CONTRACT ID NO.

20Z00010
Marawi Transcentral Road, Phase III under
Road Network Development Project in Affected Areas in Mindanao (RNDP-CAAM)
Contract Package 3B
WEEKLY ACCOMPLISHMENT REPORT NO. 40
(May 23-May 29, 2022)

ACCOMPLISHMENT
PREVIOUS TO DATE
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT % Wt. TOTAL
(May 14, 2021 to May 22, 2022) (May 23-May 29, 2022)
Qty % Qty % Qty % % wt.
PART A: FACILITIES FOR THE ENGINEER 1.00 l.s. 11,916,014.88 11,916,014.88 6.870 0.840 84.00% 0.019 1.90% 0.859 85.90% 5.902
PART B: OTHER GENERAL REQUIREMENTS 1.00 l.s. 12,490,961.53 12,490,961.53 7.202 0.234 23.38% 0.005 0.54% 0.239 23.93% 1.723
PART C: EARTHWORKS - -
100(1) Clearing and Grubbing 4.65 Ha. 168,723.19 784,394.11 0.452 3.413 73.41% - 0.00% 3.413 73.41% 0.332

101(1) Removal of Actual Structures/Obstruction 1.00 l.s. 520,852.12 520,852.12 0.300 - 0.00% - 0.00% - 0.00% -

Removal of Actual Structures/Obstruction


101(3)b2 16,276.00 sq.m. 187.21 3,047,029.96 1.757 10,556.418 64.86% 250.000 1.54% 10,806.418 66.39% 1.166
(PCCP Unreinforced 200mm thk)
102(2) Surplus Common Excavation 11,848.00 cu.m. 221.33 2,622,317.84 1.512 8,494.712 71.70% - 0.00% 8,494.712 71.70% 1.084
103(1)a Structure Excavation (Common Soil) 11,606.00 cu.m 273.03 3,168,786.18 1.827 5,516.016 47.53% 0.00% 5,516.016 47.53% 0.868
Embankment From Roadway Excavation –
104(1)a 7,667.00 cu.m. 383.20 2,937,994.40 1.694 2,886.453 37.65% - 0.00% 2,886.453 37.65% 0.638
Common Soil
105(1)a Subgrade Preparation (Common Material) 36,623.00 sq.m. 18.27 669,102.21 0.386 22,070.828 60.26% 864.000 2.36% 22,934.828 62.62% 0.242
SUB-TOTAL (Part C) 13,750,476.82 7.928 - 4.330
PART D: SUBBASE AND BASE COURSE - -
200(1) Aggregate Subbase Course (300mm thk) 9,710.00 cu.m. 1,932.36 18,763,215.60 10.818 5,672.343 58.42% 106.800 1.10% 5,779.143 59.52% 6.439
SUB-TOTAL (Part D) 18,763,215.60 10.818 - 6.439
PART E: SURFACE COURSE 1.00 l.s. 63,765,547.71 63,765,547.71 36.765 0.628 62.85% 0.023 0.652 65.18% 23.962
Portland Cement Concrete Pavement
311(1)c1 5,522.00 sq.m. 1,718.06 9,487,127.32 5.470 2,770.030 50.16% 96.000 1.74% 2,866.030 51.90% 2.839
(Unreinforced, 230mm thk)
Portland Cement Concrete Pavement
311(1)e1 24,671.00 sq.m. 2,200.09 54,278,420.39 31.295 16,052.330 65.07% 600.000 2.43% 16,652.330 67.50% 21.123
(Unreinforced, 280mm thk)
SUB-TOTAL (Part E) 63,765,547.71 36.765 23.962
PART F: BRIDGE CONSTRUCTION 1.00 l.s. 2,656,604.15 2,656,604.15 1.532 0.353 35.33% - 0.00% 0.353 35.33% 0.541
PART G: DRAINAGE AND SLOPE PROTECTION STRUCTURES 1.00 l.s. 40,010,765.88 40,010,765.88 23.069 0.3426 34.26% 0.00% 0.343 34.26% 7.904
500(3)b1 Lined Canal (Rectangular Concrete) 8,133.00 l.m. 4,909.64 39,930,102.12 23.022 3,653.709 44.92% 160.000 1.97% 3,813.709 46.89% 10.795
505(1)a Riprap Class A 18.00 cu.m. 4,481.32 80,663.76 0.047 - 0.00% 0.00% - 0.00% -
SUB-TOTAL (Part G) 40,010,765.88 23.069 10.795
PART H: MISCELANEOUS STRUCTURES 1.00 l.s. 45,961,607.33 45,961,607.33 26.500 - 0.00% 0.00% - 0.00% -

TOTAL AMOUNT 173,442,206.06 100.000 52.059 1.634 53.692

Prepared by: Checked/Verified by: Noted by:

OSMAN M. SARIP GENESIS B. SUBALDO JOSEFINO S. SARIGAN


QUANTITY ENGINEER RESIDENT ENGINEER PROJECT MANAGER