Professional Documents
Culture Documents
14-1 EVMS Ex.
14-1 EVMS Ex.
Definition
Management Reserve
P
Raleigh R
Distribution PMB O
J
E
C
T
E
D
$ S
L
BCWPC I
BCWSC P
P
ACWPC A
G
E
Time Completion
Now Date
“Objectively Measures Performance”
• Performance Measurement
Assessing the progress of acquisition
programs against cost, schedule and technical
standards
• Earned Value
Measuring work performed in terms of the budget
assigned to that work
Traditional Measurement
PLANNED ACTUAL COST
2 2
= $15
10 10
5 5 5 5
= $25
3 3
BUDGET = $50 COST = $40
5 5 5 5 5 5 5 5
= $25
3 3 3 3
BUDGET = $50 EARNED = $35 COST = $40
STATUS: Schedule Variance = Earned - Budget = -15Unfavorable
Cost Variance = Earned - Actual = - 5Unfavorable
Earned Value Terminology
Acronym Term Meaning
BCWS Budget Cost of Work Scheduled Baseline - PMB
BCWP Budget Cost of Work Performed Earned Value
ACWP Actual Cost of Work Performed Actuals
BAC Budget At Completion Planned Cost
EAC Estimate At Completion Forecasted Cost
Accomplishment
SV Schedule Variance
Variance
CV Cost Variance Planned vs Actual
Cost
VAC Variance At Completion Forecasted
Overrun / Underrun
The Performance
Measurement Baseline
The time-phased budget plan against which
contract performance is measured.
Management Reserve
PMB
BCWS C
Time
Completion
Now
Date
Developing the PMB
1. Scope 1. Identify SOW
2. Extend WBS to
control account
Reports
work package
Time
COMMON SCHEDULE PRESENTATIONS
ID
1
Task Name Dec
AWARD
Jan Feb Mar
1997
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Milestone Chart: Provides key events
2 SDR or completion points of activities.
3 PDR
Used as objectives or output of a network.
4 CDR
5 DTE
Needs to show baseline & current
6 Delivery
projection.
2
Task 1
Task 2
4
Task 3
Task 4
Task 2 Task 4
2 5d 4 5d
1/31/97 2/6/97 2/7/97 2/13/97
Task 1
Task 5
Network (pert): Shows order of the activities.
1
1/24/97
5d
1/30/97 5 5d Generally does not clearly show time location or
Task 3 2/14/97 2/20/97
3 5d
amount completed (start / finish).
1/31/97 2/6/97
CRITICAL PATH = 0 FLOAT
50 / 50 % 2-3 Mths 15 15
Variant
3 or More Mths 5 15 10
Milestone
Level of Effort Varies 10 10 10
Project WBS
Design
Manufacture
Component Test
Assemble
Integrated Test
1. THE PLAN Work Plan
w
o
r
k
s
c
o
p
e $
Time Period
1. THE PLAN Budget Plan
w
o
2 4 2
r
k
2 2 2
s 2
c
o 1 1 1 1
p
e $ 20
Time Period
Time-Phased Plan
BUDGETED COST
DEFINE SCHEDULE OF WORK
WORK SCHEDULED ($M)
Design 4
Manufacture 6
Component Test 4
Assemble 4
Integrated Test 2
0 2 4 6 8 10 12 14 16 18 20 $20
Months
The Time-Phased Spend Plan
NEGOTIATED CONTRACT COST
22 Management
20
} Reserve
18
16
Budget at
14
Performance Completion
$ 12 Measurement BAC
10 Baseline
Cumulative
8 Budgeted PMB
6 Cost of Work
4 Scheduled
2 BCWS
0
0 2 4 6 8 10 12 14 16 18 20
Completion
Months Point
EV in Program Execution
• Data Analysis
– Variances
– Performance Indices
• Identify trends
-- Where are we headed?
-- Any cost, schedule surprises ?
Variances
Cost and schedule
Current month and cumulative
Performance indices
Cost Performance Index (CPI)
Schedule Performance Index (SPI)
Percent complete
Percent spent
1. THE PLAN
Actual Costs
w
o 2 2
r
k 2 2 2
s
c 1 1 1 1
o
p
e $ 14
Time Period
2. ACTUAL COSTS
Time Period
The Actual Cost
Budget Actual
Plan, Cost,
DEFINE SCHEDULE BCWS ACWP
WORK ($M) ($M)
Design 4 4
Manufacture 6 6
Component Test 4 3
Assemble
Integrated Test
0 2 4 6 8 10 12 14 16 18 20 $14 $13
Months (Now)
Actual Cost Imposed On The Spend Plan
NEGOTIATED CONTRACT COST
22 Management
20 } Reserve
18
16
14 Budget at
Completion
$ 12 (BAC)
10 BCWS
8
6
ACWP
4
2
0
0 2 4 6 8 10 12 14 16 18 20
Completion
Time
Months Point
Now
1. THE PLAN Earned Value3. WORK PERFORMED
w
o 2 2 2
r
k 2 2 2 2
2
s
c 1 1 1 1 1 1 1 1
o
p
e $ 14 $ 10
Time Period Time Period
2. ACTUAL COSTS 4. VARIANCES
Time Period
Earned Value Current Status
Earned
Value
Performance
DEFINE SCHEDULE BCWS BCWP ACWP
WORK ($M) ($M) ($M)
Design 4 4 4
Manufacture 6 4 6
Component Test 4 2 3
Assemble
Integrated Test
8
6
4 BCWP
2
0
0 2 4 6 8 10 12 14 16 18 20
Completion
Time
Months Point
Now
Cumulative Dollar Variance
Cost and Schedule Trends
$ in Millions
1.0
(1.0)
(2.0)
CV
(3.0)
(4.0) SV
Performance Metrics
Estimate at Completion
BAC/CPI = 20/.77 = $26M
Estimate at Completion
(EAC)
ACWP = $13M
1.3
1.2
1.1
1
0.9
0.8 CUM SPI
0.7
0.6 CUM CPI
0.5
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Nov