PSSR Checksheet - Offshore Asset - Draft
PSSR Checksheet - Offshore Asset - Draft
Status
HSE
PSSR Query Expectation client operator By when Response Notes / Future Actions Evidences (Links)
Element Yes No N/A % Complete
CONTENTS
Have all HAZID and safety study actions which are required to be completed before + HAZID actions identified as 'to be closed prior to start-up' must be closed to To ensure all actions in the Copy of HAZOP
4 No Close out report to be verify
start-up been closed (and accepted by Operations)? the satisfaction of Operations close out report is close. close out report.
EIA report is
Have environmental risks been identified for the start-up activities (i.e. increased EIA report is available. The EIA approval EIA report is available. The EIA available. The EIA
1 Yes
venting and flaring, spill potential) and are risks being mitigated? condition is available. approval condition is available. approval condition
is available.
Open 1 of 6
[Jitang: FPSO MTC Ledang & WHP] - Pre-Start-up Safety Review Checklist
Status
HSE
PSSR Query Expectation client operator By when Response Notes / Future Actions Evidences (Links)
Element Yes No N/A % Complete
EIA report is
Has the Environmental Aspects and Impacts Register on site been updated to reflect EIA report is available. The EIA approval EIA report is available. The EIA available. The EIA
2 Yes
the new facilities being introduced? condition is available. approval condition is available. approval condition
is available.
Are there any concerns about flaring and have local residents been made aware of
3 N/A
additional flaring?
Have site security personnel been made aware of the content of the Site Security Plan To get the approval for both Approved MFSP &
2 Yes MFSO is aware of the security plan.
and their individual responsibilities in situations which pose a threat to security? documents MFSA
Has the plan been tested to ensure site security personnel as well as others (staff, The drill, requiremernt as per security plan to To execute as per MFSP & Evidence of
3 No
contractors and visitors) are aware of the actions necessary in security situations? be tested prior RFSU. MFSA implementation.
Have suitable provisions been made in the Site Security Plan for the management of To get the approval for both Approved MFSP &
4 Yes MFSO is aware of the security plan.
contractors? documents MFSA
Are there any special PPE requirements to resolve prior to operating? (Consider + The requirement for specialist PPE should be determined via risk assessment.
2 N/A
working environment and seasonal issues) Personnel will require training in the use of this equipment
Have personnel been issued with PPE in accordance with site policy / PPE Matrix and is + Supply contracts and storage of appropriate quanties of PPE onsite to be
3 sufficient specialist PPE available for personnel involved with the start-up of the new established commensurate with the hazards presented during start-up Yes As per EPOMS PPE Guideline.
facility? operations
Have any / all community awareness & outreach issues been resolved or
4 No To notify adjacent field - TBK & BRT
communicated relative to starting up new the facilities?
Is there a comprehensive list of all the applicable laws and regulations applicable for VPSB Legal Register is available. To review To provide updated Legal Copy of Legal
5 Yes
the Development? compliance compatibility with Jitang. register for offshore operations Register
Have the requirements outlined in the VPSB E&P Guidance for the management of
Operability Assurance Programs been identified for the Development? What is the
progress? During ORA weekly meeting and Jitang ORA
6 Yes
- Operability Plan workshop
- Operations Readiness Plan
- Closure of shortfall issues
Open 2 of 6
[Jitang: FPSO MTC Ledang & WHP] - Pre-Start-up Safety Review Checklist
Status
HSE
PSSR Query Expectation client operator By when Response Notes / Future Actions Evidences (Links)
Element Yes No N/A % Complete
Has the major equipment involved been designed, constructed and installed in Compliance is as per OSRMS requirement - Copy of certificates
7 Yes To conduct pest stump
accordance with the design specifications, codes and/or standards specified? certificates and other documents and documents
Copy of approved
Have existing Safety Procedures been verified and applicable and adequate? List To finalise and make available
8 No Review in progress safety procedures
deficiencies noted and/or additional requirements if any. the document
i.e. Site Specific ErP
Copy of approved
Have existing Maintenance Procedures been verified and applicable and adequate? To finalise and make available
9 No Review in progress maintenance
List deficiencies noted and/or additional requirements if any. the document
procedures
4 IMPROVEMENT
N/A for Start-Up
7 DESIGN, OPERATIONS AND MAINTENANCE
A Safe Systems of Work Yes No N/A % Complete
+ The PTW Procedure is the principal method through which work activities on
site are controlled
+ The PTW should determine include clear roles and responsibilities for the
preparation, risk assessment, review, issue, performance, and closure of tasks
1 Has a Permit to Work Procedure been established to manage work activities on site? on site
+ The PTW Procedure should determine different work practices for the
management of hot work activities versus cold work activities
+ The PTW Procedure should provide specific guidance for the management of
work involving isolations, confined space entry, work with excavations
2 Has PTW training been provided to personnel in accordance with a defined program?
Has a Lock Out/Tag Out system been established on site and are appropriate
3
Boards/Lock-out boxes available?
4 Has a Blind Register been prepared (record of blinds installed)?
5 Has a Long Term Isolation Register been established?
+ Isolation Certification
+ Electrical High Voltage Permit
6 Are there other Registers developed?
+ Permit Register
+ Confined Space Register
B Site Safety / Housekeeping Yes No N/A % Complete
Have all leftover materials such as scaffolds, tools, nuts, bolts, gaskets, pipe,
1
instruments, etc., been removed from the job site?
2 Has the areas been cleared of litter such as bottles, cans, other trash, etc.?
3 Have adequate steps been taken in avoid slipping and/or stumbling hazards?
4 Have sewer gratings been properly fitted in catch basins and trenches?
5 Is drainage adequate in all areas?
6 Have all gas cylinders either been removed or properly stored if left on-site?
+ A means to ensure that all holes / access manways etc are appropriately
covered (to prevent slip, trip and fall hazards) should be established prior to
Have all open holes in the area been covered by appropriate means to avoid starting up new plant
7
inadvertent injury of personnel? + This activity should be ongoing throughout the construction phase and a
final check of the work site should conducted immediately (1-2 days) prior to
starting the plant to ensure hazards such as these have been eliminated
C Waste Management Yes No N/A % Complete
Has piping been adequately protected for external corrosion (cathodic protection,
1
wrapped, etc.)?
Open 3 of 6
[Jitang: FPSO MTC Ledang & WHP] - Pre-Start-up Safety Review Checklist
Status
HSE
PSSR Query Expectation client operator By when Response Notes / Future Actions Evidences (Links)
Element Yes No N/A % Complete
11 Are small piping connections in process service seal welded to the first block valve
3 Can the valve be readily reached without scaffolding for checking of tags and seals?
Can the valve be readily lowered to grade safely with either portable or permanent
4
rigging equipment?
5 Does the inlet line appear adequate to avoid restricting flow to the safety valve?
6 Is the suction or discharge piping of safety valves free of trapped sections?
Is safety valve inlet and outlet piping properly supported to avoid undue stresses on
7
the safety valve?
8 Are block valves oriented to prevent gates from dropping in the line?
9 Have drain and vent valves been installed to depressure for safety valve removal?
10 Do safety valve stacks have drains to remove water or liquid accumulation?
Are bellows safety valve vents piped to a location where the vent does not impinge on
11
flange, bolting, or pipeline?
Are all bleeders and small connections on line to and from PSV’s seal welded (if
12
required)?
13 Do all safety valves have maintenance access?
14 Are car seals in place on inlet and outlet valves for safety valves?
G Blowdown, Flare and Pumpout Systems Yes No N/A % Complete PUNCH LIST ITEMS
1 Are headers free of trapped sections?
2 Are all valves car sealed open as necessary?
Have block valves in pressure relieving systems been installed with stems in horizontal
3
position to guard against dropping gate into line?
4 Has pumpout been designed for emergency, as well as routine shutdown conditions?
H Machinery - Pumps, Compressors etc. Yes No N/A % Complete PUNCH LIST ITEMS
1 Are small piping connections in process service seal welded and gusseted?
Is piping adequately supported so equipment can be removed for maintenance
2
without undue piping stresses being developed?
3 Have coupling guards been provided and are they sufficient for personnel protection?
3 Are local switch handles equipped with proper identification and on-off markings?
Open 4 of 6
[Jitang: FPSO MTC Ledang & WHP] - Pre-Start-up Safety Review Checklist
Status
HSE
PSSR Query Expectation client operator By when Response Notes / Future Actions Evidences (Links)
Element Yes No N/A % Complete
8 Is permanent equipment hooked up with proper electrical cable rather than cords?
3 Have fire wall drain valves been provided along with safe access to the drain valve?
Open 5 of 6
[Jitang: FPSO MTC Ledang & WHP] - Pre-Start-up Safety Review Checklist
Status
HSE
PSSR Query Expectation client operator By when Response Notes / Future Actions Evidences (Links)
Element Yes No N/A % Complete
6 Has a simplified sewer map been provided for use by operating personnel?
O Tools / Parts / Materials Required for Start-Up Yes No N/A % Complete
Has an assessment been made to ensure there are adequate materials available for
1
Commissioning and Start-Up?
2 Has a Tool Inventory been established which includes issue and receipt status?
3 Are diesel stocks adequate?
4 Are lubricant stocks adequate?
5 Are coolant stocks adequate?
6 Are chemical stocks adequate?
P Construction Yes No N/A % Complete
Review how the project has ensured that design standards and specifications were
followed and adhered to throughout the design and construction phases. Have any
1
deviation from recognized design standards been reviewed by the appropriate subject
matter experts?
Have any changes been made since the risk studies were completed that could
2 material affect safety of people, the environment or facilities. How have changes been
reviewed and included in the project? Has it been reviewed by Operations?
Review the construction QA/QC process and materials inspection program. Spot check
3 a few critical components to determine if the QA/QC program functioned as planned.
Verify any QA/QC mishaps have been corrected.
Open 6 of 6