1. Which of the following must be considered while conducting a road survey?


a) Density
b) Alignment of the curves
c) Specific gravity
d) Atmospheric conidtion
Answer: b
Clarification: Road survey is conducted for having a better output with the right alignment of the curves. The placement of
the curve must be noticed while determining the alignment. Consideration of slopes is an important task while handling road
survey.

2. Skid resistance is calculated while conducting road survey.


a) True
b) False
Answer: a
Clarification: The determination of skid resistance is must be done while conducting a road survey because this determines
the efficiency of the road. The application of skid resistance can be calculated by the amount of super elevation provided.

3. Which of the following indicates the objective of road survey?


a) Specific gravity
b) Density
c) Pavement design
d) Detailed layout of road way
Answer: d
Clarification: The main objective of road survey is to have detailed layout of road way, observation of potholes, speed
breakers and determination of loss of effective width at different locations.

4. Density of the road is not taken into consideration.


a) True
b) False
Answer: b
Clarification: The determination of density of road plays a major role in the lifespan of the road. If the density is more the
average life span of the road will increase and vice-versa. The decrease in density is due to the formation of pot holes.

5. Which of the following will come under the manual method of road survey?
a) GIS
b) Walking and windshield survey
c) Walking survey
d) Windshield survey
Answer: c
Clarification: Road survey can be done either in manual method or by an automatic method. The manual methodology
includes walking survey, windshield survey and the combination of both.

6. Which of the following software’s can be useful while conducting road survey?
a) GIS
b) RS
c) STAAD Pro
d) Revit
Answer: a
Clarification: Among the following, GIS can be used in the process of Road survey. It is having the properties of the
classification methods which can be accessed to have a better result.

7. Which of the following road survey method is a time consuming method?


a) Walking and windshield survey
b) Walking survey
c) Windshield survey
d) GIS
Answer: b
Clarification: Among all the methods available, the walking survey is a tedious procedure and involves walking on the
pavement for taking observations. Even though it is a lengthy procedure, it is proven as the best method for an accurate
result.

8. Which of the following procedure involves both technological and human interpretation?
a) GIS
b) Windshield survey
c) Walking survey
d) Walking and windshield survey
Answer: d
Clarification: Manual method is sometimes elected as the best method based on the conditions and the output obtained. In
the manual methods available, a combination of walking and windshield survey involves usage of both technological and
human activities.

9. Among the interpretation methods available, which is opted as the best?


a) STAAD Pro
b) RS
c) GIS
d) Walking survey
Answer: c
Clarification: Road survey can be done either manually or by machine. Both are capable of giving the best results. But in
terms of time, the automatic methods are chosen. Among them, GIS method is the best as the interpretation is easy and
accurate.

10. Which of the following is included in the road project survey report?
a) Location
b) Terrain
c) Slope
d) Gradient
Answer: a
Clarification: After completion of the road survey, a report has to be submitted to clarify certain things regarding the
selection of alignment. It includes observation details, justification, location, time and date, duration etc.

---- >> Below Are The Related Posts Of Above Questions :::

------>>[MOST IMPORTANT]<<------

1. 250+ TOP MCQs on Railway Project Survey and Answers


2. 250+ TOP MCQs on Hydrographic Survey – Marine Survey and Answers
3. 250+ TOP MCQs on Project Survey – Tunnelling and Answers
4. 250+ TOP MCQs on Project Survey – Docks, Harbours and Port and Answers
5. 250+ TOP MCQs on Project Survey – Sanitary Scheme and Answers
6. 250+ TOP MCQs on Project Survey – Water Supply Scheme and Answers
7. 250+ TOP MCQs on Airport Survey and Answers Online Quiz
8. 250+ TOP MCQs on Topographic Survey and Answers
9. 250+ TOP MCQs on Reconnaissance Survey and Answers
10. 250+ TOP MCQs on Final Location Survey and Answers
11. 250+ TOP MCQs on Introduction – Survey Stations Selection and Answers
12. 250+ TOP MCQs on Preliminary Survey and Answers
13. 250+ TOP MCQs on Traffic Survey and Answers
14. 250+ TOP MCQs on Hydrographic Survey – Introduction and Answers
15. 250+ TOP MCQs on Road-side Development and Arboriculture and Answers
16. What is the purpose of the gap in the road on this bridge?
17. 250+ TOP MCQs on Highway Planning, Classification of Road and Road Patterns and Answers
18. 250+ TOP MCQs on Introduction – Chain Survey Equipments and Answers
19. The sequence of four stages of survey in a highway alignment is | HIGHWAY ENGINEERING
20. 250+ TOP MCQs on Flow Irrigation Survey and Answers

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Comment *

Name *

Email *

Website

Post Comment

Engineering 2023 , FAQs Interview Questions , Theme by Engineering|| Privacy Policy|| Terms and Conditions|| ABOUT US|| Contact US||
Engineering interview questions,Mcqs,Objective Questions,Class Lecture Notes,Seminor topics,Lab Viva Pdf PPT Doc Book free download. Most Asked Technical Basic CIVIL |
Mechanical | CSE | EEE | ECE | IT | Chemical | Medical MBBS Jobs Online Quiz Tests for Freshers Experienced .

You might also like