Professional Documents
Culture Documents
Design Report Class Iv Rock Mass
Design Report Class Iv Rock Mass
NH-39 (New NH-02), NH-150(New NH-02), NH-61(New NH-29) and NH-39 (New NH-02)
from Design Km 10.500 to design Km 21.00 [Design Length – 10.500 Km] in the state of
Nagaland Under SARDP-NE on EPC Mode (Package II)
R1 05-07-2021
Draft 28-05-2021
Rev Date Description
Design consultant:
CivilMantra Infracon Pvt. Ltd.
2. Scope
As per geotechnical investigation class III & Class IV rock is present along the tunnel chainage.
This design note covers design of primary support elements for Rock Class IV. Two separate
support design is presented for the same rock (class IV) based on overburden depth. The
primary supports for tunnel at ‘portal reach’ is designed for overburden depth smaller than
30m. For larger overburden depth (i.e., between 30 to 60m) a separate design is presented.
3. Design Input
There are essentially three major inputs for the analytical design.
• Excavation geometry and depth of tunnel
• Geotechnical Parameters of rock to be supported
• Material parameters of the components used for design.
Rock Class Final Lining Final Lining Primary Construction Over- Expected
Tolerance Thickness Support Tolerance excavation Convergence
(mm) (mm) Thickness (mm) (mm) (mm)
(mm)
Class IV
(Portal 325 32 21
50 350 50
Reach)
Class IV 375 96 26
Previously the strength properties of rock mass are taken from the guidelines presented in
IS:13365 P-1. However, upon recommendations during design review meetings it was decided
to verify the design using Hoek-Brown failure criterion.
The design team visited the site for the first-hand information for rock mass evaluation and
concluded that prima-facie rock mass could be categorized as shown in following table. These
values are further moderated for design purposes as shown in table 2 in order to be on safer
side of design. Geological Strength Index (GSI) has been estimated from 𝐺𝑆𝐼 = 𝑅𝑀𝑅 − 5.
Table 1: Expected RMR and Q ranges of rock mass along Kohima Tunnel alignment
From the rock mass evaluation and using above correlation for GSI, it was concluded that the
rock mass has GSI range as shown in the following figure.
The material parameters used for design are presented below, Other required Hoek Brown
parameters are calculated automatically by Phase2 program. The Poisson’s ratio is taken as
0.25. Table 2 presents the input values of various rock mass parameters to RocLab program. The
output of the program is presented in following figures. There values have been used in Phase2
program.
Preliminary unsupported tunnel models show complete collapse of tunnel cavity, with yield
zone extending up-to ground surface. Also due to extremely poor rock mass geomechanical
values it was decided to grout the surrounding rock mass up to a thickness of 5m. Consolidation
grouting is recommended with cement grout injected under pressure of 5 to 10 kg/cm2 with
the hole spacing of 500 to 1000 mm or as deemed fit as per site conditions. The objective of
grouting is to form an improved layer of rock mass 5m thick around the tunnel excavated
periphery. The rock mass should be grouted at least 1D ahead of excavation face for both
heading and benching, where D is the tunnel diameter.
Table 3: Primary supports used for Rock Class IV at different overburden depths.
Figure 3: FEM model of tunnel in Phase2 program for Class IV rock mass at portal reaches.
Figure 5: Longitudinal Displacement Profiles (LDP) templates suggested by Vlachopolous & Diedrichs (2009).
Table 4: Calculation of pre-convergence from LDP profiles as shown in Fig. 2 for Class IV rock mass with maximum
overburden.
Figure 8: Displacement contours for tunnel in class IV rock mass at portal reaches.
Figure 9: Moment - Thrust diagram for tunnel in class IV rock mass at portal reaches.
5. Conclusion
This design note presents design for proposed Kohima Bypass tunnel. As per the site
investigation the tunnel will be excavated in class IV and class V rock mass. The rock mass
behavior has been established from geological and geotechnical investigations. The rock
mass is assumed to have elasto-plastic behavior with strength specified by Hoek-Brown
failure criterion.
For design purposes Class IV rock mass is divided into two categories, one found in portal
reaches with maximum overburden of 30m and another at maximum overburden depth of
60m. The rock mass should be grouted with cement grout to form a grouted arch of 5 m
thickness all around. For tunnel sections with overburden >30m rock mass below invert
should also be grouted, whereas invert grouting is not necessary for tunnel sections with
overburden <30m. The rock is further supported with 4m long SN/SD type rock bolts applied
at a spacing of 1.5m x 1.5m.
For maximum overburden section the primary support of ISMB 250 @ 500mm c/c with a
M25 grade backfill concrete of 300mm thickness is found to be sufficient. For rock mass at
portal reaches, ISMB 200 @ 500mm c/c along with backfill concrete of 250 mm thickness is
found to be sufficient. The safety of supports is estimated using moment-thrust diagrams.
From the results of Phase2 analysis it is concluded that the applied supports are sufficiently
safe.
List of Appendices
Appendix A: Phase2 report of FEM modelling of tunnel excavation and support for Class IV
rock mass in portal reaches i.e. low overburden conditions.
Appendix B: Phase2 report of FEM modelling of tunnel excavation and support for Class IV
rock mass in high overburden conditions.