BACKFILL IN TBMs
BACKFILLING
Filling the gap in TBM excavation
Excavation with shielded tunnel boring machines (TBMs) The filling of this annular gap with a proper material is very
requires that precast concrete segments are continuously important during the excavation process and following goals
installed behind the shield to form the tunnel lining. are considered:
Allowing movement flexibility to the machine and providing ́́ The filling helps fixing the precast segments into position.
space to install the precast segments – where the advance ́́ Keeping the natural state of the ground after excavation,
cylinders push to move forward-, the excavated diameter avoiding settlements.
is bigger than the external diameter of the segments. This ́́ It ensures homogeneous contact of the precast segments
difference in the diameters and the space resulting depend to the ground.
on the type of geology to be excavated and the specific TBM ́́ It transfers the load from the TBM back-up to the ground.
design. This space is normally identified as annular gap and ́́ Together with the precast segments, it helps the water-
generally counts some centimeters. proofing of the tunnel.
Backfilling grouts
CONCRETE
2 BACKFILL IN TBMs
In order to satisfy specific requirements, the filling of the Depending on the type of machine and the requirements dur-
annular gap needs to consider the following aspects during ing the excavation, the type of filling can be classified in three
operation: groups:
́́ The filling material needs to be easily pumped, even over ́́ Inert mixes are based on sand and gravel with the possibi-
long distances inside the machine or into the tunnel. lity to inject the bottom tunnel section with a mortar in a
́́ The filling material should allow continuous injection during later stage.
TBM advance. ́́ Mortar mixes made with water, cement, fillers, fine agrega-
́́ Blockages in the injection lines, damages of the injection tes and chemical admixtures.
pumps and sedimentation in the storage tanks should be ́́ Two component grouts are very fluid mixes specially stabi-
avoided. lized, needing a separated accelerator to start “gelling” in
́́ The reparation and down-time for the different components shorter time.
of the system needs to be minimized as much as possible.
́́ The annular gap needs to be fully filled avoiding any space
inside the filling material.
́́ Even by presence of ground water, the pumped material 7
needs to remain in place and cannot be washed. 8 3
2
́́ Depending on the ground to be excavated, specific require-
6 6 1
ments for compressive strength and hardening of the filling 4
material may be required. 4 5
́́ Considering possible stops during the excavation of the
TBM, the injection of the filling material may be stopped 1 2 3 4
and re-started in short periods of time without affecting Wire brush Tailskin Backfill Grease
the advance of the machine or the quality of the final lines
injection.
5 6 7 8
Concrete Tail Seal Ground Grout
segment Sealant lines
CONCRETE
BACKFILL IN TBMS 3
ONE OR TWO COMPONENT
The right option for your TBM
Sika offers a complete range of Stabilizers and Retarders to Before the mix gels, it can fill every gap behind the tunnel lin-
prepare these mixes. ing. After hardening, it has comparable compressive strength
to the surrounding ground.
CONCRETE
4 BACKFILL IN TBMs
CONCRETE
BACKFILL IN TBMS 5
SUPPORTING YOUR PROJECT
Our technologies around the world
CONCRETE
6 BACKFILL IN TBMs
CONCRETE
BACKFILL IN TBMS 7
GLOBAL BUT LOCAL PARTNERSHIP
WE ARE SIKA
Sika is a specialty chemicals company with a leading position in the
development and production of systems and products for bonding,
sealing, damping, reinforcing and protecting in the building sector and
the motor vehicle industry. Sika’s product lines feature concrete admix-
tures, mortars, sealants and adhesives, structural strengthening sys-
tems, industrial flooring as well as roofing and waterproofing systems. © SIKA SERVICES AG / CONCRETE
Our most current General Sales Conditions shall apply. Please consult
the most current local Product Data Sheet prior to any use.