In order to facilitate management of suppliers and contractors doing business with the
communities, the Program shall establish procedures for evaluating, documenting, and
reporting the supplier/contractor’s performance under a contract for purchase of goods,
performance of services, consulting, construction or improvement of facilities. These
procedures shall include a process for performance appraisal, communication of
feedback to vendors, forms and documentation requirements.
Purposes
1. Quality
2. Delivery
3. Compliance to Environmental Laws
4. Technical Support
5. Management Attitude
The Rating
Blacklisting
The purpose of blacklisting is to protect the project from risks associated with awarding
contracts to persons or firms having exhibited an inability or unwillingness to fulfill
contractual obligations, and to protect the project’s interests and the integrity of the
procurement process by preventing individuals or firms who have displayed improper
conduct from participating on project requirements for specific periods of time.
Sanction/s
Discussion
The evaluation procedures must be discussed with the suppliers and or contractors during
contractors’ conference/meeting or pre-bidding conferences.
Annex 1: For Goods
Name of Sub-project:____________________________________
Contract Package No.: ___________________
Method of Procurement Used: _______ Shopping ______ (Bidding)
Assigned Points:
Very
Satisfactory (S) Unsatisfactory %
Criteria Satisfactory
(US) Rating
(VS)
A. QUALITY (40%)
Conformance to the Quality of Quality of all the Quality of some
Technical Specifications as materials materials or all of the
indicated in the exceeded the complied with materials did not
Contract/Purchase Order minimum the minimum complied with
requirement of requirement of the minimum
the PO the PO requirement of
the PO
40%=VS
20%=S
Unsatisfactory:
15%= if less than 25% of the materials (in terms
of amount) did not comply with the
requirement and were replaced prior to
deadline of delivery
10%= if less than 50% of the materials (in terms
of amount) did not comply with the
requirement and were replaced prior to
deadline of delivery
5%= if more than 50% of the materials (in terms
of amount) did not comply with the
requirement and were replaced prior to
deadline of delivery
0%= if more than 50% of the materials (in terms
of amount) did not comply with the
requirement and/or any one or more of the ____%
Very
Satisfactory (S) Unsatisfactory %
Criteria Satisfactory
(US) Rating
(VS)
defective material/s was/were NOT
replaced prior to deadline of delivery
B. Delivery (30%)
Period of Delivery All items were All items were Delayed full
delivered and delivered on the delivery by
accepted prior or agreed deadline One (1) CD up
ahead of the to seven (7) CD
agreed deadline from the agreed
deadline
30% = VS
15%=S
10%=US
5%=delayed 8CD or more
0%=Terminated due to the default of the
Supplier ____%
C. Compliance to Environmental
Laws (10%)
Methods of delivery Compliant to the Partially Violations were
provision of the compliant to the identified
approved ESMP approved ESMP
10%=VS
5%=S
0%=US ____%
D. Technical Support (10%)
Provision of technical Provides Satisfactory No technical
support/Responsiveness assistance even complies within assistance
without the agreed provided or
Notice/Request timeline failed to comply
from the BSPMC with the
request/s
10%=VS
5%=S
0%=US ____%
E. Contractor/Supplier Yes No
Management Attitude (10%)
Treated the community
volunteers and KC-NCDDP
staff with due courtesy and
respect;
Faithfully complied with all
the requirement of the
Contract;
Satisfactory acted all the
complaint forwarded within
the prescribed period;
The contract was executed
and completed by the
registered owner;
10%= 4 (Yes)
8%= 3 (Yes) & 1 (No)
5% =2 (Yes) & 2 (No)
3%= 1 (Yes) & 3 (No)
0% = 4 (No)
___ %
TOTAL: ___%
Categorical Rating:
Rated by:
Approved by:
Noted by:
Name of Sub-project:____________________________________
Contract Package No.: ___________________
Method of Procurement Used: _______ Shopping ______ (Bidding)
Assigned Points:
Very
Satisfactory (S) Unsatisfactory %
Criteria Satisfactory
(US) Rating
(VS)
A. QUALITY (40%)
Undertaking according to
prescribed plans and
specifications:
a. Materials and workmanship Quality of Quality of all the Quality of some
employed are according to materials materials or all of the
the contract specifications exceeded the complied with materials did not
minimum the the minimum complied with
requirement of requirement of the minimum
the contract the contract requirement
b. No punch list during contract No items in With item/s in All or any one of
implementation period the punch list the punch list the item/s in the
but was/were Punch list
rectified within was/were NOT
the agreed rectified within
duration the agreed
duration
c. Subproject condition during No defect With minor With minor or
the Defect & Liabilities period occurred defect/s but major defects
were rectified that were not
within the rectified within
agreed period
Very
Satisfactory (S) Unsatisfactory %
Criteria Satisfactory
(US) Rating
(VS)
the agreed
period
Submission of the required Complete Complete Delayed or
Quality Assurance test results submission submission on incomplete
ahead of time time submission
40%= 4 (VS)
35% = 3(VS) & 1(S)
30% =2(VS) & 2(S)
25%= 1(VS) & 3(S)
20%= 4(S)
Rated by:
Approved by:
Noted by:
SIGNATURE OVER PRINTED NAME
ACT Technical Facilitator