(a) 2006 2007 2008

Cost incurred to date P 1,000,000 P  5,500,000 P10,000,000


Divide by total estimated cost to complete P 9,000,000 P11,000,000 _12,000,000
Percentage of Completion 11.11% 50% 83.33%

2006 2007 2008


(b) Contract Price P15,000,000 P15,000,000 P15,000,000
Less: Total Estimated Cost to complete
Cost incurred to date 1,000,000 5,500,000 10,000,000
Estimated costs to complete __8,000,000 __5,500,000 __2,000,000
Total __9,000,000 _11,000,000 _12,000,000
Estimated gross profit 6,000,000 4,000,000 3,000,000
Percentage of completion ___11.11% ______50% ___83.33%
Gross profit earned to date 666,600 2000,000 9,500,000
Less: Gross profit earned in previous years ________– ___666,600 _2,000,000
Gross profit earned this year P   666,600 P  1,333,400 P   500,000