LIST OF BULK VESSEL ACTIVITIES No.

of Hours
LP Anchorage 24
LP POB & Manuever for Docking 2
Loading Activities
Single Product Loading
Hose Connection & Survey 2
Airblow pre-loading 1
Product Loading
Airblow post loading 1
Hose Disconnection & Survey 2
Two Product Loading
*Cargo Hold Cleaning (if switching from Premium to OPC) 6
*Cargo Hold Flushing internal in ship (if switching from Premium to OPC) 3
Loading Sequence for vessel with Two (2) cargo hold
1st Sequence OPC
Hose Connection & Survey (ship & shore) 2
Airblow pre-loading 1
Product Loading
Airblow post loading 1
Hose Disconnection & Survey (shore) 1
2nd Sequence T1P
Hose Connection (shore) 1
Airblow pre-loading 1
Product Loading
Airblow post loading 1
Hose Disconnection & Survey (shore) 1
3rd Sequence OPC
Hose Connection (shore) 1
Airblow going to T1P cargo hold 1
Flushing going to T1P cargo hold 0.5
Airblow going to T1P cargo hold 0.5
Divert to OPC cargo hold start Product Loading
Airblow post loading 1
Hose Disconnection & Survey (ship & shore) 2
Vessel Clearance PCG & CPA 2
LP POB undocking manuever 2
Intransit from LP to DP

DP Arrival Anchorage 24
DP Maneuver for Docking 2
DP Port Formalities (for foreign flag ship) 2
Discharging Activities
Single Product Discharging
Hose Connection & Survey (ship & shore) 2
Airblow pre-discharging 1
Product discharging
Airblow post discharging 1
Hose Disconnection & Survey (shore) 3
Two Product Discharging
Discharging Sequence for vessel with Two (2) cargo hold
1st Sequence OPC
Hose Connection & Survey (ship & shore) 3
Airblow pre-discharging 1
Product discharging at Silo 1
Airblow post discharging 1
Draft Survey (shore side) 1
2nd Sequence T1P
Transfer of pipe Blind at terminal side 2
Airblow pre-discharging 1
Product discharging at Silo 2
Airblow post discharging 1
Draft Survey (shore side) 1
3rd Sequence OPC
Draft Survey (shore side) 1
flushing OPC to Silo 2 0.5
Draft Survey (shore side) 1
Transfer of pipe Blind at terminal side 2
Airblow pre-discharging 1
Product discharging at silo 1
Airblow post discharging 1
Hose Disconnection & Survey (ship & shore side) 3
DP POB undocking manuever 2
Intransit from DP to LP
VESSEL PARTICULARS
Kota Padang Procida Vivara Valbella APO TERMINAL Distance (NM)
Speed 11 11 11 11 MANILA 432
Load Rate 500 250 250 250 BATANGAS 334
Capacity 8,000 7,000 7,000 8,000 ILOILO 183
BACOLOD 171
DAVAO 563
APO PORT CEBU Load Port
DISCHARGING RATE (MAX)
700
750
250
120
250
Load Port