Quantity
Items Specification Unit Remarks
Total
1. Culverts (Pemathang)
Hot dipped galvanized MS Railing: The steel connections shown are schematic only.
The structural steel shall be Grade E250 (Fe410) as per IS 2062-2006. The The fabricator shall prepare shop drawings for all
weld metal shall be EX4XXX, tensile strength range 410 - 530 MPa as per IS the connections.
814. The bolts shall be minimum grade/ property class 4.6 as per IS 1367. The shop drawing shall be verified and approved
Steel Railings by the Engineer, GI or consultant.
After the approval, the fabricator shall go ahead
Drawing reference: GYAL/PEM/C-06 with the fabrication.
Rails Mild Steel (Grade 250) RHS tubes (127x50x3.6) kg 2434.69 8 Nos. 4.5 m + 8 Nos. 3.5m + 72 Nos. 2.5m
Posts Mild Steel Posts (955x200x20) kg 4078.23 136 Nos.
Base Plates Mild Steel Posts Base plates (450x225x20) kg 1080.95 68 Nos.
Bolts Bolts ( dia 16 mm, size 370 mm ) kg 173.94 272 Nos.
Nuts Nuts (inner dia 16 mm, size 24 mm) kg 5.74 272 Nos.
2. Bridge 01 (Pemathang)
Hot dipped galvanized MS Railing: The steel connections shown are schematic only.
The structural steel shall be Grade E250 (Fe410) as per IS 2062-2006. The The fabricator shall prepare shop drawings for all
weld metal shall be EX4XXX, tensile strength range 410 - 530 MPa as per IS the connections.
814. The bolts shall be minimum grade/ property class 4.6 as per IS 1367. The shop drawing shall be verified and approved
by the Engineer, GI or consultant.
Steel Railings
After the approval, the fabricator shall go ahead
Drawing reference: with the fabrication.
GI-PT-Br1-Str-04 & GI-PT-Br1-Str-15
Rails Mild Steel (Grade 250) RHS tubes (127x50x3.6) kg 2414.80 16 Nos. 5.378 m + 8 Nos. 18.398 m
Posts Mild Steel Posts (955x200x20) kg 2159.06 72 Nos.
Base Plates Mild Steel Posts Base plates (450x225x20) kg 572.27 36 Nos.
Bolts Bolts ( dia 16 mm, size 370 mm ) kg 89.45 144 Nos.
Nuts Nuts (inner dia 16 mm, size 24 mm) kg 2.95 144 Nos.
3. Bridge 02 (Pemathang)
Hot dipped galvanized MS Railing: The steel connections shown are schematic only.
The structural steel shall be Grade E250 (Fe410) as per IS 2062-2006. The The fabricator shall prepare shop drawings for all
weld metal shall be EX4XXX, tensile strength range 410 - 530 MPa as per IS the connections.
814. The bolts shall be minimum grade/ property class 4.6 as per IS 1367. The shop drawing shall be verified and approved
by the Engineer, GI or consultant.
Steel Railings After the approval, the fabricator shall go ahead
Drawing reference: with the fabrication.
GI-PT-Br2-Str-10 & GI-PT-Br2-Str-13
Rails Mild Steel (Grade 250) RHS tubes (127x50x3.6) kg 1479.456 16 Nos. 4.14 m + 8 Nos. 9.299 m
Posts Mild Steel Posts (955x200x20) kg 1439.38 48 Nos.
Base Plates Mild Steel Posts Base plates (450x225x20) kg 381.51 24 Nos.
Bolts Bolts ( dia 16 mm, size 370 mm ) kg 59.6352 96 Nos.
4. Chadrichu Bridge (Khotoka)
Hot dipped galvanized MS Railing: The steel connections shown are schematic only.
The structural steel shall be Grade E250 (Fe410) as per IS 2062-2006. The The fabricator shall prepare shop drawings for all
weld metal shall be EX4XXX, tensile strength range 410 - 530 MPa as per IS the connections.
814. The bolts shall be minimum grade/ property class 4.6 as per IS 1367. The shop drawing shall be verified and approved
Steel Railings by the Engineer, GI or consultant.
After the approval, the fabricator shall go ahead
Drawing reference: with the fabrication.
GI-Kh-CB-SD05 & GI-Kh-CB-SD14
Rails Mild Steel (Grade 250) RHS tubes (127x50x3.6) kg 1877.26528 16 Nos., 3.440 m + 8 Nos., 15.756 m
Posts Mild Steel Posts (955x200x20) kg 1799.22 60 Nos.
Base Plates Mild Steel Posts Base plates (450x225x20) kg 476.8875 30 Nos.
Bolts Bolts ( dia 16 mm, size 370 mm ) kg 74.544 120 Nos.
Nuts Nuts (inner dia 16 mm, size 24 mm) kg 2.46 120 Nos.
Quantity
Items Specification Unit Remarks
Total
1. For Culverts (Pemathang)
Galvaniszd Drain Spout
Overall size: 130mm X 130mm. The fabricator shall prepare shop drawings for all
Drain Pipe 100 mm dia, 400 mm length the connections.
Drain Spouts Specification: Grated using MS Flats Nos. 26 The shop drawing shall be verified and approved
by the Engineer, GI or consultant.
Drawing reference: GYAL/PEM/C-06 After the approval, the fabricator shall go ahead
with the fabrication.
2. For Bridges (Pemathang)
Galvanized Drain Spout
Overall size: 250mm X 250mm. The fabricator shall prepare shop drawings for all
Drain Pipe 110 mm dia, 565 mm length the connections.
Drain Spouts Specification: Grated using MS Flats. The shop drawing shall be verified and approved
by the Engineer, GI or consultant.
After the approval, the fabricator shall go ahead
with the fabrication.
Bridge 01 Drawing reference: GI-PT-Br2-Str-16 Nos. 3
Bridge 02 Drawing reference: GI-PT-Br2-Str-14 Nos. 2
3. Chadri chu Bridge (Khotoka)
Galvanized Drain Spouts:
4R00Name: Type 1, DrainBFT87TP The fabricator shall prepare shop drawings for
Overall size: 250mm X 250mm. all the connections.
Drain Spouts Drain Pipe: 865mm The shop drawing shall be verified and
Nos. 4
Type 1 Specification: Grated using MS Flats. approved by the Engineer, GI or consultant.
Drawing reference GI-Kh-CB-SD13 After the approval, the fabricator shall go ahead
with the fabrication.
Note:
1. Drawing with dimensions of railllings & Drain Spouts is attached
2. The procurement to select the finishes, material strength, fixing mechanism and approve
3. The total quantities worked out are for Gyalsung Academy- Pemathang only
D2-2
D2
D2.1
D2-1
D2.1
DRAIN SPOUT
110
3-5x25 MS FLAT BAR
IN EQUAL SPACE
125
8-8 mm Ø BOLTS
PVC BEND FOR
14
58
100 MM Ø PVC PIPE
130
100
(5X25) IN EQUAL SPACE
6 6
400
14
14
130 100 MM Ø PVC DRAIN PIPE
20X20X6 MS ANGLE FRAME
RESOURCE PLAN FOR BRIDGE # 01
Name of Bridge Bridge #01
Project Activity Code 4.5.1
Review Activity Railings & Drainage
Quantity reviewed for GA-Pemathang
Gyalsung Academy
BSR
Items Specification Unit Quantity Remarks
Code
Hot dipped galvanized MS Railing: The steel connections shown are schematic
The structural steel shall be Grade E250 (Fe410) as only.
per IS 2062-2006. The weld metal shall be The fabricator shall prepare shop drawings for
EX4XXX, tensile strength range 410 - 530 MPa as all the connections.
per IS 814. The bolts shall be minimum grade/ The shop drawing shall be verified and
property class 4.6 as per IS 1367. approved by the Engineer, GI or consultant.
After the approval, the fabricator shall go ahead
Drawing reference: with the fabrication.
AR Steel Railings GI-PT-Br1-Str-04 & GI-PT-Br1-Str-15
Mild Steel (Grade 250) RHS tubes (127x50x3.6) kg 2414.80 16 Nos., 5.378 m & 8 Nos., 18.398 m
Mild Steel Posts (955x200x20) kg 2159.06 72 Nos.
Mild Steel Posts Base plates (450x225x20) kg 572.27 36 Nos.
Bolts ( dia 16 mm, size 370 mm ) kg 89.45 144 Nos.
Nuts (inner dia 16 mm, size 24 mm) kg 2.95 144 Nos.
Note:
1. Drawing with dimensions of railllings & Drain Spouts is attached
2. The procurement to select the finishes, material strength, fixing mechanism and approve
3. The total quantities worked out are for Gyalsung Academy- Pemathang only
D2-2
D2
D2.1
D2-1
D2.1
DRAIN SPOUT
RESOURCE PLAN FOR BRIDGE # 02
Name of Bridge Bridge #02
Project Activity Code 4.5.1
Review Activity Railings & Drainage Spouts
Quantity reviewed for
Gyalsung Academy GA-Pemathang
BSR
Items Specification Unit Quantity Remarks
Code
Hot dipped galvanized MS Railing: The steel connections shown are
The structural steel shall be Grade E250 (Fe410) as schematic only.
per IS 2062-2006. The weld metal shall be The fabricator shall prepare shop
EX4XXX, tensile strength range 410 - 530 MPa as drawings for all the connections.
per IS 814. The bolts shall be minimum grade/ The shop drawing shall be verified and
property class 4.6 as per IS 1367. approved by the Engineer, GI or
consultant.
Drawing reference: After the approval, the fabricator shall
GI-PT-Br2-Str-10 & GI-PT-Br2-Str-13 go ahead with the fabrication.
AR Steel Railings
Mild Steel (Grade 250) RHS tubes (127x50x3.6) kg 1479.46 16 Nos., 4.14 m 8 Nos., 9.299 m
Mild Steel Posts (955x200x20) kg 1439.38 48 Nos.
Mild Steel Posts Base plates (450x225x20) kg 381.51 24 Nos.
Bolts ( dia 16 mm, size 370 mm ) kg 59.64 96 Nos.
Nuts (inner dia 16 mm, size 24 mm) kg 1.97 96 Nos.
Note:
1. Drawing with dimensions of railllings & Drain Spouts is attached
2. The procurement to select the finishes, material strength, fixing mechanism and approve
3. The total quantities worked out are for Gyalsung Academy- Pemathang only
D2-2
D2
D2.1
D2-1
D2.1
DRAIN SPOUT
RESOURCE PLAN FOR KHOTOKA BRIDGE
Name of Bridge Chadrichu Bridge
Project Activity Code 4.5.1
Review Activity Railings & Drainage
Quantity reviewed for Gyalsung GA-Khotoka
Academy
BSR
Items Specification Unit Quantity Remarks
Code
Hot dipped galvanized MS Railing: The steel connections shown are schematic
The structural steel shall be Grade E250 (Fe410) as only.
per IS 2062-2006. The weld metal shall be The fabricator shall prepare shop drawings for
EX4XXX, tensile strength range 410 - 530 MPa as all the connections.
per IS 814. The bolts shall be minimum grade/ The shop drawing shall be verified and
property class 4.6 as per IS 1367. approved by the Engineer, GI or consultant.
After the approval, the fabricator shall go ahead
Drawing reference: with the fabrication.
AR Steel Railings GI-Kh-CB-SD05 & GI-Kh-CB-SD14
Mild Steel (Grade 250) RHS tubes (127x50x3.6) kg 1877.27 16 Nos., 3.440 m & 8 Nos., 15.756 m
Mild Steel Posts (955x200x20) kg 1799.22 60 Nos.
Mild Steel Posts Base plates (450x225x20) kg 476.89 30 Nos.
Bolts ( dia 16 mm, size 370 mm ) kg 74.54 120 Nos.
Nuts (inner dia 16 mm, size 24 mm) kg 2.46 120 Nos.
Note:
1. Drawing with dimensions of railllings & Drain Spouts is attached
2. The procurement to select the finishes, material strength, fixing mechanism and approve
3. The total quantities worked out are for Gyalsung Academy- Khotokha only
D2-2
D2
D2.1
D2-1
D2.1
DRAIN SPOUT
QUANTITY CALCULATION
Bridge Name: Bridge No. 02, Pemathang
Activity Code: 4.5.1/ Bridge 02/ GA- Pemathang/ Quantity Work out Page 15 of 32
QUANTITY CALCULATION
Bridge Name: Bridge No. 02, Pemathang
4. REINFORCEMENT
Providing and laying reinforcement bars High yield steel
deformed Reinforcing Bars Fe500 including bending,
binding, putting in position all complete.
4.1 Rebar for all components 1 22.70 22.70 ton
Total: 22.70 ton
5. MISCELLANEOUS WORKS
5.1 Stone Works
5.1.1 Stone soling for Bridge 1 14.31 12.37 0.20 35.40 CuM
Activity Code: 4.5.1/ Bridge 02/ GA- Pemathang/ Quantity Work out Page 16 of 32
QUANTITY CALCULATION
Bridge Name: Bridge No. 02, Pemathang
Activity Code: 4.5.1/ Bridge 02/ GA- Pemathang/ Quantity Work out Page 17 of 32
RESOURCE PLAN (MATERIALS)
Bridge Name: Bridge 02, Boulevard 3, GA Pemathang
Bridge type: Reinforced Concrete Box Frame
Code
Sl. Length Breadth Height Total
(LMC Iitem of work No. Unit Remarks
No. (m) (m) (m) Quantity
2021)
1 RAILINGS
Materal, fabrication , supply and
1.1 SW0110 installation of steel railings (grade E
250)
Stainless steel (Grade 250) RHS tubes
1.1.1 8 18.0 1479.4560 kg
(127x50x3.6)
2 REINFORCEMENT STEEL
2.1 RC0083 P&L Thermo Mechanically Treated (TMT) bars of Grade Fe 500:
2.1.1 8 mm dia 18.69 kg
2.2.2 12 mm dia 15909.48 kg
2.1.2 16 mm dia 5526.19 kg
2.2.3 20 mm dia 2377.08 kg
Activity Code:4.5.1/ Bridge 02/ GA- Pemathang/ Resource Plan (MMM) Page 1 of 32
ANALYSIS OF RATE
Bridge Name : Bridge 02
Location: Boulevard 03, GA Pemathang
Bridge Type: Reinforced Concrete Box Frame
GYALSUNG INFRA MARKET RATE BSR-2022
TOTAL
SL. CODE QUANTITY OF RESOURCE/ BSR WITH
ITEM DESCRIPTIONS UNIT UNIT RESOURCE BASIC ANALYSED BASIC ANALYSED
NO (LMC 2021) WORK UNIT WORK RATE COST
(IN NOS.) RATES RATE RATE RATE
INDEX
1000 EARTH WORK
1 EW0046 Earth work in excavation over areas by Excavator including levelling and dressing - All types of soils
LB0039 Work Supervisor (Lajab) 0.00253 day 0.65 700 1.77 700.00 1.77 632.50 1.60
256.93 Cum
MP0125 Excavator CAT 320 or equivalent 0.0035 day 0.90 13600 47.60 20,038.40 70.13 15,544.00 54.40
49.37 71.91 56.00
Add for tools & plants % 2% 0.99 1.44 1.12
Add for water charges % -
Add for over head charges % 6% 2.96 4.31 3.36
Add for OHS % 2% 0.99 1.44 1.12
cu.m Nu. 54.31 79.10 61.60
2 EW0047 Earth work in excavation over areas by Excavator including levelling and dressing - All types of rocks (blasted)
LB0039 Work Supervisor (Lajab) 0.00253 day 0.07 700 1.77 700.00 1.77 632.50 1.60
28.55 Cum
MP0125 Excavator CAT 320 or equivalent 0.0037 day 0.11 13600 50.32 20,038.40 74.14 15,544.00 57.51
52.09 75.91 59.11
Add for tools & plants % 2% 1.04 1.52 1.18
Add for water charges % -
Add for over head charges % 6% 3.13 4.55 3.55
Add for OHS % 2% 1.04 1.52 1.18
cu.m Nu. 57.30 83.50 65.02
2000 CONCRETEretaining
WORKSwalls,+FORM WORKS
return & REINFORCEMENT
walls, walls (any thickness) including attached
4 CW0024 pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string
or lacing
LB0036 Mason courses, parapets, coping, bedblocks, anchor blocks, plain
Gd.1 0.07011 day 3.06 700 49.08 700.00 49.08 632.50 44.34
LB0039 Work Supervisor (Lajab) 0.03895 day 1.70 700 27.27 700.00 27.27 632.50 24.64
LB0051 Mason Gd.2 0.07011 day 3.06 650 45.57 650.00 45.57 575.00 40.31
LB0053 Plant Operator Gd.3 0.05453 day 2.38 600 32.72 600.00 32.72 575.00 31.35
LB0077 Labour 2.08285 day 91.03 500 1,041.43 500.00 1,041.43 460.00 958.11
MP0111 Concrete Mixer(7/5 cu.ft) 43.70 Cum 0.07000 day 3.06 1891.2 132.38 1,891.20 132.38 1,832.00 128.24
MP0112 Concrete Vibrator(M/C5) 0.07000 day 3.06 1266.4 88.65 1,266.40 88.65 1,136.00 79.52
MT0043 Sand 0.48500 cu.m 21.20 1036.13 502.52 1,388.97 673.65 473.33 229.57
MT0070 Crushed Rock - 20 mm 0.72700 cu.m 31.77 1518.53 1,103.97 1,885.98 1,371.11 967.20 703.15
MT0071 Crushed Rock - 12.5 mm - 6 mm 0.24200 cu.m 10.58 1553.84 376.03 2,129.60 515.36 963.02 233.05
MT0145 Cement (OPC / PSC) 0.22000 tonne 9.61 7522.60 1,654.97 9,191.63 2,022.16 6,627.50 1,458.05
5,054.58 5,999.37 3,930.34
Add for tools & plants % 2% 101.09 119.99 78.61
Add for water charges % -
Add for over head charges % 6% 303.27 359.96 235.82
Add for OHS % 2% 101.09 119.99 78.61
cu.m Nu. 5,560.04 6,599.31 4,323.37
P&L in position reinforced cement concrete 1:1:2 ( 1 cement : 1 sand : 2 graded crushed rock 20 mm nominal size ) work in walls ( any thickness ) including attached pilasters buttresses, piers, abutments etc. upto floor five level
5 RC0005 excluding the cost of centering, shuttering and reinforcement.
LB0036 Mason Gd.1 0.05055 day 6.29 700 35.39 700.00 35.39 632.50 31.97
LB0039 Work Supervisor (Lajab) 0.05055 day 6.29 700 35.39 700.00 35.39 632.50 31.97
LB0051 Mason Gd.2 0.05055 day 6.29 650 32.86 650.00 32.86 575.00 29.07
LB0053 Plant Operator Gd.3 0.07077 day 8.80 600 42.46 600.00 42.46 575.00 40.69
LB0077 Labour 1.25625 day 156.28 500 628.13 500.00 628.13 460.00 577.88
MP0111 Concrete Mixer(7/5 cu.ft) 124.40 Cum. 0.07 day 8.71 1891.2 132.38 1,891.20 132.38 1,832.00 128.24
MP0112 Concrete Vibrator(M/C5) 0.07 day 8.71 1266.4 88.65 1,266.40 88.65 1,136.00 79.52
MT0043 Sand 0.45 cu.m 55.98 1036.13 466.26 1,388.97 625.04 473.33 213.00
MT0070 Crushed Rock - 20mm 0.675 cu.m 83.97 1518.53 1,025.01 1,885.98 1,273.04 967.20 652.86
MT0071 Crushed Rock - 12.5mm - 6 mm 0.225 cu.m 27.99 1553.84 349.61 2,129.60 479.16 963.02 216.68
MT0145 Cement (OPC / PSC) 0.61 tonne 75.88 7522.60 4,588.79 9,191.63 5,606.89 6,627.50 4,042.78
7,424.91 8,979.37 6,044.65
Add for tools & plants % 2% 148.50 179.59 120.89
Add for water charges % -
Add for over head charges % 6% 445.49 538.76 362.68
Add for OHS % 2% 148.50 179.59 120.89
cu.m Nu. 8,167.40 9,877.31 6,649.12
Activity Code: 4.5.1/ Bridge 02/ Rate Analysis/ GA- Pemathang Page 2 of 32
ANALYSIS OF RATE
Bridge Name : Bridge 02
Location: Boulevard 03, GA Pemathang
Bridge Type: Reinforced Concrete Box Frame
GYALSUNG INFRA MARKET RATE BSR-2022
TOTAL
SL. CODE QUANTITY OF RESOURCE/ BSR WITH
ITEM DESCRIPTIONS UNIT UNIT RESOURCE BASIC ANALYSED BASIC ANALYSED
NO (LMC 2021) WORK UNIT WORK RATE COST
(IN NOS.) RATES RATE RATE RATE
INDEX
P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20mm nominal size ) work in kerbs, steps and the like upto floor five level excluding the cost of centering, shuttering and reinforcement.
6 RC0020
LB0036 Mason Gd.1 0.07077 day 9.99 700 49.54 700.00 49.54 632.50 44.76
LB0039 Work Supervisor (Lajab) 0.07077 day 9.99 700 49.54 700.00 49.54 632.50 44.76
LB0051 Mason Gd.2 0.07077 day 9.99 650 46.00 650.00 46.00 575.00 40.69
LB0053 Plant Operator Gd.3 0.07077 day 9.99 600 42.46 600.00 42.46 575.00 40.69
LB0077 Labour 1.33125 day 187.99 500 665.63 500.00 665.63 460.00 612.38
MP0111 Concrete Mixer(7/5 cu.ft) 141.22 Cum 0.07 day 9.89 1891.2 132.38 1,891.20 132.38 1,832.00 128.24
MP0112 Concrete Vibrator(M/C5) 0.07 day 9.89 1266.4 88.65 1,266.40 88.65 1,136.00 79.52
MT0043 Sand 0.45 cu.m 63.55 1036.13 466.26 1,388.97 625.04 473.33 213.00
MT0070 Crushed Rock - 20mm 0.675 cu.m 95.32 1518.53 1,025.01 1,885.98 1,273.04 967.20 652.86
MT0071 Crushed Rock - 12.5mm - 6 mm 0.225 cu.m 31.77 1553.84 349.61 2,129.60 479.16 963.02 216.68
MT0145 Cement (OPC / PSC) 0.61 tonne 86.14 7522.60 4,588.79 9,191.63 5,606.89 6,627.50 4,042.78
7,503.86 9,058.32 6,116.36
Add for tools & plants % 2% 150.08 181.17 122.33
Add for water charges % -
Add for over head charges % 6% 450.23 543.50 366.98
Add for OHS % 2% 150.08 181.17 122.33
cu.m Nu. 8,254.25 9,964.16 6,727.99
P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nominal size ) work in suspended floor, roofs having slope up to 15 degree, landings, balconies, shelves and chajjas up to floor five
7 RC0013 level excluding the cost of centering, shuttering and reinforcement.
LB0036 Mason Gd.1 0.12638 day 5.47 700 88.47 700.00 88.47 632.50 79.94
LB0039 Work Supervisor (Lajab) 0.1011 day 4.38 700 70.77 700.00 70.77 632.50 63.95
LB0051 Mason Gd.2 0.12638 day 5.47 650 82.15 650.00 82.15 575.00 72.67
LB0053 Plant Operator Gd.3 0.07077 day 3.06 600 42.46 600.00 42.46 575.00 40.69
LB0077 Labour 1.4625 day 63.33 500 731.25 500.00 731.25 460.00 672.75
MP0111 Concrete Mixer(7/5 cu.ft) 43.30 Cum 0.07 day 3.03 1891.2 132.38 1,891.20 132.38 1,832.00 128.24
MP0112 Concrete Vibrator(M/C5) 0.07 day 3.03 1266.4 88.65 1,266.40 88.65 1,136.00 79.52
MT0043 Sand 0.45 cu.m 19.49 1036.13 466.26 1,388.97 625.04 473.33 213.00
MT0070 Crushed Rock - 20mm 0.675 cu.m 29.23 1518.53 1,025.01 1,885.98 1,273.04 967.20 652.86
MT0071 Crushed Rock - 12.5mm - 6 mm 0.225 cu.m 9.74 1553.84 349.61 2,129.60 479.16 963.02 216.68
MT0145 Cement (OPC / PSC) 0.61 tonne 26.41 7522.60 4,588.79 9,191.63 5,606.89 6,627.50 4,042.78
7,665.79 9,220.25 6,263.07
Add for tools & plants % 2% 153.32 184.41 125.26
Add for water charges % -
Add for over head charges % 6% 459.95 553.22 375.78
Add for OHS % 2% 153.32 184.41 125.26
cu.m Nu. 8,432.37 10,142.28 6,889.37
8 RC0090 Providing & fixing centering and shuttering (formwork) , Including strutting, propping etc. and removal of form work - Foundation and plinth etc.
LB0033 Carpenter Gd.2 0.11965 day 650 77.77 650.00 77.77 650.00 77.77
LB0077 Labour 0.10951 day 500 54.76 500.00 54.76 500.00 54.76
33.06 Sq m
MT0325 Ballies 75 to 125mm dia 0.42 m 30.43 12.78 30.43 12.78 30.43 12.78
MT0330 Rough-sawn timber (urban rate) - Class 'B' (conifer) 0.0135 cu.m 7416.07 100.12 12,194.30 164.62 12,973.87 175.15
245.43 309.93 320.46
Add for tools & plants % 2% 4.91 6.20 6.41
Add for water charges % -
Add for over head charges % 6% 14.73 18.60 19.23
Add for OHS % 2% 4.91 6.20 6.41
sq.m Nu. 269.97 340.92 352.50
9 RC0091 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of form work-Walls, pilasters, buttresses, string course etc.
LB0033 Carpenter Gd.2 0.62641 day 433.14 650 407.17 650.00 407.17 575.00 360.19
LB0077 Labour 0.25328 day 175.13 500 126.64 500.00 126.64 460.00 116.51
691.46 Sq m
MT0325 Ballies 75 to 125mm dia 0.91 m 629.23 30.43 27.69 30.43 27.69 30.43 27.69
MT0330 Rough-sawn timber (urban rate) - Class 'B' (conifer) 0.0144 cu.m 9.96 7416.07 106.79 12,194.30 175.60 12,973.87 186.82
0.00 668.29 737.10 691.21
Add for tools & plants % 0.00 2% 13.37 14.74 13.82
Add for water charges % 0.00 -
Add for over head charges % 0.00 6% 40.10 44.23 41.47
Add for OHS % 0.00 2% 13.37 14.74 13.82
sq.m 0.00 Nu. 735.12 810.81 760.33
10 RC0095 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of form work- Suspended floor, roof, landing, shelves and their supports, balconies, chajjas, etc.
LB0033 Carpenter Gd.2 0.42952 day 94.43 650 279.19 650.00 279.19 632.50 271.67
LB0077 Labour 0.39312 day 86.43 500 196.56 500.00 196.56 460.00 180.84
219.85 Sq m
MT0325 Ballies 75 to 125mm dia 2.075 m 456.18 30.43 63.14 30.43 63.14 30.43 63.14
MT0330 Rough-sawn timber (urban rate) - Class 'B' (conifer) 0.0168 cu.m 3.69 7416.07 124.59 12,194.30 204.86 12,973.87 217.96
663.48 743.75 733.61
Add for tools & plants % 2% 13.27 14.88 14.67
Add for water charges % -
Add for over head charges % 6% 39.81 44.63 44.02
Add for OHS % 2% 13.27 14.88 14.67
sq.m Nu. 729.83 818.13 806.97
Activity Code: 4.5.1/ Bridge 02/ Rate Analysis/ GA- Pemathang Page 3 of 32
ANALYSIS OF RATE
Bridge Name : Bridge 02
Location: Boulevard 03, GA Pemathang
Bridge Type: Reinforced Concrete Box Frame
GYALSUNG INFRA MARKET RATE BSR-2022
TOTAL
SL. CODE QUANTITY OF RESOURCE/ BSR WITH
ITEM DESCRIPTIONS UNIT UNIT RESOURCE BASIC ANALYSED BASIC ANALYSED
NO (LMC 2021) WORK UNIT WORK RATE COST
(IN NOS.) RATES RATE RATE RATE
INDEX
11 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 Mpa ) for R.C.C work including cutting, bending, binding and placing in position complete
LB0032 Blacksmith (metal-worker) 0.01142 day 0.26 700 7.99 700.00 7.99 632.50 7.22
LB0077 Labour 22.70 ton 0.01142 day 0.26 500 5.71 500.00 5.71 460.00 5.25
MT0208 Reinforcing Bars & Mesh - Thermo Mechanically Treated Bars (TMT bars 1.05 kg 23.84 70.94 74.49 74.74 78.48 51.29 53.85
8 mm dia 17.80 1.05 kg 18.69
12 mm dia 15151.89 1.05 kg 15909.48
16 mm dia 5263.04 1.05 kg 5526.19
20 mm dia 2263.88 1.05 kg 2377.08
0.00 88.19 92.18 66.33
Add for tools & plants % 0.00 2% 1.76 1.84 1.33
Add for water charges % 0.00 -
Add for over head charges % 0.00 6% 5.29 5.53 3.98
Add for OHS % 0.00 2% 1.76 1.84 1.33
kg 0.00 Nu. 97.01 101.40 72.96
1 ton 0.00 97,010.10 101,399.10 72,963.94
13 SM0005 P&L Random Rubble Masonry with hard stone in foundation & plinth - In cement mortar 1:4
LB0051 Mason Gd.2 0.6302 day 90.78 650 409.63 650.00 409.63 575.00 362.37
LB0077 Labour 3.10907 day 447.88 500 1,554.54 500.00 1,554.54 460.00 1,430.17
MT0043 Sand 144.06 Cu m 0.3531 cu.m 50.87 1036.13 365.86 1,388.97 490.45 473.33 167.13
MT0060 Boulder 1 cu.m 144.06 1046.02 1,046.02 1,440.02 1,440.02 861.81 861.81
MT0145 Cement (OPC / PSC) 0.1254 tonne 18.06 7522.60 943.33 9,191.63 1,152.63 6,627.50 831.09
4,319.38 5,047.26 3,652.57
Add for tools & plants % 2% 86.39 100.95 73.05
Add for water charges % -
Add for over head charges % 6% 259.16 302.84 219.15
Add for OHS % 2% 86.39 100.95 73.05
cu.m Nu. 4,751.31 5,551.99 4,017.83
14 SM0026 Providing &laying Coursed Rubble Masonry with hard stone hammer-dressed in foundation & plinth - In cement mortar 1:4
LB0051 Mason Gd.2 1.0362 day 0.00 650 673.53 650.00 673.53 575.00 595.82
LB0077 Labour 3.3137 day 0.00 500 1,656.85 500.00 1,656.85 460.00 1,524.30
MT0043 Sand Cu m 0.321 cu.m 0.00 1036.13 332.60 1,388.97 445.86 473.33 151.94
MT0060 Boulder 1.1 cu.m 0.00 1046.02 1,150.62 1,440.02 1,584.02 861.81 947.99
MT0145 Cement (OPC / PSC) 0.114 tonne 0.00 7522.60 857.58 9,191.63 1,047.85 6,627.50 755.54
4,671.17 5,408.11 3,975.58
Add for tools & plants % 2% 93.42 108.16 79.51
Add for water charges % -
Add for over head charges % 6% 280.27 324.49 238.53
Add for OHS % 2% 93.42 108.16 79.51
cu.m Nu. 5,138.29 5,948.92 4,373.14
16 PO0036 P&L H.D.P.E Pipes, PN 6, including H.D.P.E fittings (excluding trenching, refilling & thrust block) - 110mm
LB0038 Plumber Gd.1 0.03666 day 1.72 700 25.66 700.00 25.66 632.50 23.19
LB0077 Labour 46.80 Mtr 0.07582 day 3.55 500 37.91 500.00 37.91 460.00 34.88
MT0836 H.D.P.E Pipes of pressure class 6kg/sq.cm - 110mm 1m 46.80 309.12 309.12 386.40 386.40 386.40 386.40
Activity Code: 4.5.1/ Bridge 02/ Rate Analysis/ GA- Pemathang Page 4 of 32
ANALYSIS OF RATE
Bridge Name : Bridge 02
Location: Boulevard 03, GA Pemathang
Bridge Type: Reinforced Concrete Box Frame
GYALSUNG INFRA MARKET RATE BSR-2022
TOTAL
SL. CODE QUANTITY OF RESOURCE/ BSR WITH
ITEM DESCRIPTIONS UNIT UNIT RESOURCE BASIC ANALYSED BASIC ANALYSED
NO (LMC 2021) WORK UNIT WORK RATE COST
(IN NOS.) RATES RATE RATE RATE
INDEX
17 AR Providing and fixing stainless steel (Gradee 250) railing made of Hollow tubes,channels,platesetc…including welding, grinding, buffing, polishing and making curvature (wherever required ) and fittings the same with necessary
LB0032 stainless
Blacksmithsteel nuts and
(metal bolts complete, i/c fixing railing with necessary accessories and stainless steel dash fasteners,stainless
worker) 0.02301 day steel bolts etc, of required size
73.92 700on the top 16.11
of the floor or700.00
the side of waist 16.11
slab with suitable arrangement14.55
632.50 as
LB0077 per approval of engineers in charge.
Labour 0.00702 day 22.55 500 3.51 500.00 3.51 460.00 3.23
LB0039 Work supervisor 3,212.51 Kg 0.0767 day 246.40 700 53.69 700.00 53.69 632.50 48.51
MT0259 Stainless steel (Grade 250) Hollow section round/square tubes 1.1 kg 3533.76 84.15 92.57 92.97 102.27 52.39 57.63
MT0260 Stainless steel bolts/square bar and plates 1 kg 3212.51 75.15 75.15 83.07 83.07 57.38 57.38
RHS tubes (127x50x3.6) 1330.016 Kg 1.1 1463.02
Posts (955x200x20) 1439.38 Kg 1 1439.38
Base plates (450x225x20) 381.51 Kg 1 381.51
Bolts ( dia 16 mm, size 370 mm ) 59.64 Kg 1 59.64
Nuts (inner dia 16 mm, size 24 mm) 1.97 Kg 1 1.97
241.02 258.64 181.30
Add for tools & plants % 2% 4.82 5.17 3.63
Add for water charges % -
Add for over head charges % 6% 14.46 15.52 10.88
Add for OHS % 2% 4.82 5.17 3.63
kg Nu. 265.12 284.51 199.44
Providing and Laying Asphalt/Bituminous Concrete to required degree of compaction based on the job mixture design approved by the supervising engineer using asphaltplant, paver, steelroller, tyreroller etc. as per material
18 RW0143 gradation and aggregate quality specified : 50mm
LB0077 Labour 0.01001 day 1.348 500 5.01 500.00 5.01
MP0167 Tractor with trailer, Toyota 0.00007 Day 0.009 4957.67 0.35 5,063.54 0.35
MP0103 Asphalt/Bitumen Heating kettle, India make 0.00044 day 0.059 3300 1.45 3,300.00 1.45
MP0160 Spot Mix Plant, 10/16 TPH 0.00161 day 0.217 18,368 29.57 18,368.00 29.57
MP0102 Asphalt Paver 0.00014 day 0.019 8942.8 1.25 9,207.00 1.29
MP0151 Road Roller ( SV91, Sakai) 0.00045 day 0.061 11968.64 5.39 11,928.00 5.37
MP0150 Road Roller ( Pneumatic tyre), TS - 300 134.64 Sq m 0.00045 day 0.061 11,366.68 5.12 11,881.00 5.35
MP0145 Pay Loader ( CAT or Equivalent) 0.00091 day 0.123 10591.6 9.64 11,032.00 10.04
MP0165 TATA tipper 1612SE 0.0018 day 0.242 11500 20.70 14,984.00 26.97
MP0110 Compactor, plate type 0.0033 day 0.444 1575.19 5.20 1,638.00 5.41
MT0001 Bitumen VG - 10 0.00746 MT 1.004 42,027.19 313.52 42,027.19 313.52
MT0071 Crushed rock , 12.5 mm to 6mm ( preferably 10 mm) 0.02604 cu.m 3.506 1553.84 40.46 2,176.45 56.67
MT0043 sand 0.02604 cu.m 3.506 1036.13 26.98 1,442.51 37.56
0.000 464.63 498.56
Add for tools & plants % 0.000 2% 9.29 9.97
Add for water charges % 0.000 -
Add for over head charges % 0.000 6% 27.88 29.91
Add for OHS % 0.000 2% 9.29 9.97
sq.m 0.000 Nu. 511.09 548.42 599.75 758.08
Activity Code: 4.5.1/ Bridge 02/ Rate Analysis/ GA- Pemathang Page 5 of 32
RESOURCE PLAN (MEN, MATERIALS & MACHINERIES)
Bridge Name: Bridge 02, Boulevard 3, GA Pemathang
Bridge type: Reinforced Concrete Box Frame
Reinforcing Bars (TMT bars) Rough-sawn
Stainless steel Stainless steel H.D.P.E Pipes Crushed
Stainless steel Bolts ( dia 16 Nuts (inner Crushed Ballies 75 timber
Code (Grade 250) Posts Base Drainage of pressure Rock - 12.5 Cement Bitumen
Sl. Quantity of RHS tubes Posts mm, size 370 dia 16 mm, Boulder Rock - 20 Sand to 125mm (urban rate)
(LMC Description of item Unit plates Spouts class 6kg/sq.cm mm - 6 (OPC / PSC) VG - 10
No work (955x200x20) mm ) size 24 mm) (8 mm) (12 mm) (16 mm) (20 mm) mm dia - Class 'B'
2021) (127x50x3.6) (450x225x20) - 110mm mm
(conifer)
( in kg) ( in kg) ( in kg) ( in kg) ( in kg) ( in kg) ( in Nos.) ( in m) ( in cu m) ( in cu m) ( in cu m) ( in cu m) ( in MT) ( in MT) (in m) (in cu m)
1 EARTH WORK
1.1 EW0046 Structure excavation - Hard soil m3 256.93
1.2 Structure excavation - Ordinary rock m3 28.55
EW0047
Backfilling for bridge (qty. for till
1.3 EW0195 the end of approach slab) + River m3 657.63
Training (RT) Wall
Total for Earth Works:
2 CONCRETE WORKS
Providing & laying lean concrete
2.1 CW0024 m3 43.70 31.7720 10.5761 21.1959 9.6146
M10
Activity Code:4.5.1/ Bridge 02/ GA- Pemathang/ Resource Plan (MMM) Page 1 of 32
RESOURCE PLAN (MEN, MATERIALS & MACHINERIES)
Bridge Name: Bridge 02, Boulevard 3, GA Pemathang
Bridge type: Reinforced Concrete Box Frame
Asphalt/
Tractor Spot Mix Road Road Roller (
Work Plant Blacksmith Excavator Concrete Concrete Bitumen Pay Loader TATA
Code Plumber Mason Mason Carpenter with Plant, Asphalt Roller ( Pneumatic
Sl. Quantity of Supervisor Operator Labour (metal- CAT 320 or Mixer (7/5 Vibrator Heating ( CAT or tipper
(LMC Description of item Unit Gd.1 Gd 1 Gd 2 Gd.2 trailer, 10/16 Paver SV91, tyre), TS -
No work (Lajab) Gd.3 worker) equivalent cu.ft) (M/C5) kettle, India Equivalent) 1612SE
2021) Toyota TPH Sakai) 300
make
(in
(in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.) (in Nos.)
Nos.)
1 EARTH WORK
1.1 EW0046 Structure excavation - Hard soil m3 256.93 0.6500 0.8992
1.2 Structure excavation - Ordinary rock m3 28.55 0.0722 0.1056
EW0047
Backfilling for bridge (qty. for till
1.3 EW0195 the end of approach slab) + River m3 657.63 136.4196
Training (RT) Wall
Total for Earth Works: 0.72 136.42 1.00
2 CONCRETE WORKS
Providing & laying lean concrete
2.1 CW0024 m3 43.70
M10
Activity Code:4.5.1/ Bridge 02/ GA- Pemathang/ Resource Plan (MMM) Page 2 of 32
RESOURCE PLAN (MEN, MATERIALS & MACHINERIES)
Bridge Name: Bridge 02, Boulevard 3, GA Pemathang
Bridge type: Reinforced Concrete Box Frame
Code Compactor,
Sl. Quantity of plate type
No
(LMC Description of item Unit
work
2021)
(in Nos.)
1 EARTH WORK
1.1 EW0046 Structure excavation - Hard soil m3 256.93
1.2 Structure excavation - Ordinary rock m3 28.55
EW0047
Backfilling for bridge (qty. for till
1.3 EW0195 the end of approach slab) + River m3 657.63
Training (RT) Wall
Total for Earth Works:
2 CONCRETE WORKS
Providing & laying lean concrete
2.1 CW0024 m3 43.70
M10
Activity Code:4.5.1/ Bridge 02/ GA- Pemathang/ Resource Plan (MMM) Page 3 of 32
CATEGORY-INFRASTRUCTURE & SERVICES
BRIDGE 02
COST ESTIMATE
GYALSUNG INFRA
DECEMBER 2022
BILL OF QUANTITIES (BoQ)
Bridge Name: Bridge 02, Boulevard 3, GA Pemathang
Bridge type: Reinforced Concrete Box Frame
Rate Amount
Sl.No Code Description of item Unit Quantity
(Nu) (Nu)
1000 EARTHWORK
The quantities for earthwork are calculated
as "Solid Volume"
1 1001 Structure excavation - Hard soil m3 256.93 54.31 13,953.18
2 1002 Structure excavation - Ordinary rock m3 28.55 57.30 1,635.77
3 1003 Backfilling for bridge (qty. for till the end of
approach slab) + River Training (RT) Wall m3 657.63 114.09 75,030.80
1000 EARTHWORK
2000 CONCRETE WORKS + FORMWORK + REBAR
Providing & laying lean concrete M10 for bridge
4 CW0024 foundations, RT wall and underneath of approach m3 43.70
slabs.
Rate Amount
Sl.No Code Description of item Unit Quantity
(Nu) (Nu)
1000 EARTHWORK
The quantities for earthwork are calculated
as "Solid Volume"
1 1001 Structure excavation - Hard soil m3 1,091.41 54.31 59,272.51
2 1002 Structure excavation - Ordinary rock m3 272.85 57.30 15,634.50
3 1003 Backfilling m3 1,947.86 114.09 222,235.24
Total for Earth Works: 297,142.26
2000 CONCRETE WORKS + FORMWORK + REBAR
4 2001 Providing & laying lean concrete M10 for m3 16.83 5,560.04 93,588.01
Abutment foundations, underneath of approach
slabs.
5 2002 Prviding and laying M25 grade concrete for:
2002.1 Components of the abutments - footing slab, m3 239.50 8,167.40 1,956,123.28
stem/front wall, return walls.
2002.2 Deck/top slab and kerks m3 168.61 8,254.25 1,391,715.95
2002.3 Approach slabs m3 22.05 8,432.37 185,933.80
6 2003 Providing and fixing formwork for:
2003.1 Abutment Footing slabs m2 58.00 269.97 15,658.12
2003.2 Abutment Wall and components m2 524.14 735.12 385,307.76
2003.3 Deck Slab m2 168.11 729.83 122,687.78
2003.4 kerbs m2 43.36 269.97 11,706.33
7 2004 Providing and laying Thermo Mechanically
Treated (TMT) bars of Grade Fe 500:
8 2004.1 Substructure + approach slab tons 16.80 97,010.10 1,629,769.68
9 2004.2 Deck + kerb tons 15.07 97,010.10 1,461,942.21
Total for Concrete+Formwork+Rebar: 7,254,432.91
11 3002 Levelling concrete, Grade M10 for bank m3 17.45 5,560.04 97,015.78
protection works
12 3003 Providing and laying Random Rubble Masonry m3 508.20 4,751.31 2,414,617.08
with CM 1:4 for river bank protection wall
13 3004 Providing and laying Coursed Rubble Masonry m3 74.76 5,138.29 384,138.71
with CM 1:4 for river bank protection wall
14 3004 Providing and laying Boulder Walls for bank m3 958.50 4,751.31 4,554,133.16
protection as per the details shown in the relevant
drawings.
15 3005 Material, fabrication and installation of drainage
spouts for:
3005.1 Type 1; drain pipep length = 865mm pcs 4.00 3,185.75 12,743.02
3005.2 Type 1; drain pipep length = 570mm pcs 2.00 3,185.75 6,371.51
Page 1 of 32
KHOTOKHA CHADRICHU BRIDGE
BILL OF QUANTITIES (BoQ)
Bridge Name: Chadrichu Bridge, GA Khotokha
Bridge type: Reinforced Concrete Rigid Frame
Rate Amount
Sl.No Code Description of item Unit Quantity
(Nu) (Nu)
16 3006 Providing and laying 110mm diameter HDPE m3
pipe as weep holes for:
3005.1 For abutments - Length = 950 mm m 20.90 409.96 8,568.19
3005.2 For bank protection walls - Length= 1560mm m 346.32 409.96 141,977.76
17 3007 Materal, fabrication , supply and installation of m 45.60 265.12 12,089.66
steel railings as per the details shown in the
drawings
18 3008 Ashphat Wearing Course 50mm thick on the m2 192.45 511.09 98,360.19
bridge deck and the approach slabs.
Total for Miscellaneous Works: 7,809,583.73