Professional Documents
Culture Documents
Tendering Notes
Tendering Notes
Financially stable
Having good business records e.g. Completion, quality, etc.
Proper contractor for the right size of the job, i.e. the project shouldn’t be too big
nor he too small to him.
Competent in workmanship and organization.
If the period which the contractor get to prepare the tender is in adequate
Intending tenders notifies these
If a sufficient number of block forms (tender documents) are not issued to
intending contractors
If important changes in the tender are considered necessary since the issuing of
the tender notice.
1. Open tendering: The procedure here is to advertise through the press, inviting firm
that wishes to do so to submit a tender; the advertisement will give outline details of
the type of work, its scale, the programme and any other key features. Interested firms
apply for the tender documents and there are usually no formalities other than a
deposit of few shillings, which is returned on submission of a real tender. The deposit
covers the cost of the documents.
Advantages.
(i) It gives the chance of tendering to any firm that wishes to do so and may provide
a room for some relatively unknown but capable firm.
(ii) Since there is no restriction there can be no chance of favoritisms in drawing up
the list of tenderers. (This is a valid point in the case of public accountability)
(iii) Just as there is no restriction on “who should tender”, so there is no obligation to
tender.
1
(iv) Presumably no one is going to put a tender in just to oblige/force/request,
and therefore all tenders should be genuine.
(v) The appeal of open tendering is that it should secure maximum competition.
(vi) It effectively prevents firms in an area from forming an exclusive ring and
keeping up prices.
Disadvantages.
(i) It is costly as tender list turns to be very long and hence many tender documents
have to be distributed.
(ii) Much time is taken to prepare and check many documents; Contractors also tend
to waste a lot of time tendering mostly without success.
(iii) The client is tempted to accept lowest offer which may not always be correct.
(iv) The contract can be awarded to a poor contractor
(v) Competent contractors may refuse to compete.
Thereafter a list is minimized to 8 —10 contractors. This case usually the lowest
tendered is the one who is taken although duration of the contract can affect the
selection.
2
Disadvantages of selective tendering
(i) Tender prices are usually higher than they would have been under open tendering.
(ii) In selective tendering by listing few contractors, there may be contractors who are
not willing to tender who may quote very high prices for the sake of filling
documents and maintain good business relationship. These excessively high
prices can be confusing to the client,
(iii) There are some possibilities of favoritism in drawing up the list of prequalified
contractors.
(iv) Consultants or clients maintain a list of good or likely contractors for particular
level of projects, this habit may reduce the chances of new competent contractors
joining the list and old but and incompetent contractors may not be removed from
the list easily.
(v) There are chances of collusion between contractors as contractors may agree
between each other that whoever is selected or awarded a contract, he must make
a super profit
(ii) Serial tendering: For large projects, it is useful for a series of closely similar
scheme which are to be carried out over a period of time within the same area and
permitting the phased utilisation of organization and plant available at the site.
3
(ii) The amount of work available for open competitive tendering is reduced tending
to diminish the construction industry.
Negotiated Tendering
There are occasions when it would suit the client to dispense with the element of
competition all together and approach only single contractor who is considered to be
capable to execute the work. The client may reach the decision and employ a particular
contractor whose methods and policies are known and which has in the past proved
capable of satisfactory fulfilling the clients’ requirements
The use of a nominated bill involves the use of a priced bill of quantities for a similar
project previously carried out under similar conditions which serves as the basis for
determining the price of the new project. The assessment of cost may also involve
preparation of bills of quantities or use of approximate estimates. Rates both unit and
composite to suit the condition are built up from the scratch using suppliers prices for
materials and goods. Other constituents of the negotiated tendering include the items
other than the unit rates;
4
Tendering Procedures
The following are the procedures that are followed during the tendering process.
The advertisement should appear well in advance in order to afford prospective bidders a
reasonable time for making the necessary inquiries and for collecting any background
information that they may require: a period of 14 days for national projects and 30-45
days for international projects is sufficient as provided in the Tanzanian Public
Procurement Act (2004).
Pre-tender conference
Sometimes for the purpose of obtaining necessary clarifications a pre-tender conference
should be held preferably at a place near the site of the proposed work. The prospective
bidders should be invited to attend the conference at their own cost.
5
(g) Availability of data forms of tender and other tender documents, and other
relevant information, e.g. where, from whom, and at what cost the documents
will be collected.
(h) Earnest money required along with the tender
(i) Security deposit
(j) The last date the place and the time of receipt of sealed bids
(k) The date, time, place and procedure of opening the tender
(1) Reservation of the right to reject bids
(c) Important changes in the tender are considered necessary after the issuing of
the tender notice.
In such circumstances, the extended date and time of issuing and accepting the
tenders must be brought to the notice of all concerned. The usual way is to issue
a notice in an advertisement on those newspapers and/or journals that carried
the original tender notice. The extension notice carries the heading of
CORRIGENDUM TO TENDER NOTICE
6
-
3. Un remunerative work required – work needed before the commencement of the
construction job e.g. access roads, offices, water and energy connection as well as
store sheds preparation
4. Time for completion – It helps the contractor in calculating time for the work
On – cost - Over heads
Estimation - Payment schedule
The unit price for each item is worked out separately by distributing on cost and
profit without losing the job.
The contractors have to be careful in estimating the quantities
OPENING OF TENDERS
In the case of public bodies the tenders are usually read at stated hour day as notified
in tender notice. The representatives of each bidder are allowed to attend.
COMPARING TENDERS
The consultant recommend to the client which contractors offer should be accepted
7
RESECTING THE TENDER AT SUBMISSION TIME
The tender may be rejected right at the submission due to the following:-
The tender proposes in the tender any alterations in the work specified or in the
time allowed for carrying out the work or any other conditions which are not
acceptable to the owner
Any of the pages in the tender are removed/ replaced
No sign or signature of partnership of the company
Any erasures are made by the tenders in the tender
8
TENDER DOCUMENT
The following are important to be included in a tender document:
2. Bills of Quantities: These are used for large projects. The traditional approach has
been to send one copy to each tenderer and then to ask the tender whose tender is
initially under consideration to copy his price into further copy for examination.
To avoid delays in traditional approach it has sometimes become the practice to send
each tenderer two copies of the bill and to ask for one to be returned priced at the
same time as the form of tender but sealed in a separate or the same envelope.
4. The form of tender: The form of tender is a letter accepting the offer made on the
form will be evidence of a binding contract until the formalities have been completed.
The tenderer should sign and date on the form, giving his tender amount in figures
and words and also giving the contract period if this is not already included.
5. Drawings: It is good policy to issue some drawings to tenderers with the other
documents. These drawings will mainly be the general arrangements drawings and
any other drawings needed for tenderes to assess the constructional apprnahu1at the
project will demand. In addition there will be the site layout drawing and any
drawings governing phasing and other special conditions.
Drawings that simply show detail need not be issued but should he on display at the
various professional offices for tenderers to insect if they wish. All drawings meant
for tendering should he stamped to ensure that all contractors receive the same
revision of drawings.
9
6. Return envelope: A ready addressed envelope should have been provide for the
return of the tender, stating when it is to be received, title of the project but giving no
indication of the sender.
Tenderers should acknowledge the receival of tender documents and inform the
client/architect thereafter.
2. Performance bond:
In most large contracts it is necessary that the contract it is necessary that the
contractor produce a security bond e.g. bank or insurance company with
guarantees that the contractor will finish the work as stipulated in the contract
documents.
In use of failure to perform the job the bank or insurance bank or company will
refund some amount to the client
Conclusion / remarks
The process of tendering, evaluating, selecting and awarding the contract is a trick
one. It requires a good understanding and knowledge of the construction industry
in project management, materials, Labour, and equipment management.
10