Technical Site Survey Report And

Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG

Vendor ID : ZSLO_0554

Site ID : ZSLO_0554

Site Name : MANGGUNG

Subcon Contact Person : DGS

Surveyor : RUPADI

Survey Date : 6-Jun-20

Hardsplit Become TDD(8T8R)+FDD(2T2R) (6 port


Propose Configuration :
Antenna (1))+ (10 Port Hybrid Antenna (1))

Note:It is forbidden to operate on customer`s network until customer permission and confirmation is
obtained.

HARDSPLIT_TSSR&Design Drawing_ZSLO_0554 MANGGUNG/Cover Page 1 of 13


Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG

SITE LOCATION MAP


(GOOCLE MAP)

Page 2 of 13
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG
1 Current Information
1.1 Site Information
Survey Items Survey Contents
Site ID ZSLO_0554 Site Name MANGGUNG

Site Location Information Address Genengan, Manggung, Kec. Ngemplak, Kabupaten Boyolali, Jawa Tengah 57375

Longitude (E) 110.77887 Latitude (S) -7.48969

Property Type Equipment Room Location Installation Type


High Rise Bldg Rooftop Fan room Shelter
Gov. Premises Greenfield Meter room Equipment room
Public Housing Water tank Other: Cabinet/ODC
Site Environment
Greenfield Building Floor no Specify _________________ Other:
Checking
Ruko Elevator room Specify _________________
MCP On Pole `
Other: Pump room
Specify _________________
Office
Site Owner/Principle owner Mitratel

Defined by coverage Macro Micro/SmallCell/Shooter In Building


Defined by location Indoor/Shelter Outdoor

Site type: Rooftop Greenfield Core Site

Site Type 3 Legged 4 Legged Monopole RT Pole


Tower type:
Guyed Must Camouflage Others Specify ____________
Tower/Pole Height (m) (AGL) 42 m Building Height: m
Outdoor foundation / PAD NA Available W*D Specify ……m x …..m
Shelter/RooM Building NA Available H*W*D Specify ……m x ….m x ….m

Remarks
1.2 Existing Equipment Information
Existing equipment TDD+FDD TDD Only FDD Only
AC DC
PLN Voltage: 220 V Voltage 52.6 VDC
PLN Capacity : 25 KVA Current Load 54.5 A
Main Breaker rate at KWH : 5.5 A Max Rectifier Module Qty 4 Pcs
Single Phase Three Phases Rectifier Module Equipped 3 Pcs
Current Load R 20.9 A Each Rectifier Module Capacity 50 A
S 20.9 A Max Battery Bank Qty 2 Bank
T 20.9 A Battery Bank Equipped Qty 2 Bank
Power Supply Rectifier MCB cap at ACPDB 20 A Each Battery Capacity 150 Ah

1P Spare MCB at ACPDB LLVD 1 MCB Spare


Qty 2 Qty 1 1 4
Cap 16A Cap 125A 63A 16A
3P Spare MCB at ACPDB LLVD 2 MCB Spare
Qty 1 Qty 1
Cap 20A Cap 63A
Fix Genset Available Not Available Capacity : KVA
Main Grounding bar Qty / number of port (Outdoor): __1Pcs__ / __14Port_ Length from Grouding bar to BBU (m) /
Grounding Main Grounding Bar Qty / number of port (Indoor) 2Pcs / 14 Port Length from Grouding bar to BBU (m) 8M

Tower/Pole Grounding bar Qty / number of port : 1Pcs / 14Port Length from Grouding bar to RRU (m) 7M

Transmission Type MW Optical Sharelink Others Specify ____________


Tower/Pole No Diameter Antenna Height (AGL) Type Pole No Azimuth
1
2
Transmission 3
IDU Brand Capacity FE Sye ID

1
2
3
Length of GPS Cable to BTS 25 M
Existing GPS System
GPS Antenna Height (AGL) 15 M

Remark _________________________________________________________________________________________________________________

1.3 Existing Feeder and Antenna Information,


Antenna Type TDD+FDD TDD Only FDD Only
Sector No. Model Azimuth (º) Downtilt (º) Ant. Height (m)* Jumper length (m) Feeder length (m) Remark

1 CVV65CSX-M 0 0 40 5 60

2 CVV65CSX-M 120 0 40 5 60

3 CVV65CSX-M 240 0 40 5 60

4
Remark *) Building+Pole/ Tower (m)
Antenna Type(extra antenna) TDD+FDD TDD Only FDD Only
Outdoor Antenna and
Cable/Feeder Ant No. Model Azimuth (º) Downtilt (º) Ant. Height Jumper length (m) Feeder length (m) Remark

1
2
3
4
Remark *) Building+Pole/ Tower (m)
Tray cable from euipment to antenna available NA Available Width cable tray : ……….cm.

Mounting antenna available NA Available Length pipe/boom : ……….m and qty : ……..pcs

Remarks __________________________________________________________________________
Space available for new equipment (indoor/outdoor): Yes No
Civil work Outdoor foundation / PAD Concrete Steel Base Frame W*D Specify ……m x …..m
Shelter/RooM Building Brick Wall Wall Shelter H*W*D Specify ……m x ….m x ….m
Remarks __________________________________________________________________________

Page 3 of 13
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And Design


Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG
2 New Equipment Information
2.1 Summary
New Equipment for LTE (eNodeB) without Power
New Equipment for LTE (eNodeB) including Power
Implementation summary
TDD / FDD Upgrade
Sectorization

2.2 Preliminary Solution


BBU INSTALLATION LOCATION
Indoor Outdoor
BBU in new 19 Rack BBU in new Power system cabinet
Site Configuration
BBU in existing 19 Rack BBU on top ODC (min space 1600mm from top cabinet to canopy)
information
BBU in new Power system cabinet Others BBU In Cabinet Balitower
BBU in existing Power system cabinet

Others : _______________
__________
Power Equipment Type Qty.
Rectifier Rack ZXDU68 W201 1
Rectifier Module ZXD3000 3
DC
Battery FT12-150 2
Power
DC Distribution N/A

Breaker N/A
AC
AC Distribution Box
ACPDB to BTS AC cable Length (Rectifier cabinet) : 9M
DC cable from rectifier to BBU : 8M
BTS to Grounding Bar (eNB plinth to Nearest Grounding Bar) : 8M

ID OD Cable Routing Sct1 Sct2 Sct3 Sct4 Sct5 Sct6


ID OD DC Rectifier-RRU cable length (m)
Cable
ID OD BBU-RRU Optical fiber length (m) 60
ID OD Jumper cable RRU-Filter (m) 2
ID OD Jumper cable RRU-Antenna (m) 5
ID OD RRU GND to Nearest Ground bar (m) 7
BBU Transmission Cable Required No Yes Length m ________
Items Existing Proposed Length/Height (m)
Proposed GPS System GPS Cable 15

GPS Antenna Height 15

New Antenna
Sector No Pole No Ant Model Pole Height Ant Height Azimuth Down tilt

1 1 MB-G64O9X50V-00 39 155 0
Antenna Type 2 1
3 1
4
5

Remarks _________________________________________________________________________________________________________________

Page 4 of 13
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG
SN Detail Photo Taken Num Of Photo

4.1 Site Overview Photo YES


1 Site Overview Photo(ground) YES 1

2 Tower overview photo(from groud to tower top) YES 1

3 GPS photo YES 1

4.2 Existing Equipment Information YES


1 Existing Antenna RF YES 1

2 Existing Antenna MW YES 1

3 Existing KWH Meter YES 1

4 Existing main MCB at KWH meter YES 1

5 Existing ACPDB YES 1

6 Existing AC Current Load YES 1

7 Existing Rectifier Cabinet YES 1

8 Existing DC Current Load YES 1

9 Existing DCPDB internal (at rectifier rack) YES 1

10 Existing DCPDB external (outside rectifier rack) YES 1

11 Existing Battery System YES 1

12 Existing Transmission Equipment YES 1

13 Existing Cable Tray/ladder(from BBU to Tower) YES 1

14 Existing Indoor Grounding Bar YES 1

15 Existing Outdoor Grounding Bar YES 1

16 Existing Foundation Outdoor YES 1

17 Other YES 1

4.3 Panoramic View YES


1 0 degree YES 1

2 30 degree YES 1

3 60 degree YES 1

4 90 degree YES 1

5 120 degree YES 1

6 150 degree YES 1

7 180 degree YES 1

8 210 degree YES 1

9 240 degree YES 1

10 270 degree YES 1

11 300 degree YES 1

12 330 degree YES 1

13 Antenna azimuth sector 1 YES 1

14 Antenna azimuth sector 2 YES 1

15 Antenna azimuth sector 3 YES 1

16 Antenna Mechnical down tile sector 1 YES 1

17 Antenna Mechnical down tile sector 2 YES 1

18 Antenna Mechnical down tile sector 3 YES 1

4.4 New Equipment Proposal YES

Page 5 of 14
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG
SN Detail Photo Taken Num Of Photo

1 Proposed New BBU location YES 1

2 Proposed new Rectifier System location YES 1

3 Proposed New RF Antenna and height YES 1

4 Proposed Reuse existing/new MCB for eNB YES 1

Page 6 of 14
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG

4 Site photo

4,1. Site Overview Photo

1. Site Overview Photo(ground) 2. Tower overview photo(from groud to tower top) 3. GPS photo

4,2. Existing Equipment Information

N/A

1. Existing Antenna RF 2. Existing Antenna MW 3. Existing KWH Meter

N/A N/A N/A

4. Existing main MCB at KWH meter 5. Existing ACPDB 6. Existing AC Current Load

N/A

7. Existing Rectifier Cabinet 8. Existing DC Current Load 9. Existing DCPDB internal (at rectifier rack)

N/A

10. Existing DCPDB external (outside rectifier rack) 11. Existing Battery System 12. Existing Transmission Equipment

Page 7 of 13
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG

N/A N/A

13. Existing Cable Tray/ladder(from BBU to Tower) 14. Existing Indoor Grounding Bar 15. Existing Outdoor Grounding Bar

N/A N/A N/A

16. Existing Foundation Outdoor 17. Other 17. Other

4,3. Panoramic View

1. 0 degree 2. 30 degree 3. 60 degree

4. 90 degree 5. 120 degree 6. 150 degree

7. 180 degree 8. 210 degree 9. 240 degree

Page 8 of 13
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG

10. 270 degree 11. 300 degree 12. 330 degree

N/A N/A

13. Antenna azimuth sector 1 14. Antenna azimuth sector 2 15. Antenna azimuth sector 3

N/A N/A

16. Antenna Mechnical down tile sector 1 17. Antenna Mechnical down tile sector 2 18. Antenna Mechnical down tile sector 3

4,4. New Equipment Proposal

N/A N/A
Prop. Swap Antenna Sec A
CVV65CSX-M TO
(MB-G64O9X50V-00)
On Hight : 40m

1. Proposed New BBU location 2. Proposed new Rectifier System location 3. Proposed New RF Antenna and height

N/A N/A N/A

4. Proposed Reuse existing/new MCB for eNB

Page 9 of 13
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG

5.1 Site lay out ZSLO_0554

N 15°

5.2 Proposed Equipment layout ZSLO_0554

Page 10 of 13
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG
5.3.1 Proposed RRU & antenna placement ZSLO_0554

N 15°

Ground Level
A B

5.3.2 Proposed RRU & antenna placement ZSLO_0554

Page 11 of 13
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG
5.4 Proposed cable routing layout and table ZSLO_0554

5.5 Rectifier DCPDB MCB allocation ZSLO_0554

B P N2
B P N2

CRO
PM10B B P N2

SA
CCE1

Page 12 of 13
Doc. Name:Site Survey detailed site-wise design

Technical Site Survey Report And


Design Drawing
For Smartfren LTE project
ZSLO_0554 MANGGUNG
5.6 Conectivity wiring diagram of power monitoring/new monitoring ZSLO_0554

REUSED EGUARD

5.6 Block Diagram ZSLO_0554

R8964 PROPOSED SWAP ANTENNA LTE 850 & 2300 MHz


10 ports( MB-G64O9X50V-00) on 40 m
R8862A Filter

8300 R8984E
(TDD+FDD)

R8964
EXISTING ANTENNA LTE 850 & 2300 MHz
6 ports(CVV65CSX-M) on 40 m
R8862A Filter

DCPDB6

R8964
EXISTING ANTENNA LTE 850 & 2300 MHz
6 ports(CVV65CSX-M) on 40 m
R8862A Filter

ZXDU68
W201

See TX Database

Legend :

DC Power Cable
Fiber Optic
Jumper 1/2"

Page 13 of 13
DESIGN PACK DRAWING
ZSLO_0554 MANGGUNG

16 JUNI 2020
N

Approved by : Sign.

Checked by : Sign.

Checked by ( PT. ZTE) : Sign.

Scale :

Drawing
No.: Unit : mm

Ed. Description Date : Drawn by :

1 New Creation

A4
Approved by : Sign.

Checked by : Sign.

Checked by ( PT. ZTE) : Sign.

Scale :

Drawing
No.: Unit : mm

Ed. Description Date : Drawn by :

1 New Creation

A4
N

Approved by : Sign.

Checked by : Sign.

Checked by ( PT. ZTE) : Sign.

Scale :

Drawing
No.: Unit : mm

Ed. Description Date : Drawn by :

1 New Creation

Ground Level
A B

A4
Approved by : Sign.

Checked by : Sign.

Checked by ( PT. ZTE) : Sign.

Scale :

Drawing
No.: Unit : mm

Ed. Description Date : Drawn by :

1 New Creation

A4
Approved by : Sign.

Checked by : Sign.

Checked by ( PT. ZTE) : Sign.

Scale :

Drawing
No.: Unit : mm

Ed. Description Date : Drawn by :

1 New Creation

A4
DC Input DC Output Circuit Breaker (*9) 1 2 3 4 5 6 7 8 9
10A 10A 10A 10A 10A 10A 10A 10A 10A

BPN
BPN2

BPN
BPN2
CRO
PM10B

BPN
BPN2
HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA

HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63

SA C63 C25 C25 C25 C25 C25 C25 C25 C63 C16 C16 C16 C16 C16 C16 C16 C16

SA
230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V-
EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1
GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON

CCE1 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF

HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA HUAJIA

HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-63 HGM45-125 HGM45-125
C63 C25 C25 C25 C25 C25 C25 C25 C63 C16 C16 C16 C16 C16 C16 C16 C16 C120 C120
230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V- 230 / 400V-
EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1 EC / EN 60898 - 1
GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON GB12963.1 1 ON
0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF 0 OFF

Approved by : Sign.

Checked by : Sign.

Checked by ( PT. ZTE) : Sign.

Scale :

Drawing
No.: Unit : mm

Ed. Description Date : Drawn by :

1 New Creation

A4
REUSED EGUARD
Approved by : Sign.

Checked by : Sign.

Checked by ( PT. ZTE) : Sign.

Scale :

Drawing
No.: Unit : mm

Ed. Description Date : Drawn by :

1 New Creation

A4
R8964 PROPOSED SWAP ANTENNA LTE 850 & 2300 MHz
10 ports( MB-G64O9X50V-00) on 40 m
R8862A Filter

8300 R8984E
(TDD+FDD)

R8964
EXISTING ANTENNA LTE 850 & 2300 MHz
6 ports(CVV65CSX-M) on 40 m
R8862A Filter

DCPDB6

R8964
EXISTING ANTENNA LTE 850 & 2300 MHz
6 ports(CVV65CSX-M) on 40 m
R8862A Filter

ZXDU68
W201

Approved by : Sign.

See TX Database
Checked by : Sign.

Checked by ( PT. ZTE) : Sign.

Scale :