Professional Documents
Culture Documents
Biaya Over Head Project: Rubber Wood Processing Plant Pt. Tiga Mutiara Nusantara
Biaya Over Head Project: Rubber Wood Processing Plant Pt. Tiga Mutiara Nusantara
Biaya Over Head Project: Rubber Wood Processing Plant Pt. Tiga Mutiara Nusantara
B MAKAN PERSONIL
1 Personil Management & Staff Pendukung 7.00 Persons 181.00 Days 20,000.00 25,340,000.00
2 Operator Alat Berat 3.00 Persons 90.00 Days 60,000.00 16,200,000.00
3 Tenaga Harian 6.00 Persons 181.00 Days 15,000.00 16,290,000.00
C MOBILISASI / DEMOBILISASI
1 Transport Staff 7.00 Persons 6.00 Times 100,000.00 4,200,000.00
2 Transport Material 25.00 Trips 1.00 Times 350,000.00 8,750,000.00
3 Transport Alat Berat 3.00 Trips 2.00 Times 2,500,000.00 15,000,000.00
SUB TOTAL 158,890,000.00
II BIAYA UMUM
A PEKERJAAN PEMBERSIHAN
1 Pekerjaan Awal
- Babat Rumput 1.00 Ls 1.00 Ls 2,000,000.00 2,000,000.00
- Stripping Top Soil (Buldozer) u/ Bangunan KD 1.00 Ls 16.00 Hours 250,000.00 4,000,000.00
2 Pekerjaan Akhir 1.00 Ls 1.00 Times 1,500,000.00 1,500,000.00
B TEMPORARY FACILITIES
1 Buat Kantor/ Gudang sementara 1.00 Ls 1.00 Ls 15,000,000.00 15,000,000.00
2 Sewa Mess (2 Rumah) 2.00 Unit 6.00 Months 750,000.00 9,000,000.00
3 Pengadaan Air Kerja 1.00 Ls 6.00 Months 500,000.00 3,000,000.00
4 Penerangan/ Lampu/ listrik Kerja (Genset) 1.00 Ls 6.00 Months 3,500,000.00 21,000,000.00
5 Pengukuran awa dan Pematokan 1.00 Ls 1.00 Ls 2,000,000.00 2,000,000.00
C BIAYA MAINTANENCE
1 Alat Kerja 1.00 Ls 1.00 Ls 1,500,000.00 1,500,000.00
D ADMINISTRATION
1 Alat Tulis Kantor dan Foto kopi 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
2 Dokumentasi 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
E KOMUNIKASI
1 Telephone/ Fax/ Internet 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
2 Rekening HP Staff Executive 1.00 Persons 6.00 Months 500,000.00 3,000,000.00
3 Rekening HP Staff 7.00 Persons 6.00 Months 200,000.00 8,400,000.00
4 Expedisi Laporan 1.00 Ls 6.00 Months 100,000.00 600,000.00
TOTAL 251,390,000.00
1
INFORMASI PROYEK
PROYEK TIGA MUTIARA NUSANTARA
2. Bangunan Baja
5,226,859,997.04
251,390,000.00
Total 5,478,249,997.04
Dibuat Oleh :
1 H. ARITONANG : ______________
2 ANDY : ______________
Diperiksa Oleh :
1 Z. Pohan : ______________
2 Ruddy : ______________
Disetujui Oleh :
B MAKAN PERSONIL
1 Personil Management & Staff Pendukung 7.00 Persons 181.00 Days 30,000.00 38,010,000.00
2 Operator Alat Berat 3.00 Persons 90.00 Days 60,000.00 16,200,000.00
3 Tenaga Harian 6.00 Persons 181.00 Days 15,000.00 16,290,000.00
C MOBILISASI / DEMOBILISASI
1 Transport Staff 7.00 Persons 6.00 Times 100,000.00 4,200,000.00
2 Transport Material 20.00 Trips 1.00 Times 2,500,000.00 50,000,000.00
3 Transport Alat Berat 3.00 Trips 2.00 Times 2,500,000.00 15,000,000.00
SUB TOTAL 233,575,000.00
II BIAYA UMUM
A PEKERJAAN PEMBERSIHAN
1 Pekerjaan Awal
- Babat Rumput 1.00 Ls 1.00 Ls 2,000,000.00 2,000,000.00
- Stripping Top Soil (Buldozer) u/ Bangunan KD 1.00 Ls 16.00 Hours 250,000.00 4,000,000.00
2 Pekerjaan Akhir 1.00 Ls 1.00 Times 1,500,000.00 1,500,000.00
B TEMPORARY FACILITIES
1 Buat Kantor/ Gudang sementara 1.00 Ls 1.00 Ls 15,000,000.00 15,000,000.00
2 Sewa Mess (2 Rumah) 2.00 Unit 6.00 Months 750,000.00 9,000,000.00
3 Pengadaan Air Kerja 1.00 Ls 6.00 Months 500,000.00 3,000,000.00
4 Penerangan/ Lampu/ listrik Kerja (Genset) 1.00 Ls 6.00 Months 3,500,000.00 21,000,000.00
5 Pengukuran awa dan Pematokan 1.00 Ls 1.00 Ls 2,000,000.00 2,000,000.00
C BIAYA MENTENENCE
1 Mentenence/ Alat Kerja 1.00 Ls 1.00 Ls 1,500,000.00 1,500,000.00
D ADMINISTRATION
1 Alat Tulis Kantor dan Foto kopi 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
2 Dokumentasi 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
E KOMUNIKASI
1 Telephone/ Fax/ Internet 1.00 Ls 6.00 Months 250,000.00 1,500,000.00
2 Rekening HP Staff Executive 1.00 Persons 6.00 Months 500,000.00 3,000,000.00
3 Rekening HP Staff 7.00 Persons 6.00 Months 200,000.00 8,400,000.00
4 Expedisi Laporan 1.00 Ls 6.00 Months 100,000.00 600,000.00
4
BIAYA OVER HEAD
PROJECT : RUBBER WOOD PROCESSING PLANT
PT. TIGA MUTIARA NUSANTARA
Resources Duration Unit Price Amount
No. Description
QTY Unit QTY Unit ( Rp ) ( Rp )
TOTAL 340,450,000.00
5
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
I PEKERJAAN PERSIAPAN
10 Pengukuran/ Pematokan & Pemasangan Bowplank m'
Materials
600.00 0.5 Btg Btg - Kayu Sembarang 2".3"
360.00 0.3 Btg Kpg - Papan Sembarang 3/4".8"
30.00 0.025 kg kg - Nails
Labour
1,200.00 1 Ls m' - Vitzet
1,200.00 1 Ls m' - Pasang Bowplank
Equipment
1,200.00 1 Ls - Tools
2 Pasir Urug t = 5 cm m3
a. Materials
3.9984 1.20 m3 m3 - Pasir
b. Labour
0.9996 0.30 - Pekerja
0.03332 0.01 - Mandor
4 Bekesting m2
a Materials
1.65 0.012 m3 m3 - SK Wood
46.82 0.34 pcs Lbr - Triplex 12 mm thick
55.08 0.40 kg kg - Nails
b. Labour
137.70 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
137.70 1.00 m2 m2 - Tools
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
5 Besi Beton Kg
a. Materials
2,092.80 1.03 kg kg - Rebar U32
40.64 0.02 kg kg - Bindraad
b. Labour
2,031.84 1.00 kg kg - Fabricatiom, Installation
2,031.84 1.00 kg kg - Transportation & lifting
c. Equipment
2,031.84 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
2 Pasir Urug t = 5 cm m3
a. Materials
3.0576 1.20 m3 m3 - Pasir
b. Labour
0.7644 0.30 - Pekerja
0.02548 0.01 - Mandor
c. Equipment
2.55 1.00 m3 m3 - Lory, timber, ducting etc.
4 Bekesting m2
a Materials
1.23 0.012 m3 m3 - SK Wood
34.83 0.34 pcs Lbr - Triplex 12 mm thick
40.98 0.40 kg kg - Nails
b. Labour
102.44 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
102.44 1.00 m2 m2 - Tools
5 Besi Beton Kg
a. Materials
1,600.37 1.03 kg kg - Rebar U32
31.08 0.02 kg kg - Bindraad
b. Labour
1,553.76 1.00 kg kg - Fabricatiom, Installation
1,553.76 1.00 kg kg - Transportation & lifting
c. Equipment
1,553.76 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
2 Pasir Urug t = 5 cm m3
a. Materials
4.00 1.20 m3 m3 - Pasir
b. Labour
1.00 0.30 - Pekerja
0.03 0.01 - Mandor
4 Bekesting m2
a Materials
1.65 0.012 m3 m3 - SK Wood
46.82 0.34 pcs pcs - Triplex 12 mm thick
55.08 0.40 kg kg - Nails
b. Labour
137.70 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
137.70 1.00 m2 m2 - Tools
5 Besi Beton Kg
a. Materials
2,092.80 1.03 kg kg - Rebar U32
40.64 0.02 kg kg - Bindraad
b. Labour
2,031.84 1.00 kg kg - Fabricatiom, Installation
2,031.84 1.00 kg kg - Transportation & lifting
c. Equipment
2,031.84 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
3 Batu Bata m2
1 Materials
18,200.70 63.00 pcs pcs - Brick
4,004.15 13.86 kg kg - Portland Cement
11.56 0.040 m3 m3 - Pasir
2 Labour
288.90 1.00 m2 m2 - Brick Work
3 Equipment
288.90 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools
3 Batu Bata m2
1 Materials
4,183.20 63.00 pcs pcs - Brick
920.30 13.86 kg kg - Portland Cement
2.66 0.040 m3 m3 - Pasir
2 Labour
66.40 1.00 m2 m2 - Brick Work
3 Equipment
66.40 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools
4 Plasteran m2
1 Materials
480.66 5.94 kg kg - Portland Cement
1.70 0.021 m3 m3 - Pasir
2 Labours
80.92 1.00 m2 m2 - Cement Plaster
3 Equipment
80.92 1.00 m2 m2 - Supporting Tools
2 Pasir Urug t = 5 cm m3
a. Materials
15.71 1.20 m3 m3 - Pasir
b. Labour
3.93 0.30 - Pekerja
0.13 0.01 - Mandor
4 Bekesting m2
a Materials
5.59 0.012 m3 m3 - SK Wood
158.30 0.34 pcs pcs - Triplex 12 mm thick
186.24 0.40 kg kg - Nails
b. Labour
465.60 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
465.60 1.00 m2 m2 - Tools
5 Besi Beton Kg
a. Materials
10,679.38 1.03 kg kg - Rebar U32
207.37 0.02 kg kg - Bindraad
b. Labour
10,368.33 1.00 kg kg - Fabricatiom, Installation
10,368.33 1.00 kg kg - Transportation & lifting
c. Equipment
10,368.33 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
- Lantai t = 150 mm
1 Pasir Urug t = 5 cm m3
a. Materials
518.40 1.20 m3 m3 - Pasir
b. Labour
129.60 0.30 - Pekerja
4.32 0.01 - Mandor
5 Bekesting m2
a Materials
2.67 0.012 m3 m3 - SK Wood
75.74 0.34 pcs pcs - Triplex 12 mm thick
89.10 0.40 kg kg - Nails
b. Labour
222.75 1.00 m2 m2 - Fabrication, Installation, Remove
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
c. Equipment
222.75 1.00 m2 m2 - Tools
B. Bangunan Baja
- Pekerjaan Struktur Baja
1 WF-350x175x7x11 Kg
1 Material
113,617.73 1.01 kg kg - WF-350x175x7x11
1,349.91 0.012 kg kg Welding Electroda
2 Labour
112,492.80 1.00 kg kg - Fabrication, Installation
3 Equipment
112,492.80 1.00 ls kg - Transportation Cost
112,492.80 1.00 ls kg - Steel Structure Tools
2 WF-300x150x6,5x9 Kg
1 Material
22,691.06 1.01 kg kg - WF-300x150x6,5x9
269.60 0.012 kg kg Welding Electroda
2 Labour
22,466.40 1.00 kg kg - Fabrication, Installation
3 Equipment
22,466.40 1.00 ls kg - Transportation Cost
22,466.40 1.00 ls kg - Steel Structure Tools
3 UNP-125x65x6 Kg
1 Material
5,927.89 1.01 kg kg - UNP-125x65x6
70.43 0.012 kg kg Welding Electroda
2 Labour
5,869.20 1.00 kg kg - Fabrication, Installation
3 Equipment
5,869.20 1.00 ls kg - Transportation Cost
5,869.20 1.00 ls kg - Steel Structure Tools
4 CNP-150x50x20x2,3 Kg
1 Material
49,631.60 1.01 kg kg - CNP-150x50x20x2,3
589.68 0.012 kg kg Welding Electroda
2 Labour
49,140.20 1.00 kg kg - Fabrication, Installation
3 Equipment
49,140.20 1.00 ls kg - Transportation Cost
49,140.20 1.00 ls kg - Steel Structure Tools
5 CNP-125x50x20x2,3 Kg
1 Material
2,299.16 1.01 kg kg - CNP-125x50x20x2,3
27.32 0.012 kg kg Welding Electroda
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
2 Labour
2,276.40 1.00 kg kg - Fabrication, Installation
3 Equipment
2,276.40 1.00 ls kg - Transportation Cost
2,276.40 1.00 ls kg - Steel Structure Tools
6 Plat t 15 mm Kg
1 Material
1,166.55 1.01 kg kg - Plat t 15 mm
13.86 0.012 kg kg Welding Electroda
2 Labour
1,155.00 1.00 kg kg - Fabrication, Installation
3 Equipment
1,155.00 1.00 ls kg - Transportation Cost
1,155.00 1.00 ls kg - Steel Structure Tools
7 Plat t 12 mm Kg
1 Material
3,699.02 1.01 kg kg - Plat t 12 mm
43.95 0.012 kg kg Welding Electroda
2 Labour
3,662.40 1.00 kg kg - Fabrication, Installation
3 Equipment
3,662.40 1.00 ls kg - Transportation Cost
3,662.40 1.00 ls kg - Steel Structure Tools
8 Plat t 10 mm Kg
1 Material
5,029.21 1.01 kg kg - Plat t 10 mm
59.75 0.012 kg kg Welding Electroda
2 Labour
4,979.42 1.00 kg kg - Fabrication, Installation
3 Equipment
4,979.42 1.00 ls kg - Transportation Cost
4,979.42 1.00 ls kg - Steel Structure Tools
9 Plat t 8 mm Kg
1 Material
940.41 1.01 kg kg - Plat t 8 mm
11.17 0.012 kg kg Welding Electroda
2 Labour
931.10 1.00 kg kg - Fabrication, Installation
3 Equipment
931.10 1.00 ls kg - Transportation Cost
931.10 1.00 ls kg - Steel Structure Tools
10 Plat t 6 mm Kg
1 Material
2,328.68 1.01 kg kg - Plat t 6 mm
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
11 L-50x50x5 Kg
1 Material
23,406.75 1.01 kg kg - L-50x50x5
278.10 0.012 kg kg Welding Electroda
2 Labour
23,175.00 1.00 kg kg - Fabrication, Installation
3 Equipment
23,175.00 1.00 ls kg - Transportation Cost
23,175.00 1.00 ls kg - Steel Structure Tools
2 Plasteran m2
1 Materials
1,272.11 5.94 kg kg - Portland Cement
4.50 0.021 m3 m3 - Pasir
2 Labours
214.16 1.00 m2 m2 - Cement Plaster
3 Equipment
214.16 1.00 m2 m2 - Supporting Tools
- Pekerjaan Pengecatan
1 Cat Tembok Ex. Vinilex m2
1 Material
30.20 0.141 kg kg Cat dasar Kimex
60.82 0.284 kg kg Cat Finish Vinilex
2 Labour
214.16 1 Upah
3 Equipment
214.16 1.00 ls ls - Supporting Tools
2 Plasteran m2
1 Materials
1,905.55 5.94 kg kg - Portland Cement
6.74 0.021 m3 m3 - Pasir
2 Labours
320.80 1.00 m2 m2 - Cement Plaster
3 Equipment
320.80 1.00 m2 m2 - Supporting Tools
- Pekerjaan Pengecatan
1 Pengecatan dinding ½ bata m2
1 Material
45.23 0.141 kg kg Cat dasar Kimex
91.11 0.284 kg kg Cat Finish Vinilex
2 Labour
320.80 1 m2 Upah
3 Equipment
320.80 1.00 ls ls - Supporting Tools
1 Material
5.08 0.141 kg kg Cat dasar Kimex
10.22 0.284 kg kg Cat Finish Vinilex
2 Labour
36.00 1 m2 Upah
3 Equipment
36.00 1.00 ls ls - Supporting Tools
3 Bekesting lantai m2
a Materials
0.86 0.012 m3 m3 - SK Wood
24.48 0.34 pcs pcs - Triplex 12 mm thick
28.80 0.40 kg kg - Nails
b. Labour
72.00 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
72.00 1.00 m2 m2 - Tools
2 Besi beton Kg
a. Materials
173.16 1.03 kg kg - Rebar U32
3.36 0.02 kg kg - Bindraad
b. Labour
168.12 1.00 kg kg - Fabricatiom, Installation
168.12 1.00 kg kg - Transportation & lifting
c. Equipment
168.12 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
3 Bekesting m2
a Materials
0.26 0.012 m3 m3 - SK Wood
7.24 0.34 pcs pcs - Triplex 12 mm thick
8.52 0.40 kg kg - Nails
b. Labour
21.30 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
21.30 1.00 m2 m2 - Tools
B. Bangunan Baja
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
2 WF-300x150x6,5x9 Kg
1 Material
4,892.84 1.01 kg kg - WF-300x150x6,5x9
58.13 0.012 kg kg Welding Electroda
2 Labour
4,844.40 1.00 kg kg - Fabrication, Installation
3 Equipment
4,844.40 1.00 ls ls - Steel Structure Tools
4,844.40 1.00 kg kg - Transportation Cost
3 Plat t = 16 mm Kg
1 Material
376.73 1.01 kg kg - Plat t = 16 mm
4.48 0.012 kg kg Welding Electroda
2 Labour
373.00 1.00 kg kg - Fabrication, Installation
3 Equipment
373.00 1.00 ls ls - Steel Structure Tools
373.00 1.00 kg kg - Transportation Cost
2 UNP-125x65x6 Kg
1 Material
406.02 1.01 kg kg - UNP-125x65x6
4.82 0.012 kg kg Welding Electroda
2 Labour
402.00 1.00 kg kg - Fabrication, Installation
3 Equipment
402.00 1.00 ls ls - Steel Structure Tools
402.00 1.00 kg kg - Transportation Cost
6 L-65x65x6 Kg
1 Material
35.86 1.01 kg kg - L-65x65x6
0.43 0.012 kg kg Welding Electroda
2 Labour
35.50 1.00 kg kg - Fabrication, Installation
3 Equipment
35.50 1.00 ls ls - Steel Structure Tools
35.50 1.00 kg kg - Transportation Cost
7 Plat Bunga t = 6 mm Kg
1 Material
348.45 1.01 kg kg - Plat Bunga t = 6 mm
4.14 0.012 kg kg Welding Electroda
2 Labour
345.00 1.00 kg kg - Fabrication, Installation
3 Equipment
345.00 1.00 ls ls - Steel Structure Tools
345.00 1.00 kg kg - Transportation Cost
8 Plat Tapak 16 mm Kg
1 Material
376.73 1.01 kg kg - Plat Tapak 16 mm
4.48 0.012 kg kg Welding Electroda
2 Labour
373.00 1.00 kg kg - Fabrication, Installation
3 Equipment
373.00 1.00 ls ls - Steel Structure Tools
373.00 1.00 kg kg - Transportation Cost
9 Plat t = 6mm Kg
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
1 Material
9.85 1.01 kg kg - Plat t = 6mm
0.12 0.012 kg kg Welding Electroda
2 Labour
9.75 1.00 kg kg - Fabrication, Installation
3 Equipment
9.75 1.00 ls ls - Steel Structure Tools
9.75 1.00 kg kg - Transportation Cost
2 Pasir Urug t = 5 cm m3
a. Materials
3.80 1.20 m3 m3 - Pasir
b. Labour
0.95 0.30 - Pekerja
0.03 0.01 - Mandor
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
4 Bekesting m2
a Materials
1.23 0.012 m3 m3 - SK Wood
34.75 0.34 pcs pcs - Triplex 12 mm thick
40.88 0.40 kg kg - Nails
b. Labour
102.21 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
102.21 1.00 m2 m2 - Tools
5 Besi Beton Kg
a. Materials
2,062.24 1.03 kg kg - Rebar U32
40.04 0.02 kg kg - Bindraad
b. Labour
2,002.18 1.00 kg kg - Fabricatiom, Installation
2,002.18 1.00 kg kg - Transportation & lifting
c. Equipment
2,002.18 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
2 Pasir Urug t = 5 cm m3
a. Materials
7.86 1.20 m3 m3 - Pasir
b. Labour
1.97 0.30 - Pekerja
0.07 0.01 - Mandor
4 Bekesting m2
a Materials
2.36 0.012 m3 m3 - SK Wood
66.81 0.34 pcs pcs - Triplex 12 mm thick
78.60 0.40 kg kg - Nails
b. Labour
196.51 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
196.51 1.00 m2 m2 - Tools
5 Besi Beton Kg
a. Materials
5,596.40 1.03 kg kg - Rebar U32
108.67 0.02 kg kg - Bindraad
b. Labour
5,433.40 1.00 kg kg - Fabricatiom, Installation
5,433.40 1.00 kg kg - Transportation & lifting
c. Equipment
5,433.40 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
2 Pasir Urug t = 5 cm m3
a. Materials
5.62 1.20 m3 m3 - Pasir
b. Labour
1.40 0.30 - Pekerja
0.05 0.01 - Mandor
4 Bekesting m2
a Materials
2.53 0.012 m3 m3 - SK Wood
71.65 0.34 pcs pcs - Triplex 12 mm thick
84.29 0.40 kg kg - Nails
b. Labour
210.74 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
5 Besi Beton Kg
a. Materials
1,470.97 1.03 kg kg - Rebar U32
28.56 0.02 kg kg - Bindraad
b. Labour
1,428.13 1.00 kg kg - Fabricatiom, Installation
1,428.13 1.00 kg kg - Transportation & lifting
c. Equipment
1,428.13 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
8 Plasteran m2
1 Materials
18,756.62 5.94 kg kg - Portland Cement
66.31 0.021 m3 m3 - Pasir
2 Labours
3,157.68 1.00 m2 m2 - Cement Plaster
3 Equipment
3,157.68 1.00 m2 m2 - Supporting Tools
5 Bekesting m2
a Materials
0.82 0.012 m3 m3 - SK Wood
23.12 0.34 pcs pcs - Triplex 12 mm thick
27.20 0.40 kg kg - Nails
b. Labour
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
2 Pasir Urug t = 5 cm m3
a. Materials
8.80 1.20 m3 m3 - Pasir
b. Labour
2.20 0.30 - Pekerja
0.07 0.01 - Mandor
4 Plasteran m2
1 Materials
1,974.69 5.94 kg kg - Portland Cement
6.98 0.021 m3 m3 - Pasir
2 Labours
332.44 1.00 m2 m2 - Cement Plaster
3 Equipment
332.44 1.00 m2 m2 - Supporting Tools
B. Bangunan Baja
- Pekerjaan Struktur Baja
1 WF-250x125x6x9 Kg n/a
2 WF-200x100x5.5x8 Kg n/a
3 UNP-125x65x6 Kg n/a
4 UNP-125x50x5 Kg n/a
5 CNP-150x50x20x2. Kg n/a
6 L.50.50.5 Kg n/a
7 Plat t = 15 mm Kg n/a
8 Plat t = 10 mm Kg n/a
9 Plat t = 8 mm Kg n/a
10 Plat t = 6 mm Kg n/a
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
2 Pasir Urug t = 5 cm m3
a. Materials
0.69 1.20 m3 m3 - Pasir
b. Labour
0.17 0.30 - Pekerja
0.01 0.01 - Mandor
4 Bekesting m2
a Materials
0.13 0.012 m3 m3 - SK Wood
3.60 0.34 pcs pcs - Triplex 12 mm thick
4.23 0.40 kg kg - Nails
b. Labour
10.58 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
10.58 1.00 m2 m2 - Tools
5 Besi Beton Kg
a. Materials
374.95 1.03 kg kg - Rebar U32
7.28 0.02 kg kg - Bindraad
b. Labour
364.03 1.00 kg kg - Fabricatiom, Installation
364.03 1.00 kg kg - Transportation & lifting
c. Equipment
364.03 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
- Pondasi F2 = 4 Units
1 Galian Pondasi m3
a. Labour
5.76 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
5.76 1.00 m3 m3 - Excavator
2 Pasir Urug t = 5 cm m3
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
a. Materials
0.35 1.20 m3 m3 - Pasir
b. Labour
0.09 0.30 - Pekerja
0.00 0.01 - Mandor
4 Bekesting m2
a Materials
0.10 0.012 m3 m3 - SK Wood
2.79 0.34 pcs pcs - Triplex 12 mm thick
3.28 0.40 kg kg - Nails
b. Labour
8.20 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
8.20 1.00 m2 m2 - Tools
5 Besi Beton Kg
a. Materials
187.47 1.03 kg kg - Rebar U32
3.64 0.02 kg kg - Bindraad
b. Labour
182.01 1.00 kg kg - Fabricatiom, Installation
182.01 1.00 kg kg - Transportation & lifting
c. Equipment
182.01 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
a. Material
5.22 1.2 m3 m3 - Tanah merah
b. Labour
1.09 0.25 - Pekerja
0.04 0.01 - Mandor
2 Pasir Urug t = 5 cm m3
a. Materials
1.44 1.20 m3 m3 - Pasir
b. Labour
0.36 0.30 - Pekerja
0.01 0.01 - Mandor
4 Bekesting m2
a Materials
0.43 0.012 m3 m3 - SK Wood
12.24 0.34 pcs pcs - Triplex 12 mm thick
14.40 0.40 kg kg - Nails
b. Labour
36.00 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
36.00 1.00 m2 m2 - Tools
5 Besi Beton Kg
a. Materials
1,025.26 1.03 kg kg - Rebar U32
19.91 0.02 kg kg - Bindraad
b. Labour
995.40 1.00 kg kg - Fabricatiom, Installation
995.40 1.00 kg kg - Transportation & lifting
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
c. Equipment
995.40 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
5 Bekesting m2
a Materials
0.22 0.012 m3 m3 - SK Wood
6.12 0.34 pcs pcs - Triplex 12 mm thick
7.20 0.40 kg kg - Nails
b. Labour
18.00 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
18.00 1.00 m2 m2 - Tools
2 Pasir Urug m3
a. Materials
2.78 1.20 m3 m3 - Pasir
b. Labour
0.70 0.30 - Pekerja
0.02 0.01 - Mandor
4 Plasteran m2
1 Materials
623.64 5.94 kg kg - Portland Cement
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
B. Bangunan Baja
- Pekerjaan Struktur Baja
1 WF-250x125x6x9 Kg
1 Material
4,898.90 1.01 kg kg - WF-250x125x6x9
58.20 0.012 kg kg Welding Electroda
2 Labour
4,850.40 1.00 kg kg - Fabrication, Installation
3 Equipment
4,850.40 1.00 ls ls - Steel Structure Tools
4,850.40 1.00 kg kg - Transportation Cost
2 WF-200x100x5.5x8 Kg
1 Material
775.68 1.01 kg kg - WF-200x100x5.5x8
9.22 0.012 kg kg Welding Electroda
2 Labour
768.00 1.00 kg kg - Fabrication, Installation
3 Equipment
768.00 1.00 ls ls - Steel Structure Tools
768.00 1.00 kg kg - Transportation Cost
3 UNP-125x65x6 Kg
1 Material
487.22 1.01 kg kg - UNP-125x65x6
5.79 0.012 kg kg Welding Electroda
2 Labour
482.40 1.00 kg kg - Fabrication, Installation
3 Equipment
482.40 1.00 ls ls - Steel Structure Tools
482.40 1.00 kg kg - Transportation Cost
4 CNP-150x50x20x2.3 Kg
1 Material
3,852.54 1.01 kg kg - CNP-150x50x20x2.3
45.77 0.012 kg kg Welding Electroda
2 Labour
3,814.40 1.00 kg kg - Fabrication, Installation
3 Equipment
3,814.40 1.00 ls ls - Steel Structure Tools
3,814.40 1.00 kg kg - Transportation Cost
5 CNP-125x50x20x2.3 Kg
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
1 Material
164.23 1.01 kg kg - CNP-125x50x20x2.3
1.95 0.012 kg kg Welding Electroda
2 Labour
162.60 1.00 kg kg - Fabrication, Installation
3 Equipment
162.60 1.00 ls ls - Steel Structure Tools
162.60 1.00 kg kg - Transportation Cost
6 Plat t = 15 mm Kg
1 Material
97.93 1.01 kg kg - Plat t = 15 mm
1.16 0.012 kg kg Welding Electroda
2 Labour
96.96 1.00 kg kg - Fabrication, Installation
3 Equipment
96.96 1.00 ls ls - Steel Structure Tools
96.96 1.00 kg kg - Transportation Cost
7 Plat t = 12 mm Kg
1 Material
282.80 1.01 kg kg - Plat t = 12 mm
3.36 0.012 kg kg Welding Electroda
2 Labour
280.00 1.00 kg kg - Fabrication, Installation
3 Equipment
280.00 1.00 ls ls - Steel Structure Tools
280.00 1.00 kg kg - Transportation Cost
8 Plat t = 8 mm & 6 mm Kg
1 Material
210.08 1.01 kg kg - Plat t = 8 mm & 6 mm
2.50 0.012 kg kg Welding Electroda
2 Labour
208.00 1.00 kg kg - Fabrication, Installation
3 Equipment
208.00 1.00 ls ls - Steel Structure Tools
208.00 1.00 kg kg - Transportation Cost
2 Labour
394.00 1.00 m2 m2 - Install, Lifting, Fixing
3 Equipment
394.00 1.00 m2 m2 - Supporting Tools & Transportation
2 Pasir urug t = 5 cm m3
a. Materials
2.07 1.20 m3 m3 - Pasir
b. Labour
0.52 0.30 - Pekerja
0.02 0.01 - Mandor
3 Cor K-125 m3
a. Materials
2.87 0.91 m3 m3 - Batu krikil
14.32 4.54 zak zak - P. Cement
1.70 0.54 m3 m3 - Pasir
b. Labour
3.19 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
3.16 1.00 m3 m3 - Lory, timber, ducting etc.
-
4 Bekesting m3
a Materials
0.70 0.012 m3 m3 - SK Wood
19.94 0.34 pcs pcs - Triplex 12 mm thick
23.46 0.40 kg kg - Nails
b. Labour
58.65 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
58.65 1.00 m2 m2 - Tools
6 Besi Beton Kg
a. Materials
223.85 1.03 kg kg - Rebar U32
4.35 0.02 kg kg - Bindraad
b. Labour
217.33 1.00 kg kg - Fabricatiom, Installation
217.33 1.00 kg kg - Transportation & lifting
c. Equipment
217.33 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
8 Plasteran m2
1 Materials
392.04 5.94 kg kg - Portland Cement
1.39 0.021 m3 m3 - Pasir
2 Labours
66.00 1.00 m2 m2 - Cement Plaster
3 Equipment
66.00 1.00 m2 m2 - Supporting Tools
3 Kramik 40 x 40 cm ex Roman m2
a. Materials
33.60 1.05 Ktk Ktk - Kramik 40 x 40 cm ex Roman
190.08 5.94 kg kg - Portland Cement
0.67 0.021 m3 m3 - Pasir
0.64 0.02 Kg Kg - Semen putih
b. Labour
32.00 1.00 m2 m2 - Brick Work
c. Equipment
32.00 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
10 Meranti Keras m3
1 Material
2.02 1.01 SheetsSheets - Meranti Keras
2 Equipment
2.00 1.00 ls ls - Supporting Tools
- 2" x 2" m3
- 2" x 3" m3
- 2" x 4" m3
a Materials
0.19 1.010 m3 m3 - 1" x 6"
0.05 1.010 m3 m3 - 1" x 9"
0.03 1.010 m3 m3 - 2" x 2"
0.64 1.010 m3 m3 - 2" x 3"
0.10 1.010 m3 m3 - 2" x 4"
b. Labour
1.00 1 m2 m2 - Fabrication
c. Equipment
2.99 3.00 m2 m2 - Suporting Tools
16 Asbestos t=4 mm m2
1 Material
41.97 1.01 m2 m2 - Asbestos t=4 mm
2 Labour
41.55 1.00 m2 m2 - Install
3 Equipment
41.55 1.00 ls ls - Supporting Tools
17 Tripleks 4 mm m2
1 Material
64.64 1.01 m2 m2 - Tripleks 4 mm
2 Labour
64.00 1.00 m2 m2 - Install
3 Equipment
64.00 1.00 ls ls - Supporting Tools
18 Cat dinding m2
1 Material
19.04 0.141 kg kg Cat dasar (KIMEX)
38.34 0.284 kg kg Cat Finish (VINILEX)
2 Labour
135.00 1 Upah
3 Equipment
135.00 1.00 ls ls - Supporting Tools
1 Material
15.51 0.141 kg kg Cat dasar
31.24 0.284 kg kg Cat Finish
2 Labour
110.00 1 Upah
3 Equipment
110.00 1.00 ls ls - Supporting Tools
2 Cor K-125 m3
a. Materials
1.69 0.91 m3 m3 - Batu krikil
8.44 4.54 zak zak - P. Cement
1.00 0.54 m3 m3 - Pasir
b. Labour
1.88 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
1.86 1.00 m3 m3 - Lory, timber, ducting etc.
-
4 Plasteran m2
1 Materials
905.97 5.94 kg kg - Portland Cement
3.20 0.021 m3 m3 - Pasir
2 Labours
152.52 1.00 m2 m2 - Cement Plaster
3 Equipment
152.52 1.00 m2 m2 - Supporting Tools
VI RUMAH JAGA
A. Pekerjaan Sipil
- Bangunan
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
1 Galian Pondasi m3
a. Labour
6.38 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
6.38 1.00 m3 m3 - Excavator
2 Pasir urug m3
a. Materials
0.91 1.20 m3 m3 - Pasir
b. Labour
0.23 0.30 - Pekerja
0.01 0.01 - Mandor
3 Bekesting m2
a Materials
0.31 0.012 m3 m3 - SK Wood
8.79 0.34 pcs pcs - Triplex 12 mm thick
10.34 0.40 kg kg - Nails
b. Labour
25.84 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
25.84 1.00 m2 m2 - Tools
5 Cor K-175 m3
a. Materials
2.16 0.82 m3 m3 - Batu krikil
17.92 6.8 zak zak - P. Cement
1.42 0.54 m3 m3 - Pasir
b. Labour
2.66 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
2.64 1.00 m3 m3 - Lory, timber, ducting etc.
-
6 Besi Beton Kg
a. Materials
98.62 1.03 kg kg - Rebar U32
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
8 Pasangan Bata m2
1 Materials
957.60 63.00 pcs pcs - Brick
210.67 13.86 kg kg - Portland Cement
0.61 0.040 m3 m3 - Pasir
2 Labour
15.20 1.00 m2 m2 - Brick Work
3 Equipment
15.20 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools
9 Plasteran m2
1 Materials
180.58 5.94 kg kg - Portland Cement
0.64 0.021 m3 m3 - Pasir
2 Labours
30.40 1.00 m2 m2 - Cement Plaster
3 Equipment
30.40 1.00 m2 m2 - Supporting Tools
10 Pasir dipadatkan m3
a. Materials
1.56 1.20 m3 m3 - Pasir
b. Labour
0.39 0.30 - Pekerja
0.01 0.01 - Mandor
2 Cor K-125 m3
a. Materials
0.46 0.91 m3 m3 - Batu krikil
2.30 4.54 zak zak - P. Cement
0.27 0.54 m3 m3 - Pasir
b. Labour
0.51 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
0.51 1.00 m3 m3 - Lory, timber, ducting etc.
-
Plasteran m2
1 Materials
448.11 5.94 kg kg - Portland Cement
1.58 0.021 m3 m3 - Pasir
2 Labours
75.44 1.00 m2 m2 - Cement Plaster
3 Equipment
75.44 1.00 m2 m2 - Supporting Tools
VII TOILET
A. Pekerjaan Sipil
- Bangunan
1 Galian Pondasi m3
a. Labour
11.67 1.00 m3 m3 - Setting, Leveling, Cleaning and Compacted
b. Equipment
11.67 1.00 m3 m3 - Excavator
2 Pasir urug m3
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
a. Materials
1.67 1.20 m3 m3 - Pasir
b. Labour
0.42 0.30 - Pekerja
0.01 0.01 - Mandor
3 Bekesting m2
a Materials
0.90 0.012 m3 m3 - SK Wood
25.45 0.34 pcs pcs - Triplex 12 mm thick
29.94 0.40 kg kg - Nails
b. Labour
74.84 1.00 m2 m2 - Fabrication, Installation, Remove
c. Equipment
74.84 1.00 m2 m2 - Tools
4 Cor K-125 m3
a. Materials
5.21 0.91 m3 m3 - Batu krikil
26.01 4.54 zak zak - P. Cement
3.09 0.54 m3 m3 - Pasir
b. Labour
5.79 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
5.73 1.00 m3 m3 - Lory, timber, ducting etc.
-
5 Cor K-175 m3
a. Materials
6.22 0.82 m3 m3 - Batu krikil
51.56 6.8 zak zak - P. Cement
4.09 0.54 m3 m3 - Pasir
b. Labour
7.66 1.01 m3 m3 - Pouring Concrete, Cleaning
- Equipment
7.58 1.00 m3 m3 - Lory, timber, ducting etc.
-
6 Besi Beton Kg
a. Materials
180.29 1.03 kg kg - Rebar U32
3.50 0.02 kg kg - Bindraad
b. Labour
175.04 1.00 kg kg - Fabricatiom, Installation
175.04 1.00 kg kg - Transportation & lifting
c. Equipment
175.04 1.00 kg kg - Bar Cutter, Bar Bender, Supporting Tool & Material handling
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
8 Pasangan Bata m2
1 Materials
1,867.32 63.00 pcs pcs - Brick
410.81 13.86 kg kg - Portland Cement
1.19 0.040 m3 m3 - Pasir
2 Labour
29.64 1.00 m2 m2 - Brick Work
3 Equipment
29.64 1.00 m2 m2 - Mortar Mixer, Lorry, Supporting Tools
9 Plasteran m2
1 Materials
352.12 5.94 kg kg - Portland Cement
1.24 0.021 m3 m3 - Pasir
2 Labours
59.28 1.00 m2 m2 - Cement Plaster
3 Equipment
59.28 1.00 m2 m2 - Supporting Tools
10 Pasir dipadatkan m3
a. Materials
1.92 1.20 m3 m3 - Pasir
b. Labour
0.48 0.30 - Pekerja
0.02 0.01 - Mandor
16 Floordrain Pcs
a Materials
2.00 1.000 Set Set - Floordrain
b. Labour
2.00 1.00 m2 unit - Instalation
c. Equipment
2.00 1.00 m2 m2 - Suporting Tools
2 Cor K-125 m3
a. Materials
0.74 0.91 m3 m3 - Batu krikil
3.67 4.54 zak zak - P. Cement
0.44 0.54 m3 m3 - Pasir
b. Labour
0.82 1.01 m3 m3 - Pouring Concrete, Cleaning
Equipment
0.81 1.00 m3 m3 - Lory, timber, ducting etc.
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
4 Plasteran m2
1 Materials
716.01 5.94 kg kg - Portland Cement
2.53 0.021 m3 m3 - Pasir
2 Labours
120.54 1.00 m2 m2 - Cement Plaster
3 Equipment
120.54 1.00 m2 m2 - Supporting Tools
TOTAL
1,200.00
66.64
3.33 65,000.00
3.33
137.70
29.58
30.40
Tanah merah - -
50.96
2.55 65,000.00
2.55
102.44
1,553.76
22.15
23.71
Tanah merah - -
-
Pekerja 28,050 166,280
Mandor 45,900 10,884
Sub Total 177,164
66.64
3.33
137.70
29.58
Tanah merah - -
-
Pekerja 28,050.00 193,840
Mandor 45,900.00 12,688
Sub Total 206,527
121.34
20.22
288.90
404.46
11.66
-
Setting, Leveling, Cleaning and Compacted 4,500 52,479
Equipment -
Excavator 16,500 192,423
Sub Total 244,902
2.10
66.40
80.92
195.30
130.95
13.10
13.10
465.60
10,368.33
65.48
432.00
432.00
8,640.00
1,296.00
222.75
112,492.80
22,466.40
5,869.20
49,140.20
2,276.40
1,155.00
3,662.40
4,979.42
931.10
2,305.63
23,175.00
3,412.80
2,888.00
368.00
80.00
8,988.00
27,826.00
288.00
10,705.00
Material zincalume 0,45 TCT
Atap Primadeck t = 0.45 mm 46,303 505,583,064
1,680.00
444.00
68.00
340.00
231,866.35
214.16
-
Portland Cement 612 778,532
Pasir 35,700 160,556
-
Cement Plaster 13,000 2,784,080
Equipment -
Supporting Tools 2,000 428,320
Sub Total 4,151,487
1.00
14.00
214.16 -
-
Cat dasar Kimex 5,793.60 174,947
Cat Finish Vinilex 10,098.00 614,175
-
Upah 5,000.00 1,070,800
Equipment -
Supporting Tools 125 26,770
Sub Total 1,886,692
1.00
14.00
160.40 -
-
Brick 357 3,607,556
Portland Cement 612 1,360,564
Pasir 35,700 229,051
-
Brick Work 15,000 2,406,000
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 320,800
Sub Total 7,923,972
320.80
5.00
1.00
Kusen + Jendela gendong (Allumunium) 1,000,000 1,000,000
-
Installation 250,000 250,000
Equipment -
Supporting Tools 10,000 10,000
Sub Total 1,260,000
72.00
36.00
320.80
-
Cat dasar Kimex 5,793.60 262,061
Cat Finish Vinilex 10,098.00 920,001
-
Upah 5,000.00 1,604,000
Equipment -
Supporting Tools 125 40,100
Sub Total 2,826,161
72.00
36.00
Cat dasar Kimex 5,793.60 29,408
Cat Finish Vinilex 10,098.00 103,242
-
Upah 5,000.00 180,000
Equipment -
Supporting Tools 125 4,500
Sub Total 317,150
10.80
1,702.29 -
-
Rebar U32 5,579 9,782,690
Bindraad 6,630 225,724
-
Fabricatiom, Installation 700 1,191,603
Transportation & lifting 25 42,557
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 85,115
Sub Total 11,327,688
72.00
-
SK Wood 2,203,200 1,903,565
Triplex 12 mm thick 117,300 2,871,504
Nails 9,078 261,446
-
Fabrication, Installation, Remove 20,000 1,440,000
Equipment -
Tools 1,000 72,000
Sub Total 6,548,515
1.08
21.30
1.00
1.00
-
UNP.125.65.6 6,630 6,696
Batu krikil 117,300 106,743
P. Cement 24,480 111,139
Pasir 35,700 19,278
Anchor bolt 5/8" 8,160 8,242
-
Civil Work 500,000 500,000
Steel work (Pipe) 200,000 400,000
Equipment -
Supporting Tools 5,000 5,000
Sub Total 1,157,098
902.72 -
-
WF-350x175x7x11 6,630 6,044,884
Welding Electroda 10,710 116,018
-
Fabrication, Installation 800 722,176
Equipment -
Steel Structure Tools 125 112,840
Transportation Cost 350 315,952
Sub Total 7,311,870
4,844.40
373.00
46.00
8.00 -
-
Baut anchor dia. 22 mm 20,910 167,280
-
Setting 9,500 76,000
Equipment -
Transportation 500 4,000
Sub Total 247,280
108.00
-
Baut dia. 3/4" 2,553 278,488
Equipment -
Steel Structure Tools 125 13,500
Transportation Cost 500 54,000
Sub Total 345,988
6,166.12
148.80
402.00
12.20
118.68
Pipa dia 1½" t = 2,9 mm 151,980 18,217,356
Welding Electroda 10,710 15,253
-
Fabrication, Installation 800 94,944
Equipment -
Steel Structure Tools 125 14,835
Transportation Cost 350 41,538
Sub Total 18,383,926
123.30
35.50
345.00
373.00
9.75
Plat t = 6mm 7,497 73,827
Welding Electroda 10,710 1,253
-
Fabrication, Installation 800 7,800
Equipment -
Steel Structure Tools 125 1,219
Transportation Cost 350 3,413
Sub Total 87,511
20.00
8.00
1,568.23
63.36
3.17
102.21
2,002.18
15.53
47.83
Tanah merah - -
-
Pekerja 28,050.00 335,394
Mandor 45,900.00 21,953
Sub Total 357,347
39.30
6.55
6.55
196.51
5,433.40
-
Rebar U32 5,579 31,224,554
Bindraad 6,630 720,469
-
Fabricatiom, Installation 700 3,803,379
Transportation & lifting 25 135,835
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 271,670
Sub Total 36,155,906
19.65
Batu krikil 117,300 1,959,203
P. Cement 24,480 4,088,772
Pasir 35,700 385,828
-
Pouring Concrete, Cleaning 50,000 992,325
Equipment -
Lory, timber, ducting etc. 2,000 39,300
Sub Total 7,465,428
24.24
Tanah merah - -
-
Pekerja 28,050.00 169,983
Mandor 45,900.00 11,126
Sub Total 181,109
56.20
4.68
28.10
210.74
1,428.13
11.24
-
Batu krikil 117,300 1,120,684
P. Cement 24,480 2,338,819
Pasir 35,700 220,697
-
Pouring Concrete, Cleaning 50,000 567,620
Equipment -
Lory, timber, ducting etc. 2,000 22,480
Sub Total 4,270,301
1,578.84
3,157.68
7.97
132.63
132.63
2,652.68
347.90 -
-
Batu krikil 117,300 34,687,569
P. Cement 24,480 72,391,448
Pasir 35,700 6,831,056
-
Pouring Concrete, Cleaning 50,000 17,569,051
Equipment -
Lory, timber, ducting etc. 2,000 695,804
Sub Total 132,174,928
68.00
77.73
7.33
259.11 -
-
Brick 357 5,827,553
P. Cement 612 2,197,820
Pasir 35,700 370,003
-
Brick Work 15,000 3,886,590
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 518,212
Sub Total 12,800,178
332.44
-
-
-
-
-
SUPPLY B
-
-
-
-
SUPPLY BY OWNER
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
11.52
0.58
0.58
10.58
364.03 -
-
Rebar U32 5,579 2,092,002
Bindraad 6,630 48,270
2.82 -
-
Batu krikil 117,300 281,567
P. Cement 24,480 587,618
Pasir 35,700 55,449
-
Pouring Concrete, Cleaning 50,000 142,612
Equipment -
Lory, timber, ducting etc. 2,000 5,648
Sub Total 1,072,894
8.70 -
-
Tanah merah - -
-
Pekerja 28,050.00 60,981
Mandor 45,900.00 3,991
Sub Total 64,972
5.76
0.29 -
-
Pasir 35,700 12,338
-
Pekerja 28,050.00 2,424
Mandor 45,900.00 132
Sub Total 14,894
0.29
8.20
182.01
1.41
4.35
Tanah merah - -
-
Pekerja 28,050.00 30,490
Mandor 45,900.00 1,996
Sub Total 32,486
7.20
1.20
1.20
36.00
995.40
-
Rebar U32 5,579 5,720,347
Bindraad 6,630 131,990
-
Fabricatiom, Installation 700 696,780
Transportation & lifting 25 24,885
Equipment -
Bar Cutter, Bar Bender, Supporting Tool & Material handling 50 49,770
Sub Total 6,623,772
0.36
4.44
Tanah merah - -
-
Pekerja 28,050.00 31,136
Mandor 45,900.00 2,038
Sub Total 33,173
10.80
10.80
216.00
18.00 -
-
SK Wood 2,203,200 475,891
Triplex 12 mm thick 117,300 717,876
Nails 9,078 65,362
-
Fabrication, Installation, Remove 20,000 360,000
Equipment -
Tools 1,000 18,000
Sub Total 1,637,129
24.55
2.32
81.83
104.99
4,850.40
768.00
482.40
3,814.40
162.60
CNP-125x50x20x2.3 6,120 1,005,063
Welding Electroda 10,710 20,897
-
Fabrication, Installation 800 130,080
Equipment -
Steel Structure Tools 125 20,325
Transportation Cost 350 56,910
Sub Total 1,233,275
96.96
280.00
208.00
227.52
12.00 -
-
Turn Bucles dia. 5/8" 7,650 92,718
Equipment -
Steel Structure Tools 125 1,500
Transportation Cost 500 6,000
Sub Total 100,218
220.00
232.00
680.00
3,182.00
394.00 -
-
Atap Primadeck t=0.45 mm 46,303 18,608,102
-
Install, Lifting, Fixing 3,500 1,379,000
Equipment -
Supporting Tools & Transportation 1,000 394,000
Sub Total 20,381,102
187.00 -
-
Clading Primadeck t=0.40 mm 40,934 7,807,791
-
Install, Lifting, Fixing 3,500 654,500
Equipment -
Supporting Tools & Transportation 1,000 187,000
Sub Total 8,649,291
20.00
36.00
10,890.28
14.50
3.16
58.65
7.12
217.33
66.00
1.75
3.50
32.00
Kramik K. mandi dinding t=15 cm + bak dan tempat air Wudhu 43,860.00 851,981
Portland Cement 612 67,253
Pasir 35,700 13,869
Semen putih 2,040.00 755
-
Ceramic Instalation 15,000 277,500
Equipment -
Mortar Mixer, Lorry, Supporting Tools 2,000 37,000
Sub Total 1,248,357
5.00
1.00
1.00
5.00
2.00
2.00
2.00
1.00
1.00
0.19 -
0.05 -
0.03 -
0.63 -
0.10 -
-
1" x 6" 2,750,000.00 527,725
1" x 9" 2,750,000.00 136,098
2" x 2" 2,750,000.00 73,882
2" x 3" 2,750,000.00 1,755,380
2" x 4" 2,750,000.00 274,973
-
Fabrication 900,000 896,940
Equipment -
Suporting Tools 1,000 2,990
Sub Total 3,667,986
33.63
41.55
64.00
135.00
110.00
Cat dasar 5,793.60 89,859
Cat Finish 10,098.00 315,462
-
Upah 5,000.00 550,000
Equipment -
Supporting Tools 125 13,750
Sub Total 969,070
20.46
1.86
70.68
152.52
0.76 -
-
Pasir 35,700 32,558
-
Pekerja 27,500 6,270
Mandor 35,000 266
Sub Total 39,094
25.84
3.14
2.64
95.75
18.00
15.20
30.40
1.30
0.15
0.20
0.25
0.46
11.20
1.00
1.00
-
Jendela + Accessories + Pengecatan 960,000 11,520
-
Fabrication 250,000 250,000
Equipment -
Suporting Tools 1,000 1,000
Sub Total 262,520
78.35
0.51 -
-
Batu krikil 117,300 54,012
P. Cement 24,480 56,236
Pasir 35,700 9,755
-
Pouring Concrete, Cleaning 50,000 25,553
Equipment -
Lory, timber, ducting etc. 2,000 1,012
75.44 -
-
Portland Cement 612 274,246
Pasir 35,700 56,557
-
Cement Plaster 13,000 980,720
Equipment -
Supporting Tools 2,000 150,880
Sub Total 1,462,403
-
-
-
11.67 -
-
Setting, Leveling, Cleaning and Compacted 4,500 52,515
Equipment -
Excavator 16,500 192,555
Sub Total 245,070
1.39
Pasir 35,700 59,548
-
Pekerja 28,050.00 11,697
Mandor 45,900.00 638
Sub Total 71,882
74.84 -
-
SK Wood 2,203,200 1,978,756
Triplex 12 mm thick 117,300 2,984,928
Nails 9,078 271,774
-
Fabrication, Installation, Remove 20,000 1,496,880
Equipment -
Tools 1,000 74,844
Sub Total 6,807,182
5.73
7.58
175.04
29.64
59.28
1.60
0.07 -
0.29 -
0.37 -
-
1" x 6" 2,750,000 12,210
2" x 3" 2,750,000 48,279
2" x 4" 2,750,000 60,225
-
Fabrication 900,000 658,440
Equipment -
Suporting Tools 1,000 732
Sub Total 779,886
2.00
Pintu + Accessories + Pengecatan 960,000 1,920,000
-
Fabrication 250,000 500,000
Equipment -
Suporting Tools 1,000 2,000
Sub Total 2,422,000
16.50
49.50
5.00
2.00
2.00
-
Kran air biasa 25,500 51,000
-
Instalation 20,000 40,000
Equipment -
Suporting Tools 1,000 2,000
Sub Total 93,000
5.00
-
Closed duduk Merk KIA standart 1,020,000 5,100,000
-
Instalation 150,000 750,000
Equipment -
Suporting Tools 1,000 5,000
Sub Total 5,855,000
52.00
-
Atap seng "BJLS" 41,412 2,196,492
Nails 9,078 70,808
-
Instalation 20,000 1,040,000
Equipment -
Suporting Tools 1,000 52,000
Sub Total 3,359,301
187.20
-
Cat dasar (Kimex) 5,793.60 152,923
Cat Finish (Vinilex) 10,098.00 536,858
-
Upah 5,000.00 936,000
Equipment -
Supporting Tools 125 23,400
Sub Total 1,649,181
16.17
0.81
55.86
120.54
UPAH:
Pekerja Rp. 28,050.00 27,500.00 / hari
Mandor Rp. 45,900.00 45,000.00 / hari
Tukang Rp. 40,800.00 40,000.00 / hari
Kepala tukang Rp. 45,900.00 45,000.00 / hari
Pemasak aspal Rp. 28,050.00 27,500.00 / hari
Jaga malam Rp. 25,500.00 25,000.00 / hari
BAHAN: Harga
Tanah merah Rp. 0.00 0.00 / m3
Pasir Rp. 35,700.00 35,000.00 / m3
Batu Kerikil Rp. 117,300.00 115,000.00 / m3
P. Cement Ex Andalas @ 40 Kg Rp. 24,480.00 24,000.00 / Zak @ 40 Kg
P. Cement Ex Andalas Rp. 612.00 600.00 / Kg
Batu Bata Mesin Rp. 357.00 350.00 / Pcs
Riol Beton dia. 30 mm Rp. 34,170.00 33,500.00 / Pcs
Asbes/ Eternit Rp. 7,650.00 7,500.00 / Lbr
Lat Asbes Rp. 7,650.00 7,500.00 / Btg
Profil Sudut kayu Rp. 15,300.00 15,000.00 / Btg
Wiremesh M-7 Rp. 302,940.00 297,000.00 / Lbr
Wiremesh M-7 Rp. 28,579.25 28,018.87 / m2
Wiremesh M-8 Rp. 405,960.00 398,000.00 / Lbr
Wiremesh M-8 Rp. 38,298.11 37,547.17 / m2
Kayu Sembarang Rp. 2,203,200.00 2,160,000.00 / m3
Kayu Sembarang Rp. 1,632,000.00 1,600,000.00 / Ton
Kayu Sembarang - 2" x 2" Rp. 14,280.00 14,000.00 / Btg
Papan Sembarang Rp. 1,734,000.00 1,700,000.00 / Ton
Papan Sembarang Rp. 24,480.00 24,000.00 / Btg
Kayu Meranti Rp. 2,244,000.00 2,200,000.00 / Ton
Kayu Meranti - 2" x 6" Rp. 79,560.00 78,000.00 / Btg
Kayu Meranti - 2" x 9" Rp. 128,520.00 126,000.00 / Btg
Tripleks - 3 mm Rp. 33,660.00 33,000.00 / Lbr
Tripleks - 4 mm Rp. 39,270.00 38,500.00 / Lbr
Tripleks - 9 mm Rp. 44,880.00 44,000.00 / Lbr
Tripleks - 12 mm Rp. 117,300.00 115,000.00 / Lbr
Garuda Form 18 mm Rp. 173,400.00 170,000.00 / Lbr
Paku Rp. 9,078.00 8,900.00 / Kg
Besi Beton Polos Rp. 5,579.40 5,470.00 / Kg
Besi Beton - dia. 16 mm Polos Rp. 105,672.00 103,600.00 / Btg
Kawat Beton Rp. 6,630.00 6,500.00 / Kg
Pipa PVC dia 4" AW Rp. 201,434.70 197,485.00 / Btg
Pipa PVC dia 3" AW Rp. 121,528.92 119,146.00 / Btg
Lem Pipa Rp. 58,650.00 57,500.00 / Kg
Keramik lantai 40x40 Roman Rp. 40,800.00 40,000.00 / Ktk
Keramik lantai K.mandi Roman Rp. 43,860.00 43,000.00 / Ktk
Keramik dinding K.mandi Roman Rp. 47,430.00 46,500.00 / Ktk
Semen Putih Rp. 2,040.00 2,000.00 / kg
Closed Jongkok KIA Rp. 122,400.00 120,000.00 / Set
Closed duduk KIA Rp. 1,020,000.00 1,000,000.00 / Set
Wastafel KIA studio 50 Rp. 357,000.00 350,000.00 / Set
Kran air PIO Rp. 153,000.00 150,000.00 / Set
Kran air biasa Rp. 25,500.00 25,000.00 / Set
Pintu PVC (deco door 90cmx210cm) Rp. 201,960.00 198,000.00 / Set
Floordrain 3" Biasa Rp. 45,900.00 45,000.00 / Set
Atap seng BJLS 40 7' x 11 Parit Rp. 41,412.00 40,600.00 / Lbr
Ready Mix K-125 Batu Guli Rp. 314,160.00 308,000.00 / m3
Ready Mix K-175 Batu Guli Rp. 264,180.00 259,000.00 / m3
Ready Mix K-225 Batu Guli Rp. 351,900.00 345,000.00 / m3
Kawat Las RB Rp. 10,710.00 10,500 / Kg
WF.350 KS Rp. 6,630.00 6,500.00 / Btg
WF.300 KS Rp. 6,630.00 6,500.00 / Btg
WF.250 KS Rp. 6,630.00 6,500.00 / Btg
WF.200 KS Rp. 6,630.00 6,500.00 / Btg
UNP. 125.65.6 KS Rp. 6,630.00 6,500.00 / Btg
UNP. 125.50.5 KS Rp. 6,630.00 6,500.00 / Btg
CNP. 150.50.20.2,3 KS Rp. 6,120.00 6,000.00 / Btg
Rekapitulasi Pemakaina Bahan Sementara
Proyek Rubber Wod Processing Plants
/
/
/
/
/
/
Keperluan
/
/ 2,403.03 m3
/ 2,238.33 m3
/ 45,728.98 Zak @ 40 Kg
/
/ 187,563.35 Pcs
/ 197.25 m'
/
/
/
/ 11,518.53 m2
/
/ 220.32 m2
/
/
/
/
/
/
/
/
/
/
/
/
/
/
119,000 / 18 Kg 847.03 Kg
/
/
/ 574.99 Kg
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/ 3,005.89 Kg
3,778,350 /
2,794,500 /
2,255,000 /
1,625,000 /
485,000 /
/
165,000 /
ahan Sementara
cessing Plants
146,000 /
/
2,555,000 /
2,044,000 /
1,700,000 /
1,365,000 /
1,022,000 /
1,120,000 /
135,000 /
210,000 /
425,000 /
149,000 /
188,000 /
8,000 /
20,500 /
13,000 /
7,500 /
/
2,503 /
1,228 /
642 /
190 /
/
34,500.00 / m'
30,500 / m'
30,500 / m'
15,250 / m'
/
/
/
/
/
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan sebelum Pekerjaan Ls 1.00 42,000,000.00 42,000,000
2 Pembuatan Direksi Keet/ Gudang Ls 1.00 36,750,000.00 36,750,000
3 Mobilisasi/ Demobolisasi Ls 1.00 42,000,000.00 42,000,000
4 Management Fee Ls 1.00 9,975,000.00 9,975,000
5 Pengadaan Air Kerja Ls 1.00 4,725,000.00 4,725,000
6 Penerangan Lampu/ Listrik Kerja Ls 1.00 37,800,000.00 37,800,000
7 Biaya Keamanan/ Jaga Malam/ OKP Ls 1.00 37,800,000.00 37,800,000
8 Dokumentasi Ls 1.00 7,875,000.00 7,875,000
9 Pembersihan Lapangan setelah selesai Pekerjaan Ls 1.00 26,250,000.00 26,250,000
10 Pengukuran/ Pematokan & Pemasangan Bowplank m' 1,501.00 18,375.00 27,580,875
Sub Total 272,755,875
II BANGUNAN PABRIK uk. 30M x 96M (3 Unit)
A. Pekerjaan Sipil uk. 30m x 96m (3 Unit)
- Pondasi Type F1 = 34 Units
1 Galian Pondasi m3 66.64 22,000.00 1,466,080
2 Pasir Urug t = 5 cm m3 3.33 65,000.00 216,580
3 Lantai Kerja K-125 t = 5 cm m3 3.33 495,000.00 1,649,340
4 Bekesting m2 137.70 60,000.00 8,262,000
5 Besi Beton Kg 2,031.84 8,850.00 17,981,784
6 Cor Beton K-225 m3 29.58 625,000.00 18,487,500
7 Timbunan Kembali Bekas Galian m3 30.40 12,500.00 380,000
Sub Total 48,443,284
- Pondasi Type F2 = 26 Units
1 Galian Pondasi m3 50.96 22,000.00 1,121,120
2 Pasir Urug t = 5 cm m3 2.55 65,000.00 165,620
3 Lantai Kerja K-125 t = 5 cm m3 2.55 495,000.00 1,261,260
4 Bekesting m2 102.44 60,000.00 6,146,400
5 Besi Beton Kg 1,553.76 8,850.00 13,750,776
6 Cor Beton K-225 m3 22.15 625,000.00 13,845,000
7 Timbunan Kembali Bekas Galian m3 23.71 12,500.00 296,400
Sub Total 36,586,576
- Pondasi Type F3 = 34 Units -
1 Galian Pondasi m3 66.64 22,000.00 1,466,080
2 Pasir Urug t = 5 cm m3 3.33 65,000.00 216,580
3 Lantai Kerja K-125 t = 5 cm m3 3.33 495,000.00 1,649,340
4 Bekesting m2 137.70 60,000.00 8,262,000
5 Besi Beton Kg 2,031.84 8,850.00 17,981,784
6 Cor Beton K-225 m3 29.58 625,000.00 18,487,500
7 Timbunan Kembali Bekas Galian m3 27.64 12,500.00 345,525
Sub Total 48,408,809
- Saluran Terbuka (Fabrik)
1 Galian m3 121.34 22,000.00 2,669,480
2 Cor Beton K-175 m3 20.22 575,000.00 11,628,225
3 Batu Bata m2 288.90 44,950.00 12,986,055
4 Plasteran sisi bagian dalam m2 404.46 22,500.00 9,100,350
Sub Total 36,384,110
- Bak Kontrol uk. 300 x 400 mm (34 Units) -
1 Galian m3 11.66 22,000.00 256,564
2 Cor Beton K-175 m3 2.10 575,000.00 1,207,500
3 Batu Bata m2 66.40 44,950.00 2,984,680
4 Plasteran m2 80.92 22,500.00 1,820,700
BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
TOTAL 6,380,857,245
MARGIN (5 %) 319,042,862
TOTAL 6,699,900,107
PPN (10 %) 669,990,011
TOTAL KESELURUHAN 7,369,890,118
SUMMARY - BILL OF QUANTITIES
Project : PT. TIGA MUTIARA NUSANTARA
Work (S) : BANGUNAN PABRIK
TOTAL 6,380,857,245
MARGIN (5 %) 319,042,862
TOTAL 6,699,900,107
PPN (10 %) 669,990,011
TOTAL KESELURUHAN 7,369,890,118