Bored Piles Vs Driven Piles

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Bored piles Driven piles

Constructability Issues Length is not easy to adjust but Length is easy to adjust using
must take into consideration some elements
some procedures (Splicing or
(Cage modifications) cut-off of steel piles, cut-
off of PSC piles).
Redundancy & Loading Issues • Bigger elements • Smaller elements
• Higher capacity • Lower capacity
• Higher cost • Lower cost
• Fewer elements used • More elements used
Integrity & Reliability Issues  Defects may occur  Delivered free of
during construction. defects.
 Damage after  May be damaged during
construction is possible or infrequently, after
but rare. installation.
 Defects are not easily  Damage is typically
quantified. easily.
 Repair is generally very  Repair generally
complex. consists of adding a
new pile.

Material:

Driven Piles are constructed using prefabricated material that can be physically inspected before and
during installation. The material is installed by impact hammering, vibrating, or pushing into the ground.
The shape and size of the material are predefined. Timber, steel, or precast concrete piles may be
among them.

Cast-in-place concrete piles, or bored piles, are constructed on the construction site. Drilled Shafts, Mini
Piles, Micro Piles, Drilled Displacement, Sectional Flight Auger (SFA), and Continuous Flight Auger (CFA)
piles are a few examples of these.

Equipment:

Driven Pile Construction Equipment typically consists of a crane, hammer, piling rig, powerpack
(hydraulic or air-hammer), casing, slurry handling, cage erection template, concrete truck, and concrete
pump truck. Bored Pile Construction Equipment typically consists of a drill rig, helper crane, spoil
handling (loader, skip pan, etc.), spoil handling, casing, and slurry handling.
Advantages Disadvantages
Bored piles 1.Variable-length piles can be 1. The fact that bored piles take
extended into acceptable more time than other systems
bearing. are one of their key drawbacks.
2.Piles can be lowered to levels This is particularly true for
below seasonal moisture smaller projects because only
variation and frost penetration. one foundation system, such as
3.Prolonged backfilling and this one, can be used
large excavations are successfully rather than two
minimized. different systems cooperating
4. The nearby earth is less as in larger projects where pile
disturbed. foundations and spread footings
5. The vibration is quite can both be used successfully
moderate, which lessens simultaneously on various parts
disruption to nearby piles or of a building's structure.
structures. 2. Noise pollution brought on by
6. Bored piles offer higher installation machinery.
capacity and potentially better 3. Require skilled equipment
economies than driven piles in and operators.
many design scenarios.
Driven piles 1. Installing driven piles is not 1. The cost of installation may
that difficult. be high.
2. They can be set up in 2. The installation process might
different kinds of soil. be disruptively noisy.
3. Effective ways to aid in the 3. The possibility of
creation of a new structure. underground utilities being
4. Fast installation. harmed exists.
5. They can be used in areas 4. The main drawback of piles is
that have minimal or no ground that they need to be buried
preparation, as they require no deeply in the ground to obtain
excavation work to install them. sufficient support.
5. If piles are not evenly spaced
apart, this imbalance may affect
other piles and produce more
settlement or bearing failure.

You might also like