Client:  Petroleum Developement Oman


MARMUL CONTRACTING & TRADING COMPANY LLC.
Mobilization Plan for Earthworks PDO North Oman -
24-May-14

Qarnalam
Activity ID Activity Name
Original Planned Planned
Month

Duration Start Finish


8

1 2 3 4
5 6 7
Mobilization Plan for Earthworks PDO North Oman - Qarnalam
173d 15-Dec-14 05-Jun-15
05-Jun-15, Mobilization Plan for Earthworks

Mobilization of Contract Key & Core Personnel


18d 15-Dec-14 01-Jan-15 01-Jan-15, Mobilization of
Contract Key & Core Personnel
A1000 Notification for Key & Core Personnel
1d 15-Dec-14 15-Dec-14 Notification for Key & Core Personnel
A1010 HSE Tr aining for All Personnel
14d 16-Dec-14 29-Dec-14 HSE Tr aining for All Personnel
A1020 Mobilization of HSE Trained Per sonnel
14d 19-Dec-14 01-Jan-15 Mobilization of HSE Trained Per
sonnel
A1030 PDO Assessment for Key & Core Personnel (If Required)
7d 26-Dec-14 01-Jan-15 PDO Assessment for Key & Core
Personnel (If Required)
PDO Approval for Industrial & Residential Facilities
23d 02-Jan-15 24-Jan-15 24-Jan-15,
PDO Approval for Industrial & Residential Facilities
A1040 Internal Inspection for Existing Industrial & Residential
Facilities 4d 02-Jan-15 05-Jan-15 Internal
Inspection for Existing Industrial & Residential Facilities
A1050 Renting / Leasing the Industrial & Residential Facilities
2d 06-Jan-15 07-Jan-15 Renting / Leasing the
Industrial & Residential Facilities
A1060 Renovation of the Rented Leased Facilities
7d 08-Jan-15 14-Jan-15 Renovation of the
Rented Leased Facilities
A1070 Arranging Water, Electricity & Waste Management from PDO
7d 15-Jan-15 21-Jan-15 Arranging
Water, Electricity & Waste Management from PDO
A1080 PDO Inspection for the Renovated Facilities
2d 22-Jan-15 23-Jan-15 PDO
Inspection for the Renovated Facilities
A1090 PDO Approval for the Inspected Facilities
1d 24-Jan-15 24-Jan-15 PDO Approval
for the Inspected Facilities
Contract HSE & Quality Plans
8d 02-Jan-15 09-Jan-15 09-Jan-15, Contract HSE &
Quality Plans
A1100 Submission of Contract HSE Plan
1d 02-Jan-15 02-Jan-15 Submission of Contract HSE Plan
A1110 Submission of Contract Quality Plan
1d 02-Jan-15 02-Jan-15 Submission of Contract Quality
Plan
A1120 PDO Review of Submitted Plans
6d 03-Jan-15 08-Jan-15 PDO Review of Submitted
Plans
A1130 Getting PDO Approval for the Reviewed Plans
1d 09-Jan-15 09-Jan-15 Getting PDO Approval for
the Reviewed Plans
Mobilization of Vehicle, Plant & Equipments
133d 16-Dec-14 27-Apr-15
27-Apr-15, Mobilization of Vehicle, Plant & Equipments
A1140 Procurement/ Hiring of Vehicle, Plant & Equipments
120d 16-Dec-14 14-Apr-15
Procurement/ Hiring of Vehicle, Plant & Equipments
A1150 Fixing PDO Specifications
120d 16-Dec-14 14-Apr-15
Fixing PDO Specifications
A1160 Internal Inspection for the Vehicle, Plant & Equipments
120d 21-Dec-14 19-Apr-15
Internal Inspection for the Vehicle, Plant & Equipments
A1170 Mobilization of Inspected EVPs
120d 23-Dec-14 21-Apr-15
Mobilization of Inspected EVPs
A1180 PDO Inspection for the Vehicle, Plants & Equipments
120d 27-Dec-14 25-Apr-15
PDO Inspection for the Vehicle, Plants & Equipments
A1290 Getting PDO Approval for Inspected EVSs
120d 29-Dec-14 27-Apr-15
Getting PDO Approval for Inspected EVSs
A1300 Dispatch to Site Locations
120d 29-Dec-14 27-Apr-15
Dispatch to Site Locations
Mobilization of Construction Crews
172d 16-Dec-14 05-Jun-15
05-Jun-15, Mobilization of Construction Crew
Assigning Construction Crews
120d 16-Dec-14 14-Apr-15
14-Apr-15, Assigning Construction Crews
A1190 HSE Tr aining for the Constr uction Crews
120d 16-Dec-14 14-Apr-15
HSE Tr aining for the Constr uction Crews
A1200 Recruting / Hiring PDO Approved Permit Holders & Applicants
15d 31-Dec-14 14-Jan-15 Recruting / Hiring
PDO Approved Permit Holders & Applicants
A1210 Assigning Crews for Individual Location / Activities
120d 16-Dec-14 14-Apr-15
Assigning Crews for Individual Location / Activities
Dispatching Construction Crews
162d 26-Dec-14 05-Jun-15
05-Jun-15, Dispatching Construction Crews
A1230 Earth Work Crews for Qarnalam Field
7d 26-Dec-14 01-Jan-15 Earth Work Crews for Qarnalam
Field
A1240 Structure Work Crews for Qarnalam Field
7d 02-Jan-15 08-Jan-15 Structure Work Crews for
Qarnalam Field
A1250 Earth Work Crews for Musallam Field
7d 04-Feb-15 10-Feb-15
Earth Work Crews for Musallam Field
A1260 Structure Work Crews for Musallam Field
7d 11-Feb-15 17-Feb-15
Structure Work Crews for Musallam Field
A1270 Road Work Crew for the Contract
7d 30-May-15 05-Jun-15
Road Work Crew for the Contract
A1280 Civil Crew for Concrete Precast Yard
7d 15-Jan-15 21-Jan-15 Civil Crew for
Concrete Precast Yard
Engineering & Construction
7d 26-Dec-14 02-Jan-15 02-Jan-15, Engineering &
Construction
A1310 Start of Engineering Activities
0d 26-Dec-14 Start of Engineering Activities, 26-
Dec-14
A1320 Start of Construction Activities
0d 02-Jan-15 Start of Construction
Activities, 02-Jan-15

Page 1 of 1 TASK filter: All


Activities
Actual Level of Effort Remaining Work
Milestone
Actual Work Critical Remaining Work
summary