Professional Documents
Culture Documents
Introduction BAUR Products VLF TD PD MWT IEEE 2018
Introduction BAUR Products VLF TD PD MWT IEEE 2018
Cable Testing
Why VLF testing
Standards and VLF waveforms
Cable Diagnostics
Dissipation Factor (tan δ) Diagnostics
Partial Discharge Diagnostic
Why combined tan δ and PD diagnostics are important ?
2
Overview Cable Testing Standards
for 6 -500kV cables
3
Actual IEEE standards for cable testing
4
Standards
IEEE 400 - 2012: what’s new?
0
~kV Charging
Remaining DC test voltage
space charge voltage
voltage
80
70
60
50
68%
40
30
20
22% 5% 4%
10
0
12 30
Time to Breakdown / min45 60
10
Standards
IEC 60060-3
IEC 60060-3
Space charging!
VLF testing
Test setup
14
BAUR VLF truesinus® testing generators
15
VLF Testing
Simple Withstand Test
Status: Widely accepted, Standards available, Easy applicable
1.5*Uo
Remaining
1.0*Uo lifetime?
1hour?
0.5*Uo 10years?
t [min]
5 10 15 20 25 30 35 …. …. 60
What is better than VLF testing?
Benefits of VLF Technology
VLF Diagnostics
17
VLF Diagnostics
Standards
IEEE 400.2 - 2013
tan delta
Integral insulation
condition
Diagnostics
non-destructive
PD
Localization of singular
source of discharges
VLF Diagnostics
Methods to assess the cable quality
IR
VLF IC
Source
δ
C
Insulation damage: Cable
• Water trees capacity
• Moist joints
• Aging U
• Partial discharges
21
VLF Diagnostics
What is the Dissipation Factor (tan δ) measurement?
electrical
tree
Outer semi-
conductor
Insulation
Water tree
inner Semi-
conductor
conductor
22
VLF Diagnostics
Example of the progression of a fault caused by a watertree and
the resultant electrical tree in insulation
23
VLF Diagnostics
1mm
1mm 500µm
1mm
25
VLF Diagnostics
Tan delta measurement sequence
1.0E-3
2.0E-3 Good
U
0.5*U0 1.0*U0 1.5*U0
1.0E-3
t SDTD 0.05 0.06 0.1 E-3
Δ0.25
U/Uo U/Uo
TD
0.5Uo 1.0Uo 1.5Uo 0.5Uo 1.0Uo 1.5Uo
TD
U/Uo U/Uo
PD activity
Water trees
TD(2xUo)>2,2
Absolute TD value:
Acc. To IEEE 400.2-2001 … up to 2Uo
TD(2xUo)<1,2 TD(2xUo)>1,2
same condition in all phases same TD graph TD graph: Cable in good condition, <1.2E-2 @ 2 Uo, IEEE
TD(2xUo)>2,2
TD(2xUo)<1,2 TD(2xUo)>1,2
31
VLF Diagnostics
Application tan δ measurement
Application TD measurement:
• Condition of aged cable lines – service life forecast
• Condition after Repairs or replacements of cable sections
• Regular inspection of cables lines
• “Fingerprints” of new cable lines
32
VLF Diagnostics
TD setup
I_Test + I_Earth
I_Earth
I_Test
33
VLF Diagnostics
tan delta
Integral insulation condition
Diagnostics
non-destructive
PD
Localization of singular source of
discharges
34
VLF Diagnostics
Methods to assess the cable quality
36
VLF Diagnostics
Why do partial discharges occur?
PDs are caused by high local electrical field strength due to defects within the
isolation material
37
VLF Diagnostics
Typical PD sources
Mounting failures in joints & terminations
carbon tracking
Carbon tracking
on the line
Carbon mark
VLF Diagnostics
Typical PD sources
Mounting failures in joints & terminations
39
VLF Diagnostics
PD measurement sequence
1. step: 0,5 Uo
2. step: 1,0 Uo
3. step: 1,5 Uo
40
VLF Diagnostics
PD evaluation criteria
41
VLF Diagnostics
Phase Resolved Partial Discharge (Pattern) - PRPD
Locally resolved phase resolution for more than one PD failure along a cable
42
VLF Diagnostics
Understand the characteristic of the PD source
Phase and locally resolved PD (PRPD) test
Phase-resolved
pattern 2-6 m for
fault position 4.7 m
Phase-resolved
pattern 92-97 m for
fault position 95 m
4.7 m 95 m
VLF Diagnostics
PD setup
44
Calibration of PD-level and length measurement
PD-level
45
Standards Reference for Monitored Withstand Test MWT
IEEE 400 - 2012
47
Monitored Withstand Test MWT - TD
Phase 2: MWT - Hold
U [kV]
2.0*U0 Continuous monitoring
of 3 criteria (MTD,
1.5*U0 0 – 10min:
Continuous Recommendation of SDTD, ΔTDt) against
1.0*U0 evaluation After 10 min: suitable test duration, based defined threshold values
of MTD, New criterion: on the evaluation of MTD,
SDTD ΔTDt SDTD, ΔTDt and the
0.5*U0 evaluation in the ramp-up
phase
t [min]
TD [] 5 10 15 20 25 30 Recommended
Calculation of ΔTDt test duration
3.0E-3
Measures required: 60min
5 10 15 20 25 30 t [min]
48
Cable Testing & Diagnostics – the modern way
- Combination of Methods
TD
PD
TD//PD
TD - MWT
PD - MWT
Full MWT
BAUR PD-TaD 60
Summary
Information Benefits
content
VLF 3*Uo VLF
• Voltage stress test – very
Testing t simple!
TD
2*Uo • Measurement of dielectric losses (TD)
TD • Indication of water trees and PD
t
2*Uo PD
• Location of insulation defects
PD
t
• TD & PD
TD &PD
2*Uo • Better identification of masked
TD//PD insulation defects (!)
t • Reduced measuring time (parallel)
VLF&TD
2*Uo • TD
TD -
• Reduced test time (for good cables)
MWT t
VLF&PD • PD
PD - 2*Uo
• Reduced test time (for good cables)
MWT t
• TD & PD
VLF&
Full - 2*Uo TD & • Better identification of masked
PD
insulation defects (!)
MWT t • Reduced test time (for good cables)
• Parallel measurement
BAUR PD-TaD 62
Application – Parallel TD/PD or Full MWT
Full MWT
Standards - Reference for Monitored Withstand Test MWT
IEC 60502-2014
53
VLF Diagnostics – Measurement examples
PD localisation results
XLPE cable
54
VLF Diagnostics – Measurement examples
Application example:
PD failure in joint
Spain
PILC 20kV
Age approx. 25 years
June 2006
58
VLF Diagnostics – Measurement examples
59
Example of Full MWT – TD / PD
Example of XLPE cable with joint with water ingress
Visible PD
Ref.12752
Case Study # 1 …1
Cable details:
11kV, 3core XLPE 32
heat shrink joints cable
length 3099m
TD Result 17.10.2011
Case Study # 1 …2
TD analysis of L2
Clear indication of
▼ 0.45 ▼ 0.75 ▼ 1.32
Water Ingress in at least
one of the Joints!
+5m
67
PD diagnostics – PD pin-pointing
Confirmation of pre-located PD location with Tracy
Pinpointing of joints with water ingress
Step voltage with AC
frida TD PD TaD62
viola TD
PHG TD / PD
71
viola TD
72
PD TaD 62
PD TaD 62
up to 44 kVrms
in combination with frida / viola
parallel measurement of TD / PD
In combination with
frida TD
viola TD
73
Cost Saving by part exchange of a cable
line, Germany
Cable was scheduled for exchange because of Kastellaun
frequent failures ! KEM Priess
Kastellaun
St. Priess
Topografie
Kastellaun
KEM Priess
618 m of a total of 1945m were exchanged!
328m
Comparison of costs:
partial change:
618m x € 100,- + accessories € 66.135,-
--------------------