Excavation of 1000 m3 TIME COST Feasibility Analysis For Internal Purposes
Excavation of 1000 m3 TIME COST Feasibility Analysis For Internal Purposes
Excavation of 1000 m3 TIME COST Feasibility Analysis For Internal Purposes
ACTIVITY COM-14
ESTIMATED WORK 250.00
UNIT M3
CUMILATIVE BUDGET LINE
QTY QTY rate amount
LABOUR MANPOWER 01:18:30:00 16,150.00 36,337.50
MACHINE
6013 TRACTOR LOADER1.5M3CAT953 00:11:48:00 4,500.00 53,100.00
6032 LOADER ATTACHMENTMULTI SHANK RIPPERD8 00:11:48:00 1,500.00 17,700.00
F6013 FUELTRACTOR LOADER1.5M3CAT953 224.20 130.00 29,146.00
6061 PERCUSSION BREAKER ATTACHMENT310KGBRH125 00:12:00:00 10,500.00 3,150.00
6089 EXCAVATOR HYDRAULIC BACKACTER CRAWLER0.40M311.50 TONNE 01:18:30:00 2,922.85 124,221.07
F6089 FUEL EXCAVATOR HYDRAULIC BACKACTER CRAWLER0.40M311.50 TONNE 291.25 130.00 37,862.50
0
-
dd,hh,min,sec 301,517.07
Total estimated time required to complete the 250 m3 up to 3m deep of General Excavation using
SUM above machines 01:18:30:00 42 hr 8.40 Working Days
NOTE:
Reference Spons Civil Engineering Price book for general excavaton
EXCAVATION COTROL - Filling Up to 3m Deep for 250 m3 are as follows.
ACTIVITY COM-14-1
ESTIMATED WORK 250
UNIT M3
MACHINE
6013 TRACTOR LOADER1.5M3CAT953 00:13:15:00 4,500.00 59,625.00
F6013 FUELTRACTOR LOADER1.5M3CAT953 251.75 130.00 32,727.50
6144 MACHINE3 WHEEL DEAD WAIGHT ROLLER10 TONNEHAMM HW902020MM WIDTH 00:08:45:00 3,691.06 32,296.80
F6144 FUEL 3 WHEEL DEAD WAIGHT ROLLER10 TONNEHAMM HW90 140.00 130.00 18,200.00
-
FILL IMPORIMPORTED
17 SUITABLE FILLING 487.96 290.28 121,990.17
dd,hh,min,sec 272,439.47
Total estimated time required to complete the 250 m3 up to 3m deep of General Excavation using
SUM above machines 01:17:00:00 41hr 8.20 Working Days
NOTE:
Reference Spons Civil Engineering Price book for general filling
EXCAVATION COTROL - Excavate 250 meters up to 3 to 6 meter deep Using Tractor Loader 1.5 m3 CAT
953 with ripper teeth. And Exavator Hydraulic Backacter Crawler Mounted with 310 KG BRH 125
Breaker with 2.5 Man Hours per hour per line.
General excavation using backacters and tractor loadersExcavation of unacceptable material Class U1 / U2 in structural foundationsne 6.0 m deep
PREVIOUS MONTH THIS MONTH
month Friday, January 7, 2022
Jan/22
ACTIVITY COM-15
ESTIMATED WORK 250
UNIT M3
MACHINE
6013 TRACTOR LOADER1.5M3CAT953 00:22:12:00 4,500.00 99,900.00
6032 LOADER ATTACHMENTMULTI SHANK RIPPERD8 00:22:12:00 1,500.00 33,300.00
F6013 FUELTRACTOR LOADER1.5M3CAT953 421.80 130.00 54,834.00
6061 PERCUSSION BREAKER ATTACHMENT310KGBRH125 00:22:00:00 10,500.00 5,775.00
6089 EXCAVATOR HYDRAULIC BACKACTER CRAWLER0.40M311.50 TONNE 03:08:00:00 2,922.85 233,827.90
F6089 FUELEXCAVATOR HYDRAULIC BACKACTER CRAWLER0.40M311.50 TONNE 140.00 130.00 18,200.00
0
-
dd,hh,min,sec 514,236.90
Total estimated time required to complete the 250 m3 up to 3m deep of General Excavation using
SUM above machines 03:08:00:00 80hr 16.00 Working Days
NOTE:
Reference Spons Civil Engineering Price book for general excavaton
EXCAVATION COTROL - Filling Up to 3m Deep for 250 m3 are as follows.
ACTIVITY COM-15-1
ESTIMATED WORK 250
UNIT M3
CUMILATIVE BUDGET LINE
QTY QTY rate amount
LABOUR MANPOWER 01:17:00:00 1,900.00 7,600.00
MACHINE
6013 TRACTOR LOADER1.5M3CAT953 00:13:15:00 4,500.00 59,625.00
F6013 FUELTRACTOR LOADER1.5M3CAT953 251.75 130.00 32,727.50
6144 MACHINE3 WHEEL DEAD WAIGHT ROLLER10 TONNEHAMM HW902020MM WIDTH 00:08:45:00 3,691.06 32,296.80
F6144 FUEL3 WHEEL DEAD WAIGHT ROLLER10 TONNEHAMM HW90 140.00 130.00 18,200.00
-
FILL IMPORIMPORTED
17 SUITABLE FILLING 487.96 290.28 121,990.17
dd,hh,min,sec 272,439.47
Total estimated time required to complete the 250 m3 up to 3m deep of General Excavation using
SUM above machines 01:17:00:00 41 hr 10.20 Working Days