LIFTING OPERATIONS PLAN

‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Location: Area:
A/Q Petroleum Company A/Q - Maadia Yard
‫ﺍﻟﻣﻧﻁﻘﺔ‬ ‫ﺍﻟﻣﻭﻗﻊ‬

Lifting Plan No: Category of Lift:


LP002 Complex
‫ﺭﻗﻡ ﺧﻁﺔ ﺍﻟﺭﻓﻊ‬ ‫ﺗﺻﻧﻳﻑ ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬

Drawings reference: Risk Assessment No:


AS ATTACHED
‫ﺭﻗﻡ ﺍﻟﺭﺳﻡ‬ ‫ﺭﻗﻡ ﺗﻘﻳﻳﻡ ﺍﻟﻣﺧﺎﻁﺭ‬

Description of lifting operation ‫ﻭﺻﻑ ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬

TRANSFERING ENGINE (Z1), (Z2), (Z3) ,(Z4) TO LANDING AREA THEN, LOADING FROM GROUND TO TRUCK AND VICE VERSA

‫( ﺍﻟﻲ ﻣﻛﺎﻥ ﺍﻟﺗﺣﻣﻳﻝ ﺛﻡ ﺍﻟﺗﺣﻣﻳﻝ ﻣﻥ ﺍﻻﺭﺽ ﺍﻟﻲ ﺍﻟﻛﻧﻭﺭ ﻭ ﺍﻟﻌﻛﺱ‬Z1), (Z2), (Z3) ,(Z4) ‫ﻧﻘﻝ ﺍﻟﻣﺣﺭﻙ‬

Description of Load ‫ﻭﺻﻑ ﺍﻟﺣﻣﻭﻟﺔ‬

Weight (kg): 13 TE (ESTIMATED) Dimensions:


3.6 m (L) X 2 m (W) X 2 m (H)
‫ﺍﻟﻭﺯﻥ‬ ‫ ﻁﻥ‬13 ‫)ﺗﻘﺩﻳﺭﻱ( ﺍﻟﻭﺯﻥ‬ ‫ﺍﻷﺑﻌﺎﺩ‬
Shape: Symmetric Position of C.G:
At load centre ‫ﻓﻰ ﻣﻧﺗﺻﻑ ﺍﻟﺣﻣﻝ‬
‫ﺍﻟﺷﻛﻝ‬ ‫ﻣﺗﻣﺎﺛﻝ‬ ‫ﺇﺣﺩﺍﺛﻳﺎﺕ ﻣﺭﻛﺯ ﺍﻟﺛﻘﻝ‬/‫ﻣﻭﻗﻊ‬
Type/Position of Lifting Points:
Lifting by 4 lifting point as per drawing ‫ﺍﻟﺭﻓﻊ ﺑﺈﺳﺗﺧﺩﺍﻡ ﻁﺭﻳﻘﺔ ﺍﺭﺑﻊ ﻧﻘﻁ ﺭﻓﻊ ﻛﻣﺎ ﺑﺎﻟﺭﺳﻡ‬
‫ﻧﻭﻉ ﻭﻣﻛﺎﻥ ﻧﻘﻁ ﺍﻟﺭﻓﻊ ﺍﻟﻣﻭﺟﻭﺩﻩ ﻋﻠﻰ ﺍﻟﺣﻣﻝ‬
Lifting Equipment and Accessories Details ‫ﺗﻔﺎﺻﻳﻝ ﻣﻌﺩﺍﺕ ﻭﺃﺩﻭﺍﺕ ﺍﻟﺭﻓﻊ ﺍﻟﻣﻁﻠﻭﺑﺔ‬

Type: 80 Ton Mobile Crane Max. Required Raduis:


10 m
‫ﺍﻟﻧﻭﻉ‬ ‫ﻭﻧﺵ ﻣﺗﺣﺭﻙ‬ ‫ﺃﻗﺻﻰ ﻧﺻﻑ ﻗﻁﺭ ﻣﻁﻠﻭﺏ‬

ID / Model: SWL at Max. Required Raduis:


Crane Specs 18.6 ton
‫ ﺍﻟﻣﻭﺩﻳﻝ‬/ ‫ﺍﻟﺭﻗﻡ ﺍﻟﻛﻭﺩﻱ‬ ‫ﺍﻟﺣﻣﻭﻟﺔ ﺍﻷﻣﻧﺔ ﻋﻧﺩ ﺃﻗﺻﻰ ﻧﺻﻑ ﻗﻁﺭ ﻣﻁﻠﻭﺏ‬
‫ﻣﻭﺍﺻﻔﺎﺕ ﺍﻟﻭﻧﺵ‬
Boom Length: Maximum Height of Lift:
‫ﻁﻭﻝ ﺍﻟﺑﻭﻣﺔ‬ ‫ﺃﻗﺻﻰ ﺍﺭﺗﻔﺎﻉ ﻳﻣﻛﻥ ﺭﻓﻊ ﺍﻟﺣﻣﻭﻟﻪ ﺍﻟﻳﻪ‬
Others:
Required crane capacity is 17 ton at point of lift.
‫ﻣﻭﺍﺻﻔﺎﺕ ﺃﺧﺭﻯ‬

Note: All lifting gears shall be color coded by the current color code ‫ﺍﻟﻛﻠﺭ ﺍﻟﻛﻭﺩﻯ ﺍﻟﺣﺎﻟﻰ‬/‫ ﻳﺟﺏ ﺃﻥ ﺗﻛﻭﻥ ﺟﻣﻳﻊ ﺃﺩﻭﺍﺕ ﺍﻟﺭﻓﻊ ﺍﻟﻣﺳﺗﺧﺩﻣﻪ ﻋﻠﻳﻬﺎ ﺍﻟﻠﻭﻥ‬:‫ﻣﻠﺣﻭﻅﺔ‬

Item Description ‫ﺍﻟﻭﺻﻑ‬ SWL ‫ﺍﻟﺣﻣﻭﻟﺔ ﺍﻷﻣﻧﺔ‬ Length ‫ﺍﻟﻁﻭﻝ‬ QTY ‫ﺍﻟﻛﻣﻳﺔ‬ Others ‫ﻣﻭﺍﺻﻔﺎﺕ ﺃﺧﺭﻯ‬
To be tested before
1 Anchor Point (For skidding operation) 10 ton 1
used
Or other cover the
2 Mobile Crane 80 ton 1 required SWL at
required raduis

Will be certified and


3 Two leg wire rope sling 14 ton 2m 1
color coded

Will be certified and


4 single leg wire rope sling 5 ton 2m 4
color coded

Will be certified and


5 Safety pin bow shackle 9.5 ton 8
color coded

Will be certified and


6 Safety pin bow shackle 4.75 ton 4
color coded

Will be certified and


7 Lifting Beam 14 ton 2mtr 8
color coded

Will be certified and


8 Lever hoist 3 ton 6 mtr 2
color coded
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

All used to be
inspected and
9 Pad eye / Fork lift counter weight 4.75 ton as needed certified or using
forklift counter weight
as anchored point.

10 Tag Line ‫ﺣﺑﻝ ﺗﻭﺟﻳﻪ‬ 10 mtr 2

Enviroment / Weather Limitations ‫ﺣﺩﻭﺩ ﺍﻟﻁﻘﺱ ﻭﺍﻟﻅﺭﻭﻑ ﺍﻟﺑﻳﺋﻳﺔ‬


Max. Wind Speed (Knots): Max. Wave Height: Sea State:
25 Knots N/A N/A
‫ﺳﺭﻋﺔ ﺍﻟﺭﻳﺎﺡ ﺍﻟﻘﺻﻭﻯ‬ ‫ﺃﻗﺻﻰ ﺍﺭﺗﻔﺎﻉ ﻟﻠﻣﻭﺝ‬ ‫ﺣﺎﻟﺔ ﺍﻟﺑﺣﺭ‬

Lifting Operation Required Crew/Personnel ‫ﺍﻷﻓﺭﺍﺩ ﺍﻟﻣﻁﻠﻭﺑﺔ ﻟﺗﻧﻔﻳﺫ ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬/‫ﺍﻟﻁﺎﻗﻡ‬


Title/Position QTY Title/Position QTY Title/Position QTY
‫ﺍﻟﻣﺳﻣﻲ‬/‫ﺍﻟﻭﻅﻳﻔﺔ‬ ‫ﺍﻟﻌﺩﺩ‬ ‫ﺍﻟﻣﺳﻣﻲ‬/‫ﺍﻟﻭﻅﻳﻔﺔ‬ ‫ﺍﻟﻌﺩﺩ‬ ‫ﺍﻟﻣﺳﻣﻲ‬/‫ﺍﻟﻭﻅﻳﻔﺔ‬ ‫ﺍﻟﻌﺩﺩ‬
Lifting Supervisor Banks Man Plant Operator (Crane,.etc)
1 1 2
‫ﻣﺷﺭﻑ ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬ ‫ﺭﺟﻝ ﺍﻹﺷﺎﺭﺓ‬ (‫ﻣﺷﻐﻝ ﺍﻟﻣﻌﺩﺓ )ﻣﺛﻝ ﺍﻟﻭﻧﺎﺵ‬

Technicians 4 Rope access N/A Divers N/A

Rigger & Slinger Area Authority


4 1 HSE / Safety Supervisor 1
‫ﺍﻟﺑﺣﺭﻱ‬ ‫ﻣﺳﺋﻭﻝ ﺍﻟﻣﻧﻁﻘﺔ‬

Others: 1- Technicians and Rigger will be suplied from SQUARE company side.
‫ﻣﻭﺍﺻﻔﺎﺕ ﺃﺧﺭﻯ‬ 2- One Banks Man needed to signal to the crane at each location.

Possible safety measures to be considered for all lifting operations (put Yes for the selected one)
‫ ﺿﻊ ﻧﻌﻡ ﻋﻧﺩ ﺍﻟﻧﻘﻁ ﺍﻟﻣﺧﺗﺎﺭﺓ‬- ‫ﻭﺳﺎﺋﻝ ﻭﺗﺩﺍﺑﻳﺭ ﺍﻟﺳﻼﻣﺔ ﺍﻟﻣﻣﻛﻧﺔ ﻟﻌﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬
Weight not verified Lifting equipment/accessories certificates
Yes Yes
‫ﺍﻟﺗﺣﻘﻖ ﻣﻥ ﻭﺯﻥ ﺍﻟﺣﻣﻝ‬ ‫ﻣﻌﺩﺍﺕ ﻭﺃﺩﻭﺍﺕ ﺍﻟﺭﻓﻊ ﻣﻌﺗﻣﺩﺓ ﻭﻟﻬﺎ ﺷﻬﺎﺩﺓ‬
Stability of load Stability of lifting equipment
Yes Yes
‫ﺍﺳﺗﻘﺭﺍﺭ ﻭﺛﺑﺎﺕ ﺍﻟﺣﻣﻝ‬ ‫ﺍﺳﺗﻘﺭﺍﺭ ﻭﺛﺑﺎﺕ ﻣﻌﺩﺓ ﺍﻟﺭﻓﻊ‬
High centre of gravity Pre-use equipment checks
No Yes
‫ﻣﺭﻛﺯ ﺍﻟﺛﻘﻝ ﻟﻠﺣﻣﻝ ﻣﺭﺗﻔﻊ‬ ‫ﻓﺣﺹ ﺍﻟﻣﻌﺩﺍﺕ ﻗﺑﻝ ﺍﻻﺳﺗﺧﺩﺍﻡ‬
Awkward size/shape/sharp edges Environment: visibility/wind speed/wave height/tide
No Yes
‫ﻭﺟﻭﺩ ﺣﻭﺍﻑ ﺣﺎﺩﺓ‬/‫ﻋﺩﻡ ﻣﻼﺋﻣﺔ ﻭﺧﻁﻭﺭﺓ ﺣﺟﻡ ﻭﺷﻛﻝ ﺍﻟﺣﻣﻝ‬ ‫ﺍﻟﻅﺭﻭﻑ ﺍﻟﺑﻳﺋﻳﺔ ﻣﺛﻝ ﺍﻟﺭﺅﻳﺔ ﻭﺳﺭﻋﺔ ﺍﻟﺭﻳﺎﺡ ﻭﺍﺭﺗﻔﺎﻉ ﺍﻟﻣﻭﺝ ﻭﺍﻟﻣﺩ ﻭﺍﻟﺟﺯﺭ‬
No dedicated lift points Vessel stability
No N/A
‫ﻋﺩﻡ ﻭﺟﻭﺩ ﻧﻘﻁ ﺭﻓﻊ ﻣﺣﺩﺩﻩ ﻟﻠﺭﻓﻊ ﻣﻧﻬﺎ‬ ‫ﺍﺍﻟﺑﻭﺕ‬/‫ﺍﺳﺗﻘﺭﺍﺭ ﻭﺛﺑﺎﺕ ﺍﻟﻣﺭﻛﺏ‬
No certified suspension points for lifting equipment Load visibility during night/subsea working
Yes Yes
‫ﻟﻬﺎ ﺷﻬﺎﺩﺓ ﻟﺗﻌﻠﻳﻖ ﻣﻌﺩﺓ ﺍﻟﺭﻓﻊ ﻋﻠﻳﻬﺎ‬/‫ﻋﺩﻡ ﻭﺟﻭﺩ ﻧﻘﻁ ﺗﻌﻠﻳﻖ ﻣﻌﺗﻣﺩﺓ‬ ‫ﺭﺅﻳﺔ ﺍﻟﺣﻣﻝ ﺍﺛﻧﺎء ﺍﻟﻌﻣﻝ ﺑﺎﻟﻠﻳﻝ ﻭﺍﻟﻌﻣﻝ ﺃﺳﻔﻝ ﺳﻁﺢ ﺍﻟﺑﺣﺭ‬
Loose objects removed from load Lifting over live plant/equipment/assets
Yes N/A
‫ﺇﺯﺍﻟﺔ ﺍﻷﺷﻳﺎء ﺍﻟﺣﺭﻩ ﺍﻟﻐﻳﺭ ﻣﺛﺑﺗﻪ ﺑﺎﻟﺣﻣﻝ‬ ‫ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ ﻓﻭﻕ ﺧﻁﻭﻁ ﻭﻣﻌﺩﺍﺕ ﺣﻳﺔ ﻣﺛﻝ ﺧﻁ ﻳﻣﺭ ﺑﻪ ﻏﺎﺯ‬
Load on pallet requires securing Lay-down area size/strength/stability
N/A Yes
‫ﺗﺛﺑﻳﺕ ﺍﻷﺣﻣﺎﻝ ﺍﻟﻣﻭﺟﻭﺩﻩ ﻋﻠﻰ ﺍﻟﻁﺑﺎﻟﻰ‬ ‫ﺣﺟﻡ ﻭﻣﺗﺎﻧﺔ ﻭﺍﺳﺗﻘﺭﺍﺭ ﺍﻟﻣﻛﺎﻥ ﺍﻟﺫﻱ ﺳﻳﻭﺿﻊ ﻋﻠﻳﻪ ﺍﻟﺣﻣﻝ‬
Experience,Competence and Training of personal Route and lay-down area clear
Yes Yes
‫ﺧﺑﺭﺓ ﻭﻛﻔﺎءﺓ ﻭﺗﺩﺭﻳﺏ ﺍﻷﻓﺭﺍﺩ‬ ‫ﻭﺿﻭﺡ ﺍﻟﻁﺭﻳﻖ ﺍﻟﺫﻯ ﺳﺗﻣﺭ ﻣﻧﻪ ﺍﻟﺣﻣﻭﻟﻪ ﻭﻛﺫﻟﻙ ﻣﻭﺿﻊ ﺗﻧﺯﻳﻝ ﺍﻟﺣﻣﻭﻟﻪ‬
Blind lifting Route and lay-down area obstructed
No Yes
‫ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ ﻓﻲ ﺣﺎﻟﺔ ﻭﺟﻭﺩ ﺳﺎﺗﺭ ﻳﻣﻧﻊ ﺍﻟﺭﺅﻳﺔ‬ ‫ﻋﺩﻡ ﻭﺟﻭﺩ ﻣﻌﻭﻗﺎﺕ ﻓﻲ ﻁﺭﻳﻖ ﺍﻟﺣﻣﻭﻟﺔ ﻭﻛﺫﻟﻙ ﻣﻭﺿﻊ ﺗﻧﺯﻳﻠﻬﺎ‬
Lifting of chemicals load within crane capacity as per load chart
No Yes
‫ﺍﻟﺧﻁﺭﺓ‬/‫ﺭﻓﻊ ﺍﻟﻣﻭﺍﺩ ﺍﻟﻛﻳﻣﻳﺎﺋﻳﺔ‬ ‫ﻭﺯﻥ ﺍﻟﺣﻣﻝ ﻓﻲ ﺣﺩﻭﺩ ﻭﺍﻣﻛﺎﻧﻳﺎﺕ ﺍﻟﻭﻧﺵ ﺃﻭ ﻣﻌﺩﺓ ﺍﻟﺭﻓﻊ‬
Access and egress for slinging Conflicting operations
Yes No
‫ﻭﺟﻭﺩ ﻣﺩﺧﻝ ﻭﻣﺧﺭﺝ ﻟﻠﺑﺣﺭﻱ ﻟﺗﺻﺑﻳﻥ ﺍﻟﺣﻣﻭﻟﺔ‬ ‫ﻭﺟﻭﺩ ﺃﻋﻣﺎﻝ ﻣﺗﺯﺍﻣﻧﺔ ﻭﻣﺗﻌﺎﺭﺿﺔ ﻣﻊ ﺑﻌﺿﻬﺎ‬
No lift point directly above load Cultural, communication, language issues
N/A Yes
‫ﻋﺩﻡ ﻭﺟﻭﺩ ﻧﻘﻁﺔ ﺭﻓﻊ ﻓﻭﻕ ﺍﻟﺣﻣﻝ ﻣﺑﺎﺷﺭﺓ‬ ‫ﺍﻟﺛﻘﺎﻓﺔ ﻭﺍﻟﺗﻭﺍﺻﻝ ﻭﺍﻟﻠﻐﺔ‬
Accessories/equipment fit for purpose/SWL Diving operations – precautions
Yes No
‫ﻣﻌﺩﺍﺕ ﻭﺃﺩﻭﺍﺕ ﺍﻟﺭﻓﻊ ﻣﻧﺎﺳﺑﺔ ﻟﻠﻐﺭﺽ ﻭﻟﻠﺣﻣﻭﻟﺔ‬ ‫ﺍﺣﺗﻳﺎﻁﺎﺕ ﻋﻣﻠﻳﺎﺕ ﺍﻟﻐﻁﺱ‬
Working under suspended load Underground services / Excavations
No No
‫ﺍﻟﻌﻣﻝ ﺃﺳﻔﻝ ﺃﺣﻣﺎﻝ ﻣﻌﻠﻘﺔ‬ ‫ﻭﺟﻭﺩ ﺧﺩﻣﺎﺕ ﻭﺧﻁﻭﻁ ﺗﺣﺕ ﺍﻷﺭﺽ ﺃﻭ ﺃﻋﻣﺎﻝ ﺣﻔﺭ‬
Others: NEVER SET UP THE CRANE BESIDE SLOPE
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

‫ﺃﺧﺭﻯ‬ ‫ﻣﻣﻧﻭﻉ ﺇﻳﻘﺎﻑ ﺍﻟﻭﻧﺵ ﺑﺟﻭﺍﺭ ﺍﻟﻣﻧﺣﺩﺭﺍﺕ ﺍﻭ ﺃﻋﻣﺎﻝ ﺍﻟﺣﻔﺭ‬


Pre-Job preparation
‫ﺍﻋﺩﺍﺩﺍﺕ ﻣﺎ ﻗﺑﻝ ﺍﻟﻌﻣﻝ‬
Task Desciption Conducted by
Step No.
‫ﻭﺻﻑ ﺍﻟﻣﻬﻣﺔ‬ ‫ﺍﻟﺷﺧﺹ ﺍﻟﻣﺳﺋﻭﻝ‬
All Persons involved in the Lifting Operations to conduct Tool Box Talk to review the lifting operations about to be
undertaken. Each Lifting operation Phase Must receive aunique Tool Box Talk. Area Authority
1
‫ ﻳﺗﻡ ﻋﻘﺩ ﺍﺟﺗﻣﺎﻉ ﺳﻼﻣﺔ ﻗﺑﻝ ﻛﻝ ﻋﻣﻠﻳﺔ ﺭﻓﻊ ﻣﺣﺩﺩﺓ‬- ‫ﺟﻣﻳﻊ ﺍﻷﻓﺭﺍﺩ ﺍﻟﻣﺷﺎﺭﻛﺔ ﻓﻲ ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ ﺗﺣﺿﺭ ﺍﺟﺗﻣﺎﻉ ﺍﻟﺳﻼﻣﺔ ﻟﻣﺭﺍﺟﻌﺔ ﺧﻁﺔ ﺍﻟﺭﻓﻊ‬ ‫ﻣﺳﺋﻭﻝ ﺍﻟﻣﻧﻁﻘﻪ‬
As part of the Tool Box Talk, personnel involved in the lifting operations must review & complete the associated JRA
ensuring all potential hazards & mitigating actions A JRA must be completed.
Area Authority
2
‫ﻳﺗﻡ ﻣﺭﺍﺟﻌﺔ ﻭﻣﻠﺊ ﻓﻭﺭﻣﺔ ﺗﺣﻠﻳﻝ ﺍﻟﻣﺧﺎﻁﺭ ﻣﻥ ﻗﺑﻝ ﺟﻣﻳﻊ ﺍﻟﻣﺷﺎﺭﻛﻳﻥ ﻓﻲ ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬ ‫ﻣﺳﺋﻭﻝ ﺍﻟﻣﻧﻁﻘﻪ‬
Assure the actual weights of the cargo measured by the crane is matching with the lifting plan and check the Integrity of
Lifting Supervisor
3 loads and associated equipment.
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
‫ﺍﻟﺗﺄﻛﺩ ﻣﻥ ﺃﻥ ﻭﺯﻥ ﺍﻟﺣﻣﻭﻻﺕ ﺍﻟﻣﺑﻳﻧﺔ ﻋﻠﻲ ﺟﻬﺎﺯ ﺍﻷﺣﻣﺎﻝ ﺑﺎﻟﻭﻧﺵ ﻋﻧﺩ ﺭﻓﻊ ﺍﻟﺣﻣﻝ ﻣﻁﺎﺑﻘﺔ ﻟﻣﺎ ﻫﻲ ﻣﻭﺟﻭﺩﺓ ﺑﺧﻁﺔ ﺍﻟﺭﻓﻊ‬
Check for debris or potential dropped objects & remove as required. Lifting Supervisor
4
‫ﺍﻟﺗﺄﻛﺩ ﻣﻥ ﻋﺩﻡ ﻭﺟﻭﺩ ﺃﻱ ﺃﺷﻳﺎء ﻗﺩ ﺗﺳﻘﻁ ﻣﻥ ﻋﻠﻰ ﺍﻟﺣﻣﻝ ﺃﺛﻧﺎء ﺍﻟﺭﻓﻊ‬ ‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
Ensure all restraints have been removed & the Load is free for lifting. Lifting Supervisor
5
‫ﺻﻣﺎﻡ ﻗﺑﻝ ﺭﻓﻌﻪ‬/‫ ﻣﺛﻝ ﺍﻟﺗﺄﻛﺩ ﻣﻥ ﻓﻙ ﻣﺳﺎﻣﻳﺭ ﺗﺛﺑﻳﺕ ﺑﻠﻑ‬- ‫ﺍﻟﺗﺄﻛﺩ ﻣﻥ ﺃﻥ ﺍﻟﺣﻣﻝ ﺣﺭ ﻭﻻ ﺗﻭﺟﺩ ﻋﻭﺍﺋﻖ ﺗﻣﻧﻊ ﺭﻓﻌﻪ‬ ‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
Visually inspect the Lift appliances & lift rigging & lifting points to confirm they are in good condition & have not been
Lifting Supervisor
6 damaged during the previous lift or during transit.
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
‫ﻳﺗﻡ ﻓﺣﺹ ﻣﻌﺩﺍﺕ ﻭﺃﺩﻭﺍﺕ ﻭﻧﻘﻁ ﺍﻟﺭﻓﻊ ﺟﻳﺩﺍ ﻗﺑﻝ ﺍﻟﺑﺩﺃ ﺑﺎﻟﻌﻣﻝ ﻭﺍﻟﺗﺄﻛﺩ ﺃﻧﻬﺎ ﺧﺎﻟﻳﺔ ﻣﻥ ﺃﻯ ﻋﻳﻭﺏ‬

Check The crane Route/Access/Egress, underground services,Ground Bearing Pressure, All power Lines Lifting Supervisor
7
‫ﻳﺗﻡ ﺍﻟﺗﺣﻘﻖ ﻣﻥ ﺍﻟﻁﺭﻳﻖ ﻭﺍﻟﻣﺩﺧﻝ ﻭﺍﻟﻣﺧﺭﺝ ﺍﻟﺫﻯ ﺳﻳﻣﺭ ﻣﻧﻪ ﺍﻟﻭﻧﺵ ﻭﻛﺫﻟﻙ ﺃﻱ ﺃﻋﻣﺎﻝ ﺗﺣﺕ ﺍﻷﺭﺽ ﻭﻣﺗﺎﻧﺔ ﺍﻷﺭﺽ ﺍﻟﺗﻲ ﺳﻳﻘﻑ ﻋﻠﻳﻬﺎ ﺍﻟﻭﻧﺵ‬ ‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
Ensure no conflicting activities ongoing is surrounded/landing areas and load path is clear of obstructions.
Lifting Supervisor
8 ‫ﺍﻟﺗﺄﻛﺩ ﻣﻥ ﻋﺩﻡ ﻭﺟﻭﺩ ﺃﻋﻣﺎﻝ ﻣﺗﺯﺍﻣﻧﺔ ﻭﻣﺗﻌﺎﺭﺿﺔ ﻣﻊ ﺑﻌﺿﻬﺎ ﻭﻋﺩﻡ ﻭﺟﻭﺩ ﻣﻌﻭﻗﺎﺕ ﻓﻲ ﻁﺭﻳﻖ ﺍﻟﺣﻣﻭﻟﺔ ﻭﻛﺫﻟﻙ ﻣﻭﺿﻊ ﺗﻧﺯﻳﻠﻬﺎ‬
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
Ensure all non essential personnel are clear of the load & lift route. Lifting Supervisor
9
‫ﺍﻟﺗﺄﻛﺩ ﻣﻥ ﺟﻣﻳﻊ ﺍﻷﻓﺭﺍﺩ ﺍﻟﻐﻳﺭ ﻣﺷﺗﺭﻛﺔ ﺑﻌﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ ﻭﺍﻟﻐﻳﺭ ﺿﺭﻭﺭﻳﺔ ﺑﻌﻳﺩﺓ ﻋﻥ ﻁﺭﻳﻖ ﺍﻟﺣﻣﻝ ﻭﻣﻧﻁﻘﺔ ﺍﻟﺭﻓﻊ‬ ‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
Ascertain that the environmental conditions are within crane parameters as the wind speed not exceeding the
Lifting Supervisor
10 Manufacture/Regulation Specs.
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
‫ﺍﻟﺗﺄﻛﺩ ﻣﻥ ﺃﻥ ﺍﻟﻅﺭﻭﻑ ﺍﻟﺑﻳﺋﻳﺔ ﻣﺛﻝ ﺳﺭﻋﺔ ﺍﻟﺭﻳﺎﺡ ﻻ ﺗﺗﻌﺩﻯ ﺍﻟﻘﻳﻡ ﺍﻟﻣﺻﺻﻡ ﻋﻠﻳﻬﺎ ﺍﻟﻭﻧﺵ ﺃﻭ ﻣﻌﺩﺍﺕ ﺍﻟﺭﻓﻊ‬
Carry out a radio communications check with all lifting personnel (If Radio is used) Lifting Supervisor
11
‫ﺗﺳﺕ ﻗﺑﻝ ﺍﻟﺑﺩﺃ ﻓﻲ ﺍﻟﻌﻣﻝ ﻟﻠﺗﺄﻛﺩ ﻣﻥ ﺃﻧﻪ ﻳﻌﻣﻝ ﺟﻳﺩﺍ‬/‫ ﻓﻳﺗﻡ ﻋﻣﻝ ﺍﺧﺗﺑﺎﺭ‬،‫ﺍﺫﺍ ﻛﺎﻥ ﺍﻟﺭﺍﺩﻳﻭ ﻣﺳﺗﺧﺩﻡ ﻛﻭﺳﻳﻠﺔ ﺗﻭﺍﺻﻝ ﺃﺛﻧﺎء ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬ ‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
Area of Lifting must be isolated by caution tape. Lifting Supervisor
12
‫ﻳﺗﻡ ﻋﻣﻝ ﺣﻭﺍﺟﺯ ﺣﻭﻝ ﻣﻧﻁﻘﺔ ﺍﻟﺭﻓﻊ ﺑﺎﺳﺗﺧﺩﺍﻡ ﺷﺭﻳﻁ ﺍﻟﺗﺣﺫﻳﺭ‬ ‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
Perform all Lifting operation as per Lifting Plan & method Statement. Lifting Supervisor
13
‫ﻳﺗﻡ ﺗﻧﻔﻳﺫ ﺟﻣﻳﻊ ﺧﻁﻭﺍﺕ ﺍﻟﺭﻓﻊ ﻁﺑﻘﺎ ﻟﻣﺎ ﻫﻭ ﻣﻭﺟﻭﺩ ﺑﺧﻁﺔ ﺍﻟﺭﻓﻊ‬ ‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
If a previous point is ok, start performs the lifting operation. Lifting Supervisor
14
‫ ﻳﺗﻡ ﺍﻟﺑﺩﺃ ﻓﻲ ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬، ‫ﺍﺫﺍ ﻛﺎﻧﺕ ﺍﻟﻧﻘﺎﻁ ﺍﻟﺳﺎﺑﻘﺔ ﻣﺣﻘﻘﺔ ﻭﺗﻡ ﺍﻟﺗﺄﻛﺩ ﻣﻧﻬﺎ ﺟﻳﺩﺍ‬ ‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
Task Details & Procedures (Step by Step) Transferring and loading (Z1)
‫ﺗﻔﺎﺻﻳﻝ ﻭﺧﻁﻭﺍﺕ ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬
Task Desciption Conducted by
Step No.
‫ﻭﺻﻑ ﺍﻟﻣﻬﻣﺔ‬ ‫ﺍﻟﺷﺧﺹ ﺍﻟﻣﺳﺋﻭﻝ‬
1-lifting supervisor, 1- banks man, 4 - Technicians, 4 - rigger and 1- Plant Operator to be attend throughout the
lifting operation. Lifting Supervisor
1
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
‫ ﻣﺷﺭﻑ ﺭﻓﻊ ﺃﺛﻧﺎء ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬1 ‫ ﻓﻧﻳﻥ ﻭ‬4 ,‫ ﺑﺣﺭﻯ‬4,‫ﺑﺣﺭﻯ ﺇﺷﺎﺭﻩ‬1

Lifting supervisor signal technician to erect the skidding tools as per drawing (1).
Lifting Supervisor
2
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬
Lifting supervisor signal technician to lift load by screw pin to height of position (2), so technician can isert
beams underneath load as per drawing (2). Lifting Supervisor
3
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬

Lifting supervisor signal technician to insert skids beam underneath the load as per drawing (3).
Lifting Supervisor
4
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

4
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬

Lifting supervisor signal technician to lower load by screw pin to be rested overs skids beam as per drawing (4).
Lifting Supervisor
5
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬
if load stable over skids, lifting subervisor signal to riggers to pulling load to be at position (3) as per drawing
(5). Lifting Supervisor
6
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬
At position (3),Lifting supervisor signal technician to lift load by screw pin to height, so technician can remove
beams from underneath load as per drawing (6). Lifting Supervisor
7
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬
At position (3),Lifting supervisor signal technician to lift load by screw pin to height, so technician can remove
beams from underneath load as per drawing (6). Lifting Supervisor
8
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬

Lifting supervisor signal technician to remove skids beam from underneath the load as per drawing (7).
Lifting Supervisor
9
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬

Lifting supervisor signal technician to lower load by screw pin to be rested overs main beam as per drawing (8).
Lifting Supervisor
10
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬
if load stable over main beam, lifting subervisor signal to riggers to pulling load to be at position (4) as per
drawing (9). Lifting Supervisor
11
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬
At position (4), banks man signal crane operator to lower hook so the rigger can attach sling with hook block
as per rigging drawing. Banks man
12
‫ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﻬﻭﻙ ﺣﺗﻰ ﻳﺗﻣﻛﻥ ﺍﻟﺑﺣﺭﻯ ﻣﻥ ﺗﻌﻠﻳﻖ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻋﻠﻰ ﺍﻟﻬﻭﻙ‬

Riggers attach sling to the load as per rigging drawing.


Lifting Supervisor
13
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﻘﻭﻡ ﺍﻟﺑﺣﺭﻯ ﺑﺗﻭﺻﻳﻝ ﺍﻟﺻﺑﺎﻧﻲ ﻣﻊ ﺍﻟﺣﻣﻝ ﻛﻣﺎ ﺑﺎﻟﺭﺳﻡ‬

Banks man signal crane operator to lift hook slowly to tension slings then stop.
Banks man
14
‫ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺭﻓﻊ ﺍﻟﻬﻭﻙ ﺑﺑﻁﺊ ﻟﺷﺩ ﺍﻟﺻﺑﺎﺑﻳﻥ ﺛﻡ ﺍﻟﺗﻭﻗﻑ‬

Riggers attach tag lines to the load.


Lifting Supervisor
15
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﻳﻘﻭﻡ ﺍﻟﺑﺣﺭﻯ ﺑﺭﺑﻁ ﺣﺑﻝ ﺣﻭﻝ ﺍﻟﺣﻣﻝ‬

Banks man signal crane operator to lift load slowly to height 10 cm to check balance.
Banks man
16
‫ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ‬
.‫ ﺳﻡ ﻟﻠﺗﺣﻘﻖ ﻣﻥ ﺇﺗﺯﺍﻥ ﺍﻟﺣﻣﻝ‬10 ‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺭﻓﻊ ﺍﻟﺣﻣﻝ ﺑﺑﻁﺊ ﻹﺭﺗﻔﺎﻉ‬

If load is stable, Banks man signal crane operator to lift load and swing to truck as per drawing (10).
Banks man
17
‫ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ‬
.‫ ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺭﻓﻊ ﺍﻟﺣﻣﻝ ﻭﺍﻟﺩﻭﺭﺍﻥ ﻣﻥ ﺍﻟﻛﻧﻭﺭ ﺍﻟﻲ ﻣﻧﻁﻘﻪ ﺍﻟﻣﺣﺩﺩﻩ‬,‫ﺇﺫﺍ ﻛﺎﻥ ﺍﻟﺣﻣﻝ ﻣﻭﺯﻭﻥ‬

Banks man signal to crane operator to lower load to truck and lower crane hook block.
Banks man
18
‫ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ‬
.‫ﻳﺷﻳﺭ ﻋﺎﻣﻝ ﺍﻻﺷﺎﺭﻩ ﻟﻠﻭﻧﺎﺵ ﺑﺗﻧﺯﻳﻝ ﺍﻟﺣﻣﻝ ﻟﻔﺻﻝ ﻫﻭﻙ ﺍﻟﻭﻧﺵ‬

Once load is secure riggers remove slings and tag lines from the load.
Lifting Supervisor
19
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ ﻳﻘﻭﻡ ﺍﻟﺑﺣﺭﻯ ﺑﻔﺻﻝ ﺍﻟﺻﺑﺎﺑﻳﻥ ﻭ ﺍﻟﺣﺑﻝ ﻣﻥ ﺍﻟﺣﻣﻝ‬,‫ﺑﻣﺟﺭﺩ ﺗﺎﻣﻳﻥ ﺍﻟﺣﻣﻝ‬

Repeat steps 3 to 19 to offload other loads (Z2), (Z3) ,(Z4) respectively.


Lifting Supervisor
20
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
‫( ﻋﻠﻲ ﺍﻟﺗﻭﺍﻟﻲ‬Z2), (Z3) ,(Z4) ‫ ﻟﻛﻝ‬19 ‫ ﺍﻟﻲ‬3 ‫ﺗﻛﺭﺍﺭ ﺍﻟﺧﻁﻭﺍﺕ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Cease and tidy work site & post use inspect all lifting equipments.
Lifting Supervisor
21
‫ﻣﺷﺭﻑ ﺍﻟﺭﻓﻊ‬
.‫ﺇﻧﻬﺎء ﺍﻟﻌﻣﻝ ﻭﺗﻧﻅﻳﻑ ﺍﻟﻣﻛﺎﻥ ﻗﺑﻝ ﺍﻟﻣﻐﺎﺩﺭﻩ ﻭﻓﺣﺹ ﻣﻌﺩﺍﺕ ﺍﻟﺭﻓﻊ‬

Methods of Communication to Be Used (put Yes for the selected one) ‫ﻁﺭﻕ ﺍﻟﺗﻭﺍﺻﻝ ﺍﻟﻣﺳﺗﺧﺩﻣﻪ ﻓﻲ ﻋﻣﻠﻳﺔ ﺍﻟﺭﻓﻊ‬

Radio (VHF) Verbal Hand Signal


YES YES YES
‫ﺍﻟﺭﺍﺩﻳﻭ‬ ‫ﺷﻔﻭﻯ‬ ‫ﺇﺷﺎﺭﺓ ﺍﻟﻳﺩ‬

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬

Planned By: Signature: Date:


Hassan AbdelHamid
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Calculation Sheet

Weight of the load (Wt) 13 tonne

Contingency Factor (C.F) 1.2

Wt X C.F 15.6 tonne 1

Weight of hook blocks + Weight of rigging +


Weight of wires fall lines 1 tonne 2

Step 1 + Step 2 16.6 tonne 3

Dynamic Amplification Factor (D.A.F) 1

Step 3 X D.A.F 16.6 tonne

Minimum Crane Capacitiy At Point Of Lift Is 16.6 tonne @ Radius 10 MTR

Note: Offshore Dynamic Amplification Factor Used Only For Static Load Chart.
** The Required Input Data Are The Cells With Colour

NOTE:
A)This calculations for (onshore transfer with mobile crane static load chart)

B) These adding factors like (D.A.F) and (C.F) are according to DNV Noble Denton

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan AbdelHamid
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Load Chart

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬

Planned By: Signature: Date:


Hassan AbdelHamid
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Crane position and Skidding way layout

* Z1,Z2,Z3 AND Z4 IS ENGINES
* Z1 IS REQUIRED TO BE LIFTED
Landing 

Z2 Z3 Z4

Landing 
Z1

Concrete 

Landing area 

Planned By: Signature: Date:


Hassan AbdelHamid
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Rigging Drawing

1, Two leg wire rope 
sling  14 ton X 2mtr

8,  safety pin bow 
shackle 9.5 ton

1, Lifting Beam  14 
ton X 2mtr

4, single leg wire rope
sling  5 ton X 2mtr

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬

Planned By: Signature: Date:


Hassan AbdelHamid
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (1)

*Alignment Bolt

Used to lift the load to  
height enough so riggers 
can insert skidding beam 
and skids under load

Beam extension for pulling

Stiffener plate
Fixation Bolt

Loading skid
Position No.  (1)

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (2)

Position No.  (2)

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (3)

Lever hoist 3 ton X 6 mtr

Shackle 4.75 ton

Fixation Bolt

U beam skids

Stiffener 
I beam skidding 

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (4)

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (5)

Position No.  (3) 
Side view

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (6)

Position No.  (3) 
Elevation view

ancored 
point

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (7)

ancored 
point

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (8)

ancored 
point

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (9)

Position No.  (4) 

ancored 
point

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬


Planned By: Signature: Date:
Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Elevation View Step Drawing (10)

Approvals & Signatures ‫ﺍﻻﻋﺗﻣﺎﺩ ﻭﺍﻻﻣﺿﺎءﺍﺕ‬

Planned By: Signature: Date:


Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Top View Step Drawing (11)

Load 
Egress  Z3 Z4
Z2
Position No.  
(1) & (2)
Landing 
Z1

Position 

Landing area 

Position 

ancored 
point
Crane access 
and egress way 

Planned By: Signature: Date:


Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Top View Step Drawing (12)

Load 
Egress  Z2 Z3 Z4

Position No.  
(1) & (2)
Landing 
Z1 Z1

Position 

Landing area 

Position 

ancored 
point
Crane access 
and egress way 

Planned By: Signature: Date:


Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Top View Step Drawing (13)

Load 
Egress 
Z2 Z3 Z4

Position No.  
(1) & (2)
Landing 
Z1

Position 
No.  (3) 

Landing area 
Z1
Position 
No.  (4) 

ancored 
point

Crane access 
and egress way 

Planned By: Signature: Date:


Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Top View Step Drawing (14)

Load 
Egress 
Z2 Z3 Z4

Position No.  
(1) & (2)
Landing 
Z1

Position 

Landing area 
Z1
Position 

ancored 
point Position 
No.  (5) 
Truck  and Crane 
accessand egress 

Planned By: Signature: Date:


Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬
LIFTING OPERATIONS PLAN
‫ﺧﻁﺔ ﻋﻣﻠﻳﺎﺕ ﺍﻟﺭﻓﻊ‬

Lifting Plan No: LP002 Top View Step Drawing (15)

Load 
Egress 
Z2 Z3 Z4

Position No.  
(1) & (2)
Landing 

Position 

Landing area 

Position 

ancored  Z1
point Position 
No.  (5) 
Truck  and Crane 
accessand egress 

Planned By: Signature: Date:


Hassan Ramadan
‫ﺍﻋﺩﺍﺩ ﺑﻭﺍﺳﻁﺔ‬ ‫ﺍﻻﻣﺿﺎء‬ ‫ﺍﻟﺗﺎﺭﻳﺦ‬