This document shows the percentage of completion and gross profit calculations for a construction project over three years from 2006 to 2008. The percentage of completion increased each year from 11.11% in 2006 to 50% in 2007 and 83.33% in 2008. The gross profit earned also increased each year, with P666,600 earned in 2006, P1,333,400 earned in 2007, and P500,000 earned in 2008.
This document shows the percentage of completion and gross profit calculations for a construction project over three years from 2006 to 2008. The percentage of completion increased each year from 11.11% in 2006 to 50% in 2007 and 83.33% in 2008. The gross profit earned also increased each year, with P666,600 earned in 2006, P1,333,400 earned in 2007, and P500,000 earned in 2008.
This document shows the percentage of completion and gross profit calculations for a construction project over three years from 2006 to 2008. The percentage of completion increased each year from 11.11% in 2006 to 50% in 2007 and 83.33% in 2008. The gross profit earned also increased each year, with P666,600 earned in 2006, P1,333,400 earned in 2007, and P500,000 earned in 2008.
Cost incurred to date P 1,000,000 P 5,500,000 P10,000,000
Divide by total estimated cost to complete P 9,000,000 P11,000,000 _12,000,000 Percentage of Completion 11.11% 50% 83.33%
2006 2007 2008
(b) Contract Price P15,000,000 P15,000,000 P15,000,000 Less: Total Estimated Cost to complete Cost incurred to date 1,000,000 5,500,000 10,000,000 Estimated costs to complete __8,000,000 __5,500,000 __2,000,000 Total __9,000,000 _11,000,000 _12,000,000 Estimated gross profit 6,000,000 4,000,000 3,000,000 Percentage of completion ___11.11% ______50% ___83.33% Gross profit earned to date 666,600 2000,000 9,500,000 Less: Gross profit earned in previous years ________– ___666,600 _2,000,000 Gross profit earned this year P 666,600 P 1,333,400 P 500,000