 m2 m2 - Atap Primadeck t = 0.45 mm
2 Labour
10,705.00 1.00 m2 m2 - Install, Lifting, Fixing
3 Equipment
10,705.00 1.00 m2 m2 - Supporting Tools & Transportation

21 Clading Primadeck t = 0.40 mm m2


1 Material
1,696.80 1.01 m2 m2 - Clading Primadeck t = 0.40 mm
2 Labour
1,680.00 1.00 m2 m2 - Install
3 Equipment
1,680.00 1.00 ls ls - Supporting Tools
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

22 Rabung Galvalume m'


1 Material
309.06 1.01 SheetsSheets - Rabung Galvalume
2 Labour
306.00 1.00 m2 m2 - Installation & Fabrication
3 Equipment
306.00 1.00 ls ls - Supporting Tools
306.00 1.00 ls ls - Transportation Cost

23 Flashing Galvalume m'


1 Material
448.44 1.01 SheetsSheets - Flashing Galvalume
2 Labour
444.00 1.00 m2 m2 - Installation & Fabrication
3 Equipment
444.00 1.00 ls ls - Supporting Tools
444.00 1.00 ls ls - Transportation Cost

24 Talang PVC dia. 4" Ttk


1 Material
68.68 1.01 SheetsSheets - Talang PVC dia. 4"
2 Labour
68.00 1.00 m2 m2 - Installation & Fabrication
3 Equipment
68.00 1.00 ls ls - Supporting Tools
68.00 1.00 ls ls - Transportation Cost

25 Cleam Talang Pcs


1 Material
343.40 1.01 Pcs Pcs - Cleam Talang
2 Labour
340.00 1.00 m2 m2 - Installation & Fabrication
3 Equipment
340.00 1.00 ls ls - Supporting Tools
340.00 1.00 ls ls - Transportation Cost

26 Painting Material Baja Kg


1 Material
2,318.66 0.010 Kg Kg - Primer (Kansai)
4,637.33 0.020 Kg Kg - Finish (Bee Brand)
2 Labour
231,866.35 1.00 Kg Kg - Primer & Finish
3 Equipment
231,866.35 1.00 ls ls - Supporting Tools

KANTOR DALAM PABRIK


A. Pekerjaan Sipil
- Pekerjaan Pasangan dinding Lantai dasar
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

1 Pasangan dinding ½ bata 1:4 m2


1 Materials
6,746.04 63.00 pcs pcs - Brick
1,484.13 13.86 kg kg - Portland Cement
4.28 0.040 m3 m3 - Pasir
2 Labour
107.08 1.00 m2 m2 - Brick Work
3 Equipment
107.08 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

2 Plasteran m2
1 Materials
1,272.11 5.94 kg kg - Portland Cement
4.50 0.021 m3 m3 - Pasir
2 Labours
214.16 1.00 m2 m2 - Cement Plaster
3 Equipment
214.16 1.00 m2 m2 - Supporting Tools

- Pekerjaan pasangan Kosen Pintu dan Jendela


1 Kosen & Pintu Panel Uk. 1200x2100 Bh
1 Material
1.01 1.01 Sheets Unit - Kosen & Pintu Panel Uk. 1200x2100
2 Labour
1.00 1.00 m2 Unit - Installation & Setting
3 Equipment
1.00 1.00 ls ls - Supporting Tools

2 Jalusi Lubang Angin Bh


1 Material
14.14 1.01 Sheets unit - Jalusi Lubang Angin
2 Labour
14.00 1.00 m2 unit - Installation & Setting
3 Equipment
14.00 1.00 ls ls - Supporting Tools

- Pekerjaan Pengecatan
1 Cat Tembok Ex. Vinilex m2
1 Material
30.20 0.141 kg kg Cat dasar Kimex
60.82 0.284 kg kg Cat Finish Vinilex
2 Labour
214.16 1 Upah
3 Equipment
214.16 1.00 ls ls - Supporting Tools

2 Cat Pintu Panel Bh


1 Material
1.00 1 kg kg Dempul
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

1.00 1 kg kg Cat Finish Bee Brand


2 Labour
1.00 1 Upah
3 Equipment
1.00 1.00 ls ls - Supporting Tools

3 Cat Jalusi Lubang Angin Bh


1 Material
14.00 1 kg kg Dempul
14.00 1 kg kg Cat Finish Bee Brand
2 Labour
14.00 1 unit Upah
3 Equipment
14.00 1.00 ls ls - Supporting Tools

- Pekerjaan Pasangan dinding Lantai dua


1 Pasangan dinding ½ bata 1:4 m2
1 Materials
10,105.20 63.00 pcs pcs - Brick
2,223.14 13.86 kg kg - Portland Cement
6.42 0.040 m3 m3 - Pasir
2 Labour
160.40 1.00 m2 m2 - Brick Work
3 Equipment
160.40 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

2 Plasteran m2
1 Materials
1,905.55 5.94 kg kg - Portland Cement
6.74 0.021 m3 m3 - Pasir
2 Labours
320.80 1.00 m2 m2 - Cement Plaster
3 Equipment
320.80 1.00 m2 m2 - Supporting Tools

- Pekerjaan pasangan Kosen Pintu dan Jendela


1 Kusen Jendela + Jalusi 4 Lubang, Rangka Bh
Allumunium (Lokal) dan daun kaca gelap 5 mm
1 Material
5.00 1.00 Set Set - Kusen + Jendela + Jalusi (Allumunium)
2 Labour
5.00 1.00 m2 Unit - Installation
3 Equipment
5.00 1.00 ls ls - Supporting Tools

2 Kusen pintu & jendela gendong 2 daun rangka Bh


allumunium (lokal), daun pintu, daun jendela
allumunium (lokal) + kaca gelap 5 mm
1 Material
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

1.00 1.00 Set Set - Kusen + Jendela gendong (Allumunium)


2 Labour
1.00 1.00 m2 Unit - Installation
3 Equipment
1.00 1.00 ls ls - Supporting Tools

- Pekerjaan Pasangan Plafond


1 Plafond Tripleks t = 3 mm rangka kayu m2
1 Material
0.86 0.012 m3 m3 - Kayu meranti
72.00 1 lbr lbr - Asbes / eternit
72.00 1 btg btg - Lat asbes
1.44 0.02 kg kg - Paku asbes
14.40 0.2 kg kg - Nails
2 Labour
75.60 1.05 m2 - Fabrication and Instalation
3 Equipment
72.00 1 Ls - Supporting Tools

2 Profil sudut kayu m'


1 Material
36.00 1 btg btg - Profil sudut kayu
0.72 0.02 kg kg - Paku asbes
7.20 0.2 kg kg - Nails
2 Labour
36.00 1 m' - Fabrication and Instalation
3 Equipment
36.00 1 Ls - Supporting Tools

- Pekerjaan Pengecatan
1 Pengecatan dinding ½ bata m2
1 Material
45.23 0.141 kg kg Cat dasar Kimex
91.11 0.284 kg kg Cat Finish Vinilex
2 Labour
320.80 1 m2 Upah
3 Equipment
320.80 1.00 ls ls - Supporting Tools

2 Pengecatan plafond tripliex m2


1 Material
10.15 0.141 kg kg Cat dasar Kimex
20.45 0.284 kg kg Cat Finish Vinilex
2 Labour
72.00 1 m2 Upah
3 Equipment
72.00 1.00 ls ls - Supporting Tools

3 Pengecatan profil kayu m'


Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

1 Material
5.08 0.141 kg kg Cat dasar Kimex
10.22 0.284 kg kg Cat Finish Vinilex
2 Labour
36.00 1 m2 Upah
3 Equipment
36.00 1.00 ls ls - Supporting Tools

- Pekerjaan Beton Lantai


1 Cor beton t = 15 cm K-175 m2
a. Material
8.86 0.82 m3 m3 - Batu krikil
73.44 6.8 zak zak - P. Cement
5.83 0.54 m3 m3 - Pasir
b. Labour
10.91 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
10.80 1.00 m3 m3 - Lory, timber, ducting etc.

2 Besi beton dia. 12 mm Kg


a. Materials
1,753.36 1.03 kg kg - Rebar U32
34.05 0.02 kg kg - Bindraad
b. Labour
1,702.29 1.00 kg kg - Fabricatiom, Installation
1,702.29 1.00 kg kg - Transportation & lifting
c. Equipment
1,702.29 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

3 Bekesting lantai m2
a Materials
0.86 0.012 m3 m3 - SK Wood
24.48 0.34 pcs pcs - Triplex 12 mm thick
28.80 0.40 kg kg - Nails
b. Labour
72.00 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
72.00 1.00 m2 m2 - Tools

- Pekerjaan Beton Ring Balok uk. 250 x 200


1 Beton K-175 m3
a. Material
0.89 0.82 m3 m3 - Batu krikil
7.34 6.8 zak zak - P. Cement
0.58 0.54 m3 m3 - Pasir
b. Labour
1.09 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
1.08 1.00 m3 m3 - Lory, timber, ducting etc.
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

2 Besi beton Kg
a. Materials
173.16 1.03 kg kg - Rebar U32
3.36 0.02 kg kg - Bindraad
b. Labour
168.12 1.00 kg kg - Fabricatiom, Installation
168.12 1.00 kg kg - Transportation & lifting
c. Equipment
168.12 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

3 Bekesting m2
a Materials
0.26 0.012 m3 m3 - SK Wood
7.24 0.34 pcs pcs - Triplex 12 mm thick
8.52 0.40 kg kg - Nails
b. Labour
21.30 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
21.30 1.00 m2 m2 - Tools

- Pekerjaan Pondasi Tangga


1 Pondasi tiang pipa dia. 4" Unit
1 Material
1.01 1.01 Sheets Btg - Pipa dia. 4"
0.91 0.91 m3 m3 - Batu krikil
4.54 4.54 zak zak - P. Cement
0.54 0.54 m3 m3 - Pasir
1.01 1.01 Pcs Pcs - Anchor bolt 5/8"
2 Labour
1.00 1.00 m2 Unit - Civil Work
1.00 1.00 Set Unit Steel work (Pipe)
3 Equipment
1.00 1.00 ls ls - Supporting Tools

2 Pondasi tiang UNP-125x65x6 Unit


1 Material
1.01 1.01 SheetsSheets - UNP.125.65.6
0.91 0.91 m3 m3 - Batu krikil
4.54 4.54 zak zak - P. Cement
0.54 0.54 m3 m3 - Pasir
1.01 1.01 Pcs Pcs - Anchor bolt 5/8"
2 Labour
1.00 1.00 m2 Unit - Civil Work
2.00 2.00 Btg Unit Steel work (Pipe)
3 Equipment
1.00 1.00 ls ls - Supporting Tools

B. Bangunan Baja
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

- Pekerjaan Konstruksi Baja Gelagar


1 WF-350x175x7x11 Kg
1 Material
911.75 1.01 kg kg - WF-350x175x7x11
10.83 0.012 kg kg Welding Electroda
2 Labour
902.72 1.00 kg kg - Fabrication, Installation
3 Equipment
902.72 1.00 ls ls - Steel Structure Tools
902.72 1.00 kg kg - Transportation Cost

2 WF-300x150x6,5x9 Kg
1 Material
4,892.84 1.01 kg kg - WF-300x150x6,5x9
58.13 0.012 kg kg Welding Electroda
2 Labour
4,844.40 1.00 kg kg - Fabrication, Installation
3 Equipment
4,844.40 1.00 ls ls - Steel Structure Tools
4,844.40 1.00 kg kg - Transportation Cost

3 Plat t = 16 mm Kg
1 Material
376.73 1.01 kg kg - Plat t = 16 mm
4.48 0.012 kg kg Welding Electroda
2 Labour
373.00 1.00 kg kg - Fabrication, Installation
3 Equipment
373.00 1.00 ls ls - Steel Structure Tools
373.00 1.00 kg kg - Transportation Cost

4 Besi Beton dia. 12 mm anchor c/c 300 mm Kg


1 Material
46.46 1.01 kg kg - Besi Beton dia. 12 mm anchor c/c 300 mm
0.55 0.012 kg kg Welding Electroda
2 Labour
46.00 1.00 kg kg - Fabrication, Installation
3 Equipment
46.00 1.00 ls ls - Steel Structure Tools
46.00 1.00 kg kg - Transportation Cost

5 Baut anchor dia. 22 mm Pcs


1 Material
8.00 1.00 pcs pcs - Baut anchor dia. 22 mm
2 Labour
8.00 1.00 pcs pcs - Setting
3 Equipment
8.00 1.00 pcs pcs - Transportation
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

6 Baut dia. 3/4" Pcs


1 Material
109.08 1.01 Pcs Pcs - Baut dia. 3/4"
3 Equipment
108.00 1.00 ls ls - Steel Structure Tools
108.00 1.00 kg Pcs - Transportation Cost

7 Painting material Baja Kg


1 Material
61.66 0.010 Kg Kg - Primer (Kansai)
123.32 0.020 Kg Kg - Finish (Bee Brand)
2 Labour
6,166.12 1.00 Kg Kg - Primer & Finish
3 Equipment
6,166.12 1.00 ls ls - Supporting Tools

- Pekerjaan Konstruksi Baja Tangga


1 WF-350x175x7x11 Kg
1 Material
150.29 1.01 kg kg - WF-350x175x7x11
1.79 0.012 kg kg Welding Electroda
2 Labour
148.80 1.00 kg kg - Fabrication, Installation
3 Equipment
148.80 1.00 ls ls - Steel Structure Tools
148.80 1.00 kg kg - Transportation Cost

2 UNP-125x65x6 Kg
1 Material
406.02 1.01 kg kg - UNP-125x65x6
4.82 0.012 kg kg Welding Electroda
2 Labour
402.00 1.00 kg kg - Fabrication, Installation
3 Equipment
402.00 1.00 ls ls - Steel Structure Tools
402.00 1.00 kg kg - Transportation Cost

3 Pipa Medium dia. 4" Kg


1 Material
12.32 1.01 kg kg - Pipa Medium dia. 4"
0.15 0.012 kg kg Welding Electroda
2 Labour
12.20 1.00 kg kg - Fabrication, Installation
3 Equipment
12.20 1.00 ls ls - Steel Structure Tools
12.20 1.00 kg kg - Transportation Cost

4 Pipa dia 1½" t = 2,9 mm Kg


1 Material
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

119.87 1.01 kg kg - Pipa dia 1½" t = 2,9 mm


1.42 0.012 kg kg Welding Electroda
2 Labour
118.68 1.00 kg kg - Fabrication, Installation
3 Equipment
118.68 1.00 ls ls - Steel Structure Tools
118.68 1.00 kg kg - Transportation Cost

5 Pipa dia. 2" t = 2,9 mm Kg


1 Material
124.53 1.01 kg kg - Pipa dia. 2" t = 2,9 mm
1.48 0.012 kg kg Welding Electroda
2 Labour
123.30 1.00 kg kg - Fabrication, Installation
3 Equipment
123.30 1.00 ls ls - Steel Structure Tools
123.30 1.00 kg kg - Transportation Cost

6 L-65x65x6 Kg
1 Material
35.86 1.01 kg kg - L-65x65x6
0.43 0.012 kg kg Welding Electroda
2 Labour
35.50 1.00 kg kg - Fabrication, Installation
3 Equipment
35.50 1.00 ls ls - Steel Structure Tools
35.50 1.00 kg kg - Transportation Cost

7 Plat Bunga t = 6 mm Kg
1 Material
348.45 1.01 kg kg - Plat Bunga t = 6 mm
4.14 0.012 kg kg Welding Electroda
2 Labour
345.00 1.00 kg kg - Fabrication, Installation
3 Equipment
345.00 1.00 ls ls - Steel Structure Tools
345.00 1.00 kg kg - Transportation Cost

8 Plat Tapak 16 mm Kg
1 Material
376.73 1.01 kg kg - Plat Tapak 16 mm
4.48 0.012 kg kg Welding Electroda
2 Labour
373.00 1.00 kg kg - Fabrication, Installation
3 Equipment
373.00 1.00 ls ls - Steel Structure Tools
373.00 1.00 kg kg - Transportation Cost

9 Plat t = 6mm Kg
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

1 Material
9.85 1.01 kg kg - Plat t = 6mm
0.12 0.012 kg kg Welding Electroda
2 Labour
9.75 1.00 kg kg - Fabrication, Installation
3 Equipment
9.75 1.00 ls ls - Steel Structure Tools
9.75 1.00 kg kg - Transportation Cost

10 Baut dia. ½" Pcs


1 Material
20.20 1.01 Pcs Pcs - Baut dia. ½"
3 Equipment
20.00 1.00 ls ls - Steel Structure Tools
20.00 1.00 kg Pcs - Transportation Cost

11 Baut Anchor dia. 5/8" Pcs


1 Material
8.00 1.00 pcs pcs - Anchor Bolt dia.16 mm - 50 cm
2 Labour
8.00 1.00 pcs pcs - Setting
3 Equipment
8.00 1.00 pcs pcs - Transportation

12 Painting Material Baja Kg


1 Material
15.68 0.010 Kg Kg - Primer (Kansai)
31.36 0.020 Kg Kg - Finish (Bee Brand)
2 Labour
1,568.23 1.00 Kg Kg - Primer & Finish
3 Equipment
1,568.23 1.00 ls ls - Supporting Tools

III BANGUNAN KLIN DRIER


A. Pekerjaan Sipil
- Pondasi F1 = 44 Units
1 Galian Pondasi m3
a. Labour
63.36 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
63.36 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
a. Materials
3.80 1.20 m3 m3 - Pasir
b. Labour
0.95 0.30 - Pekerja
0.03 0.01 - Mandor
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
2.88 0.91 m3 m3 - Batu krikil
14.38 4.54 zak zak - P. Cement
1.71 0.54 m3 m3 - Pasir
b. Labour
3.20 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
3.17 1.00 m3 m3 - Lory, timber, ducting etc.
-

4 Bekesting m2
a Materials
1.23 0.012 m3 m3 - SK Wood
34.75 0.34 pcs pcs - Triplex 12 mm thick
40.88 0.40 kg kg - Nails
b. Labour
102.21 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
102.21 1.00 m2 m2 - Tools

5 Besi Beton Kg
a. Materials
2,062.24 1.03 kg kg - Rebar U32
40.04 0.02 kg kg - Bindraad
b. Labour
2,002.18 1.00 kg kg - Fabricatiom, Installation
2,002.18 1.00 kg kg - Transportation & lifting
c. Equipment
2,002.18 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-225 m3


a. Material
13.20 0.85 m3 m3 - Batu krikil
132.02 8.5 zak zak - P. Cement
8.54 0.55 m3 m3 - Pasir
b. Labour
15.69 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
15.53 1.00 m3 m3 - Lory, timber, ducting etc.

7 Timbunan Kembali Bekas Galian m3


a. Material
57.39 1.2 m3 m3 - Tanah merah
b. Labour
11.96 0.25 - Pekerja
0.48 0.01 - Mandor
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

- Pekerjaan Sloof uk. 200 x 300 mm


1 Galian m3
a. Labour
39.30 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
39.30 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
a. Materials
7.86 1.20 m3 m3 - Pasir
b. Labour
1.97 0.30 - Pekerja
0.07 0.01 - Mandor

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
5.96 0.91 m3 m3 - Batu krikil
29.74 4.54 zak zak - P. Cement
3.54 0.54 m3 m3 - Pasir
b. Labour
6.62 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
6.55 1.00 m3 m3 - Lory, timber, ducting etc.
-

4 Bekesting m2
a Materials
2.36 0.012 m3 m3 - SK Wood
66.81 0.34 pcs pcs - Triplex 12 mm thick
78.60 0.40 kg kg - Nails
b. Labour
196.51 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
196.51 1.00 m2 m2 - Tools

5 Besi Beton Kg
a. Materials
5,596.40 1.03 kg kg - Rebar U32
108.67 0.02 kg kg - Bindraad
b. Labour
5,433.40 1.00 kg kg - Fabricatiom, Installation
5,433.40 1.00 kg kg - Transportation & lifting
c. Equipment
5,433.40 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-225 m3


a. Material
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

16.70 0.85 m3 m3 - Batu krikil


167.03 8.5 zak zak - P. Cement
10.81 0.55 m3 m3 - Pasir
b. Labour
19.85 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
19.65 1.00 m3 m3 - Lory, timber, ducting etc.

7 Timbunan Kembali Bekas Galian m3


a. Material
29.09 1.2 m3 m3 - Tanah merah
b. Labour
6.06 0.25 - Pekerja
0.24 0.01 - Mandor

- Pekerjaan pondasi menerus


1 Galian m3
a. Labour
56.20 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
56.20 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
a. Materials
5.62 1.20 m3 m3 - Pasir
b. Labour
1.40 0.30 - Pekerja
0.05 0.01 - Mandor

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
4.26 0.91 m3 m3 - Batu krikil
21.26 4.54 zak zak - P. Cement
2.53 0.54 m3 m3 - Pasir
b. Labour
4.73 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
4.68 1.00 m3 m3 - Lory, timber, ducting etc.
-

4 Bekesting m2
a Materials
2.53 0.012 m3 m3 - SK Wood
71.65 0.34 pcs pcs - Triplex 12 mm thick
84.29 0.40 kg kg - Nails
b. Labour
210.74 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

210.74 1.00 m2 m2 - Tools

5 Besi Beton Kg
a. Materials
1,470.97 1.03 kg kg - Rebar U32
28.56 0.02 kg kg - Bindraad
b. Labour
1,428.13 1.00 kg kg - Fabricatiom, Installation
1,428.13 1.00 kg kg - Transportation & lifting
c. Equipment
1,428.13 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-225 m3


a. Material
9.55 0.85 m3 m3 - Batu krikil
95.54 8.5 zak zak - P. Cement
6.18 0.55 m3 m3 - Pasir
b. Labour
11.35 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
11.24 1.00 m3 m3 - Lory, timber, ducting etc.

7 Pasangan dinding ½ bata 1:4 m2


1 Materials
99,466.92 63.00 pcs pcs - Brick
21,882.72 13.86 kg kg - P. Cement
63.15 0.040 m3 m3 - Pasir
2 Labour
1,578.84 1.00 m2 m2 - Brick Work
3 Equipment
1,578.84 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

8 Plasteran m2
1 Materials
18,756.62 5.94 kg kg - Portland Cement
66.31 0.021 m3 m3 - Pasir
2 Labours
3,157.68 1.00 m2 m2 - Cement Plaster
3 Equipment
3,157.68 1.00 m2 m2 - Supporting Tools

9 Cor Beton K-175 m3


a. Material
6.53 0.82 m3 m3 - Batu krikil
54.16 6.8 zak zak - P. Cement
4.30 0.54 m3 m3 - Pasir
b. Labour
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

8.04 1.01 m3 m3 - Pouring Concrete, Cleaning


c. Equipment
7.97 1.00 m3 m3 - Lory, timber, ducting etc.

- Pekerjaan lantai bangunan t = 150 mm


1 Pasir Urug t = 5 cm m3
a. Materials
159.16 1.20 m3 m3 - Pasir
b. Labour
39.79 0.30 - Pekerja
1.33 0.01 - Mandor

2 Lantai Kerja K-125 t = 5 cm m3


a. Materials
120.70 0.91 m3 m3 - Batu krikil
602.16 4.54 zak zak - P. Cement
71.62 0.54 m3 m3 - Pasir
b. Labour
133.96 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
132.63 1.00 m3 m3 - Lory, timber, ducting etc.
-

3 Wiremesh M-7 (1 Layer) m2


1 Materials
2,705.73 1.02 m2 m2 - BRC Mesh M-7
132.63 0.05 Kg Kg - Chair (besi Beton dia.8 mm)
2 Labour Cost
2,652.68 1.00 m2 m2 - Install, Lifting
3 Equipment
2,652.68 1.00 m2 m2 - Supporting Tools

4 Cor Beton lantai K-225 t=150 mm m3


a. Material
295.72 0.85 m3 m3 - Batu krikil
2,957.17 8.5 zak zak - P. Cement
191.35 0.55 m3 m3 - Pasir
b. Labour
351.38 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
347.90 1.00 m3 m3 - Lory, timber, ducting etc.

5 Bekesting m2
a Materials
0.82 0.012 m3 m3 - SK Wood
23.12 0.34 pcs pcs - Triplex 12 mm thick
27.20 0.40 kg kg - Nails
b. Labour
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

68.00 1.00 m2 m2 - Fabrication, Installation, Remove


c. Equipment
68.00 1.00 m2 m2 - Tools

- Pekerjaan Saluran Terbuka


1 Galian m3
a. Labour
77.73 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
77.73 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
a. Materials
8.80 1.20 m3 m3 - Pasir
b. Labour
2.20 0.30 - Pekerja
0.07 0.01 - Mandor

3 Pasangan dinding ½ bata 1:4 m2


1 Materials
16,323.68 63.00 pcs pcs - Brick
3,591.21 13.86 kg kg - P. Cement
10.36 0.040 m3 m3 - Pasir
2 Labour
259.11 1.00 m2 m2 - Brick Work
3 Equipment
259.11 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

4 Plasteran m2
1 Materials
1,974.69 5.94 kg kg - Portland Cement
6.98 0.021 m3 m3 - Pasir
2 Labours
332.44 1.00 m2 m2 - Cement Plaster
3 Equipment
332.44 1.00 m2 m2 - Supporting Tools

B. Bangunan Baja
- Pekerjaan Struktur Baja
1 WF-250x125x6x9 Kg n/a
2 WF-200x100x5.5x8 Kg n/a
3 UNP-125x65x6 Kg n/a
4 UNP-125x50x5 Kg n/a
5 CNP-150x50x20x2. Kg n/a
6 L.50.50.5 Kg n/a
7 Plat t = 15 mm Kg n/a
8 Plat t = 10 mm Kg n/a
9 Plat t = 8 mm Kg n/a
10 Plat t = 6 mm Kg n/a
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

11 Besi Beton dia. 16 Kg n/a


12 Baut dia. 5/8" Pcs n/a
13 Baut dia. ½" Pcs n/a
14 Anchor bolt dia. 5/8 Pcs n/a
15 Turn Bucles dia. 5/8 Pcs n/a
16 Tie Rod dia. 12 mm Pcs n/a
17 Baut atap & Clading Pcs n/a
18 Atap Spandek Zinc m2 n/a
19 Clading spandek zi m2 n/a
20 Rabung Galvalume m' n/a
21 Flashing Galvalume m' n/a
22 Talang datar galva m' n/a
23 Talang tegak PVC 4"
- Bawah P=4,5 m ttk n/a
- Tengah P=2,5 m ttk n/a
- Atas P=1,5 m ttk n/a
23 Dinding ventilasi tinggi 2m P=2x90m
- L-60.60.6 Kg n/a
- Besi Beton dia. 1 Kg n/a
- Plat t = 8 mm Kg n/a
- Baut dia. 5/8" Pcs n/a
24 Pintu swing (double Unit n/a
L-50.50.5, daun plat t=2.8 mm termasuk Cat
Kunci grendel & Kunci slot
25 Painting Material Ba Kg n/a
26 Transportasi Materia Kg n/a
IV RUMAH BOILER DAN BANGUNAN PENDUKUNG
A. Pekerjaan Sipil
- Pondasi F1 = 8 Units
1 Galian Pondasi m3
a. Labour
11.52 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
11.52 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
a. Materials
0.69 1.20 m3 m3 - Pasir
b. Labour
0.17 0.30 - Pekerja
0.01 0.01 - Mandor

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
0.52 0.91 m3 m3 - Batu krikil
2.62 4.54 zak zak - P. Cement
0.31 0.54 m3 m3 - Pasir
b. Labour
0.58 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
0.58 1.00 m3 m3 - Lory, timber, ducting etc.
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

4 Bekesting m2
a Materials
0.13 0.012 m3 m3 - SK Wood
3.60 0.34 pcs pcs - Triplex 12 mm thick
4.23 0.40 kg kg - Nails
b. Labour
10.58 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
10.58 1.00 m2 m2 - Tools

5 Besi Beton Kg
a. Materials
374.95 1.03 kg kg - Rebar U32
7.28 0.02 kg kg - Bindraad
b. Labour
364.03 1.00 kg kg - Fabricatiom, Installation
364.03 1.00 kg kg - Transportation & lifting
c. Equipment
364.03 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-225 m3


a. Material
2.40 0.85 m3 m3 - Batu krikil
24.00 8.5 zak zak - P. Cement
1.55 0.55 m3 m3 - Pasir
b. Labour
2.85 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
2.82 1.00 m3 m3 - Lory, timber, ducting etc.

7 Timbunan Kembali Bekas Galian m3


a. Material
10.44 1.2 m3 m3 - Tanah merah
b. Labour
2.17 0.25 - Pekerja
0.09 0.01 - Mandor

- Pondasi F2 = 4 Units
1 Galian Pondasi m3
a. Labour
5.76 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
5.76 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

a. Materials
0.35 1.20 m3 m3 - Pasir
b. Labour
0.09 0.30 - Pekerja
0.00 0.01 - Mandor

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
0.26 0.91 m3 m3 - Batu krikil
1.31 4.54 zak zak - P. Cement
0.16 0.54 m3 m3 - Pasir
b. Labour
0.29 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
0.29 1.00 m3 m3 - Lory, timber, ducting etc.
-

4 Bekesting m2
a Materials
0.10 0.012 m3 m3 - SK Wood
2.79 0.34 pcs pcs - Triplex 12 mm thick
3.28 0.40 kg kg - Nails
b. Labour
8.20 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
8.20 1.00 m2 m2 - Tools

5 Besi Beton Kg
a. Materials
187.47 1.03 kg kg - Rebar U32
3.64 0.02 kg kg - Bindraad
b. Labour
182.01 1.00 kg kg - Fabricatiom, Installation
182.01 1.00 kg kg - Transportation & lifting
c. Equipment
182.01 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-225 m3


a. Material
1.20 0.85 m3 m3 - Batu krikil
12.00 8.5 zak zak - P. Cement
0.78 0.55 m3 m3 - Pasir
b. Labour
1.43 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
1.41 1.00 m3 m3 - Lory, timber, ducting etc.

7 Timbunan Kembali Bekas Galian m3


Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

a. Material
5.22 1.2 m3 m3 - Tanah merah
b. Labour
1.09 0.25 - Pekerja
0.04 0.01 - Mandor

- Pekerjaan Sloof uk. 200 x 300 mm


1 Galian m3
a. Labour
7.20 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
7.20 1.00 m3 m3 - Excavator

2 Pasir Urug t = 5 cm m3
a. Materials
1.44 1.20 m3 m3 - Pasir
b. Labour
0.36 0.30 - Pekerja
0.01 0.01 - Mandor

3 Lantai Kerja K-125 t = 5 cm m3


a. Materials
1.09 0.91 m3 m3 - Batu krikil
5.45 4.54 zak zak - P. Cement
0.65 0.54 m3 m3 - Pasir
b. Labour
1.21 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
1.20 1.00 m3 m3 - Lory, timber, ducting etc.
-

4 Bekesting m2
a Materials
0.43 0.012 m3 m3 - SK Wood
12.24 0.34 pcs pcs - Triplex 12 mm thick
14.40 0.40 kg kg - Nails
b. Labour
36.00 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
36.00 1.00 m2 m2 - Tools

5 Besi Beton Kg
a. Materials
1,025.26 1.03 kg kg - Rebar U32
19.91 0.02 kg kg - Bindraad
b. Labour
995.40 1.00 kg kg - Fabricatiom, Installation
995.40 1.00 kg kg - Transportation & lifting
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

c. Equipment
995.40 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

6 Cor Beton K-225 m3


a. Material
0.31 0.85 m3 m3 - Batu krikil
3.06 8.5 zak zak - P. Cement
0.20 0.55 m3 m3 - Pasir
b. Labour
0.36 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
0.36 1.00 m3 m3 - Lory, timber, ducting etc.

7 Timbunan Kembali Bekas Galian m3


a. Material
5.33 1.2 m3 m3 - Tanah merah
b. Labour
1.11 0.25 - Pekerja
0.04 0.01 - Mandor

- Pekerjaan Lantai Boiler


1 Pasir urug dipadatkan t = 5 cm m3
a. Materials
12.96 1.20 m3 m3 - Pasir
b. Labour
3.24 0.30 - Pekerja
0.11 0.01 - Mandor

2 Lantai Kerja K-125 t = 5 cm m3


a. Materials
9.83 0.91 m3 m3 - Batu krikil
49.03 4.54 zak zak - P. Cement
5.83 0.54 m3 m3 - Pasir
b. Labour
10.91 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
10.80 1.00 m3 m3 - Lory, timber, ducting etc.
-

3 Primamesh M-8 (1 Layer) m2


1 Materials
220.32 1.02 m2 m2 - BRC Mesh M-8
10.80 0.05 pcs pcs - Chair (Besi Beton dia.8 mm)
2 Labour Cost
216.00 1.00 m2 m2 - Install, Lifting
3 Equipment
216.00 1.00 m2 m2 - Supporting Tools
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

4 Cor Lantai K-225 m3


a. Material
27.54 0.85 m3 m3 - Batu krikil
275.40 8.5 zak zak - P. Cement
17.82 0.55 m3 m3 - Pasir
b. Labour
32.72 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
32.40 1.00 m3 m3 - Lory, timber, ducting etc.

5 Bekesting m2
a Materials
0.22 0.012 m3 m3 - SK Wood
6.12 0.34 pcs pcs - Triplex 12 mm thick
7.20 0.40 kg kg - Nails
b. Labour
18.00 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
18.00 1.00 m2 m2 - Tools

- Pekerjaan Saluran Terbuka


1 Galian m3
a. Labour
24.55 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
24.55 1.00 m3 m3 - Excavator

2 Pasir Urug m3
a. Materials
2.78 1.20 m3 m3 - Pasir
b. Labour
0.70 0.30 - Pekerja
0.02 0.01 - Mandor

3 Pas Batu Bata m2


1 Materials
5,155.29 63.00 pcs pcs - Brick
1,134.16 13.86 kg kg - Portland Cement
3.27 0.040 m3 m3 - Pasir
2 Labour
81.83 1.00 m2 m2 - Brick Work
3 Equipment
81.83 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

4 Plasteran m2
1 Materials
623.64 5.94 kg kg - Portland Cement
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

2.20 0.021 m3 m3 - Pasir


2 Labours
104.99 1.00 m2 m2 - Cement Plaster
3 Equipment
104.99 1.00 m2 m2 - Supporting Tools

B. Bangunan Baja
- Pekerjaan Struktur Baja
1 WF-250x125x6x9 Kg
1 Material
4,898.90 1.01 kg kg - WF-250x125x6x9
58.20 0.012 kg kg Welding Electroda
2 Labour
4,850.40 1.00 kg kg - Fabrication, Installation
3 Equipment
4,850.40 1.00 ls ls - Steel Structure Tools
4,850.40 1.00 kg kg - Transportation Cost

2 WF-200x100x5.5x8 Kg
1 Material
775.68 1.01 kg kg - WF-200x100x5.5x8
9.22 0.012 kg kg Welding Electroda
2 Labour
768.00 1.00 kg kg - Fabrication, Installation
3 Equipment
768.00 1.00 ls ls - Steel Structure Tools
768.00 1.00 kg kg - Transportation Cost

3 UNP-125x65x6 Kg
1 Material
487.22 1.01 kg kg - UNP-125x65x6
5.79 0.012 kg kg Welding Electroda
2 Labour
482.40 1.00 kg kg - Fabrication, Installation
3 Equipment
482.40 1.00 ls ls - Steel Structure Tools
482.40 1.00 kg kg - Transportation Cost

4 CNP-150x50x20x2.3 Kg
1 Material
3,852.54 1.01 kg kg - CNP-150x50x20x2.3
45.77 0.012 kg kg Welding Electroda
2 Labour
3,814.40 1.00 kg kg - Fabrication, Installation
3 Equipment
3,814.40 1.00 ls ls - Steel Structure Tools
3,814.40 1.00 kg kg - Transportation Cost

5 CNP-125x50x20x2.3 Kg
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

1 Material
164.23 1.01 kg kg - CNP-125x50x20x2.3
1.95 0.012 kg kg Welding Electroda
2 Labour
162.60 1.00 kg kg - Fabrication, Installation
3 Equipment
162.60 1.00 ls ls - Steel Structure Tools
162.60 1.00 kg kg - Transportation Cost

6 Plat t = 15 mm Kg
1 Material
97.93 1.01 kg kg - Plat t = 15 mm
1.16 0.012 kg kg Welding Electroda
2 Labour
96.96 1.00 kg kg - Fabrication, Installation
3 Equipment
96.96 1.00 ls ls - Steel Structure Tools
96.96 1.00 kg kg - Transportation Cost

7 Plat t = 12 mm Kg
1 Material
282.80 1.01 kg kg - Plat t = 12 mm
3.36 0.012 kg kg Welding Electroda
2 Labour
280.00 1.00 kg kg - Fabrication, Installation
3 Equipment
280.00 1.00 ls ls - Steel Structure Tools
280.00 1.00 kg kg - Transportation Cost

8 Plat t = 8 mm & 6 mm Kg
1 Material
210.08 1.01 kg kg - Plat t = 8 mm & 6 mm
2.50 0.012 kg kg Welding Electroda
2 Labour
208.00 1.00 kg kg - Fabrication, Installation
3 Equipment
208.00 1.00 ls ls - Steel Structure Tools
208.00 1.00 kg kg - Transportation Cost

9 Besi Beton dia. 16 mm Kg


1 Material
229.80 1.01 kg kg - Besi Beton dia. 16 mm
2.73 0.012 kg kg Welding Electroda
2 Labour
227.52 1.00 kg kg - Fabrication, Installation
3 Equipment
227.52 1.00 ls ls - Steel Structure Tools
227.52 1.00 kg kg - Transportation Cost
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

10 Anchor bolt dia. 5/8" Pcs


1 Material
32.00 1.00 pcs pcs - Anchor Bolt dia.16 mm - 50 cm
2 Labour
32.00 1.00 pcs pcs - Setting
3 Equipment
32.00 1.00 pcs pcs - Transportation

11 Turn Bucles dia. 5/8" Pcs


1 Material
12.12 1.01 Pcs Pcs - Turn Bucles dia. 5/8"
3 Equipment
12.00 1.00 ls ls - Steel Structure Tools
12.00 1.00 kg kg - Transportation Cost

12 Tie Rod dia. 12 mm Pcs


1 Material
222.20 1.01 Pcs Pcs - Tie Rod dia. 12 mm
2 Labour
220.00 1.00 kg kg - Installation
3 Equipment
220.00 1.00 ls ls - Steel Structure Tools
193.60 1.00 kg kg - Transportation Cost

13 Baut dia. 5/8" Pcs


1 Material
234.32 1.01 Pcs Pcs - Baut dia. 5/8"
3 Equipment
232.00 1.00 ls ls - Steel Structure Tools
232.00 1.00 kg kg - Transportation Cost

14 Baut dia. ½" Pcs


1 Material
686.80 1.01 Pcs Pcs - Baut dia. ½"
3 Equipment
680.00 1.00 ls ls - Steel Structure Tools
680.00 1.00 kg kg - Transportation Cost

15 Baut seng dia. 6 mm Pcs


1 Material
3,213.82 1.01 Pcs Pcs - Baut seng dia. 6 mm
3 Equipment
3,182.00 1.00 ls ls - Steel Structure Tools
3,182.00 1.00 kg kg - Transportation Cost

16 Atap Primadeck t=0.45 mm m2


1 Material
401.88 1.02 m2 m2 - Atap Primadeck t=0.45 mm
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

2 Labour
394.00 1.00 m2 m2 - Install, Lifting, Fixing
3 Equipment
394.00 1.00 m2 m2 - Supporting Tools & Transportation

17 Clading Primadeck t=0.40 mm m2


1 Material
190.74 1.02 m2 m2 - Clading Primadeck t=0.40 mm
2 Labour
187.00 1.00 m2 m2 - Install, Lifting, Fixing
3 Equipment
187.00 1.00 m2 m2 - Supporting Tools & Transportation

18 Rabung Galvalume t=0.40 mm m'


1 Material
20.40 1.02 m2 m2 - Rabung Galvalume t=0.40 mm
2 Labour
20.00 1.00 m2 m2 - Install, Lifting, Fixing
3 Equipment
20.00 1.00 m2 m2 - Supporting Tools & Transportation

19 Flashing Galvalume m'


1 Material
36.72 1.02 m2 m2 - Flashing Galvalume
2 Labour
36.00 1.00 m2 m2 - Install, Lifting, Fixing
3 Equipment
36.00 1.00 m2 m2 - Supporting Tools & Transportation

20 Painting Material Baja Kg


1 Material
108.90 0.010 Kg Kg - Primer (Kansai)
217.81 0.020 Kg Kg - Finish (Bee Brand)
2 Labour
10,890.28 1.00 Kg Kg - Primer & Finish
3 Equipment
10,890.28 1.00 ls ls - Supporting Tools

V KANTIN DAN MUSHALLAH


A. Pekerjaan Sipil
- Pondasi
1 Galian m3
a. Labour
14.50 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
14.50 1.00 m3 m3 - Excavator
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

2 Pasir urug t = 5 cm m3
a. Materials
2.07 1.20 m3 m3 - Pasir
b. Labour
0.52 0.30 - Pekerja
0.02 0.01 - Mandor

3 Cor K-125 m3
a. Materials
2.87 0.91 m3 m3 - Batu krikil
14.32 4.54 zak zak - P. Cement
1.70 0.54 m3 m3 - Pasir
b. Labour
3.19 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
3.16 1.00 m3 m3 - Lory, timber, ducting etc.
-

4 Bekesting m3
a Materials
0.70 0.012 m3 m3 - SK Wood
19.94 0.34 pcs pcs - Triplex 12 mm thick
23.46 0.40 kg kg - Nails
b. Labour
58.65 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
58.65 1.00 m2 m2 - Tools

5 Cor Pondasi menerus K-175 m3


a. Material
5.84 0.82 m3 m3 - Batu krikil
48.42 6.8 zak zak - P. Cement
3.84 0.54 m3 m3 - Pasir
b. Labour
7.19 1.01 m3 m3 - Pouring Concrete, Cleaning
c. Equipment
7.12 1.00 m3 m3 - Lory, timber, ducting etc.

6 Besi Beton Kg
a. Materials
223.85 1.03 kg kg - Rebar U32
4.35 0.02 kg kg - Bindraad
b. Labour
217.33 1.00 kg kg - Fabricatiom, Installation
217.33 1.00 kg kg - Transportation & lifting
c. Equipment
217.33 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

7 Pasangan Batu Bata m2


1 Materials
2,079.00 63.00 pcs pcs - Brick
457.38 13.86 kg kg - Portland Cement
1.32 0.040 m3 m3 - Pasir
2 Labour
33.00 1.00 m2 m2 - Brick Work
3 Equipment
33.00 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

8 Plasteran m2
1 Materials
392.04 5.94 kg kg - Portland Cement
1.39 0.021 m3 m3 - Pasir
2 Labours
66.00 1.00 m2 m2 - Cement Plaster
3 Equipment
66.00 1.00 m2 m2 - Supporting Tools

- Pekerjaan lantai dan Accessories


1 Pasir urug t = 5 cm m3
a. Materials
2.10 1.20 m3 m3 - Pasir
b. Labour
0.53 0.30 - Pekerja
0.02 0.01 - Mandor

2 Cor lantai K-125 m3


a. Materials
3.19 0.91 m3 m3 - Batu krikil
15.89 4.54 zak zak - P. Cement
1.89 0.54 m3 m3 - Pasir
b. Labour
3.54 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
3.50 1.00 m3 m3 - Lory, timber, ducting etc.
-

3 Kramik 40 x 40 cm ex Roman m2
a. Materials
33.60 1.05 Ktk Ktk - Kramik 40 x 40 cm ex Roman
190.08 5.94 kg kg - Portland Cement
0.67 0.021 m3 m3 - Pasir
0.64 0.02 Kg Kg - Semen putih
b. Labour
32.00 1.00 m2 m2 - Brick Work
c. Equipment
32.00 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

4 Kramik K. mandi dinding t=15 cm + bak dan tempat ai m2


a. Materials
19.43 1.05 Ktk Ktk - Kramik K. mandi dinding t=15 cm + bak dan tempat air Wudhu
109.89 5.94 kg kg - Portland Cement
0.39 0.021 m3 m3 - Pasir
0.37 0.02 kg kg - Semen putih
b. Labour
18.50 1.00 m2 m2 - Ceramic Instalation
c. Equipment
18.50 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

5 Keramik lantai K.mandi & tempat wudhu m2


a. Materials
5.25 1.05 Ktk Ktk - Keramik lantai K.mandi & tempat wudhu
29.70 5.94 kg kg - Portland Cement
0.11 0.021 m3 m3 - Pasir
0.10 0.02 kg kg - Semen putih
b. Labour
5.00 1.00 m2 m2 - Ceramic Instalation
c. Equipment
5.00 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

6 Closed Jongkok KIA Unit


a. Materials
1.01 1.01 Ktk Ktk - Closed Jongkok KIA
5.94 5.94 kg kg - Portland Cement
0.02 0.021 m3 m3 - Pasir
0.02 0.02 kg kg - Semen putih
b. Labour
1.00 1.00 m2 m2 - Ceramic Instalation
c. Equipment
1.00 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

7 Wastafel KIA studio 50, Kran air PIO Unit


a. Materials
1.00 1 Set Set - Wastafel KIA studio 50, Kran air PIO
5.94 5.94 kg kg - Portland Cement
0.02 0.021 m3 m3 - Pasir
0.02 0.02 kg kg - Semen putih
b. Labour
1.00 1.00 m2 m2 - Ceramic Instalation
c. Equipment
1.00 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

8 Kran air biasa Unit


a. Materials
5.00 1 Pcs Pcs - Kran air biasa
29.70 5.94 kg kg - Portland Cement
0.11 0.021 m3 m3 - Pasir
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

0.10 0.02 kg kg - Semen putih


b. Labour
5.00 1.00 m2 m2 - Ceramic Instalation
c. Equipment
5.00 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

9 Pintu Panel + Kosen + Jalusi (uk. 820x210 cm) Unit


1 Material
2.02 1.01 SheetsSheets - Pintu Panel + Kosen + Jalusi (uk. 820x210 cm)
2 Labour
2.00 1.00 m2 m2 - Installation & Setting
3 Equipment
2.00 1.00 ls ls - Supporting Tools

10 Meranti Keras m3
1 Material
2.02 1.01 SheetsSheets - Meranti Keras
2 Equipment
2.00 1.00 ls ls - Supporting Tools

11 Kosen Jendela kaca nako lengkap jalusi + Fixed Unit


Clear (uk. 145x240 cm)
1 Material
2.02 1.01 SheetsSheets - Kosen Jendela
2 Labour
2.00 1.00 m2 m2 - Installation & Setting
3 Equipment
2.00 1.00 ls ls - Supporting Tools

12 Kosen Lobang angin (uk. 50 x 60 cm) Unit


1 Material
1.01 1.01 SheetsSheets - Kosen Lobang angin (uk. 50 x 60 cm)
2 Labour
1.00 1.00 m2 m2 - Installation & Setting
3 Equipment
1.00 1.00 ls ls - Supporting Tools

13 Ventilasi (uk. 70 x 100 cm) Unit


1 Material
1.01 1.01 SheetsSheets - Ventilasi (uk. 70 x 100 cm)
2 Labour
1.00 1.00 m2 m2 - Installation & Setting
3 Equipment
1.00 1.00 ls ls - Supporting Tools

14 Kayu (Meranti Keras)


- 1" x 6" m3
- 1" x 9" m3
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

- 2" x 2" m3
- 2" x 3" m3
- 2" x 4" m3

a Materials
0.19 1.010 m3 m3 - 1" x 6"
0.05 1.010 m3 m3 - 1" x 9"
0.03 1.010 m3 m3 - 2" x 2"
0.64 1.010 m3 m3 - 2" x 3"
0.10 1.010 m3 m3 - 2" x 4"
b. Labour
1.00 1 m2 m2 - Fabrication
c. Equipment
2.99 3.00 m2 m2 - Suporting Tools

15 Atap seng "BJLS" m2


1 Material
33.96 1.01 m2 m2 - Atap seng "BJLS"
2 Labour
33.63 1.00 m2 m2 - Install
3 Equipment
33.63 1.00 ls ls - Supporting Tools

16 Asbestos t=4 mm m2
1 Material
41.97 1.01 m2 m2 - Asbestos t=4 mm
2 Labour
41.55 1.00 m2 m2 - Install
3 Equipment
41.55 1.00 ls ls - Supporting Tools

17 Tripleks 4 mm m2
1 Material
64.64 1.01 m2 m2 - Tripleks 4 mm
2 Labour
64.00 1.00 m2 m2 - Install
3 Equipment
64.00 1.00 ls ls - Supporting Tools

18 Cat dinding m2
1 Material
19.04 0.141 kg kg Cat dasar (KIMEX)
38.34 0.284 kg kg Cat Finish (VINILEX)
2 Labour
135.00 1 Upah
3 Equipment
135.00 1.00 ls ls - Supporting Tools

19 Cat Plafond & Listplank m2


Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

1 Material
15.51 0.141 kg kg Cat dasar
31.24 0.284 kg kg Cat Finish
2 Labour
110.00 1 Upah
3 Equipment
110.00 1.00 ls ls - Supporting Tools

- Pekerjaan Saluran Terbuka uk. 37.2 x 0.3 m


1 Galian m3
a. Labour
20.46 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
20.46 1.00 m3 m3 - Excavator

2 Cor K-125 m3
a. Materials
1.69 0.91 m3 m3 - Batu krikil
8.44 4.54 zak zak - P. Cement
1.00 0.54 m3 m3 - Pasir
b. Labour
1.88 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
1.86 1.00 m3 m3 - Lory, timber, ducting etc.
-

3 Pasangan Batu bata m2


1 Materials
4,452.84 63.00 pcs pcs - Brick
979.62 13.86 kg kg - Portland Cement
2.83 0.040 m3 m3 - Pasir
2 Labour
70.68 1.00 m2 m2 - Brick Work
3 Equipment
70.68 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

4 Plasteran m2
1 Materials
905.97 5.94 kg kg - Portland Cement
3.20 0.021 m3 m3 - Pasir
2 Labours
152.52 1.00 m2 m2 - Cement Plaster
3 Equipment
152.52 1.00 m2 m2 - Supporting Tools

VI RUMAH JAGA
A. Pekerjaan Sipil
- Bangunan
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

1 Galian Pondasi m3
a. Labour
6.38 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
6.38 1.00 m3 m3 - Excavator

2 Pasir urug m3
a. Materials
0.91 1.20 m3 m3 - Pasir
b. Labour
0.23 0.30 - Pekerja
0.01 0.01 - Mandor

3 Bekesting m2
a Materials
0.31 0.012 m3 m3 - SK Wood
8.79 0.34 pcs pcs - Triplex 12 mm thick
10.34 0.40 kg kg - Nails
b. Labour
25.84 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
25.84 1.00 m2 m2 - Tools

4 Cor pondasi menerus K-125 m3


a. Materials
2.85 0.91 m3 m3 - Batu krikil
14.23 4.54 zak zak - P. Cement
1.69 0.54 m3 m3 - Pasir
b. Labour
3.17 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
3.14 1.00 m3 m3 - Lory, timber, ducting etc.
-

5 Cor K-175 m3
a. Materials
2.16 0.82 m3 m3 - Batu krikil
17.92 6.8 zak zak - P. Cement
1.42 0.54 m3 m3 - Pasir
b. Labour
2.66 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
2.64 1.00 m3 m3 - Lory, timber, ducting etc.
-

6 Besi Beton Kg
a. Materials
98.62 1.03 kg kg - Rebar U32
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

1.92 0.02 kg kg - Bindraad


b. Labour
95.75 1.00 kg kg - Fabricatiom, Installation
95.75 1.00 kg kg - Transportation & lifting
c. Equipment
95.75 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling

7 Pipa PVC Ø. 3" m'


a Materials
18.90 1.050 m3 m3 - Pipa PVC Ø. 3"
0.90 0.05 pcs pcs - Glue
b. Labour
18.00 1.00 m2 m2 - Installation
c. Equipment
18.00 1.00 m2 m2 - Suporting Tools

8 Pasangan Bata m2
1 Materials
957.60 63.00 pcs pcs - Brick
210.67 13.86 kg kg - Portland Cement
0.61 0.040 m3 m3 - Pasir
2 Labour
15.20 1.00 m2 m2 - Brick Work
3 Equipment
15.20 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

9 Plasteran m2
1 Materials
180.58 5.94 kg kg - Portland Cement
0.64 0.021 m3 m3 - Pasir
2 Labours
30.40 1.00 m2 m2 - Cement Plaster
3 Equipment
30.40 1.00 m2 m2 - Supporting Tools

10 Pasir dipadatkan m3
a. Materials
1.56 1.20 m3 m3 - Pasir
b. Labour
0.39 0.30 - Pekerja
0.01 0.01 - Mandor

11 Kayu (Meranti Keras)


- 2" x 2" m3
- 2" x 4" m3
- 4" x 4" m3
a Materials
0.16 1.050 m3 m3 - 2" x 2"
0.21 1.050 m3 m3 - 2" x 4"
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

0.26 1.050 m3 m3 - 4" x 4"


b. Labour
0.59 1 m3 m3 - Fabrication
c. Equipment
1.78 3.00 m2 m2 - Suporting Tools

12 Papan 3/4" x 8" m3


a Materials
0.46 1.010 m3 m3 - Papan 3/4" x 8"
b. Labour
0.46 1.00 m3 m3 - Fabrication
c. Equipment
0.46 1.00 m2 m2 - Suporting Tools

13 Atap seng "BJLS" m2


a Materials
0.13 0.012 m3 m3 - Atap seng "BJLS"
b. Labour
11.20 1.00 m2 m2 - Fabrication
c. Equipment
11.20 1.00 m2 m2 - Suporting Tools

14 Pintu panel lengkap dengan jalusi, kunci Set


Accessories & Cat
a Materials
0.01 0.012 Set Set - Pintu + Accessories + Pengecatan
b. Labour
1.00 1.00 m2 m2 - Fabrication
c. Equipment
1.00 1.00 m2 m2 - Suporting Tools

15 Jendela Sisir lengkap dengan kosen daun Set


jendela uk. 600 mm x 1200 mm
a Materials
0.01 0.012 Set Set - Jendela + Accessories + Pengecatan
b. Labour
1.00 1.00 m2 m2 - Fabrication
c. Equipment
1.00 1.00 m2 m2 - Suporting Tools

16 Pengecatan dinding plafond m2


1 Material
11.05 0.141 kg kg Cat dasar (Kimex)
22.25 0.284 kg kg Cat Finish (Vinilex)
2 Labour
78.35 1 Upah
3 Equipment
78.35 1.00 ls ls - Supporting Tools
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

- Pekerjaan Saluran Terbuka


1 Galian m3
a. Labour
10.12 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
10.12 1.00 m3 m3 - Excavator

2 Cor K-125 m3
a. Materials
0.46 0.91 m3 m3 - Batu krikil
2.30 4.54 zak zak - P. Cement
0.27 0.54 m3 m3 - Pasir
b. Labour
0.51 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
0.51 1.00 m3 m3 - Lory, timber, ducting etc.
-

Pasangan bata 1:3 m2


a. Materials
2,202.48 63.00 pcs pcs - Brick
484.55 13.86 kg kg - Portland Cement
1.40 0.040 m3 m3 - Pasir
b. Labour
34.96 1.00 m3 m3 - Brick Work
c. Equipment
34.96 1.00 m3 m3 - Suporting Tools

Plasteran m2
1 Materials
448.11 5.94 kg kg - Portland Cement
1.58 0.021 m3 m3 - Pasir
2 Labours
75.44 1.00 m2 m2 - Cement Plaster
3 Equipment
75.44 1.00 m2 m2 - Supporting Tools

VII TOILET
A. Pekerjaan Sipil
- Bangunan
1 Galian Pondasi m3
a. Labour
11.67 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
11.67 1.00 m3 m3 - Excavator

2 Pasir urug m3
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

a. Materials
1.67 1.20 m3 m3 - Pasir
b. Labour
0.42 0.30 - Pekerja
0.01 0.01 - Mandor

3 Bekesting m2
a Materials
0.90 0.012 m3 m3 - SK Wood
25.45 0.34 pcs pcs - Triplex 12 mm thick
29.94 0.40 kg kg - Nails
b. Labour
74.84 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
74.84 1.00 m2 m2 - Tools

4 Cor K-125 m3
a. Materials
5.21 0.91 m3 m3 - Batu krikil
26.01 4.54 zak zak - P. Cement
3.09 0.54 m3 m3 - Pasir
b. Labour
5.79 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
5.73 1.00 m3 m3 - Lory, timber, ducting etc.
-

5 Cor K-175 m3
a. Materials
6.22 0.82 m3 m3 - Batu krikil
51.56 6.8 zak zak - P. Cement
4.09 0.54 m3 m3 - Pasir
b. Labour
7.66 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
7.58 1.00 m3 m3 - Lory, timber, ducting etc.
-

6 Besi Beton Kg
a. Materials
180.29 1.03 kg kg - Rebar U32
3.50 0.02 kg kg - Bindraad
b. Labour
175.04 1.00 kg kg - Fabricatiom, Installation
175.04 1.00 kg kg - Transportation & lifting
c. Equipment
175.04 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

7 Pipa PVC Ø. 3" m'


a Materials
15.75 1.050 m3 m3 - Pipa PVC Ø. 3"
0.75 0.050 Kg Kg - Glue
b. Labour
15.00 1.00 m2 M' - Fabrication
c. Equipment
15.00 1.00 m2 Ls - Suporting Tools

8 Pasangan Bata m2
1 Materials
1,867.32 63.00 pcs pcs - Brick
410.81 13.86 kg kg - Portland Cement
1.19 0.040 m3 m3 - Pasir
2 Labour
29.64 1.00 m2 m2 - Brick Work
3 Equipment
29.64 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

9 Plasteran m2
1 Materials
352.12 5.94 kg kg - Portland Cement
1.24 0.021 m3 m3 - Pasir
2 Labours
59.28 1.00 m2 m2 - Cement Plaster
3 Equipment
59.28 1.00 m2 m2 - Supporting Tools

10 Pasir dipadatkan m3
a. Materials
1.92 1.20 m3 m3 - Pasir
b. Labour
0.48 0.30 - Pekerja
0.02 0.01 - Mandor

11 Kayu (Meranti Keras)


- 1" x 6" m3
- 2" x 3" m3
- 2" x 4" m3
a Materials
0.00 0.012 m3 m3 - 1" x 6"
0.02 0.012 m3 m3 - 2" x 3"
0.02 0.012 m3 m3 - 2" x 4"
b. Labour
0.73 3.00 m3 m3 - Fabrication
c. Equipment
0.73 3.00 m2 m2 - Suporting Tools

12 Pintu panel (allumunium t=0.5 mm) Lokal warna Set


Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

uk. 2100 x 820 mm lengkap dengan kosen,


kunci engsel & accessoriesnya
a Materials
2.00 1.000 Set Set - Pintu + Accessories + Pengecatan
b. Labour
2.00 1.00 m2 m2 - Fabrication
c. Equipment
2.00 1.00 m2 m2 - Suporting Tools

13 Pasangan keramik lantai toilet m2


a. Materials
17.33 1.05 Ktk Ktk - Pasangan keramik lantai toilet
98.01 5.94 kg kg - Portland Cement
0.35 0.021 m3 m3 - Pasir
0.33 0.02 - Semen putih
b. Labour
16.50 1.00 m2 m2 - Brick Work
c. Equipment
16.50 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

14 Pasangan keramik dinding toilet m2


a. Materials
51.98 1.05 Ktk Ktk - Pasangan keramik dinding toilet
294.03 5.94 kg kg - Portland Cement
1.04 0.021 m3 m3 - Pasir
0.99 0.02 kg - Semen putih
b. Labour
49.50 1.00 m2 m2 - Pasangan keramik dinding toilet
c. Equipment
49.50 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

15 Pintu PVC (DECO DOOR) toilet Unit


a Materials
5.00 1.000 Set Set - Pintu + Accessories + Pengecatan
b. Labour
5.00 1.00 m2 unit - Instalation
c. Equipment
5.00 1.00 m2 m2 - Suporting Tools

16 Floordrain Pcs
a Materials
2.00 1.000 Set Set - Floordrain
b. Labour
2.00 1.00 m2 unit - Instalation
c. Equipment
2.00 1.00 m2 m2 - Suporting Tools

17 Kran air biasa Pcs


a Materials
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

2.00 1.000 Set Set - Kran air biasa


b. Labour
2.00 1.00 m2 unit - Instalation
c. Equipment
2.00 1.00 m2 m2 - Suporting Tools

18 Closed duduk Merk KIA standart Pcs


a Materials
5.00 1.000 Set Set - Closed duduk Merk KIA standart
b. Labour
5.00 1.00 m2 unit - Instalation
c. Equipment
5.00 1.00 m2 m2 - Suporting Tools

19 Atap seng "BJLS" m2


a Materials
53.04 1.020 Set Set - Atap seng "BJLS"
7.80 0.150 Kg - Nails
b. Labour
52.00 1.00 m2 m2 - Instalation
c. Equipment
52.00 1.00 m2 m2 - Suporting Tools

20 Pengecatan dinding & Plafond m2


1 Material
26.40 0.141 kg kg Cat dasar (Kimex)
53.16 0.284 kg kg Cat Finish (Vinilex)
2 Labour
187.20 1 m2 Upah
3 Equipment
187.20 1.00 ls ls - Supporting Tools

- Pekerjaan Saluran Terbuka


1 Galian m3
a. Labour
16.17 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
16.17 1.00 m3 m3 - Excavator

2 Cor K-125 m3
a. Materials
0.74 0.91 m3 m3 - Batu krikil
3.67 4.54 zak zak - P. Cement
0.44 0.54 m3 m3 - Pasir
b. Labour
0.82 1.01 m3 m3 - Pouring Concrete, Cleaning
Equipment
0.81 1.00 m3 m3 - Lory, timber, ducting etc.
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

3 Pasanagn bata 1:3 m2


1 Materials
3,519.18 63.00 pcs pcs - Brick
774.22 13.86 kg kg - Portland Cement
2.23 0.040 m3 m3 - Pasir
2 Labour
55.86 1.00 m2 m2 - Brick Work
3 Equipment
55.86 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools

4 Plasteran m2
1 Materials
716.01 5.94 kg kg - Portland Cement
2.53 0.021 m3 m3 - Pasir
2 Labours
120.54 1.00 m2 m2 - Cement Plaster
3 Equipment
120.54 1.00 m2 m2 - Supporting Tools

TOTAL
1,200.00

Kayu Sembarang 2".3" 24,480.00 14,688,000


Papan Sembarang 3/4".8" 24,480.00 8,812,800
Nails 9,078.00 272,340

Vitzet 1,000.00 1,200,000


Pasang Bowplank 1,500.00 1,800,000
Equipment
Tools 500.00 600,000
Sub Total 27,373,140

66.64

Setting, Leveling, Cleaning and Compacted 4,500 299,880


Equipment -
Excavator 16,500 1,099,560
Sub Total 1,399,440

3.33 65,000.00

Pasir 35,700 142,743

Pekerja 28,050 28,039


Mandor 45,900 1,529
Sub Total 172,311

3.33

Batu krikil 117,300 355,668


P. Cement 24,480 370,316
Pasir 35,700 64,234
-
Pouring Concrete, Cleaning 50,000 168,266
Equipment -
Lory, timber, ducting etc. 2,000 6,664
Sub Total 965,148

137.70

SK Wood 2,203,200 3,640,568


Triplex 12 mm thick 117,300 5,491,751
Nails 9,078 500,016
-
Fabrication, Installation, Remove 20,000 2,754,000
Equipment -
Tools 1,000 137,700
Sub Total 12,524,035
2,031.84

Rebar U32 5,579 11,676,542


Bindraad 6,630 269,422
-
Fabricatiom, Installation 700 1,422,288
Transportation & lifting 25 50,796
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 101,592
Sub Total 13,520,640

29.58

Batu krikil 117,300 2,949,274


P. Cement 24,480 6,155,006
Pasir 35,700 580,803
-
Pouring Concrete, Cleaning 50,000 1,493,790
Equipment -
Lory, timber, ducting etc. 2,000 59,160
Sub Total 11,238,034

30.40

Tanah merah - -

Pekerja 28,050 213,180


Mandor 45,900 13,954
Sub Total 227,134

50.96

Setting, Leveling, Cleaning and Compacted 4,500 229,320


Equipment -
Excavator 16,500 840,840
Sub Total 1,070,160

2.55 65,000.00

Pasir 35,700 109,156


-
Pekerja 28,050 21,441
Mandor 45,900 1,170
Sub Total 131,767

2.55

Batu krikil 117,300 271,981


P. Cement 24,480 283,183
Pasir 35,700 49,120

Pouring Concrete, Cleaning 50,000 128,674


Equipment -
Lory, timber, ducting etc. 2,000 5,096

Sub Total 738,054

102.44

SK Wood 2,203,200 2,708,350


Triplex 12 mm thick 117,300 4,085,512
Nails 9,078 371,980
-
Fabrication, Installation, Remove 20,000 2,048,800
Equipment -
Tools 1,000 102,440
Sub Total 9,317,082

1,553.76

Rebar U32 5,579 8,929,120


Bindraad 6,630 206,029
-
Fabricatiom, Installation 700 1,087,632
Transportation & lifting 25 38,844
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 77,688
Sub Total 10,339,313

22.15

Batu krikil 117,300 2,208,665


P. Cement 24,480 4,609,388
Pasir 35,700 434,955
-
Pouring Concrete, Cleaning 50,000 1,118,676
Equipment -
Lory, timber, ducting etc. 2,000 44,304
Sub Total 8,415,988

23.71

Tanah merah - -
-
Pekerja 28,050 166,280
Mandor 45,900 10,884
Sub Total 177,164

66.64

Setting, Leveling, Cleaning and Compacted 4,500 299,880


Equipment -
Excavator 16,500 1,099,560
Sub Total 1,399,440
3.33 65,000.00

Pasir 35,700 142,743


-
Pekerja 28,050 28,039
Mandor 45,900 1,529
Sub Total 172,311

3.33

Batu krikil 117,300 355,668


P. Cement 24,480 370,316
Pasir 35,700 64,234
-
Pouring Concrete, Cleaning 50,000 168,266
Equipment -
Lory, timber, ducting etc. 2,000 6,664

Sub Total 965,148

137.70

SK Wood 2,203,200 3,640,568


Triplex 12 mm thick 117,300 5,491,751
Nails 9,078 500,016
-
Fabrication, Installation, Remove 20,000 2,754,000
Equipment -
Tools 1,000 137,700
Sub Total 12,524,035
-
2,031.84

Rebar U32 5,579 11,676,542


Bindraad 6,630 269,422
-
Fabricatiom, Installation 700 1,422,288
Transportation & lifting 25 50,796
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 101,592
Sub Total 13,520,640

29.58

Batu krikil 117,300 2,949,274


P. Cement 24,480 6,155,006
Pasir 35,700 580,803
-
Pouring Concrete, Cleaning 50,000 1,493,790
Equipment -
Lory, timber, ducting etc. 2,000 59,160
Sub Total 11,238,034
27.64

Tanah merah - -
-
Pekerja 28,050.00 193,840
Mandor 45,900.00 12,688
Sub Total 206,527

121.34

Setting, Leveling, Cleaning and Compacted 4,500 546,030


Equipment -
Excavator 16,500 2,002,110
Sub Total 2,548,140

20.22

Batu krikil 117,300 1,945,169


P. Cement 24,480 3,366,401
Pasir 35,700 389,859
-
Pouring Concrete, Cleaning 50,000 1,021,262
Equipment -
Lory, timber, ducting etc. 2,000 40,446
Sub Total 6,763,137

288.90

Brick 357 6,497,650


Portland Cement 612 2,450,542
Pasir 35,700 412,549
-
Brick Work 15,000 4,333,500
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 577,800
Sub Total 14,272,041

404.46

Portland Cement 612 1,470,325


Pasir 35,700 303,224
-
Cement Plaster 13,000 5,257,980
Equipment -
Supporting Tools 2,000 808,920
Sub Total 7,840,449

11.66
-
Setting, Leveling, Cleaning and Compacted 4,500 52,479
Equipment -
Excavator 16,500 192,423
Sub Total 244,902

2.10

Batu krikil 117,300 1,945,169


P. Cement 24,480 3,366,401
Pasir 35,700 389,859
-
Pouring Concrete, Cleaning 50,000 106,050
Equipment -
Lory, timber, ducting etc. 2,000 4,200
Sub Total 5,811,680

66.40

Brick 357 1,493,402


Portland Cement 612 563,226
Pasir 35,700 94,819
-
Brick Work 15,000 996,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 132,800
Sub Total 3,280,248

80.92

Portland Cement 612 294,167


Pasir 35,700 60,666
-
Cement Plaster 13,000 1,051,960
Equipment -
Supporting Tools 2,000 161,840
Sub Total 1,568,633

195.30

Riol beton dia. 300 mm 34,170 6,740,135


Brick 357 4,392,492
Portland Cement 612 1,656,597
Pasir 35,700 278,888
-
Riol Work 15,000 2,929,500
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 390,600
Sub Total 16,388,213

130.95

Setting, Leveling, Cleaning and Compacted 4,500 589,275


Equipment -
Excavator 16,500 2,160,675
Sub Total 2,749,950

13.10

Pasir 35,700 560,990


-
Pekerja 28,050 110,194
Mandor 45,900 6,011
Sub Total 677,195

13.10

Batu krikil 117,300 1,397,800


P. Cement 24,480 1,455,368
Pasir 35,700 252,445

Pouring Concrete, Cleaning 50,000 661,298


Equipment -
Lory, timber, ducting etc. 2,000 26,190

Sub Total 3,793,100

465.60

SK Wood 2,203,200 12,309,719


Triplex 12 mm thick 117,300 18,569,059
Nails 9,078 1,690,687
-
Fabrication, Installation, Remove 20,000 9,312,000
Equipment -
Tools 1,000 465,600
Sub Total 42,347,065

10,368.33

Rebar U32 5,579 59,584,533


Bindraad 6,630 1,374,841
-
Fabricatiom, Installation 700 7,257,831
Transportation & lifting 25 259,208
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 518,417
Sub Total 68,994,829

65.48

Batu krikil 117,300 6,988,998


P. Cement 24,480 7,276,839
Pasir 35,700 1,262,227
-
Pouring Concrete, Cleaning 50,000 3,306,488
Equipment -
Lory, timber, ducting etc. 2,000 130,950
Sub Total 18,965,502

432.00

Pasir 35,700 18,506,880


-
Pekerja 27,500 3,564,000
Mandor 35,000 151,200
Sub Total 22,222,080

432.00

Batu krikil 117,300 46,112,976


P. Cement 24,480 48,012,134
Pasir 35,700 8,328,096
-
Pouring Concrete, Cleaning 50,000 21,816,000
Equipment -
Lory, timber, ducting etc. 2,000 864,000

Sub Total 125,133,206

8,640.00

BRC Mesh M-7 28,579 251,863,173


Chair (Besi Beton dia. 8 mm) 5,579 2,410,301
Labour Cost -
Install, Lifting 2,500 21,600,000
Equipment -
Supporting Tools 500 4,320,000
Sub Total 280,193,474

1,296.00

Batu krikil 117,300 129,217,680


P. Cement 24,480 269,671,680
Pasir 35,700 25,446,960
-
Pouring Concrete, Cleaning 50,000 65,448,000
Equipment -
Lory, timber, ducting etc. 2,000 2,592,000
Sub Total 492,376,320

222.75

SK Wood 2,203,200 5,889,154


Triplex 12 mm thick 117,300 8,883,716
Nails 9,078 808,850
-
Fabrication, Installation, Remove 20,000 4,455,000
Equipment -
Tools 1,000 222,750
Sub Total 20,259,469

112,492.80

WF-350x175x7x11 6,630 753,285,537


Welding Electroda 10,710 14,457,575
-
Fabrication, Installation 800 89,994,240
Equipment -
Transportation Cost 350 39,372,480
Steel Structure Tools 125 14,061,600
Sub Total 911,171,431

22,466.40

WF-300x150x6,5x9 6,630 150,441,754


Welding Electroda 10,710 2,887,382
-
Fabrication, Installation 800 17,973,120
Equipment -
Transportation Cost 350 7,863,240
Steel Structure Tools 125 2,808,300
Sub Total 181,973,796

5,869.20

UNP-125x65x6 6,630 39,301,924


Welding Electroda 10,710 754,310
-
Fabrication, Installation 800 4,695,360
Equipment -
Transportation Cost 350 2,054,220
Steel Structure Tools 125 733,650
Sub Total 47,539,464

49,140.20

CNP-150x50x20x2,3 6,120 303,745,404


Welding Electroda 10,710 6,315,499
-
Fabrication, Installation 800 39,312,160
Equipment -
Transportation Cost 350 17,199,070
Steel Structure Tools 125 6,142,525
Sub Total 372,714,658

2,276.40

CNP-125x50x20x2,3 6,120 14,070,884


Welding Electroda 10,710 292,563
-
Fabrication, Installation 800 1,821,120
Equipment -
Transportation Cost 350 796,740
Steel Structure Tools 125 284,550
Sub Total 17,265,857

1,155.00

Plat t 15 mm 7,497 8,745,625


Welding Electroda 10,710 148,441
-
Fabrication, Installation 800 924,000
Equipment -
Transportation Cost 350 404,250
Steel Structure Tools 125 144,375
Sub Total 10,366,691

3,662.40

Plat t 12 mm 7,497 27,731,583


Welding Electroda 10,710 470,692
-
Fabrication, Installation 800 2,929,920
Equipment -
Transportation Cost 350 1,281,840
Steel Structure Tools 125 457,800
Sub Total 32,871,835

4,979.42

Plat t 10 mm 7,497 37,704,019


Welding Electroda 10,710 639,955
-
Fabrication, Installation 800 3,983,536
Equipment -
Transportation Cost 350 1,742,797
Steel Structure Tools 125 622,428
Sub Total 44,692,734

931.10

Plat t 8 mm 7,497 7,050,261


Welding Electroda 10,710 119,665
-
Fabrication, Installation 800 744,880
Equipment -
Transportation Cost 350 325,885
Steel Structure Tools 125 116,388
Sub Total 8,357,079

2,305.63

Plat t 6 mm 7,497 17,458,123


Welding Electroda 10,710 296,319
-
Fabrication, Installation 800 1,844,500
Equipment -
Transportation Cost 350 806,969
Steel Structure Tools 125 288,203
Sub Total 20,694,114

23,175.00

L-50x50x5 7,140 167,124,195


Welding Electroda 10,710 2,978,451
-
Fabrication, Installation 800 18,540,000
Equipment -
Transportation Cost 350 8,111,250
Steel Structure Tools 125 2,896,875
Sub Total 199,650,771

3,412.80

Besi Beton dia. 16 mm 5,579 19,231,790


Welding Electroda 10,710 438,613
-
Fabrication, Installation 800 2,730,240
Equipment -
Transportation Cost 350 1,194,480
Steel Structure Tools 125 426,600
Sub Total 24,021,723

2,888.00

Tie Rod dia. 12 mm 10,200 29,752,176


-
Installation 800 2,287,296
Equipment -
Transportation Cost 350 1,000,692
Steel Structure Tools 125 361,000
Sub Total 33,401,164

368.00

Anchor Bolt dia.16 mm - 50 cm 8,160 3,002,880


-
Setting 9,500 3,496,000
Equipment -
Transportation 500 184,000
Sub Total 6,682,880

80.00

Turn Bucles dia. 5/8" 7,650 618,120


Equipment -
Steel Structure Tools 125 10,000
Transportation Cost 500 40,000
Sub Total 668,120
-
2,940.00 -
-
Baut dia. 5/8" 1,253 3,719,352
Equipment -
Steel Structure Tools 125 367,500
Transportation Cost 500 1,470,000
Sub Total 5,556,852

8,988.00

Baut dia. ½" 655 5,944,559


Equipment -
Steel Structure Tools 125 1,123,500
Transportation Cost 500 4,494,000
Sub Total 11,562,059

27,826.00

Baut seng dia. 6 mm 194 5,446,606


Equipment -
Steel Structure Tools 125 3,478,250
Transportation Cost 500 13,913,000
Sub Total 22,837,856

288.00

Talang datar galvalume t=0.5 mm 55,080 16,021,670


-
Installation & Fabrication 15,000 4,320,000
Equipment -
Tools 125 36,000
Transportation Cost 500 144,000
Sub Total 20,521,670

10,705.00
Material zincalume 0,45 TCT
Atap Primadeck t = 0.45 mm 46,303 505,583,064

Install, Lifting, Fixing 3,500 37,467,500


Equipment -
Supporting Tools & Transportation 1,000 10,705,000
Sub Total 553,755,564

1,680.00

Clading Primadeck t = 0.40 mm 40,934 69,457,168


-
Install 3,500 5,880,000
Equipment -
Supporting Tools 1,000 1,680,000
Sub Total 77,017,168
306.00

Rabung Galvalume 37,332 11,537,828


-
Installation & Fabrication 2,400 734,400
Equipment -
Supporting Tools 125 38,250
Transportation Cost 500 153,000
Sub Total 12,463,478

444.00

Flashing Galvalume 55,080 24,700,075


-
Installation & Fabrication 2,400 1,065,600
Equipment -
Supporting Tools 125 55,500
Transportation Cost 500 222,000
Sub Total 26,043,175

68.00

Talang PVC dia. 4" 201,435 13,834,535


-
Installation & Fabrication 2,400 163,200
Equipment -
Supporting Tools 125 8,500
Transportation Cost 500 34,000
Sub Total 14,040,235

340.00

Cleam Talang 6,350 2,180,590


-
Installation & Fabrication 2,400 816,000
Equipment -
Supporting Tools 125 42,500
Transportation Cost 500 170,000
Sub Total 3,209,090

231,866.35

Primer (Kansai) 11,220 26,015,404


Finish (Bee Brand) 25,500 118,251,836
-
Primer & Finish 300 69,559,904
Equipment -
Supporting Tools 100 23,186,635
Sub Total 237,013,778
107.08

Brick 357 2,408,336


Portland Cement 612 908,287
Pasir 35,700 152,910
-
Brick Work 15,000 1,606,200
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 214,160
Sub Total 5,289,893

214.16
-
Portland Cement 612 778,532
Pasir 35,700 160,556
-
Cement Plaster 13,000 2,784,080
Equipment -
Supporting Tools 2,000 428,320
Sub Total 4,151,487

1.00

Kosen & Pintu Panel Uk. 1200x2100 550,000 555,500


-
Installation & Setting 100,000 100,000
Equipment -
Supporting Tools 10,000 10,000
Sub Total 665,500

14.00

Jalusi Lubang Angin 175,000 2,474,500


-
Installation & Setting 75,000 1,050,000
Equipment -
Supporting Tools 10,000 140,000
Sub Total 3,664,500

214.16 -
-
Cat dasar Kimex 5,793.60 174,947
Cat Finish Vinilex 10,098.00 614,175
-
Upah 5,000.00 1,070,800
Equipment -
Supporting Tools 125 26,770
Sub Total 1,886,692

1.00

Dempul 10,200.00 10,200


Cat Finish Bee Brand 25,500.00 25,500
-
Upah 25,000.00 25,000
Equipment -
Supporting Tools 5,000 5,000
Sub Total 65,700

14.00

Dempul 10,200.00 142,800


Cat Finish Bee Brand 25,500.00 357,000
-
Upah 25,000.00 350,000
Equipment -
Supporting Tools 5,000 70,000
Sub Total 919,800

160.40 -
-
Brick 357 3,607,556
Portland Cement 612 1,360,564
Pasir 35,700 229,051
-
Brick Work 15,000 2,406,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 320,800
Sub Total 7,923,972

320.80

Portland Cement 612 1,166,198


Pasir 35,700 240,504
-
Cement Plaster 13,000 4,170,400
Equipment -
Supporting Tools 2,000 641,600
Sub Total 6,218,702

5.00

Kusen + Jendela + Jalusi (Allumunium) 1,000,000 5,000,000


-
Installation 100,000 500,000
Equipment -
Supporting Tools 10,000 50,000
Sub Total 5,550,000

1.00
Kusen + Jendela gendong (Allumunium) 1,000,000 1,000,000
-
Installation 250,000 250,000
Equipment -
Supporting Tools 10,000 10,000
Sub Total 1,260,000

72.00

Kayu meranti 2,244,000.00 1,938,816


Asbes / eternit 7,650.00 550,800
Lat asbes 7,650.00 550,800
Paku asbes 9,078.00 13,072
Nails 9,078.00 130,723
-
Fabrication and Instalation 15,000.00 1,134,000
Equipment -
Supporting Tools 1,500 108,000
Sub Total 4,426,212

36.00

Profil sudut kayu 15,300.00 550,800


Paku asbes 9,078.00 6,536
Nails 9,078.00 65,362
-
Fabrication and Instalation 5,000.00 180,000
Equipment -
Supporting Tools 500 18,000
Sub Total 820,698

320.80
-
Cat dasar Kimex 5,793.60 262,061
Cat Finish Vinilex 10,098.00 920,001
-
Upah 5,000.00 1,604,000
Equipment -
Supporting Tools 125 40,100
Sub Total 2,826,161

72.00

Cat dasar Kimex 5,793.60 58,817


Cat Finish Vinilex 10,098.00 206,484
-
Upah 5,000.00 360,000
Equipment -
Supporting Tools 125 9,000
Sub Total 634,301

36.00
Cat dasar Kimex 5,793.60 29,408
Cat Finish Vinilex 10,098.00 103,242
-
Upah 5,000.00 180,000
Equipment -
Supporting Tools 125 4,500
Sub Total 317,150

10.80

Batu krikil 117,300 1,038,809


P. Cement 24,480 1,797,811
Pasir 35,700 208,202
-
Pouring Concrete, Cleaning 50,000 545,400
Equipment -
Lory, timber, ducting etc. 2,000 21,600
Sub Total 3,611,822

1,702.29 -
-
Rebar U32 5,579 9,782,690
Bindraad 6,630 225,724
-
Fabricatiom, Installation 700 1,191,603
Transportation & lifting 25 42,557
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 85,115
Sub Total 11,327,688

72.00
-
SK Wood 2,203,200 1,903,565
Triplex 12 mm thick 117,300 2,871,504
Nails 9,078 261,446
-
Fabrication, Installation, Remove 20,000 1,440,000
Equipment -
Tools 1,000 72,000
Sub Total 6,548,515

1.08

Batu krikil 117,300 103,881


P. Cement 24,480 179,781
Pasir 35,700 20,820
-
Pouring Concrete, Cleaning 50,000 54,540
Equipment -
Lory, timber, ducting etc. 2,000 2,160
Sub Total 361,182
168.12

Rebar U32 5,579 966,149


Bindraad 6,630 22,293
-
Fabricatiom, Installation 700 117,684
Transportation & lifting 25 4,203
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 8,406
Sub Total 1,118,735

21.30

SK Wood 2,203,200 563,138


Triplex 12 mm thick 117,300 849,487
Nails 9,078 77,345
-
Fabrication, Installation, Remove 20,000 426,000
Equipment -
Tools 1,000 21,300
Sub Total 1,937,269

1.00

Pipa dia. 4" 433,500 437,835


Batu krikil 117,300 106,743
P. Cement 24,480 111,139
Pasir 35,700 19,278
Anchor bolt 5/8" 8,160 8,242
-
Civil Work 500,000 500,000
Steel work (Pipe) 200,000 200,000
Equipment -
Supporting Tools 5,000 5,000
Sub Total 1,388,237

1.00
-
UNP.125.65.6 6,630 6,696
Batu krikil 117,300 106,743
P. Cement 24,480 111,139
Pasir 35,700 19,278
Anchor bolt 5/8" 8,160 8,242
-
Civil Work 500,000 500,000
Steel work (Pipe) 200,000 400,000
Equipment -
Supporting Tools 5,000 5,000
Sub Total 1,157,098
902.72 -
-
WF-350x175x7x11 6,630 6,044,884
Welding Electroda 10,710 116,018
-
Fabrication, Installation 800 722,176
Equipment -
Steel Structure Tools 125 112,840
Transportation Cost 350 315,952
Sub Total 7,311,870

4,844.40

WF-300x150x6,5x9 6,630 32,439,556


Welding Electroda 10,710 622,602
-
Fabrication, Installation 800 3,875,520
Equipment -
Steel Structure Tools 125 605,550
Transportation Cost 350 1,695,540
Sub Total 39,238,768

373.00

Plat t = 16 mm 7,497 2,824,345


Welding Electroda 10,710 47,938
-
Fabrication, Installation 800 298,400
Equipment -
Steel Structure Tools 125 46,625
Transportation Cost 350 130,550
Sub Total 3,347,858

46.00

Besi Beton dia. 12 mm anchor c/c 300 mm 5,579 259,219


Welding Electroda 10,710 5,912
-
Fabrication, Installation 800 36,800
Equipment -
Steel Structure Tools 125 5,750
Transportation Cost 350 16,100
Sub Total 323,781

8.00 -
-
Baut anchor dia. 22 mm 20,910 167,280
-
Setting 9,500 76,000
Equipment -
Transportation 500 4,000
Sub Total 247,280
108.00
-
Baut dia. 3/4" 2,553 278,488
Equipment -
Steel Structure Tools 125 13,500
Transportation Cost 500 54,000
Sub Total 345,988

6,166.12

Primer (Kansai) 11,220 691,839


Finish (Bee Brand) 25,500 3,144,721
-
Primer & Finish 300 1,849,836
Equipment -
Supporting Tools 50 308,306
Sub Total 5,994,702

148.80

WF-350x175x7x11 6,630 996,409


Welding Electroda 10,710 19,124
-
Fabrication, Installation 800 119,040
Equipment -
Steel Structure Tools 125 18,600
Transportation Cost 350 52,080
Sub Total 1,205,253

402.00

UNP-125x65x6 6,630 2,691,913


Welding Electroda 10,710 51,665
-
Fabrication, Installation 800 321,600
Equipment -
Steel Structure Tools 125 50,250
Transportation Cost 350 140,700
Sub Total 3,256,128

12.20

Pipa Medium dia. 4" 433,500 5,341,587


Welding Electroda 10,710 1,568
-
Fabrication, Installation 800 9,760
Equipment -
Steel Structure Tools 125 1,525
Transportation Cost 350 4,270
Sub Total 5,358,710

118.68
Pipa dia 1½" t = 2,9 mm 151,980 18,217,356
Welding Electroda 10,710 15,253
-
Fabrication, Installation 800 94,944
Equipment -
Steel Structure Tools 125 14,835
Transportation Cost 350 41,538
Sub Total 18,383,926

123.30

Pipa dia. 2" t = 2,9 mm 191,760 23,880,448


Welding Electroda 10,710 15,847
-
Fabrication, Installation 800 98,640
Equipment -
Steel Structure Tools 125 15,413
Transportation Cost 350 43,155
Sub Total 24,053,502

35.50

L-65x65x6 7,140 256,005


Welding Electroda 10,710 4,562
-
Fabrication, Installation 800 28,400
Equipment -
Steel Structure Tools 125 4,438
Transportation Cost 350 12,425
Sub Total 305,830

345.00

Plat Bunga t = 6 mm 7,905 2,754,497


Welding Electroda 10,710 44,339
-
Fabrication, Installation 800 276,000
Equipment -
Steel Structure Tools 125 43,125
Transportation Cost 350 120,750
Sub Total 3,238,712

373.00

Plat Tapak 16 mm 7,497 2,824,345


Welding Electroda 10,710 47,938
-
Fabrication, Installation 800 298,400
Equipment -
Steel Structure Tools 125 46,625
Transportation Cost 350 130,550
Sub Total 3,347,858

9.75
Plat t = 6mm 7,497 73,827
Welding Electroda 10,710 1,253
-
Fabrication, Installation 800 7,800
Equipment -
Steel Structure Tools 125 1,219
Transportation Cost 350 3,413
Sub Total 87,511

20.00

Baut dia. ½" 655 13,228


Equipment -
Steel Structure Tools 125 2,500
Transportation Cost 500 10,000
Sub Total 25,728

8.00

Anchor Bolt dia.16 mm - 50 cm 8,160 65,280


-
Setting 9,500 76,000
Equipment -
Transportation 500 4,000
Sub Total 145,280

1,568.23

Primer (Kansai) 11,220 175,955


Finish (Bee Brand) 25,500 799,797
-
Primer & Finish 300 470,469
Equipment -
Supporting Tools 50 78,412
Sub Total 1,524,633

63.36

Setting, Leveling, Cleaning and Compacted 4,500 285,120


Equipment -
Excavator 16,500 1,045,440
Sub Total 1,330,560

3.17

Pasir 35,700 135,717


-
Pekerja 27,500 26,136
Mandor 35,000 1,109
Sub Total 162,962
3.17

Batu krikil 117,300 338,162


P. Cement 24,480 352,089
Pasir 35,700 61,073
-
Pouring Concrete, Cleaning 50,000 159,984
Equipment -
Lory, timber, ducting etc. 2,000 6,336

Sub Total 917,643.5136

102.21

SK Wood 2,203,200 2,702,322


Triplex 12 mm thick 117,300 4,076,419
Nails 9,078 371,152
-
Fabrication, Installation, Remove 20,000 2,044,240
Equipment -
Tools 1,000 102,212
Sub Total 9,296,345

2,002.18

Rebar U32 5,579 11,506,069


Bindraad 6,630 265,489
-
Fabricatiom, Installation 700 1,401,523
Transportation & lifting 25 50,054
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 100,109
Sub Total 13,323,244

15.53

Batu krikil 117,300 1,548,618


P. Cement 24,480 3,231,899
Pasir 35,700 304,971
-
Pouring Concrete, Cleaning 50,000 784,366
Equipment -
Lory, timber, ducting etc. 2,000 31,064
Sub Total 5,900,917

47.83

Tanah merah - -
-
Pekerja 28,050.00 335,394
Mandor 45,900.00 21,953
Sub Total 357,347
39.30

Setting, Leveling, Cleaning and Compacted 4,500 176,850


Equipment -
Excavator 16,500 648,450
Sub Total 825,300

6.55

Pasir 35,700 280,602


-
Pekerja 27,500 54,038
Mandor 35,000 2,293
Sub Total 336,932

6.55

Batu krikil 117,300 699,167


P. Cement 24,480 727,962
Pasir 35,700 126,271
-
Pouring Concrete, Cleaning 50,000 330,775
Equipment -
Lory, timber, ducting etc. 2,000 13,100

Sub Total 1,897,274

196.51

SK Wood 2,203,200 5,195,410


Triplex 12 mm thick 117,300 7,837,212
Nails 9,078 713,567
-
Fabrication, Installation, Remove 20,000 3,930,200
Equipment -
Tools 1,000 196,510
Sub Total 17,872,899

5,433.40
-
Rebar U32 5,579 31,224,554
Bindraad 6,630 720,469
-
Fabricatiom, Installation 700 3,803,379
Transportation & lifting 25 135,835
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 271,670
Sub Total 36,155,906

19.65
Batu krikil 117,300 1,959,203
P. Cement 24,480 4,088,772
Pasir 35,700 385,828
-
Pouring Concrete, Cleaning 50,000 992,325
Equipment -
Lory, timber, ducting etc. 2,000 39,300
Sub Total 7,465,428

24.24

Tanah merah - -
-
Pekerja 28,050.00 169,983
Mandor 45,900.00 11,126
Sub Total 181,109

56.20

Setting, Leveling, Cleaning and Compacted 4,500 252,882


Equipment -
Excavator 16,500 927,234
Sub Total 1,180,116

4.68

Pasir 35,700 200,620


-
Pekerja 27,500 38,635
Mandor 35,000 1,639
Sub Total 240,894

28.10

Batu krikil 117,300 499,877


P. Cement 24,480 520,465
Pasir 35,700 90,279
-
Pouring Concrete, Cleaning 50,000 236,492
Equipment -
Lory, timber, ducting etc. 2,000 9,366

Sub Total 1,356,479

210.74

SK Wood 2,203,200 5,571,496


Triplex 12 mm thick 117,300 8,404,533
Nails 9,078 765,221
-
Fabrication, Installation, Remove 20,000 4,214,700
Equipment -
Tools 1,000 210,735
Sub Total 19,166,685

1,428.13

Rebar U32 5,579 8,207,152


Bindraad 6,630 189,370
-
Fabricatiom, Installation 700 999,691
Transportation & lifting 25 35,703
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 71,407
Sub Total 9,503,323

11.24
-
Batu krikil 117,300 1,120,684
P. Cement 24,480 2,338,819
Pasir 35,700 220,697
-
Pouring Concrete, Cleaning 50,000 567,620
Equipment -
Lory, timber, ducting etc. 2,000 22,480
Sub Total 4,270,301

1,578.84

Brick 357 35,509,690


P. Cement 612 13,392,226
Pasir 35,700 2,254,584
-
Brick Work 15,000 23,682,600
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 3,157,680
Sub Total 77,996,780

3,157.68

Portland Cement 612 11,479,051


Pasir 35,700 2,367,313
-
Cement Plaster 13,000 41,049,840
Equipment -
Supporting Tools 2,000 6,315,360
Sub Total 61,211,564

7.97

Batu krikil 117,300 766,121


P. Cement 24,480 1,325,886
Pasir 35,700 153,549
-
Pouring Concrete, Cleaning 50,000 402,233
Equipment -
Lory, timber, ducting etc. 2,000 15,930
Sub Total 2,663,719

132.63

Pasir 35,700 5,682,041


-
Pekerja 28,050 1,116,115
Mandor 45,900 60,879
Sub Total 6,859,035

132.63

Batu krikil 117,300 14,157,751


P. Cement 24,480 14,740,837
Pasir 35,700 2,556,918
-
Pouring Concrete, Cleaning 50,000 6,698,017
Equipment -
Lory, timber, ducting etc. 2,000 265,268

Sub Total 38,418,791

2,652.68

BRC Mesh M-7 28,579 77,327,824


Chair (besi Beton dia.8 mm) 5,579 740,018
Labour Cost -
Install, Lifting 2,500 6,631,700
Equipment -
Supporting Tools 750 1,989,510
Sub Total 86,689,052

347.90 -
-
Batu krikil 117,300 34,687,569
P. Cement 24,480 72,391,448
Pasir 35,700 6,831,056
-
Pouring Concrete, Cleaning 50,000 17,569,051
Equipment -
Lory, timber, ducting etc. 2,000 695,804
Sub Total 132,174,928

68.00

SK Wood 2,203,200 1,797,811


Triplex 12 mm thick 117,300 2,711,976
Nails 9,078 246,922
-
Fabrication, Installation, Remove 20,000 1,360,000
Equipment -
Tools 1,000 68,000
Sub Total 6,184,709

77.73

Setting, Leveling, Cleaning and Compacted 4,500 349,785


Equipment -
Excavator 16,500 1,282,545
Sub Total 1,632,330

7.33

Pasir 35,700 314,017


-
Pekerja 27,500 60,473
Mandor 35,000 2,566
Sub Total 377,055

259.11 -
-
Brick 357 5,827,553
P. Cement 612 2,197,820
Pasir 35,700 370,003
-
Brick Work 15,000 3,886,590
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 518,212
Sub Total 12,800,178

332.44

Portland Cement 612 1,208,512


Pasir 35,700 249,230
-
Cement Plaster 13,000 4,321,720
Equipment -
Supporting Tools 2,000 664,880
Sub Total 6,444,343

-
-
-
-
-
SUPPLY B

-
-
-
-
SUPPLY BY OWNER
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

11.52

Setting, Leveling, Cleaning and Compacted 4,500 51,840


Equipment -
Excavator 16,500 190,080
Sub Total 241,920

0.58

Pasir 35,700 24,676

Pekerja 28,050 4,847


Mandor 45,900 264
Sub Total 29,787

0.58

Batu krikil 117,300 61,484


P. Cement 24,480 64,016
Pasir 35,700 11,104
-
Pouring Concrete, Cleaning 50,000 29,088
Equipment -
Lory, timber, ducting etc. 2,000 1,152
Sub Total 166,844

10.58

SK Wood 2,203,200 279,824


Triplex 12 mm thick 117,300 422,111
Nails 9,078 38,433
-
Fabrication, Installation, Remove 20,000 211,680
Equipment -
Tools 1,000 10,584
Sub Total 962,632

364.03 -
-
Rebar U32 5,579 2,092,002
Bindraad 6,630 48,270

Fabricatiom, Installation 700 254,821


Transportation & lifting 25 9,101
Equipment
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 18,202
Sub Total 2,422,395

2.82 -
-
Batu krikil 117,300 281,567
P. Cement 24,480 587,618
Pasir 35,700 55,449
-
Pouring Concrete, Cleaning 50,000 142,612
Equipment -
Lory, timber, ducting etc. 2,000 5,648
Sub Total 1,072,894

8.70 -
-
Tanah merah - -
-
Pekerja 28,050.00 60,981
Mandor 45,900.00 3,991
Sub Total 64,972

5.76

Setting, Leveling, Cleaning and Compacted 4,500 25,920


Equipment -
Excavator 16,500 95,040
Sub Total 120,960

0.29 -
-
Pasir 35,700 12,338
-
Pekerja 28,050.00 2,424
Mandor 45,900.00 132
Sub Total 14,894

0.29

Batu krikil 117,300 30,742


P. Cement 24,480 32,008
Pasir 35,700 5,552
-
Pouring Concrete, Cleaning 50,000 14,544
Equipment -
Lory, timber, ducting etc. 2,000 576

Sub Total 83,422

8.20

SK Wood 2,203,200 216,795


Triplex 12 mm thick 117,300 327,032
Nails 9,078 29,776
-
Fabrication, Installation, Remove 20,000 164,000
Equipment -
Tools 1,000 8,200
Sub Total 745,803

182.01

Rebar U32 5,579 1,045,972


Bindraad 6,630 24,135
-
Fabricatiom, Installation 700 127,407
Transportation & lifting 25 4,550
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 9,101
Sub Total 1,211,164

1.41

Batu krikil 117,300 140,783


P. Cement 24,480 293,809
Pasir 35,700 27,725
-
Pouring Concrete, Cleaning 50,000 71,306
Equipment -
Lory, timber, ducting etc. 2,000 2,824
Sub Total 536,447

4.35
Tanah merah - -
-
Pekerja 28,050.00 30,490
Mandor 45,900.00 1,996
Sub Total 32,486

7.20

Setting, Leveling, Cleaning and Compacted 4,500 32,400


Equipment -
Excavator 16,500 118,800
Sub Total 151,200

1.20

Pasir 35,700 51,408


-
Pekerja 27,500 9,900
Mandor 35,000 420
Sub Total 61,728

1.20

Batu krikil 117,300 128,092


P. Cement 24,480 133,367
Pasir 35,700 23,134
-
Pouring Concrete, Cleaning 50,000 60,600
Equipment -
Lory, timber, ducting etc. 2,000 2,400

Sub Total 347,592

36.00

SK Wood 2,203,200 951,782


Triplex 12 mm thick 117,300 1,435,752
Nails 9,078 130,723
-
Fabrication, Installation, Remove 20,000 720,000
Equipment -
Tools 1,000 36,000
Sub Total 3,274,258

995.40
-
Rebar U32 5,579 5,720,347
Bindraad 6,630 131,990
-
Fabricatiom, Installation 700 696,780
Transportation & lifting 25 24,885
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 49,770
Sub Total 6,623,772

0.36

Batu krikil 117,300 35,894


P. Cement 24,480 74,909
Pasir 35,700 7,069
-
Pouring Concrete, Cleaning 50,000 18,180
Equipment -
Lory, timber, ducting etc. 2,000 720
Sub Total 136,771

4.44

Tanah merah - -
-
Pekerja 28,050.00 31,136
Mandor 45,900.00 2,038
Sub Total 33,173

10.80

Pasir 35,700 462,672


-
Pekerja 28,050 90,882
Mandor 45,900 4,957
Sub Total 558,511

10.80

Batu krikil 117,300 1,152,824


P. Cement 24,480 1,200,303
Pasir 35,700 208,202
-
Pouring Concrete, Cleaning 50,000 545,400
Equipment -
Lory, timber, ducting etc. 2,000 21,600

Sub Total 3,128,330

216.00

BRC Mesh M-8 38,298 8,437,840


Chair (Besi Beton dia.8 mm) 5,579 60,258
Labour Cost -
Install, Lifting 2,500 540,000
Equipment -
Supporting Tools 750 162,000
Sub Total 9,200,098
32.40

Batu krikil 117,300 3,230,442


P. Cement 24,480 6,741,792
Pasir 35,700 636,174
-
Pouring Concrete, Cleaning 50,000 1,636,200
Equipment -
Lory, timber, ducting etc. 2,000 64,800
Sub Total 12,309,408

18.00 -
-
SK Wood 2,203,200 475,891
Triplex 12 mm thick 117,300 717,876
Nails 9,078 65,362
-
Fabrication, Installation, Remove 20,000 360,000
Equipment -
Tools 1,000 18,000
Sub Total 1,637,129

24.55

Setting, Leveling, Cleaning and Compacted 4,500 110,475


Equipment -
Excavator 16,500 405,075
Sub Total 515,550

2.32

Pasir 35,700 99,389


-
Pekerja 27,500 19,140
Mandor 35,000 812
Sub Total 119,341

81.83

Brick 357 1,840,439


Portland Cement 612 694,108
Pasir 35,700 116,853
-
Brick Work 15,000 1,227,450
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 163,660
Sub Total 4,042,511

104.99

Portland Cement 612 381,668


Pasir 35,700 78,711
-
Cement Plaster 13,000 1,364,870
Equipment -
Supporting Tools 2,000 209,980
Sub Total 2,035,229

4,850.40

WF-250x125x6x9 6,630 32,479,734


Welding Electroda 10,710 623,373
-
Fabrication, Installation 800 3,880,320
Equipment -
Steel Structure Tools 125 606,300
Transportation Cost 350 1,697,640
Sub Total 39,287,367

768.00

WF-200x100x5.5x8 6,630 5,142,758


Welding Electroda 10,710 98,703
-
Fabrication, Installation 800 614,400
Equipment -
Steel Structure Tools 125 96,000
Transportation Cost 350 268,800
Sub Total 6,220,662

482.40

UNP-125x65x6 6,630 3,230,295


Welding Electroda 10,710 61,998
-
Fabrication, Installation 800 385,920
Equipment -
Steel Structure Tools 125 60,300
Transportation Cost 350 168,840
Sub Total 3,907,353

3,814.40

CNP-150x50x20x2.3 6,120 23,577,569


Welding Electroda 10,710 490,227
-
Fabrication, Installation 800 3,051,520
Equipment -
Steel Structure Tools 125 476,800
Transportation Cost 350 1,335,040
Sub Total 28,931,156

162.60
CNP-125x50x20x2.3 6,120 1,005,063
Welding Electroda 10,710 20,897
-
Fabrication, Installation 800 130,080
Equipment -
Steel Structure Tools 125 20,325
Transportation Cost 350 56,910
Sub Total 1,233,275

96.96

Plat t = 15 mm 7,497 734,178


Welding Electroda 10,710 12,461
-
Fabrication, Installation 800 77,568
Equipment -
Steel Structure Tools 125 12,120
Transportation Cost 350 33,936
Sub Total 870,264

280.00

Plat t = 12 mm 7,497 2,120,152


Welding Electroda 10,710 35,986
-
Fabrication, Installation 800 224,000
Equipment -
Steel Structure Tools 125 35,000
Transportation Cost 350 98,000
Sub Total 2,513,137

208.00

Plat t = 8 mm & 6 mm 7,497 1,574,970


Welding Electroda 10,710 26,732
-
Fabrication, Installation 800 166,400
Equipment -
Steel Structure Tools 125 26,000
Transportation Cost 350 72,800
Sub Total 1,866,902

227.52

Besi Beton dia. 16 mm 5,579 1,282,119


Welding Electroda 10,710 29,241
-
Fabrication, Installation 800 182,016
Equipment -
Steel Structure Tools 125 28,440
Transportation Cost 350 79,632
Sub Total 1,601,448
32.00

Anchor Bolt dia.16 mm - 50 cm 8,160 261,120


-
Setting 9,500 304,000
Equipment -
Transportation 500 16,000
Sub Total 581,120

12.00 -
-
Turn Bucles dia. 5/8" 7,650 92,718
Equipment -
Steel Structure Tools 125 1,500
Transportation Cost 500 6,000
Sub Total 100,218

220.00

Tie Rod dia. 12 mm 10,200 2,266,440


-
Installation 2,400 528,000
Equipment -
Steel Structure Tools 125 27,500
Transportation Cost 500 96,800
Sub Total 2,918,740

232.00

Baut dia. 5/8" 1,253 293,500


Equipment -
Steel Structure Tools 125 29,000
Transportation Cost 500 116,000
Sub Total 438,500

680.00

Baut dia. ½" 655 449,744


Equipment -
Steel Structure Tools 125 85,000
Transportation Cost 500 340,000
Sub Total 874,744

3,182.00

Baut seng dia. 6 mm 194 622,838


Equipment -
Steel Structure Tools 125 397,750
Transportation Cost 500 1,591,000
Sub Total 2,611,588

394.00 -
-
Atap Primadeck t=0.45 mm 46,303 18,608,102
-
Install, Lifting, Fixing 3,500 1,379,000
Equipment -
Supporting Tools & Transportation 1,000 394,000
Sub Total 20,381,102

187.00 -
-
Clading Primadeck t=0.40 mm 40,934 7,807,791
-
Install, Lifting, Fixing 3,500 654,500
Equipment -
Supporting Tools & Transportation 1,000 187,000
Sub Total 8,649,291

20.00

Rabung Galvalume t=0.40 mm 37,332 761,573


-
Install, Lifting, Fixing 3,500 70,000
Equipment -
Supporting Tools & Transportation 1,000 20,000
Sub Total 851,573

36.00

Flashing Galvalume 55,080 2,022,538


-
Install, Lifting, Fixing 3,500 126,000
Equipment -
Supporting Tools & Transportation 1,000 36,000
Sub Total 2,184,538

10,890.28

Primer (Kansai) 11,220 1,221,889


Finish (Bee Brand) 25,500 5,554,043
-
Primer & Finish 300 3,267,084
Equipment -
Supporting Tools 50 544,514
Sub Total 10,587,530

14.50

Setting, Leveling, Cleaning and Compacted 4,500 65,250


Equipment -
Excavator 16,500 239,250
Sub Total 304,500
1.73

Pasir 35,700 73,899


-
Pekerja 27,500 14,231
Mandor 35,000 604
Sub Total 88,734

3.16

Batu krikil 117,300 336,774


P. Cement 24,480 350,644
Pasir 35,700 60,822
-
Pouring Concrete, Cleaning 50,000 159,328
Equipment -
Lory, timber, ducting etc. 2,000 6,310

Sub Total 913,878

58.65

SK Wood 2,203,200 1,550,612


Triplex 12 mm thick 117,300 2,339,079
Nails 9,078 212,970
-
Fabrication, Installation, Remove 20,000 1,173,000
Equipment -
Tools 1,000 58,650
Sub Total 5,334,311

7.12

Batu krikil 117,300 684,844


P. Cement 24,480 1,185,224
Pasir 35,700 137,259
-
Pouring Concrete, Cleaning 50,000 359,560
Equipment -
Lory, timber, ducting etc. 2,000 14,240
Sub Total 2,381,127

217.33

Rebar U32 5,579 1,248,948


Bindraad 6,630 28,818
-
Fabricatiom, Installation 700 152,131
Transportation & lifting 25 5,433
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 10,867
Sub Total 1,446,197
33.00

Brick 357 742,203


Portland Cement 612 279,917
Pasir 35,700 47,124
-
Brick Work 15,000 495,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 66,000
Sub Total 1,630,244

66.00

Portland Cement 612 239,928


Pasir 35,700 49,480
-
Cement Plaster 13,000 858,000
Equipment -
Supporting Tools 2,000 132,000
Sub Total 1,279,409

1.75

Pasir 35,700 74,970


-
Pekerja 27,500 14,438
Mandor 35,000 613
Sub Total 90,020

3.50

Batu krikil 117,300.00 373,601


P. Cement 24,480 388,987
Pasir 35,700 67,473
-
Pouring Concrete, Cleaning 50,000 176,750
Equipment -
Lory, timber, ducting etc. 2,000 7,000

Sub Total 1,013,811

32.00

Kramik 40 x 40 cm ex Roman 40,800.00 1,370,880


Portland Cement 612 116,329
Pasir 35,700 23,990
Semen putih 2,040.00 1,306
-
Brick Work 15,000 480,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 64,000
Sub Total 2,056,505
18.50

Kramik K. mandi dinding t=15 cm + bak dan tempat air Wudhu 43,860.00 851,981
Portland Cement 612 67,253
Pasir 35,700 13,869
Semen putih 2,040.00 755
-
Ceramic Instalation 15,000 277,500
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 37,000
Sub Total 1,248,357

5.00

Keramik lantai K.mandi & tempat wudhu 43,860.00 230,265


Portland Cement 612 18,176
Pasir 35,700 3,749
Semen putih 2,040.00 204
-
Ceramic Instalation 15,000 75,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 10,000
Sub Total 337,394

1.00

Closed Jongkok KIA 122,400.00 123,624


Portland Cement 612 3,635
Pasir 35,700 750
Semen putih 2,040.00 41
-
Ceramic Instalation 75,000 75,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 2,000
Sub Total 205,050

1.00

Wastafel KIA studio 50, Kran air PIO 357,000.00 357,000


Portland Cement 612 3,635
Pasir 35,700 750
Semen putih 2,040.00 41
-
Ceramic Instalation 75,000 75,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 2,000
Sub Total 438,426

5.00

Kran air biasa 25,500.00 127,500


Portland Cement 612 18,176
Pasir 35,700 3,749
Semen putih 2,040.00 204
-
Ceramic Instalation 10,000 50,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 10,000
Sub Total 209,629

2.00

Pintu Panel + Kosen + Jalusi (uk. 820x210 cm) 175,000 353,500


-
Installation & Setting 250,000 500,000
Equipment -
Supporting Tools 10,000 20,000
Sub Total 873,500

2.00

Meranti Keras 2,244,000 4,532,880


Equipment
Supporting Tools 10,000 20,000
Sub Total 4,552,880

2.00

Kosen Jendela 175,000 353,500


-
Installation & Setting 250,000 500,000
Equipment -
Supporting Tools 10,000 20,000
Sub Total 873,500

1.00

Kosen Lobang angin (uk. 50 x 60 cm) 175,000 176,750


-
Installation & Setting 250,000 250,000
Equipment -
Supporting Tools 10,000 10,000
Sub Total 436,750

1.00

Ventilasi (uk. 70 x 100 cm) 175,000 176,750


-
Installation & Setting 250,000 250,000
Equipment -
Supporting Tools 10,000 10,000
Sub Total 436,750

0.19 -
0.05 -
0.03 -
0.63 -
0.10 -

-
1" x 6" 2,750,000.00 527,725
1" x 9" 2,750,000.00 136,098
2" x 2" 2,750,000.00 73,882
2" x 3" 2,750,000.00 1,755,380
2" x 4" 2,750,000.00 274,973
-
Fabrication 900,000 896,940
Equipment -
Suporting Tools 1,000 2,990
Sub Total 3,667,986

33.63

Atap seng "BJLS" 41,412 1,406,403


-
Install 3,500 117,688
Equipment -
Supporting Tools 1,000 33,625
Sub Total 1,557,716

41.55

Asbestos t=4 mm 7,650 321,036


-
Install 3,500 145,425
Equipment -
Supporting Tools 1,000 41,550
Sub Total 508,011

64.00

Tripleks 4 mm 39,270 2,538,413


-
Install 3,500 224,000
Equipment -
Supporting Tools 1,000 64,000
Sub Total 2,826,413

135.00

Cat dasar (KIMEX) 5,793.60 110,281


Cat Finish (VINILEX) 10,098.00 387,157
-
Upah 5,000.00 675,000
Equipment -
Supporting Tools 125 16,875
Sub Total 1,189,313

110.00
Cat dasar 5,793.60 89,859
Cat Finish 10,098.00 315,462
-
Upah 5,000.00 550,000
Equipment -
Supporting Tools 125 13,750
Sub Total 969,070

20.46

Setting, Leveling, Cleaning and Compacted 4,500 92,070


Equipment -
Excavator 16,500 337,590
Sub Total 429,660

1.86

Batu krikil 117,300 198,542


P. Cement 24,480 206,719
Pasir 35,700 35,857
-
Pouring Concrete, Cleaning 50,000 93,930
Equipment -
Lory, timber, ducting etc. 2,000 3,720

Sub Total 538,768

70.68

Brick 357 1,589,664


Portland Cement 612 599,530
Pasir 35,700 100,931
-
Brick Work 15,000 1,060,200
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 141,360
Sub Total 3,491,685

152.52

Portland Cement 612 554,453


Pasir 35,700 114,344
-
Cement Plaster 13,000 1,982,760
Equipment -
Supporting Tools 2,000 305,040
Sub Total 2,956,597
6.38
-
Setting, Leveling, Cleaning and Compacted 4,500 28,728
Equipment -
Excavator 16,500 105,336
Sub Total 134,064

0.76 -
-
Pasir 35,700 32,558
-
Pekerja 27,500 6,270
Mandor 35,000 266
Sub Total 39,094

25.84

SK Wood 2,203,200 683,168


Triplex 12 mm thick 117,300 1,030,551
Nails 9,078 93,830
-
Fabrication, Installation, Remove 20,000 516,800
Equipment -
Tools 1,000 25,840
Sub Total 2,350,189

3.14

Batu krikil 117,300 334,639


P. Cement 24,480 348,421
Pasir 35,700 60,437
-
Pouring Concrete, Cleaning 50,000 158,318
Equipment -
Lory, timber, ducting etc. 2,000 6,270

Sub Total 908,085

2.64

Batu krikil 117,300 253,450


P. Cement 24,480 438,633
Pasir 35,700 50,798
-
Pouring Concrete, Cleaning 50,000 133,068
Equipment -
Lory, timber, ducting etc. 2,000 5,270

Sub Total 881,218

95.75

Rebar U32 5,579 550,255


Bindraad 6,630 12,696
-
Fabricatiom, Installation 700 67,025
Transportation & lifting 25 2,394
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 4,788
Sub Total 637,157

18.00

Pipa PVC Ø. 3" 121,529 2,296,897


Glue 58,650 52,785
-
Installation 20,000 360,000
Equipment -
Suporting Tools 1,000 18,000
Sub Total 2,727,682

15.20

Brick 357 341,863


Portland Cement 612 128,931
Pasir 35,700 21,706
-
Brick Work 15,000 228,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 30,400
Sub Total 750,900

30.40

Portland Cement 612 110,513


Pasir 35,700 22,791
-
Cement Plaster 13,000 395,200
Equipment -
Supporting Tools 2,000 60,800
Sub Total 589,303

1.30

Pasir 35,700 55,692


-
Pekerja 27,500 10,725
Mandor 35,000 455
Sub Total 66,872

0.15
0.20
0.25

2" x 2" 2,750,000.00 429,083


2" x 4" 2,750,000.00 572,303
4" x 4" 2,750,000.00 715,234
-
Fabrication 900,000 535,050
Equipment -
Suporting Tools 1,000 1,784
Sub Total 2,253,452

0.46

Papan 3/4" x 8" 2,203,200 1,014,706


-
Fabrication 900,000 410,400
Equipment -
Suporting Tools 1,000 456
Sub Total 1,425,562

11.20

Atap seng "BJLS" 41,412 5,566


-
Fabrication 20,000 224,000
Equipment -
Suporting Tools 1,000 11,200
Sub Total 240,766

1.00

Pintu + Accessories + Pengecatan 960,000 11,520


-
Fabrication 250,000 250,000
Equipment -
Suporting Tools 1,000 1,000
Sub Total 262,520

1.00

-
Jendela + Accessories + Pengecatan 960,000 11,520
-
Fabrication 250,000 250,000
Equipment -
Suporting Tools 1,000 1,000
Sub Total 262,520

78.35

Cat dasar (Kimex) 5,793.60 64,004


Cat Finish (Vinilex) 10,098.00 224,695
-
Upah 5,000.00 391,750
Equipment -
Supporting Tools 125 9,794
Sub Total 690,242
10.12 -
-
Setting, Leveling, Cleaning and Compacted 4,500 45,540
Equipment -
Excavator 16,500 166,980
Sub Total 212,520

0.51 -
-
Batu krikil 117,300 54,012
P. Cement 24,480 56,236
Pasir 35,700 9,755
-
Pouring Concrete, Cleaning 50,000 25,553
Equipment -
Lory, timber, ducting etc. 2,000 1,012

Sub Total 146,568


-
34.96 -
-
Brick 357 786,285
Portland Cement 612 296,542
Pasir 35,700 49,923
-
Brick Work 15,000 524,400
Equipment -
Suporting Tools 17,500 611,800
Sub Total 2,268,950

75.44 -
-
Portland Cement 612 274,246
Pasir 35,700 56,557
-
Cement Plaster 13,000 980,720
Equipment -
Supporting Tools 2,000 150,880
Sub Total 1,462,403

-
-
-
11.67 -
-
Setting, Leveling, Cleaning and Compacted 4,500 52,515
Equipment -
Excavator 16,500 192,555
Sub Total 245,070

1.39
Pasir 35,700 59,548
-
Pekerja 28,050.00 11,697
Mandor 45,900.00 638
Sub Total 71,882

74.84 -
-
SK Wood 2,203,200 1,978,756
Triplex 12 mm thick 117,300 2,984,928
Nails 9,078 271,774
-
Fabrication, Installation, Remove 20,000 1,496,880
Equipment -
Tools 1,000 74,844
Sub Total 6,807,182

5.73

Batu krikil 117,300 611,637


P. Cement 24,480 636,828
Pasir 35,700 110,463
-
Pouring Concrete, Cleaning 50,000 289,365
Equipment -
Lory, timber, ducting etc. 2,000 11,460

Sub Total 1,659,753

7.58

Batu krikil 117,300 729,282


P. Cement 24,480 1,262,130
Pasir 35,700 146,166
-
Pouring Concrete, Cleaning 50,000 382,891
Equipment -
Lory, timber, ducting etc. 2,000 15,164

Sub Total 2,535,633

175.04

Rebar U32 5,579 1,005,917


Bindraad 6,630 23,210
-
Fabricatiom, Installation 700 122,528
Transportation & lifting 25 4,376
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 8,752
Sub Total 1,164,783
15.00

Pipa PVC Ø. 3" 121,529 1,914,080


Glue 58,650 43,988
-
Fabrication 20,000 300,000
Equipment -
Suporting Tools 1,000 15,000
Sub Total 2,273,068

29.64

Brick 357 666,633


Portland Cement 612 251,416
Pasir 35,700 42,326
-
Brick Work 15,000 444,600
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 59,280
Sub Total 1,464,255

59.28

Portland Cement 612 215,499


Pasir 35,700 44,442
-
Cement Plaster 13,000 770,640
Equipment -
Supporting Tools 2,000 118,560
Sub Total 1,149,142

1.60

Pasir 35,700 68,544


-
Pekerja 28,050 13,464
Mandor 45,900 734
Sub Total 82,742

0.07 -
0.29 -
0.37 -
-
1" x 6" 2,750,000 12,210
2" x 3" 2,750,000 48,279
2" x 4" 2,750,000 60,225
-
Fabrication 900,000 658,440
Equipment -
Suporting Tools 1,000 732
Sub Total 779,886

2.00
Pintu + Accessories + Pengecatan 960,000 1,920,000
-
Fabrication 250,000 500,000
Equipment -
Suporting Tools 1,000 2,000
Sub Total 2,422,000

16.50

Pasangan keramik lantai toilet 43,860.00 759,875


Portland Cement 612 59,982
Pasir 35,700 12,370
Semen putih 2,040.00 673
-
Brick Work 15,000 247,500
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 33,000
Sub Total 1,113,400

49.50

Pasangan keramik dinding toilet 47,430.00 2,465,174


Portland Cement 612 179,946
Pasir 35,700 37,110
Semen putih 2,040.00 2,020
-
Pasangan keramik dinding toilet 25,000 1,237,500
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 99,000
Sub Total 4,020,750

5.00

Pintu + Accessories + Pengecatan 960,000 4,800,000


-
Instalation 250,000 1,250,000
Equipment -
Suporting Tools 1,000 5,000
Sub Total 6,055,000

2.00

Floordrain 45,900 91,800


-
Instalation 20,000 40,000
Equipment -
Suporting Tools 1,000 2,000
Sub Total 133,800

2.00
-
Kran air biasa 25,500 51,000
-
Instalation 20,000 40,000
Equipment -
Suporting Tools 1,000 2,000
Sub Total 93,000

5.00
-
Closed duduk Merk KIA standart 1,020,000 5,100,000
-
Instalation 150,000 750,000
Equipment -
Suporting Tools 1,000 5,000
Sub Total 5,855,000

52.00
-
Atap seng "BJLS" 41,412 2,196,492
Nails 9,078 70,808
-
Instalation 20,000 1,040,000
Equipment -
Suporting Tools 1,000 52,000
Sub Total 3,359,301

187.20
-
Cat dasar (Kimex) 5,793.60 152,923
Cat Finish (Vinilex) 10,098.00 536,858
-
Upah 5,000.00 936,000
Equipment -
Supporting Tools 125 23,400
Sub Total 1,649,181

16.17

Setting, Leveling, Cleaning and Compacted 4,500 72,765


Equipment
Excavator 16,500 266,805
Sub Total 339,570

0.81

Batu krikil 117,300 86,302


P. Cement 24,480 89,856
Pasir 35,700 15,586
-
Pouring Concrete, Cleaning 50,000 40,829
Equipment -
Lory, timber, ducting etc. 2,000 1,617
Sub Total 234,191

55.86

Brick 357 1,256,347


Portland Cement 612 473,822
Pasir 35,700 79,768
-
Brick Work 15,000 837,900
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 111,720
Sub Total 2,759,558

120.54

Portland Cement 612 438,197


Pasir 35,700 90,369
-
Cement Plaster 13,000 1,567,020
Equipment -
Supporting Tools 2,000 241,080
Sub Total 2,336,665

GRAND TOTAL 5,226,859,997


Rekapitulasi Pemakaina Bahan Sementara
Proyek Rubber Wod Processing Plants

UPAH:
Pekerja Rp. 28,050.00 27,500.00 / hari
Mandor Rp. 45,900.00 45,000.00 / hari
Tukang Rp. 40,800.00 40,000.00 / hari
Kepala tukang Rp. 45,900.00 45,000.00 / hari
Pemasak aspal Rp. 28,050.00 27,500.00 / hari
Jaga malam Rp. 25,500.00 25,000.00 / hari

BAHAN: Harga
Tanah merah Rp. 0.00 0.00 / m3
Pasir Rp. 35,700.00 35,000.00 / m3
Batu Kerikil Rp. 117,300.00 115,000.00 / m3
P. Cement Ex Andalas @ 40 Kg Rp. 24,480.00 24,000.00 / Zak @ 40 Kg
P. Cement Ex Andalas Rp. 612.00 600.00 / Kg
Batu Bata Mesin Rp. 357.00 350.00 / Pcs
Riol Beton dia. 30 mm Rp. 34,170.00 33,500.00 / Pcs
Asbes/ Eternit Rp. 7,650.00 7,500.00 / Lbr
Lat Asbes Rp. 7,650.00 7,500.00 / Btg
Profil Sudut kayu Rp. 15,300.00 15,000.00 / Btg
Wiremesh M-7 Rp. 302,940.00 297,000.00 / Lbr
Wiremesh M-7 Rp. 28,579.25 28,018.87 / m2
Wiremesh M-8 Rp. 405,960.00 398,000.00 / Lbr
Wiremesh M-8 Rp. 38,298.11 37,547.17 / m2
Kayu Sembarang Rp. 2,203,200.00 2,160,000.00 / m3
Kayu Sembarang Rp. 1,632,000.00 1,600,000.00 / Ton
Kayu Sembarang - 2" x 2" Rp. 14,280.00 14,000.00 / Btg
Papan Sembarang Rp. 1,734,000.00 1,700,000.00 / Ton
Papan Sembarang Rp. 24,480.00 24,000.00 / Btg
Kayu Meranti Rp. 2,244,000.00 2,200,000.00 / Ton
Kayu Meranti - 2" x 6" Rp. 79,560.00 78,000.00 / Btg
Kayu Meranti - 2" x 9" Rp. 128,520.00 126,000.00 / Btg
Tripleks - 3 mm Rp. 33,660.00 33,000.00 / Lbr
Tripleks - 4 mm Rp. 39,270.00 38,500.00 / Lbr
Tripleks - 9 mm Rp. 44,880.00 44,000.00 / Lbr
Tripleks - 12 mm Rp. 117,300.00 115,000.00 / Lbr
Garuda Form 18 mm Rp. 173,400.00 170,000.00 / Lbr
Paku Rp. 9,078.00 8,900.00 / Kg
Besi Beton Polos Rp. 5,579.40 5,470.00 / Kg
Besi Beton - dia. 16 mm Polos Rp. 105,672.00 103,600.00 / Btg
Kawat Beton Rp. 6,630.00 6,500.00 / Kg
Pipa PVC dia 4" AW Rp. 201,434.70 197,485.00 / Btg
Pipa PVC dia 3" AW Rp. 121,528.92 119,146.00 / Btg
Lem Pipa Rp. 58,650.00 57,500.00 / Kg
Keramik lantai 40x40 Roman Rp. 40,800.00 40,000.00 / Ktk
Keramik lantai K.mandi Roman Rp. 43,860.00 43,000.00 / Ktk
Keramik dinding K.mandi Roman Rp. 47,430.00 46,500.00 / Ktk
Semen Putih Rp. 2,040.00 2,000.00 / kg
Closed Jongkok KIA Rp. 122,400.00 120,000.00 / Set
Closed duduk KIA Rp. 1,020,000.00 1,000,000.00 / Set
Wastafel KIA studio 50 Rp. 357,000.00 350,000.00 / Set
Kran air PIO Rp. 153,000.00 150,000.00 / Set
Kran air biasa Rp. 25,500.00 25,000.00 / Set
Pintu PVC (deco door 90cmx210cm) Rp. 201,960.00 198,000.00 / Set
Floordrain 3" Biasa Rp. 45,900.00 45,000.00 / Set
Atap seng BJLS 40 7' x 11 Parit Rp. 41,412.00 40,600.00 / Lbr
Ready Mix K-125 Batu Guli Rp. 314,160.00 308,000.00 / m3
Ready Mix K-175 Batu Guli Rp. 264,180.00 259,000.00 / m3
Ready Mix K-225 Batu Guli Rp. 351,900.00 345,000.00 / m3
Kawat Las RB Rp. 10,710.00 10,500 / Kg
WF.350 KS Rp. 6,630.00 6,500.00 / Btg
WF.300 KS Rp. 6,630.00 6,500.00 / Btg
WF.250 KS Rp. 6,630.00 6,500.00 / Btg
WF.200 KS Rp. 6,630.00 6,500.00 / Btg
UNP. 125.65.6 KS Rp. 6,630.00 6,500.00 / Btg
UNP. 125.50.5 KS Rp. 6,630.00 6,500.00 / Btg
CNP. 150.50.20.2,3 KS Rp. 6,120.00 6,000.00 / Btg
Rekapitulasi Pemakaina Bahan Sementara
Proyek Rubber Wod Processing Plants

CNP. 125.50.20.2,3 KS Rp. 6,120.00 6,000.00 / Btg


Plat t=16 mm 4' x 8' Rp. 7,497.00 7,350.00 / Lbr
Plat t=15 mm 4' x 8' Rp. 7,497.00 7,350.00 / Lbr
Plat t=12 mm 4' x 8' Rp. 7,497.00 7,350.00 / Lbr
Plat t=10 mm 4' x 8' Rp. 7,497.00 7,350.00 / Lbr
Plat t=8 mm 4' x 8' Rp. 7,497.00 7,350.00 / Lbr
Plat t=6 mm 4' x 8' Rp. 7,497.00 7,350.00 / Lbr
Plat bunga 6 mm 4' x 8' Rp. 7,905.00 7,750.00 / Lbr
L.50.50.5 KS Rp. 7,140.00 7,000.00 / Btg
L.65.65.6 KS Rp. 7,140.00 7,000.00 / Btg
Pipa Medium dia. 4" t=3,6 mm KS Rp. 433,500.00 425,000 / Btg
Pipa Medium dia. 1½",t=2.9mm KS Rp. 151,980.00 149,000 / Btg
Pipa Medium dia. 2",t=2.9 mm KS Rp. 191,760.00 188,000 / Btg
Anchor Bolt dia. 5/8", P=50 cm Rp. 8,160.00 8,000 / Pcs
Anchor Bolt dia. 7/8", P=60 cm Rp. 20,910.00 20,500 / Pcs
Anchor Bolt dia. 3/4", P=60 Rp. 13,260.00 13,000 / Pcs
Turn Bucles 5/8" Rp. 7,650.00 7,500 / Pcs
tie Rod dia. 12 mm P=1.25 m Rp. 10,200.00 10,000.00 / Pcs
Baut hitam + Mur + Ring - 3/4" x 2½" Rp. 2,553.06 2,503 / Pcs
Baut hitam + Mur + Ring - 5/8" x 2" Rp. 1,252.56 1,228 / Pcs
Baut hitam + Mur + Ring - ½" x 2" Rp. 654.84 642 / Pcs
Baut seng dia. 6 mm, 45 mm Rp. 193.80 190 / Pcs
Plat galvalume t=0.5 mm Rp. 55,080.00 54,000.00 / Lbr
Atap Primadeck t=0.45 Rp. 46,302.63 45,394.74 / m2
Atap Primadeck t=0.40 Rp. 40,934.21 40,131.58 / m2
Clading Primadeck t=0.40 Rp. 40,934.21 40,131.58 / m2
Rabung Galvalume t=0.40 mm Rp. 37,332.00 36,600.00 / Lbr
Cat Vinilex Rp. 10,098.00 9,900.00 / Kg
Cat Kimex Rp. 5,793.60 5,680.00 / Kg
Cat Bee Brand Rp. 25,500.00 25,000.00 / Kg
Cat Meni Kansai Rp. 11,220.00 11,000.00 / Kg
Dempul Rp. 10,200.00 10,000.00 / Kg
ahan Sementara
cessing Plants

/
/
/
/
/
/

Keperluan
/
/ 2,403.03 m3
/ 2,238.33 m3
/ 45,728.98 Zak @ 40 Kg
/
/ 187,563.35 Pcs
/ 197.25 m'
/
/
/
/ 11,518.53 m2
/
/ 220.32 m2
/
/
/
/
/
/
/
/
/
/
/
/
/
/
119,000 / 18 Kg 847.03 Kg
/
/
/ 574.99 Kg
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/ 3,005.89 Kg
3,778,350 /
2,794,500 /
2,255,000 /
1,625,000 /
485,000 /
/
165,000 /
ahan Sementara
cessing Plants

146,000 /
/
2,555,000 /
2,044,000 /
1,700,000 /
1,365,000 /
1,022,000 /
1,120,000 /
135,000 /
210,000 /
425,000 /
149,000 /
188,000 /
8,000 /
20,500 /
13,000 /
7,500 /
/
2,503 /
1,228 /
642 /
190 /
/
34,500.00 / m'
30,500 / m'
30,500 / m'
15,250 / m'
/
/
/
/
/
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Unit Rate Amount


Description Unit Volume
No. ( Rp ) ( Rp )

I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan sebelum Pekerjaan Ls 1.00 42,000,000.00 42,000,000
2 Pembuatan Direksi Keet/ Gudang Ls 1.00 36,750,000.00 36,750,000
3 Mobilisasi/ Demobolisasi Ls 1.00 42,000,000.00 42,000,000
4 Management Fee Ls 1.00 9,975,000.00 9,975,000
5 Pengadaan Air Kerja Ls 1.00 4,725,000.00 4,725,000
6 Penerangan Lampu/ Listrik Kerja Ls 1.00 37,800,000.00 37,800,000
7 Biaya Keamanan/ Jaga Malam/ OKP Ls 1.00 37,800,000.00 37,800,000
8 Dokumentasi Ls 1.00 7,875,000.00 7,875,000
9 Pembersihan Lapangan setelah selesai Pekerjaan Ls 1.00 26,250,000.00 26,250,000
10 Pengukuran/ Pematokan & Pemasangan Bowplank m' 1,501.00 18,375.00 27,580,875
Sub Total 272,755,875
II BANGUNAN PABRIK uk. 30M x 96M (3 Unit)
A. Pekerjaan Sipil uk. 30m x 96m (3 Unit)
- Pondasi Type F1 = 34 Units
1 Galian Pondasi m3 66.64 22,000.00 1,466,080
2 Pasir Urug t = 5 cm m3 3.33 65,000.00 216,580
3 Lantai Kerja K-125 t = 5 cm m3 3.33 495,000.00 1,649,340
4 Bekesting m2 137.70 60,000.00 8,262,000
5 Besi Beton Kg 2,031.84 8,850.00 17,981,784
6 Cor Beton K-225 m3 29.58 625,000.00 18,487,500
7 Timbunan Kembali Bekas Galian m3 30.40 12,500.00 380,000
Sub Total 48,443,284
- Pondasi Type F2 = 26 Units
1 Galian Pondasi m3 50.96 22,000.00 1,121,120
2 Pasir Urug t = 5 cm m3 2.55 65,000.00 165,620
3 Lantai Kerja K-125 t = 5 cm m3 2.55 495,000.00 1,261,260
4 Bekesting m2 102.44 60,000.00 6,146,400
5 Besi Beton Kg 1,553.76 8,850.00 13,750,776
6 Cor Beton K-225 m3 22.15 625,000.00 13,845,000
7 Timbunan Kembali Bekas Galian m3 23.71 12,500.00 296,400
Sub Total 36,586,576
- Pondasi Type F3 = 34 Units -
1 Galian Pondasi m3 66.64 22,000.00 1,466,080
2 Pasir Urug t = 5 cm m3 3.33 65,000.00 216,580
3 Lantai Kerja K-125 t = 5 cm m3 3.33 495,000.00 1,649,340
4 Bekesting m2 137.70 60,000.00 8,262,000
5 Besi Beton Kg 2,031.84 8,850.00 17,981,784
6 Cor Beton K-225 m3 29.58 625,000.00 18,487,500
7 Timbunan Kembali Bekas Galian m3 27.64 12,500.00 345,525
Sub Total 48,408,809
- Saluran Terbuka (Fabrik)
1 Galian m3 121.34 22,000.00 2,669,480
2 Cor Beton K-175 m3 20.22 575,000.00 11,628,225
3 Batu Bata m2 288.90 44,950.00 12,986,055
4 Plasteran sisi bagian dalam m2 404.46 22,500.00 9,100,350
Sub Total 36,384,110
- Bak Kontrol uk. 300 x 400 mm (34 Units) -
1 Galian m3 11.66 22,000.00 256,564
2 Cor Beton K-175 m3 2.10 575,000.00 1,207,500
3 Batu Bata m2 66.40 44,950.00 2,984,680
4 Plasteran m2 80.92 22,500.00 1,820,700
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Unit Rate Amount


Description Unit Volume
No. ( Rp ) ( Rp )
5 Riol/ Bis Beton dia. 300 mm m' 195.30 85,000.00 16,600,500
Sub Total 22,869,944
- Sloof uk. 250 x 400 mm -
1 Galian m3 130.95 22,000.00 2,880,900
2 Pasir Urug t = 5 cm m3 13.10 65,000.00 851,175
3 Lantai Kerja K-125 t = 5 cm m3 13.10 495,000.00 6,482,025
4 Bekesting m2 465.60 60,000.00 27,936,000
5 Besi Beton Kg 10,368.33 8,850.00 91,759,721
6 Cor Beton K-125 m3 65.48 495,000.00 32,410,125
Sub Total 162,319,946
- Lantai t = 150 mm -
1 Pasir Urug t = 5 cm m3 432.00 65,000.00 28,080,000
2 Lantai Kerja K-125 t = 5 cm m3 432.00 495,000.00 213,840,000
3 Wiremesh M-7 ( 1 Layer ) m2 8,640.00 31,750.00 274,320,000
4 Cor beton lantai K-225 m3 1,296.00 625,000.00 810,000,000
5 Bekesting m2 222.75 60,000.00 13,365,000
Sub Total 1,339,605,000
-
B. Bangunan Baja -
- Pekerjaan Struktur Baja -
1 WF-350x175x7x11 Kg 112,492.80 9,250.00 1,040,558,400
2 WF-300x150x6,5x9 Kg 22,466.40 9,250.00 207,814,200
3 UNP-125x65x6 Kg 5,869.20 9,450.00 55,463,940
4 CNP-150x50x20x2,3 Kg 49,140.20 9,150.00 449,632,830
5 CNP-125x50x20x2,3 Kg 2,276.40 9,150.00 20,829,060
6 Plat t 15 mm Kg 1,155.00 9,600.00 11,088,000
7 Plat t 12 mm Kg 3,662.40 9,600.00 35,159,040
8 Plat t 10 mm Kg 4,979.42 9,600.00 47,802,432
9 Plat t 8 mm Kg 931.10 9,600.00 8,938,560
10 Plat t 6 mm Kg 2,305.63 9,600.00 22,134,000
11 L-50x50x5 Kg 23,175.00 9,000.00 208,575,000
12 Besi Beton dia. 16 mm Kg 3,412.80 8,850.00 30,203,280
13 Tie Rod dia. 12 mm Pcs 2,888.00 13,000.00 37,544,000
14 Anchor Bolt dia. 5/8" Pcs 368.00 37,500.00 13,800,000
15 Turn Bucles dia. 5/8" Pcs 80.00 27,500.00 2,200,000
16 Baut dia. 5/8" Pcs 2,940.00 4,000.00 11,760,000
17 Baut dia. ½" Pcs 8,988.00 2,500.00 22,470,000
18 Baut seng dia. 6 mm Pcs 27,826.00 700.00 19,478,200
19 Talang datar galvalume t=0.5 mm ,2 288.00 46,500.00 13,392,000
20 Atap Primadeck t = 0.45 mm m2 10,705.00 55,000.00 588,775,000
21 Clading Primadeck t = 0.40 mm m2 1,680.00 51,500.00 86,520,000
22 Rabung Galvalume m' 306.00 41,500.00 12,699,000
23 Flashing Galvalume m' 444.00 45,000.00 19,980,000
24 Talang PVC dia. 4" Ttk 68.00 280,000.00 19,040,000
25 Cleam Talang Pcs 340.00 15,000.00 5,100,000
26 Painting Material Baja Kg 231,866.35 750.00 173,899,759
27 Transportasi Material Baja Kg 231,866.34 250.00 57,966,586
Sub Total 3,222,823,287
-
KANTOR DALAM PABRIK -
A. Pekerjaan Sipil -
- Pekerjaan Pasangan dinding Lantai dasar -
1 Pasangan dinding ½ bata 1:4 m2 107.08 44,950.00 4,813,246
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Unit Rate Amount


Description Unit Volume
No. ( Rp ) ( Rp )
2 Plasteran m2 214.16 22,500.00 4,818,600
Sub Total 9,631,846
- Pekerjaan pasangan Kosen Pintu dan Jendela -
1 Kosen & Pintu Panel Uk. 1200x2100 Bh 1.00 750,000.00 750,000
2 Jalusi Lubang Angin Bh 14.00 250,000.00 3,500,000
Sub Total 4,250,000
- Pekerjaan Pengecatan -
1 Cat Tembok Ex. Vinilex m2 214.16 11,500.00 2,462,840
2 Cat Pinti Panel Bh 1.00 150,000.00 150,000
3 Cat Jalusi Lubang Angin Bh 14.00 100,000.00 1,400,000
Sub Total 4,012,840
- Pekerjaan Pasangan dinding Lantai dua -
1 Pasangan dinding ½ bata 1:4 m2 160.40 44,950.00 7,209,980
2 Plasteran m2 320.80 22,500.00 7,218,000
Sub Total 14,427,980
- Pekerjaan pasangan Kosen Pintu dan Jendela -
1 Kusen Jendela + Jalusi 4 Lubang, Rangka Bh 5.00 1,700,000.00 8,500,000
Allumunium (Lokal) dan daun kaca gelap 5 mm -
2 Kusen pintu & jendela gendong 2 daun rangka Bh 1.00 2,150,000.00 2,150,000
allumunium (lokal), daun pintu, daun jendela -
allumunium (lokal) + kaca gelap 5 mm -
Sub Total 10,650,000
- Pekerjaan Pasangan Plafond -
1 Plafond Tripleks t = 3 mm rangka kayu m2 72.00 47,500.00 3,420,000
2 Profil sudut kayu m' 36.00 4,500.00 162,000
Sub Total 3,582,000
- Pekerjaan Pengecatan -
1 Pengecatan dinding ½ bata m2 320.80 11,500.00 3,689,200
2 Pengecatan plafond tripliex m2 72.00 11,500.00 828,000
3 Pengecatan profil kayu m' 36.00 2,500.00 90,000
Sub Total 4,607,200
- Pekerjaan Beton Lantai -
1 Cor beton t = 15 cm K-175 m2 10.80 575,000.00 6,210,000
2 Besi beton dia. 12 mm Kg 1,702.29 8,850.00 15,065,267
3 Bekesting lantai m2 72.00 60,000.00 4,320,000
Sub Total 25,595,267
- Pekerjaan Beton Ring Balok uk. 250 x 200 -
1 Beton K-175 m3 1.08 575,000.00 621,000
2 Besi beton Kg 168.12 8,850.00 1,487,862
3 Bekesting m2 21.30 11,500.00 244,950
Sub Total 2,353,812
- Pekerjaan Pondasi Tangga -
1 Pondasi tiang pipa dia. 4" Unit 1.00 275,000.00 275,000
2 Pondasi tiang UNP-125x65x6 Unit 1.00 321,200.00 321,200
Sub Total 596,200
B. Bangunan Baja -
- Pekerjaan Konstruksi Baja Gelagar -
1 WF-350x175x7x11 Kg 902.72 9,250.00 8,350,160
2 WF-300x150x6,5x9 Kg 4,844.40 9,250.00 44,810,700
3 Plat t = 16 mm Kg 373.00 9,600.00 3,580,800
4 Besi Beton dia. 12 mm anchor c/c 300 mm Kg 46.00 8,850.00 407,100
5 Baut anchor dia. 22 mm Pcs 8.00 37,500.00 300,000
6 Baut dia. 3/4" Pcs 108.00 5,000.00 540,000
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Unit Rate Amount


Description Unit Volume
No. ( Rp ) ( Rp )
7 Painting material Baja Kg 6,166.12 750.00 4,624,590
8 Transportasi Material Baja Kg 6,166.12 250.00 1,541,530
Sub Total 64,154,880
- Pekerjaan Konstruksi Baja Tangga -
1 WF-350x175x7x11 Kg 148.80 9,250.00 1,376,400
2 UNP-125x65x6 Kg 402.00 9,450.00 3,798,900
3 Pipa Medium dia. 4" Kg 12.20 9,900.00 120,780
4 Pipa dia 1½" t = 2,9 mm Kg 118.68 9,900.00 1,174,932
5 Pipa dia. 2" t = 2,9 mm Kg 123.30 9,900.00 1,220,670
6 L-65x65x6 Kg 35.50 9,000.00 319,500
7 Plat Bunga t = 6 mm Kg 345.00 10,500.00 3,622,500
8 Plat Tapak 16 mm Kg 373.00 9,600.00 3,580,800
9 Plat t = 6mm Kg 9.75 9,600.00 93,600
10 Baut dia. ½" Pcs 20.00 2,500.00 50,000
11 Baut Anchor dia. 5/8" Pcs 8.00 21,500.00 172,000
12 Painting Material Baja Kg 1,568.23 750.00 1,176,173
13 Transportasi Material Baja Kg 1,568.23 250.00 392,058
Sub Total 17,098,312
-
III BANGUNAN KLIN DRIER -
A. Pekerjaan Sipil -
- Pondasi F1 = 44 Units -
1 Galian Pondasi m3 63.36 22,000.00 1,393,920
2 Pasir Urug t = 5 cm m3 3.17 65,000.00 205,920
3 Lantai Kerja K-125 t = 5 cm m3 3.17 495,000.00 1,568,160
4 Bekesting m2 102.21 60,000.00 6,132,720
5 Besi Beton Kg 2,002.18 8,850.00 17,719,258
6 Cor Beton K-225 m3 15.53 625,000.00 9,707,500
7 Timbunan Kembali Bekas Galian m3 47.83 12,500.00 597,850
Sub Total 37,325,328
- Pekerjaan Sloof uk. 200 x 300 mm -
1 Galian m3 39.30 22,000.00 864,600
2 Pasir Urug t = 5 cm m3 6.55 65,000.00 425,750
3 Lantai Kerja K-125 t = 5 cm m3 6.55 495,000.00 3,242,250
4 Bekesting m2 196.51 60,000.00 11,790,600
5 Besi Beton Kg 5,433.40 8,850.00 48,085,572
6 Cor Beton K-225 m3 19.65 625,000.00 12,281,250
7 Timbunan Kembali Bekas Galian m3 24.24 12,500.00 303,000
Sub Total 76,993,022
- Pekerjaan pondasi menerus -
1 Galian m3 56.20 22,000.00 1,236,312
2 Pasir Urug t = 5 cm m3 4.68 65,000.00 304,395
3 Lantai Kerja K-125 t = 5 cm m3 28.10 495,000.00 13,908,510
4 Bekesting m2 210.74 60,000.00 12,644,100
5 Besi Beton Kg 1,428.13 8,850.00 12,638,951
6 Cor Beton K-225 m3 11.24 625,000.00 7,025,000
7 Pasangan dinding ½ bata 1:4 m2 1,578.84 44,950.00 70,968,858
8 Plasteran m2 3,157.68 22,500.00 71,047,800
9 Cor Beton K-175 m3 7.97 575,000.00 4,579,875
Sub Total 194,353,801
- Pekerjaan lantai bangunan t = 150 mm -
1 Pasir Urug t = 5 cm m3 132.63 65,000.00 8,621,210
2 Lantai Kerja K-125 t = 5 cm m3 132.63 495,000.00 65,653,830
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Unit Rate Amount


Description Unit Volume
No. ( Rp ) ( Rp )
3 Wiremesh M-7 (1 Layer) m2 2,652.68 31,750.00 84,222,590
4 Cor Beton lantai K-225 t=150 mm m3 347.90 625,000.00 217,438,750
5 Bekesting m2 68.00 60,000.00 4,080,000
Sub Total 380,016,380
- Pekerjaan Saluran Terbuka -
1 Galian m3 77.73 22,000.00 1,710,060
2 Pasir Urug t = 5 cm m3 7.33 65,000.00 476,450
3 Pasangan dinding ½ bata 1:4 m2 259.11 44,950.00 11,646,815
4 Plasteran m2 332.44 22,500.00 7,479,900
Sub Total 21,313,225
-
B. Bangunan Baja -
- Pekerjaan Struktur Baja -
1 WF-250x125x6x9 Kg n/a 9,250.00
2 WF-200x100x5.5x8 Kg n/a 9,250.00
3 UNP-125x65x6 Kg n/a 9,450.00
4 UNP-125x50x5 Kg n/a 9,450.00
5 CNP-150x50x20x2.3 Kg n/a 9,150.00
6 L.50.50.5 Kg n/a 9,000.00
7 Plat t = 15 mm Kg n/a 9,600.00
8 Plat t = 10 mm Kg n/a 9,600.00
9 Plat t = 8 mm Kg n/a 9,600.00
10 Plat t = 6 mm Kg n/a 9,600.00
11 Besi Beton dia. 16 mm Kg n/a 8,850.00
12 Baut dia. 5/8" Pcs n/a 4,000.00
13 Baut dia. ½" Pcs n/a 2,500.00
14 Anchor bolt dia. 5/8" Pcs n/a 21,500.00
15 Turn Bucles dia. 5/8" Pcs n/a 27,500.00
16 Tie Rod dia. 12 mm Pcs n/a 13,000.00
17 Baut atap & Clading Pcs n/a 700.00
18 Atap Spandek Zincalumet=0.40 mm m2 n/a 68,000.00
19 Clading spandek zincalume t=0.4 mm m2 n/a 68,000.00
20 Rabung Galvalume m' n/a 22,000.00
21 Flashing Galvalume m' n/a 2,500.00
22 Talang datar galvalume t=0.5 mm m' n/a 46,500.00
23 Talang tegak PVC 4"
- Bawah P=4,5 m ttk n/a 225,000.00
- Tengah P=2,5 m ttk n/a 105,000.00
- Atas P=1,5 m ttk n/a 75,000.00
23 Dinding ventilasi tinggi 2m P=2x90m
- L-60.60.6 Kg n/a 9,000.00
- Besi Beton dia. 10 mm Kg n/a 8,850.00
- Plat t = 8 mm Kg n/a 9,600.00
- Baut dia. 5/8" Pcs n/a 4,000.00
24 Pintu swing (double) uk.1,8x2m rangka Unit n/a 3,250,000.00
L-50.50.5, daun plat t=2.8 mm termasuk Cat
Kunci grendel & Kunci slot
25 Painting Material Baja Kg n/a 750.00
26 Transportasi Material Baja Kg n/a 250.00
Sub Total -
IV RUMAH BOILER DAN BANGUNAN PENDUKUNG -
A. Pekerjaan Sipil -
- Pondasi F1 = 8 Units -
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Unit Rate Amount


Description Unit Volume
No. ( Rp ) ( Rp )
1 Galian Pondasi m3 11.52 22,000.00 253,440
2 Pasir Urug t = 5 cm m3 0.58 65,000.00 37,440
3 Lantai Kerja K-125 t = 5 cm m3 0.58 495,000.00 285,120
4 Bekesting m2 10.58 60,000.00 635,040
5 Besi Beton Kg 364.03 8,850.00 3,221,666
6 Cor Beton K-225 m3 2.82 625,000.00 1,765,000
7 Timbunan Kembali Bekas Galian m3 8.70 12,500.00 108,700
Sub Total 6,306,406
- Pondasi F2 = 4 Units -
1 Galian Pondasi m3 5.76 22,000.00 126,720
2 Pasir Urug t = 5 cm m3 0.29 65,000.00 18,720
3 Lantai Kerja K-125 t = 5 cm m3 0.29 495,000.00 142,560
4 Bekesting m2 8.20 60,000.00 492,000
5 Besi Beton Kg 182.01 8,850.00 1,610,789
6 Cor Beton K-225 m3 1.41 625,000.00 882,500
7 Timbunan Kembali Bekas Galian m3 4.35 12,500.00 54,350
Sub Total 3,327,639
- Pekerjaan Sloof uk. 200 x 300 mm -
1 Galian m3 7.20 22,000.00 158,400
2 Pasir Urug t = 5 cm m3 1.20 65,000.00 78,000
3 Lantai Kerja K-125 t = 5 cm m3 1.20 495,000.00 594,000
4 Bekesting m2 36.00 60,000.00 2,160,000
5 Besi Beton Kg 995.40 8,850.00 8,809,290
6 Cor Beton K-225 m3 0.36 625,000.00 225,000
7 Timbunan Kembali Bekas Galian m3 4.44 12,500.00 55,500
Sub Total 12,080,190
- Pekerjaan Lantai Boiler -
1 Pasir urug dipadatkan t = 5 cm m3 10.80 22,000.00 237,600
2 Lantai Kerja K-125 t = 5 cm m3 10.80 495,000.00 5,346,000
3 Primamesh M-8 (1 Layer) m2 216.00 39,500.00 8,532,000
4 Cor Lantai K-225 m3 32.40 625,000.00 20,250,000
5 Bekesting m2 18.00 60,000.00 1,080,000
Sub Total 35,445,600
- Pekerjaan Saluran Terbuka -
1 Galian m3 24.55 22,000.00 540,100
2 Pasir Urug m3 2.32 65,000.00 150,800
3 Pas Batu Bata m2 81.83 44,950.00 3,678,259
4 Plasteran m2 104.99 22,500.00 2,362,275
Sub Total 6,731,434
B. Bangunan Baja -
- Pekerjaan Struktur Baja -
1 WF-250x125x6x9 Kg 4,850.40 9,250.00 44,866,200
2 WF-200x100x5.5x8 Kg 768.00 9,250.00 7,104,000
3 UNP-125x65x6 Kg 482.40 9,450.00 4,558,680
4 CNP-150x50x20x2.3 Kg 3,814.40 9,150.00 34,901,760
5 CNP-125x50x20x2.3 Kg 162.60 9,150.00 1,487,790
6 Plat t = 15 mm Kg 96.96 9,600.00 930,816
7 Plat t = 12 mm Kg 280.00 9,600.00 2,688,000
8 Plat t = 8 mm & 6 mm Kg 208.00 9,600.00 1,996,800
9 Besi Beton dia. 16 mm Kg 227.52 8,850.00 2,013,552
10 Anchor bolt dia. 5/8" Pcs 32.00 21,500.00 688,000
11 Turn Bucles dia. 5/8" Pcs 12.00 27,500.00 330,000
12 Tie Rod dia. 12 mm Pcs 220.00 13,000.00 2,860,000
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Unit Rate Amount


Description Unit Volume
No. ( Rp ) ( Rp )
13 Baut dia. 5/8" Pcs 232.00 4,000.00 928,000
14 Baut dia. ½" Pcs 680.00 2,500.00 1,700,000
15 Baut seng dia. 6 mm Pcs 3,182.00 700.00 2,227,400
16 Atap Primadeck t=0.45 mm m2 394.00 55,000.00 21,670,000
17 Clading Primadeck t=0.40 mm m2 187.00 51,500.00 9,630,500
18 Rabung Galvalume t=0.40 mm m' 20.00 22,000.00 440,000
19 Flashing Galvalume m' 36.00 22,500.00 810,000
20 Painting Material Baja Kg 10,890.28 750.00 8,167,710
21 Transportasi Material Baja Kg 10,890.28 250.00 2,722,570
Sub Total 152,721,778
-
V KANTIN DAN MUSHALLAH -
A. Pekerjaan Sipil -
- Pondasi -
1 Galian m3 14.50 22,000.00 319,000
2 Pasir urug t = 5 cm m3 1.73 65,000.00 112,125
3 Cor K-125 m3 3.16 495,000.00 1,561,725
4 Bekesting m3 58.65 60,000.00 3,519,000
5 Cor Pondasi menerus K-175 m3 7.12 575,000.00 4,094,000
6 Besi Beton Kg 217.33 9,600.00 2,086,368
7 Pasangan Batu Bata m2 33.00 44,950.00 1,483,350
8 Plasteran m2 66.00 22,500.00 1,485,000
Sub Total 14,660,568
- Pekerjaan lantai dan Accessories -
1 Pasir urug t = 5 cm m3 1.75 65,000.00 113,750
2 Cor lantai K-125 m3 3.50 495,000.00 1,732,500
3 Kramik 40 x 40 cm ex Roman m2 32.00 85,000.00 2,720,000
4 Kramik K. mandi dinding t=15 cm + bak dan tempat air Wudhu m2 18.50 78,500.00 1,452,250
5 Keramik lantai K.mandi & tempat wudhu m2 5.00 78,000.00 390,000
6 Closed Jongkok KIA Unit 1.00 150,000.00 150,000
7 Wastafel KIA studio 50, Kran air PIO Unit 1.00 425,000.00 425,000
8 Kran air biasa Unit 5.00 50,000.00 250,000
9 Pintu Panel + Kosen + Jalusi (uk. 820x210 cm) Unit 2.00 550,000.00 1,100,000
10 Meranti Keras -
11 Kosen Jendela kaca nako lengkap jalusi + Fixed Unit 2.00 750,000.00 1,500,000
Clear (uk. 145x240 cm) -
12 Kosen Lobang angin (uk. 50 x 60 cm) Unit 1.00 125,000.00 125,000
13 Ventilasi (uk. 70 x 100 cm) Unit 1.00 175,000.00 175,000
14 Kayu (Meranti Keras) -
- 1" x 6" m3 0.19 2,750,000.00 522,500
- 1" x 9" m3 0.05 2,750,000.00 134,750
- 2" x 2" m3 0.03 2,750,000.00 73,150
- 2" x 3" m3 0.63 2,750,000.00 1,738,000
- 2" x 4" m3 0.10 2,750,000.00 272,250
15 Atap seng "BJLS" m2 33.63 25,000.00 840,625
16 Asbestos t=4 mm m2 41.55 55,000.00 2,285,250
17 Tripleks 4 mm m2 64.00 57,500.00 3,680,000
18 Cat dinding m2 135.00 11,500.00 1,552,500
19 Cat Plafond & Listplank m2 110.00 11,500.00 1,265,000
Sub Total 22,497,525
- Pekerjaan Saluran Terbuka uk. 37.2 x 0.3 m -
1 Galian m3 20.46 22,000.00 450,120
2 Cor K-125 m3 1.86 495,000.00 920,700
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Unit Rate Amount


Description Unit Volume
No. ( Rp ) ( Rp )
3 Pasangan Batu bata m2 70.68 44,950.00 3,177,066
4 Plasteran m2 152.52 22,500.00 3,431,700
Sub Total 7,979,586
-
VI RUMAH JAGA -
A. Pekerjaan Sipil -
- Bangunan -
1 Galian Pondasi m3 6.38 22,000.00 140,448
2 Pasir urug m3 0.76 65,000.00 49,400
3 Bekesting m2 25.84 60,000.00 1,550,400
4 Cor pondasi menerus K-125 m3 3.14 495,000.00 1,551,825
5 Cor K-175 m3 2.64 575,000.00 1,515,125
6 Besi Beton Kg 95.75 8,850.00 847,388
7 Pipa PVC Ø. 3" m' 18.00 32,500.00 585,000
8 Pasangan Bata m2 15.20 44,950.00 683,240
9 Plasteran m2 30.40 22,500.00 684,000
10 Pasir dipadatkan m3 1.30 65,000.00 84,500
11 Kayu (Meranti Keras) -
- 2" x 2" m3 0.15 2,750,000.00 408,650
- 2" x 4" m3 0.20 2,750,000.00 545,050
- 4" x 4" m3 0.25 2,750,000.00 681,175
12 Papan 3/4" x 8" m3 0.46 2,750,000.00 1,254,000
13 Atap seng "BJLS" m2 11.20 25,000.00 280,000
14 Pintu panel lengkap dengan jalusi, kunci Set 1.00 850,000.00 850,000
Accessories & Cat -
15 Jendela Sisir lengkap dengan kosen daun Set 1.00 450,000.00 450,000
jendela uk. 600 mm x 1200 mm -
16 Pengecatan dinding plafond m2 78.35 11,500.00 901,025
Sub Total 13,061,226
- Pekerjaan Saluran Terbuka -
1 Galian m3 10.12 22,000.00 222,640
2 Cor K-125 m3 0.51 495,000.00 250,470
3 Pasangan bata 1:3 m2 34.96 44,950.00 1,571,452
4 Plasteran m2 75.44 22,500.00 1,697,400
Sub Total 3,741,962
-
VII TOILET -
A. Pekerjaan Sipil -
- Bangunan -
1 Galian Pondasi m3 11.67 22,000.00 256,740
2 Pasir urug m3 1.39 65,000.00 90,350
3 Bekesting m2 74.84 60,000.00 4,490,640
4 Cor K-125 m3 5.73 495,000.00 2,836,350
5 Cor K-175 m3 7.58 575,000.00 4,359,650
6 Besi Beton Kg 175.04 8,850.00 1,549,104
7 Pipa PVC Ø. 3" m' 15.00 35,000.00 525,000
8 Pasangan Bata m2 29.64 44,950.00 1,332,318
9 Plasteran m2 59.28 22,500.00 1,333,800
10 Pasir dipadatkan m3 1.60 65,000.00 104,000
11 Kayu (Meranti Keras) -
- 1" x 6" m3 0.07 2,750,000.00 203,500
- 2" x 3" m3 0.29 2,750,000.00 804,650
- 2" x 4" m3 0.37 2,750,000.00 1,003,750
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Unit Rate Amount


Description Unit Volume
No. ( Rp ) ( Rp )
12 Pintu panel (allumunium t=0.5 mm) Lokal warna Set 2.00 2,750,000.00 5,500,000
uk. 2100 x 820 mm lengkap dengan kosen, -
kunci engsel & accessoriesnya -
13 Pasangan keramik lantai toilet m2 16.50 78,000.00 1,287,000
14 Pasangan keramik dinding toilet m2 49.50 78,500.00 3,885,750
15 Pintu PVC (DECO DOOR) toilet Unit 5.00 250,000.00 1,250,000
16 Floordrain Pcs 2.00 25,000.00 50,000
17 Kran air biasa Pcs 2.00 50,000.00 100,000
18 Closed duduk Merk KIA standart Pcs 5.00 150,000.00 750,000
19 Atap seng "BJLS" m2 52.00 25,000.00 1,300,000
20 Pengecatan dinding & Plafond m2 187.20 11,500.00 2,152,800
Sub Total 35,165,402
- Pekerjaan Saluran Terbuka -
1 Galian m3 16.17 22,000.00 355,740
2 Cor K-125 m3 0.81 495,000.00 400,208
3 Pasanagn bata 1:3 m2 55.86 44,950.00 2,510,907
4 Plasteran m2 120.54 22,500.00 2,712,150
Sub Total 5,979,005

TOTAL 6,380,857,245
MARGIN (5 %) 319,042,862
TOTAL 6,699,900,107
PPN (10 %) 669,990,011
TOTAL KESELURUHAN 7,369,890,118
SUMMARY - BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Jumlah Harga Sub Total Total


Description
No. ( Rp ) ( Rp ) ( Rp )

I PEKERJAAN PERSIAPAN 272,755,875.00 272,755,875.00 272,755,875.00

II BANGUNAN PABRIK uk. 30M x 96M (3 Unit) 5,078,401,293.00


A. Pekerjaan Sipil uk. 30m x 96m (3 Unit) 1,694,617,669.00
- Pondasi Type F1 = 34 Units 48,443,284.00
- Pondasi Type F2 = 26 Units 36,586,576.00
- Pondasi Type F3 = 34 Units 48,408,809.00
- Saluran Terbuka (Fabrik) 36,384,110.00
- Bak Kontrol uk. 300 x 400 mm (34 Units) 22,869,944.00
- Sloof uk. 250 x 400 mm 162,319,946.00
- Lantai t = 150 mm 1,339,605,000.00

B. Bangunan Baja 3,222,823,287.00


- Pekerjaan Struktur Baja 3,222,823,287.00

KANTOR DALAM PABRIK


A. Pekerjaan Sipil 79,707,145.00
- Pekerjaan Pasangan dinding Lantai dasar 9,631,846.00
- Pekerjaan pasangan Kosen Pintu dan Jendela 4,250,000.00
- Pekerjaan Pengecatan 4,012,840.00
- Pekerjaan Pasangan dinding Lantai dua 14,427,980.00
- Pekerjaan pasangan Kosen Pintu dan Jendela 10,650,000.00
- Pekerjaan Pasangan Plafond 3,582,000.00
- Pekerjaan Pengecatan 4,607,200.00
- Pekerjaan Beton Lantai 25,595,267.00
- Pekerjaan Beton Ring Balok uk. 250 x 200 2,353,812.00
- Pekerjaan Konstruksi Tangga 596,200.00

B. Bangunan Baja 81,253,192.00


- Pekerjaan Konstruksi Baja Gelagar 64,154,880.00
- Pekerjaan Konstruksi Baja Tangga 17,098,312.00

III BANGUNAN KLIN DRIER 710,001,756.00


A. Pekerjaan Sipil 710,001,756.00
- Pondasi F1 = 44 Units 37,325,328.00
- Pekerjaan Sloof uk. 200 x 300 mm 76,993,022.00
- Pekerjaan pondasi menerus 194,353,801.00
- Pekerjaan lantai bangunan t = 150 mm 380,016,380.00
- Pekerjaan Saluran Terbuka 21,313,225.00

B. Bangunan Baja n/a


- Pekerjaan Struktur Baja n/a

IV RUMAH BOILER DAN BANGUNAN PENDUKUNG 216,613,047.00


A. Pekerjaan Sipil 63,891,269.00
- Pondasi F1 = 8 Units 6,306,406.00
- Pondasi F2 = 4 Units 3,327,639.00
- Pekerjaan Sloof uk. 200 x 300 mm 12,080,190.00
- Pekerjaan Lantai Boiler 35,445,600.00
- Pekerjaan Saluran Terbuka 6,731,434.00

B. Bangunan Baja 152,721,778.00


SUMMARY - BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK

Bill Jumlah Harga Sub Total Total


Description
No. ( Rp ) ( Rp ) ( Rp )
- Pekerjaan Struktur Baja 152,721,778.00

V KANTIN DAN MUSHALLAH 45,137,679.00


A. Pekerjaan Sipil 45,137,679.00
- Pondasi 14,660,568.00
- Pekerjaan lantai dan Accessories 22,497,525.00
- Pekerjaan Saluran Terbuka uk. 37.2 x 0.3 m 7,979,586.00

VI RUMAH JAGA 16,803,188.00


A. Pekerjaan Sipil 16,803,188.00
- Bangunan 13,061,226.00
- Pekerjaan Saluran Terbuka 3,741,962.00

VII TOILET 41,144,407.00


A. Pekerjaan Sipil 41,144,407.00
- Bangunan 35,165,402.00
- Pekerjaan Saluran Terbuka 5,979,005.00

TOTAL 6,380,857,245
MARGIN (5 %) 319,042,862
TOTAL 6,699,900,107
PPN (10 %) 669,990,011
TOTAL KESELURUHAN 7,369,890,118

You might also like