Sal de Vida Lithium Brine Project

Package 1 Procurement & Constrution Schedule


(Critical Path)
Activity ID Activity Name Remaining Start Finish Indicators2021 2022 2023
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

Galaxy Sal de Vida Package 1 EPC Act Aug21 476 13-Jul-21 A 19-Dec-22

General 444 01-Oct-21 19-Dec-22

Milestones 444 01-Oct-21 19-Dec-22


A1215 Brine Distribution Permit for WBS 1100 & 1200 0 15-Oct-21*
A1540 WBS 1000 Main Contractor, Ready At Site 0 15-Nov-21
A1740 WBS 2000 Earthworks & Liner Contractor, Ready At Site for Pönd Works 0 01-Oct-21
A3410 Halite Ponds, H11 & H12 Ready to start Filling Up (Early Start Up from wells 08, 07 & 06) 0 18-Dec-21
A5230 Process Plant, First Produciton Ramp Up to 55% 0 19-Dec-22
A6460 Earthworks & Liner Permit for Ponds 0 01-Oct-21*
A6580 Liming Plant Start Up 0 15-Jul-22
A6660 7 month evaporation process in Halite Ponds Complete 0 19-Jul-22
A6670 5 month process in Muriate Ponds Complete 0 19-Dec-22

Wellfields & Brine Distribution 110 13-Jul-21 A 17-Dec-21

Procurement 108 13-Jul-21 A 15-Dec-21


A5570 PCK1.P0028 - VFD Variable Frecuency Drives for Wells, Bid Analysis & Po Placement 33 13-Jul-21 A 01-Oct-21
A5580 PCK1.P0028 - VFD Variable Frecuency Drives for Wells, Delivery* 75 02-Oct-21 15-Dec-21
A5590 PCK1.P0028 - VFD Variable Frecuency Drives for Wells, First Delivery At Site 0 01-Dec-21
A5780 PCK1.P0019 - Manual Valves & Proximity Switches, Fabrication & Delivery 75 24-Aug-21 A 12-Nov-21
A5790 PCK1.P0019 - Manual Valves & Proximity Switches, Pending Delivery at Site (Revisar) 0 13-Nov-21
Subcontracts 93 23-Jul-21 A 30-Nov-21
A1530 PCK1.C0020 - WBS 1000 Main Contractor, Mobilisation 30 16-Oct-21 14-Nov-21
A1670 PCK1.C0024 - Power Generators Rental, Bid Analysis & Po Placement 43 23-Jul-21 A 11-Oct-21
A1680 PCK1.C0024 - Power Generators Rental, Delivery At Vendor's Premises (Revisar) 50 12-Oct-21 30-Nov-21
A1690 PCK1.C0024 - Power Generators Rental, Transportation to Site 0 30-Nov-21
E Wellfield 33 15-Nov-21 17-Dec-21
Well SVWP20_08 30 15-Nov-21 14-Dec-21
Construction 30 15-Nov-21 14-Dec-21
A2600 SVWP20_08, Earthworks 7 15-Nov-21 21-Nov-21
A2630 SVWP20_08, Precast Elements Mounting 5 22-Nov-21 26-Nov-21
A2650 SVWP20_08, Diesel Generator & Storage Mounting 3 01-Dec-21 03-Dec-21
A2660 SVWP20_08, Electrical Equipment Mounting & Wiring 5 01-Dec-21 05-Dec-21
A5950 SVWP20_08 Valve Installation on Well Head 1 10-Dec-21 10-Dec-21
A6040 SVWP20_08, Early SU 0 14-Dec-21
A6210 SVWP20_08, Electrical Panel Installation 1 01-Dec-21 01-Dec-21
Well SVWP20_07 24 22-Nov-21 15-Dec-21
Construction 24 22-Nov-21 15-Dec-21
A2240 SVWP20_07, Earthworks 7 22-Nov-21 28-Nov-21
A2260 SVWP20_07, Well Pump Mounting 5 29-Nov-21 03-Dec-21
A2270 SVWP20_07, Precast Elements Mounting 5 29-Nov-21 03-Dec-21
A2290 SVWP20_07, Diesel Generator & Storage Mounting 3 04-Dec-21 06-Dec-21
A2300 SVWP20_07, Electrical Equipment Mounting & Wiring 5 06-Dec-21 10-Dec-21
A5960 SVWP20_07 Valve Installation on Well Head 1 11-Dec-21 12-Dec-21
A6050 SVWP20_07, Early SU 0 15-Dec-21

Actual Level of Effort Remaining Work Critical Remaining Work Page 1 of 3 TASK filter: Critical.
Actual Work Sub Critial Milestone © Oracle Corporation
Sal de Vida Lithium Brine Project
Package 1 Procurement & Constrution Schedule
(Critical Path)
Activity ID Activity Name Remaining Start Finish Indicators2021 2022 2023
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
A6220 SVWP20_07, Electrical Panel Installation 1 06-Dec-21 06-Dec-21
Well SVWP20_06 19 29-Nov-21 17-Dec-21
Construction 19 29-Nov-21 17-Dec-21
A2000 SVWP20_06, Earthworks 7 29-Nov-21 05-Dec-21
A2020 SVWP20_06, Well Pump Mounting 5 06-Dec-21 10-Dec-21
A2030 SVWP20_06, Precast Elements Mounting 5 06-Dec-21 10-Dec-21
A2050 SVWP20_06, Diesel Generator & Storage Mounting 3 11-Dec-21 13-Dec-21
A2060 SVWP20_06, Electrical Equipment Mounting & Wiring 5 13-Dec-21 17-Dec-21
A5970 SVWP20_06 Valve Installation on Well Head 1 12-Dec-21 13-Dec-21
A6080 SVWP20_06, Early SU 0 17-Dec-21
A6230 SVWP20_06, Electrical Panel Installation 1 13-Dec-21 13-Dec-21
Main Brine Duct & Interconnections 32 15-Nov-21 16-Dec-21
Construction 32 15-Nov-21 16-Dec-21
A2930 HDPE Pipe Laydown from Booster Station to Halite Ponds (5.000 Mts.) 24 15-Nov-21 08-Dec-21
A2940 Hydraulic Tests (HDPE) 15 28-Nov-21 13-Dec-21
A5890 SVWP20_08 to HDPE Main Pipeline PEX Pipe Laydown and Installation 2 08-Dec-21 09-Dec-21
A5900 SVWP20_07 to HDPE Main Pipeline PEX Pipe Laydown and Installation 1 10-Dec-21 11-Dec-21
A5910 SVWP20_06 to HDPE Main Pipeline PEX Pipe Laydown and Installation 1 11-Dec-21 12-Dec-21
A5920 SVWP20_08 to HDPE Pipe Tie In Installation 1 13-Dec-21 14-Dec-21
A5930 SVWP20_07 to HDPE Pipe Tie In Installation 1 14-Dec-21 15-Dec-21
A5940 SVWP20_06 to HDPE Pipe Tie In Installation 1 15-Dec-21 16-Dec-21
A6620 SVWP20_05 to HDPE Main Pipeline PEX Pipe Laydown and Installation 1 12-Dec-21 13-Dec-21

Evaporation Ponds, Waste & Tailings 110 09-Aug-21 A 18-Dec-21

Subcontracts 32 09-Aug-21 A 30-Sep-21


A1720 PCK1.C0021 - WBS 2000 Earthworks & Liner Contractor, Bid Analysis & Po Placement 9 09-Aug-21 A 07-Sep-21
A1735 PCK1.C0021 - WBS 2000 Earthworks & Liner Contractor, Mobilisation 10 21-Sep-21 30-Sep-21
A1745 PCK1.C0021 - WBS 2000 Earthworks & Liner Contractor, Mobilisation for Early Works 11 10-Sep-21 20-Sep-21
Halite & Mother Liquor Ponds 78 01-Oct-21 18-Dec-21
Construction 78 01-Oct-21 18-Dec-21
A3050 Halite Ponds, H11 EarthWorks & Berms Construction 51 01-Oct-21 21-Nov-21
A3090 Halite Ponds, H12 EarthWorks & Berms Construction 50 01-Oct-21 20-Nov-21
A3290 Halite Ponds, H11 Liner Installation & Testing 45 03-Nov-21 18-Dec-21
A3300 Halite Ponds, H12 Liner Installation & Testing 45 02-Nov-21 17-Dec-21

LiCO Plant & Reagents 476 30-Jul-21 A 19-Dec-22

Engineering 180 03-Dec-21 31-May-22


A4048 SDV Package 2, Detail Engineering Development 180 03-Dec-21 31-May-22
A4058 SDV Package 2, Detail Engineering Ready for Mob 0 01-Feb-22
Procurement 395 30-Jul-21 A 28-Sep-22
A4220 PCK2.M006 - Press Filter, Quotations Reception 19 13-Aug-21 A 17-Sep-21
A4230 PCK2.M006 - Press Filter, Bid Analysis & Po Placement 20 18-Sep-21 07-Oct-21
A4240 PCK2.M006 - Press Filter, Fabrication & Delivery 346 08-Oct-21 18-Sep-22
A4290 PCK2.M001-1 - Thickener, Request for Quotation (PWP & Issuance) 12 30-Jul-21 A 10-Sep-21
A4300 PCK2.M001-1 - Thickener, Quotations Reception 21 11-Sep-21 01-Oct-21
A4310 PCK2.M001-1 - Thickener, Bid Analysis & Po Placement 52 02-Oct-21 22-Nov-21

Actual Level of Effort Remaining Work Critical Remaining Work Page 2 of 3 TASK filter: Critical.
Actual Work Sub Critial Milestone © Oracle Corporation
Sal de Vida Lithium Brine Project
Package 1 Procurement & Constrution Schedule
(Critical Path)
Activity ID Activity Name Remaining Start Finish Indicators2021 2022 2023
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
A4320 PCK2.M001-1 - Thickener, Fabrication & Delivery 221 23-Nov-21 01-Jul-22
A4420 PCK2.M002 - Centrifuge, Quotations Reception 19 13-Aug-21 A 17-Sep-21
A4430 PCK2.M002 - Centrifuge, Bid Analysis & Po Placement 30 18-Sep-21 17-Oct-21
A4440 PCK2.M002 - Centrifuge, Fabrication & Delivery 346 18-Oct-21 28-Sep-22
A4450 PCK2.M001 - Conveyor, Request for Quotation (PWP & Issuance) 12 20-Aug-21 A 10-Sep-21
A4460 PCK2.M001 - Conveyor, Quotations Reception 21 11-Sep-21 01-Oct-21
A4470 PCK2.M001 - Conveyor, Bid Analysis & Po Placement 52 02-Oct-21 22-Nov-21
A4480 PCK2.M001 - Conveyor, Fabrication & Delivery 279 23-Nov-21 28-Aug-22
A4530 PCK2.M001-8 - Slaking Lime Package, Request for Quotation (PWP & Issuance) 12 13-Aug-21 A 10-Sep-21
A4540 PCK2.M001-8 - Slaking Lime Package, Quotations Reception 21 11-Sep-21 01-Oct-21
A4550 PCK2.M001-8 - Slaking Lime Package, Bid Analysis & Po Placement 52 02-Oct-21 22-Nov-21
A4560 PCK2.M001-8 - Slaking Lime Package, Fabrication & Delivery 154 23-Nov-21 25-Apr-22
Subcontracts 185 04-Aug-21 A 02-Mar-22
A4042 PCK2.W001 - EPC Contractor, Quotations Reception 25 04-Aug-21 A 23-Sep-21
A4044 PCK2.W001 - EPC Contractor, Bid Analysis & Po Placement 70 24-Sep-21 02-Dec-21
A4047 PCK2.W001 - EPC Contractor, Mobillisation 30 01-Feb-22 02-Mar-22
Liming 110 28-Mar-22 15-Jul-22
Construction 110 28-Mar-22 15-Jul-22
A5080 Early Liming, Equipment Mounting 45 27-Apr-22 10-Jun-22
A5240 Early Liming, Pumps Installation 15 01-Jun-22 15-Jun-22
A6680 Early Liming, Pipe Installation (Lime Plant to Muriate Buffer Pond) 15 16-Jun-22 30-Jun-22
A6681 Early Liming, Precomm / Com / Start Up 15 01-Jul-22 15-Jul-22
A6701 Early Liming, Precast Elements Mounting 30 28-Mar-22 26-Apr-22
Process Plant 291 03-Mar-22 19-Dec-22
Construction 291 03-Mar-22 19-Dec-22
A5095 Event Pond, Earthworks & Liner Installation 10 03-Mar-22 12-Mar-22
A5100 Process Plant, Earthworks 15 13-Mar-22 27-Mar-22
A5110 Process Plant, Precast Elements Mounting 120 28-Mar-22 25-Jul-22
A5120 Process Plant, Equipment Mounting 180 13-May-22 08-Nov-22
A5125 Process Plant, Steel Structures & Buildings Assembly 180 12-Jun-22 08-Dec-22
A5130 Process Plant, Racks Mounting 150 27-Apr-22 23-Sep-22
A5140 Process Plant, Piping Mounting & Interconnections 180 02-Jun-22 28-Nov-22
A5150 Process Plant, Electrical Trays Mounting 150 27-May-22 23-Oct-22
A5160 Process Plant, Instrumentation Trays Mounting 150 27-May-22 23-Oct-22
A5170 Process Plant, Electrical Equipment Mounting & Wiring 120 26-Jul-22 22-Nov-22
A5180 Process Plant, Instrumenation Mounting & Wiring 120 29-Jul-22 25-Nov-22
A5190 Process Plant, Hydraulic Tests 90 10-Sep-22 08-Dec-22
A5200 Process Plant, Instrumentation Calibration & Tests 90 07-Sep-22 05-Dec-22
A5210 Process Plant, Precommissioning 30 09-Nov-22 08-Dec-22
A5220 Process Plant, Commissioning 30 19-Nov-22 19-Dec-22

Onsite Infrastructure 32 16-Aug-21 A 30-Sep-21

Permanent Camp 32 16-Aug-21 A 30-Sep-21


Construction 32 16-Aug-21 A 30-Sep-21
A5850 Contractors Camp Modules, 50 Beds Delivery 32 16-Aug-21 A 30-Sep-21

Actual Level of Effort Remaining Work Critical Remaining Work Page 3 of 3 TASK filter: Critical.
Actual Work Sub Critial Milestone © Oracle Corporation