Substation
Bay/Panel
Equipment Serial No
2.0 Check List of Testing Digital& Numerical Protection & Control Relays and
IED’s
Check that Mimic and single line diagram on the relay display
is according to approved single line diagram of SS
Check that Control configuration and all functions the relay is
according to approved schematic diagram and approved
configuration.
Check interlocking logics is according to approved scheme
and conditions.
Check all breaker, disconnector and earth switch positions.
The position indications are checked by local operation in the
field and the physical position of every device has to be
compared with the shown position on the local mimic, the
displays of the relays and on the SAS.
Check all breaker, disconnector and earth switch commands.
The command has to be checked for the possible modes
(Local, Emergency & Remote,). Local operation mode at the
relay display can be selected by selector button on the relay
display. Every switching devices has to be operated (open
and close) in the local mode. Remote mode at SAS at the
relay display can be selected by selector button on the relay
Archiving System Website: http://AMAS