Method Statement For Drainage Works
Method Statement For Drainage Works
DOCUMENT NO. :
169995815.doc
SHEET 2 OF 7
DISTRIBUTION ORDER
Internal Engineering (by EDO): Internal REKAYASA (by EDO): External CONTRACTOR (by Transmittal, note-1):
Civil Lead Eng. Project Manager PGB (1+{1}) Copies
Electrical Lead Eng. Procurement Manager For Approval
Instrument Lead Eng. Project Control Manager For Review
Mechanical Lead Eng. Construction Manager For Info.
Piping Lead Eng. QA/QC Manager
Process Lead Eng.
Engineering Manager
CONTENTS
SECTION PAGE
1. GENERAL
1.1 SCOPE 4
1.2 LANGUAGE 4
1.3 UNITS OF MEASUREMENT 4
2. APPLICATION STANDARDS & REFERENCES 4
3. PREPARATION 5
4. SETTING-OUT 5
5. EXCAVATION AND COMPACTION WORK 5
6. LEVELING CONCRETE AND SAND BEDDING 6
7. INSTALLATION OF PRECAST U-DRAIN 6
8. INSTALLATION OF PRECAST PIPE 6
9. BACKFILLING AND COMPACTION 7
1. SCOPE
1.1 Scope
This document describes the method of sewer & drainage work for Kuantan
Compressor Station Expansion Project of Petronas Gas Berhad, Kuantan,
Malaysia.
This method statement covers of following steps:
• Preparation
• Surveying
• Excavation and Compaction
• Leveling Concrete and Bedding
• Installation Pre-cast U-Drain or Pipe
• Backfilling and Compaction
1.2 Language
All drawings, calculation sheets and documents shall be written in English except
where government authorities demand the local language for their approval. Such
demand shall be observed.
1. Government Legislation
• Malaysia Uniform Building by Laws
• Urban Storm Water Management Manual for Malaysia, issued by Department
of Irrigation and Drainage, Malaysia
• Jabatan Kerja Raya (JKR), Malaysia
• Bekalan Air Johor (BAJ), Malaysia
• Rules and Regulations for Electrical, Insulation, Suruhanjaya Tenaga, Energi
Commision
• Jabatan Bomba dan Peyelamat
4. Final Factual Report of Soil Investigation Works for KUANTAN Compressor Station
Expansion Project by Soil Centralab Sdn Bhd
2. PREPARATION
1) All materials to be used for this work shall meet the drawings and/ or specific job
requirements. Catalogs and/ or samples of the materials shall be submitted to
Contractor and Owner for approval prior to commencement of the work.
2) Prepare the execution plan including all related man power and equipment to be
provided, schedule, and working drawing for following works.
3) Provide mix design concrete and conduct trial mix for all required grades of concrete
3. SETTING-OUT
To get the precise position of the drainage the following items shall be carried out.
1) Set the alignment of centerline of drain by Subcontractor License Surveyor,
refer to reference drawings.
2) Establish marking at the edge of intended drain line for indicating depth of
excavation as per reference drawings.
7) Provide a red safety tape surrounding excavation pits as safety measure. Hard
barricades shall be provided where necessary.
5) Provide a recess on the bedding material to accommodate the socket. The width
of the recess of the socket by more than 50 mm.
6) Pipes shall be laid in upstream direction with the socket towards the inlet.
7) Check the alignment of pipe or drainage section by section, partially, by
Subcontractor QC and witnessed by Contractor QC.
8) Prior to jointing, rubber rings and jointing surfaces shall be cleaned of all
contaminants.
9) Rubber ring joints shall be installed strictly in accordance with the manufacturer’s
instruction.
10) The care must be taken to ensure the rubber ring is adequately compressed to
seal the joint.
11) Inspect joints by Subcontractor QC or Supervisor and witnessed by Contractor
QC.
12) After all pipes for certain section of road crossing is completely installed, the
survey on the intended invert level of the pipes to be checked and must be within the
tolerance given in the specification before the backfilling can be started.
13) Joint inspection for drainable slope of drainage between Subcontractor’s QC and
Contractor’s QC.
14) Subcontractor shall submit details of proposed methods and program for testing,
including details of test equipment, for Contractor’s approval and shall arrange for all
test to be witnessed by Contractor.