Professional Documents
Culture Documents
Break Down Cobble Final
Break Down Cobble Final
FOR
1.1 Fix Station points, PI, at 100-200m intervals for reference of the
Centreline of the Road. Where there is a Horizontal curve or
vertical curve the interval of the PIs will be less than 100 m.
KM -
Setting
out
1.2 Fix centreline of the road by putting pegs at 20m intervals
including setting of horizontal and vertical curves. Set out also
cross-section of the road at 20m intervals or less as convenient, if
terrain is very ragged, by placing pegs on centre, two sides and
drainage lines of the road as well as following design patterns of
the cobblestone. Pegs for cobblestone roads are in most cases made
from pieces of reinforcement steel for accuracy and strength for
driving them deep into the ground. The number of pegs along the
cross-section of the road ranges from 7 to 13 depending on the
pattern of the cobblestones and requirement of side drains
KM -
Sub Total -
2. Earthwork
Clearing and Grubbing
2.1 Remove trees, tree roots, bushes, big stones, grass and other
obstacles with 15m width of the road reserve to allow
movement of workers for smooth surveying and setting out
works. Those trees to be retained, as ordered by the Engineer,
will be kept undamaged. The material or debris as a result of
clearing and grubbing will be deposited to the location as
directed by the engineer.
Ha
Top
Soil Excavation
2.2 Excavate the top 15-20 cm top soil to remove the soil with grass
and organic layer of the soil which is very weak, compressible and
not required for road construction. The excavated material will be
deposited at a place directed by the Engineer(Not more than
5Km).
M2 -
2.3 Bulk
Excavation
Excavate the layer of the soil next to the top 15-20 cm, if directed by
the Engineer, where the soil layer is silt or black-cotton-soil or
humus and not accepted as a sub-grade. The excavated material
will be deposited at a place directed by the Engineer.(not more
than 5km)
M3 -
Backfill
using Sub-base Material
2.4 Supply, spread and compact 15-20cm, or more of sub-base granular
material or gravel sub-base as directed by the Engineer, to raise the
level of the road fixed by the Engineer or as per the road design to
the specific site. The material could be from a borrow pit or from
site but approved by the Engineer.
M2 -
Sub Total -
3. Cobblestone Paving
Laying
of Fine Crushed Aggregate Base Course
3.1 Supply, spread to level and compact 7 cm base course, fine crushed
aggregate from stone crusher site, keeping the design slope so as to
enable Cobblestone paving following the slope.
M2 -
Cobblestone Paving
3.2 Supply and lay to the required level 10x10x10 cm shaped
cobblestones made of hard rock as per the layout, design & slope
for the main body of the road and 15x10x10 cm shaped edge
cobblestones following the design pattern of the cobblestones road
pavement.
M2 -
Filling
Voids by Crushed Fine Aggregate and Finishing
3.3 Supply, fill and compact the 10mm spaces or voids between the
cobblestones with fine crushed aggregate to prevent the movement
of the stones due to traffic and make the pavement stiff. The surface
should be cleaned afterwards.
M2 -
Sub Total -
4. Curb stone
4.1 Provide 15cm wide and 30cm thick, C-25concrete curve stone
(price shall includes production, form works and all related
works).(Use mugher/Derba/Dangote OPC Cements only)
ml -
Sub Total -
5. Storm Water Drains
(a) Drainage Work -
M3
(b) Finshing work
Pointing the joint surface of the internal masonary part. M2 -
Copping on the top surface of the masonary wall upto 5cm to
smooth the surface of the masonary. ML -
(C) Pre Cast
M2 - -
Provide & place Ø14 c/c 20cm and Ø16 c/c 20cm steel
reinforcement bar for slab cover according to drawing. Price shall
includes cutting, bending & tying wires. (Use kality/Absynia Metal)
Kg - -
Sub Total -
Grand Total -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SETTING OUT LABOUR HOURLY OUTPUT: 0.007 km/hr.
WORK ITEM: ( 1.5) Trench excavation not exceeding 150cm.but on wet and black soil. EQUIPEMENT: Tool -335543.32
TOTAL QANTITY OF WORK ITEM: 1 m3 RESULT: - Birr/m3
** Indexed
Cost per Labour by Hourly Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Type of Equipment No. Rental Hourly Cost
red ash 20cm thick m2 0.2 0.00 0.00 Foreman 1 0.1 0.00 0.00 truk 2.00 0 0
D/L 2 1 0.00 0.00 greder 1 0 0
Site eng. 1 0.04 0 0.00 shawer truk 4 0 0
roller 1 0 0
0
0
0
0 0
0 0
Total (1:-01) 0.00 Total (1:02) 0.00 Total (1:03) -
A= Material unit cost 0 Birr/m3 B=Manpower Unit Cost 0 Birr/m3 C=Equipment Unit Cost 0 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Out 7.08/0.24 = 29.5 Hourly output: __________________
Direct Cost of work item = A + B + C = 0.00 Birr/m3
Overhead Cost : 15% 0.00 "
Profit Cost: 10% 0.00 "
Total Unit Cost : 0.00 Birr/m3
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
A= Material unit cos 0 Birr/m3 B=Manpower Unit Cost 0 Birr/m3 C=Equipment Unit Cost 0 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Out 7.08/0.24 = 29.5 Hourly output: __________________
Direct Cost of work item = A + B + C = 0.00 Birr/m3
Overhead Cost : 15% 0.00 "
Profit Cost: 10% 0.00 "
Total Unit Cost : 0.00 Birr/m3
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
** Indexed
Type of Cost per Labour by Hourly Hourly Hourly Hourly
Material Unit Qty * Rate Unit Grade No. UF Cost Cost Type of Equipment No. Rental Cost
cobble no 100 10.00 1000.00 Foreman 1 0.1 500.00 50.00 leveling instrument 1.00 100 100
paver 1 1 250.00 250.00 hammer 1 0 0
D/L 2 1 200.00 400.00 peg 4 0 0
sit eng 1 0.04 800 32.00 string 4 0 0
A= Material unit 1000 Birr/m2 B=Manpower Unit Cost 331.9728 Birr/m2 C=Equipment Unit Cost 45.351473923 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Out 7.08/0.24 = 29.5 Hourly output: __________________
Direct Cost of work item = A + B + C = 1377.32 Birr/m3
Overhead Cost : 15% 206.60 "
Profit Cost: 10% 137.73 "
Total Unit Cost : 1,721.66 Birr/m2
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: CONCRETE WORK LABOUR HOURLY OUTPUT: 19.61 ml/hr.
WORK ITEM: ( 3.5 C-25 Concrete (Mechanical Mix) 1:2:3 0.1 m thick EQUIPEMENT: Mixer & Vibrator
TOTAL QUANTITY OF WORK ITEM: 1.9 ml (Suspended slab,Stair case & landing) RESULT: 0.00 Birr/m2 0.00 Birr/m3
A= Materials Unit 0.00 Birr/m3 B=Manpower Unit Cost 0.00 Br./m3 C= Equipment Unit Cost : 0.00 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 0.00 Birr/m3
Overhead Cost: 15% 0.00 "
Profit Cost: 10% 0.00 "
Total Unit Cost : 0.00 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: POINTING WORKS LABOUR HOURLY OUTPUT: 15.13 m3/hr.
WORK ITEM50cm. thick masonry foundation (A.G.L). EQUIPEMENT:
TOTAL QANTITY OF 3 m3 RESULT 14.47 Birr/m3
A= Material 11.57217 Birr/m3 B=Manpower Unit Cost 0 Birr/m3 C=Equipment Unit Cost 0 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Outpu7.08/0.24 = 29.5 Hourly output: __________________
Direct Cost of work item = A + B + C = 11.57 Birr/m3
Overhead Cost : 15% 1.74 "
Profit Cost: 10% 1.16 "
Total Unit Cost : 14.47 Birr/m3
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Material 17.35825 Birr/m3 B=Manpower Unit Cost 0 Birr/m3 C=Equipment Unit Cost 0 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Outpu7.08/0.24 = 29.5 Hourly output: __________________
Direct Cost of work item = A + B + C = 17.36 Birr/m3
Overhead Cost : 15% 2.60 "
Profit Cost: 10% 1.74 "
Total Unit Cost : 21.70 Birr/m3
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
A= Material 0 Birr/m3 B=Manpower Unit Cost 0 Birr/m3 C=Equipment Unit Cost 0 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Out 7.08/0.24 = 29.5 Hourly output: __________________
Direct Cost of work item = A + B + C = 0.00 Birr/m3
Overhead Cost : 15% 0.00 "
Profit Cost: 10% 0.00 "
Total Unit Cost : 0.00 Birr/m3
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: CONCRETE WORK LABOUR HOURLY OUTPUT: 8.32 m2/hr.
WORK ITEM: ( 3.1 C-5
) Lean Concrete (Hand mix) 1:2:7 EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 m2 0.05 m. thick RESULT: 81.19 Birr/m2
0
0
oil 0.875 0 0
Total (1:-01) 0.88 Total (1:02) 0.00 Total (1:03) 0
A= Materials Unit 0.88 Birr/m3 B=Manpower Unit Cost 0.00 Br./m3 C= Equipment Unit Cost 0.00 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 0.88 Birr/m3
Overhead Cost: 15% 0.13 "
Profit Cost: 10% 0.09 "
Total Unit Cost : 1.09 Birr/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: 0.146 m3/hr.
WORK ITEM: ( 1.5) Trench excavation not exceeding 150cm.but on wet and black soil. EQUIPEMENT: Tool
TOTAL QANTITY OF WORK ITEM: 1 m3 RESULT: 80.00 Birr/m3
A= Materials Unit 0.88 Birr/m3 B=Manpower Unit Cost 0.00 Br./m3 C= Equipment Unit Cost 0.00 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 0.88 Birr/m3
Overhead Cost: 15% 0.13 "
Profit Cost: 10% 0.09 "
Total Unit Cost : 1.09 Birr/m3
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: CONCRETE WORK pricast dich cover 1.3m x50cm x15cm LABOUR HOURLY OUTPUT: 5.5795 pcs / hr.
WORK ITEM: ( 3.5 C-25 Concrete (Mechanical Mix) 1:2:3 (Concrete wall,Lift shaft,Elevated co EQUIPEMENT: Mixer & Vibrator
TOTAL QUANTITY OF WORK ITEM: 1 pcs RESULT: 0.00 Birr/m3
A= Materials Unit 0.00 Birr/m3 B=Manpower Unit Cost 0.00 Br./m3 C= Equipment Unit Cost : 0.00 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 0.00 Birr/m3
Overhead Cost: 15% 0.00 "
Profit Cost: 10% 0.00 "
Total Unit Cost : - Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: CONCRETE WORK pricast dich cover 1.3m x50cm x15cm LABOUR HOURLY OUTPUT: 1 m3 / hr.
WORK ITEM: ( 3.5 C-25 Concrete (Mechanical Mix) 1:2:3 (Concrete wall,Lift shaft,Elevated co EQUIPEMENT: Mixer & Vibrator
TOTAL QUANTITY OF WORK ITEM: 1 pcs RESULT: 1285.49 Birr/m3
A= Materials Unit 750.55 Birr/m3 B=Manpower Unit Cost 177.84 Br./m3 C= Equipment Unit Cost : 100.00 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 1028.40 Birr/m3
Overhead Cost: 15% 154.26 "
Profit Cost: 10% 102.84 "
Total Unit Cost : 1285.49 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 1411.00 Birr/m3 B=Manpower Unit Cost 32.50 Br./m3 C= Equipment Unit Cost : 63.75 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 1507.25 Birr/m3
Overhead Cost: 15% 226.09 "
Profit Cost: 10% 150.73 "
Total Unit Cost : 1884.06 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
A= Materials Unit 1342.64 Birr/m3 B=Manpower Unit Cost 28.48 Br./m3 C= Equipment Unit Cost : 12.80 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 1383.92 Birr/m3
Overhead Cost: 15% 207.59 "
Profit Cost: 5% 69.20 "
Total Unit Cost : 1660.70 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 1413.02 Birr/m3 B=Manpower Unit Cost 23.73 Br./m3 C= Equipment Unit Cost : 21.33 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 1458.09 Birr/m3
Overhead Cost: 15% 218.71 "
Profit Cost: 5% 72.90 "
Total Unit Cost : 1749.71 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Co 23.78 Birr/m2 B= Manpower Unit Cost 28.00 Birr/m2 C=Equipment Unit Cost 1.6 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _________________
Direct Cost of Work Item = A+B+C = 53.38 Birr/m2
Over head cost : 15% 8.01 Birr/m2
Profit Cost: 15% 8.01 Birr/m2
Total Unit Cost : 69.39 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Co 17.5 Birr/m2 B= Manpower Unit Cost 2.88 Birr/m2 C=Equipment Unit Cost 0.5 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _________________
Direct Cost of Work Item = A+B+C = 20.88 Birr/m2
Over head cost : 15% 3.13 Birr/m2
Profit Cost: 15% 3.13 Birr/m2
Total Unit Cost : 27.14 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 1348.27 Birr/m3 B=Manpower Unit Cost 165.21 Br./m3 C= Equipment Unit Cost : 58.67 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 1572.15 Birr/m3
Overhead Cost: 15% 235.82 "
Profit Cost: 15% 235.82 "
Total Unit Cost : 2043.80 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 1138.71 Birr/m3 B=Manpower Unit Cost 31.67 Br./m3 C= Equipment Unit Cost : 79.21 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 1249.59 Birr/m3
Overhead Cost: 15% 187.44 "
Profit Cost: 15% 187.44 "
Total Unit Cost : 1624.46 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 1348.27 Birr/m3 B=Manpower Unit Cost 163.08 Br./m3 C= Equipment Unit Cost : 158.42 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 1669.77 Birr/m3
Overhead Cost: 15% 250.47 "
Profit Cost: 15% 250.47 "
Total Unit Cost : 2170.70 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 1062.05 Birr/m3 B=Manpower Unit Cost 41.25 Br./m3 C= Equipment Unit Cost : 118.82 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 1222.12 Birr/m3
Overhead Cost: 15% 183.32 "
Profit Cost: 15% 183.32 "
Total Unit Cost : 1588.75 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 1354.42 Birr/m3 B=Manpower Unit Cost 94.21 Br./m3 C= Equipment Unit Cost : 137.33 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 1585.96 Birr/m3
Overhead Cost: 15% 237.89 "
Profit Cost: 15% 237.89 "
Total Unit Cost : 2061.75 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: CONCRETE WORK LABOUR HOURLY OUTPUT: 3.75 m2 / hr.
WORK ITEM: ( 3.5Ribbed slab EQUIPEMENT: Mixer & Vibrator
TOTAL QUANTITY OF WORK ITEM: 1 m2 RESULT: 346.67 Birr/m2
A= Materials Unit 254.95 Birr/m3 B=Manpower Unit Cost 11.72 Br./m3 C= Equipment Unit Cost : 0.00 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 266.67 Birr/m3
Overhead Cost: 15% 40.00 "
Profit Cost: 15% 40.00 "
Total Unit Cost : 346.67 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 3279.17 Birr/m3 B=Manpower Unit Cost 144.06 Br./m3 C= Equipment Unit Cost : 1030.00 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 4453.23 Birr/m3
Overhead Cost: 15% 667.98 "
Profit Cost: 15% 667.98 "
Total Unit Cost : 5789.20 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 72.69 Birr/m3 B=Manpower Unit Cost 14.41 Br./m3 C= Equipment Unit Cost : 103.00 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 190.10 Birr/m3
Overhead Cost: 15% 28.51 "
Profit Cost: 15% 28.51 "
Total Unit Cost : 247.12 Birr/ml
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit 129.44 Birr/m3 B=Manpower Unit Cost 14.41 Br./m3 C= Equipment Unit Cost : 103.00 Br./m3
Total of (1:02) 43.75 Total of (1:03) 46.85
Hourly Output 0.75 Hourly output: 0.75
Direct Cost of work item = A+B+C = 246.85 Birr/m3
Overhead Cost: 15% 37.03 "
Profit Cost: 15% 37.03 "
Total Unit Cost : 320.91 Birr/ml
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
Material Cost (1:01) Labour Cost (1:02) Equipment Cost (1:03)
S.n Type of Material unit Indexed Material Cost Remark Labour by Grade unit Indexed daily Cost Remark Type of Equipment unit Indexed Hourly Cost Remark
14