This document shows the contract price and estimated costs to complete a construction project over three years from 2006 to 2008. It calculates the estimated gross profit or loss for each year. In 2008, when the project was completed, it had an estimated gross loss of 600,000 pesos for that final year.
This document shows the contract price and estimated costs to complete a construction project over three years from 2006 to 2008. It calculates the estimated gross profit or loss for each year. In 2008, when the project was completed, it had an estimated gross loss of 600,000 pesos for that final year.
This document shows the contract price and estimated costs to complete a construction project over three years from 2006 to 2008. It calculates the estimated gross profit or loss for each year. In 2008, when the project was completed, it had an estimated gross loss of 600,000 pesos for that final year.
Contract Price of the construction P6,500,000 P6,500,000 P6,500,000 Less:Total Estimated Costs to complete Cost incurred to date 2,150,000 5,250,000 6,850,000 Estimated costs to complete _3,850,000 _1,500,000 ________– Total _6,000,000 _6,750,000 _6,850,000 Estimated gross profit (loss) 500,000 (250,000) (350,000) Less: Gross profit (loss) in prior yrs. ________– ___520,000 _(250,000) Gross profit (loss) this years P 520,000 P( 250,000) P( 600,000)
(2) In the year 2008 that is when the project is completed.