VT4E-MS For Grouting of Sonic Pipe For Bored Pile
VT4E-MS For Grouting of Sonic Pipe For Bored Pile
VIETNAM ELECTRICITY
Owner’s Engineer
POWER ENGINEERING
POWER ENGINEERING
CONSULTING JOINT STOCK
CONSULTING JSCOMPANY 3
COMPANY 4
Contractor
Sub-Supplier
FECON CORPORATION
CONTENT
1. PREFACE………………………………………………………………………………..2
2. RESPONSIBILITIES………………..………………………………………………….2
4. QUALITY CONTROL……………….…………………………………………………5
DOC.NO.VT4E-DD09-P3ZEN-040008 Rev. A 1 of 9
EVNGENCO3/VTTPM Vinh Tan 4 Extension Thermal Power Plant
DMPP Consortium
1.0 PREFACE
The purpose of this Method Statement is to describe the methodology involved in grout for sonic pipe and to
details out the steps to be taken in meeting the technical standard and EHS requirements of Vinh Tan 4
Extension Thermal.
Management Board
2.0 RESPONSIBILITIES
• It is overall responsibility of Project Manager to organize resources prior to perform construction activities
as per project specification in compliance with the quality, schedule & safety requirements.
• EHS Manager will ensure in coordination with Site Engineer that all measure/construction taken shall be
maintained till completion of job.
• It is the responsibility of Construction Manager/Site Engineer that construction activities are executed
according to the relevant project specification in compliance with the quality, schedule & safety
requirements.
• DMPP will ensure that all works are performed safely according to the attachment.
• The relevant DMPP Supervisor will ensure that the work is carried out in accordance with this method
statement and project specification.
• The QC Inspector will ensure that the work is executed according to the requirements of quality dossier are
fulfilled.
DOC.NO.VT4E-DD09-P3ZEN-040008 Rev. A 2 of 9
EVNGENCO3/VTTPM Vinh Tan 4 Extension Thermal Power Plant
DMPP Consortium
Step 3: Cleaning of
equipment, removal of
pump head (from 2-4 h),
cleaning of pump
Finish
a. Equipment
- High pressure specialized water pump and high pressure water pipes, flexible hose including
spraying head
- Air compressor, compressed air leading pipes
- Electrical hoist and pipe hanging stand
(Air compressor)
b. High pressure mortar pumping equipment
- Mortar mixing station and containing tank
- Pressure mortar pump (18 atm)
DOC.NO.VT4E-DD09-P3ZEN-040008 Rev. A 3 of 9
EVNGENCO3/VTTPM Vinh Tan 4 Extension Thermal Power Plant
DMPP Consortium
a. Execution staff
- Directly executing technical staff: 02 people
b. Water and compressed air cleaning team
- A team of workers consisting of 3-5 people
c. Pile bottom mortar pumping team
- A group of workers for mortar mixing and testing activities comprising of 3-4 people
- A group of workers for operation of pump, repair of execution machinery & equipment: 2 people
- A group of workers for connection & installation of pipes as well as cleaning of equipment: 4
people
3.4. Working procedure:
- To direct air hose to pipe bottom to blow out water and sediment from pipe (pressure of 4 to 6 atm
is used)
- To finish pile bottom cleaning process and to start pile bottom mortar pumping process.
b. Mortar pumping
1. Preparation of mortar
- Mortar consists Portland cement, PC sr 40 Ha Tien cement, SIKA Intraplast Z- HV and plastiment
96 additives as well as water
- To mix mortar with mixer (100kg cement + 34,7 litres water + 0,8 kg Intraplast Z- HV and 400 ml
plastiment 96). The water must be tested before making the design mixing (using the same water
for concrete work). The time for mixing mortar within five minutes and execute duration for one
times around fifteen minutes . the trial mix will be proceed before start permanent work.
- Mortar sample is taken in standard form 5 x 5 x 5 cm, at least 9 sample sets per working day
Strength of mortar sample after compression reaches grade 30 Mpa , according to ASTM C39
2. Mortar pumping process
- To direct pumping hose to the bottom of ultrasonic pipe, to pump mortar to fill the pipe to level of
pile cut, pumping pipe is taken up gradually till pumping work finished.
DOC.NO.VT4E-DD09-P3ZEN-040008 Rev. A 4 of 9
EVNGENCO3/VTTPM Vinh Tan 4 Extension Thermal Power Plant
DMPP Consortium
The Site Inspection and Test Plan (ITP) for this work summarizes various characteristics to be checked. The
concerned Site Engineer/Foreman will be responsible to ensure stage wise compliance for these operation and
the Site QA/QC Engineer/Inspector will carry-out quality control checks and report the inspection results.
DOC.NO.VT4E-DD09-P3ZEN-040008 Rev. A 5 of 9
EVNGENCO3/VTTPM Vinh Tan 4 Extension Thermal Power Plant
DMPP Consortium
A.1e Ambulance car and designated Nurse must be on stand by for the
entire working operation.
A. Working Operation
During A.1f Must use and connect 3 core codes electric wires
Night Time with separate distribution panel (must pass arrangement of ECLB).
A.2 Generator (Diesel) equipment oil leakage A.2b Regular check &monitoring of the equipment prior to use.
during operation.
A.2c Provide secondary containment protection under
the equipment to prevent contamination of soil by oil
spillage
DOC.NO.VT4E-DD09-P3ZEN-040008 Rev. A 6 of 9
EVNGENCO3/VTTPM Vinh Tan 4 Extension Thermal Power Plant
DMPP Consortium
(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing solutions that
control, minimize or eliminating hazards.
B. Transportation B.1a Stricture of nearby workers or falling by B.1a Set measures to prohibit workers from entering the site and
and carriers as a result of not implementing
Delivery of measure to prohibit workers from approaching. control nearby workers by dispatching a guidance.
Equipment B.1b Overturning of equipment due to not B.1b Check ground condition prior to setting of equipment.
placing on stable and firm ground.
B.1c Check the access road before passing the area
B.1c Crash/traffic accident B.1d Designate a signalman when moving the equipment
C. Heavy Lifting C.1 Crushing may cause fatal injury or C.1a Prepare a lifting plan
Works permanent disability
C.1b Use only a qualified and certified operators. Signalman should
be in-place.
C.1c No standing beneath the lifting areas.
C.1d Ensure loads are fixed with sling belt correctly.
C.1e All lifting equipment must be in good condition.
C.1f Experienced lifting supervisor at all times.
C.1g Provide barricades to stop unauthorized entry.
C.1g Use the lifting tools must attached monthly inspection tag.
C.1h All lifting tools must attached identification tag (include serial
number, certification number, inspection date and
due date) for visual identification.
C.1i Provide safe entrance and exit access road for the labors.
C.2 Defective lifting equipment leading to C.2a Use only qualified and certified operators. Signalman should be
mechanical failure
be in place.
C.2b Always check the equipment prior to start any work.
C.3 Improper positioning of crane C.3a Use only qualified and certified operators. Signalman should be
be in place.
D. Unloading D.1 Struck down by things and materials D.1a Make sure the sling is tied/bided correctly and tightened.
Equipment and D.1b Check the lifting devices (slings, shackles, etc) for proper
Materials
use and safety.
D.2 Squeezed by the sling D.2a Use hand gloves when tightening the slings.
D.2 b Tighten the slings before carrying-out lifting.
D.3 Squeezed by the materials D.3a Use wooden sleepers as support of the materials on the ground.
D.4 Crane fall accidentally D.4a Use the proper device and equipment,
DOC.NO.VT4E-DD09-P3ZEN-040008 Rev. A 7 of 9
EVNGENCO3/VTTPM Vinh Tan 4 Extension Thermal Power Plant
DMPP Consortium
(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing solutions that
control, minimize or eliminating hazards.
DOC.NO.VT4E-DD09-P3ZEN-040008 Rev. A 8 of 9
EVNGENCO3/VTTPM Vinh Tan 4 Extension Thermal Power Plant
DMPP Consortium
DOC.NO.VT4E-DD09-P3ZEN-040008 Rev. A 9 of 9