Project Title: -
###
Location: -
ABC: #NAME?
Duration: $ -
GENERAL CONDITIONS
All works to be undertaken shall be in accordance with the plans and working drawings. It includes the furnishing
of all materials, labor and equipment with supervision necessary for the complete construction of the said project.
The plans, detailed drawings and this scope of work shall be considered as complementing with each other, so that
what is mentioned or shown on one, although not mentioned or shown in another, shall be considered as appearing in both.
In case of conflict between the two, the same should be referred to the designing Architect/Engineer.
This program of work covers all necessary items needed for the completion of BU Polangui Campus
Computer Science and Engineering Building. Such work will cover the Ground Floor construction of additional concrete
pathway, transformer platform, & drainage line canal; complete renovation of comfort rooms; replacement of
old existing ceilings; and repainting. On the Second Floor, this program of work will cover the construction &
completion of classrooms, laboratories, storage rooms, faculty rooms/offices, corridors, and comfort rooms.
This item of work includes the provisions for Project Sign Boards, Temporary Utilities and Enclosure, and
Construction Safety and Health Programs.
This item of work includes the cleaning and clearing of site and disposal of waste materials, before and after
construction. The contractor shall submit the waste material report prior to demobilzation.
This item of work also includes excavation, backfill, filling materials, compaction, and gravel beddings
needed for:
a. 2.0 m Concrete Pathwalk [Bounded by gridlines (5 to 6)
and (B' to F') in the Ground Floor]
Excavation 92.40 m3
Filling Materials and Compaction 83.72 m3
Gravel Bedding (Material & Labor) 14.17 m3
c. Transformer Platform
Excavation 20.90 m3
Backfilling and Compaction 17.42 m3
Gravel Bedding (Material & Labor) 2.09 m3
This item of work also includes demolition/dismantling and disposal as follows:
a. Demolition and disposal of walls [Along gridline 2' (D to E);
B' (5 to 6); and F' (5 to 6) in the Ground Floor; Along
gridline 2' (D to E), and 1 (D to E) in the Second Floor]
Wall Area 15.16 m2
Also included in this item of work is the rental of plate compactor and hauling truck as necessary to finish
the work.
This item of work includes pouring of concrete (compressive strength, fc'=25MPa) for structural members
comprising of wall footings, columns, beams, suspended slabs, transformer platform, and pathwalk.
### #NAME? m3
a. Column Footing
### 5.42 m3
b. Slanted Canopy [Along gridlines B' (3' to 6), & F' (3' to 6)] 2.28 m3
c. Wall Footing 3.36 m3
d. Transformer Platform 7.44 m3
Concrete topping at the top of the porch shall be sloped towards the drain.
This item of work also includes the rental of 1-bagger concrete mixers, concrete vibrators, plate compactor
and other equipments necessary to finish the work.
All surfaces must be plain cement finished.
All materials shall be so delivered, stored and handled as to prevent the inclusion of foreign materials
and the damage of materials by water or breakage.
Packaged materials shall be so delivered and stored in original packages until ready for use.
All materials delivered shall be of the respective qualities as specified.
Water to be used in gauging concrete shall be free of oil, acid, alkali, vegetable matter or other
deleterious substance and shall be reasonably clear and clean. The use of sea or blackish water is not allowed.
Cements shall be of any standard commercial brand in standard 40kg bag. No re-bagged cement shall
be used.
Fine aggregates used in the composition of concrete mortar, grout or plaster should consist of sand or
other inert materials with similar characteristics or a combination thereof, having clean, hard, strong, durable,
uncoated grains and free from injurious amount of dust, lumps, soft or flaky particles and shall not contain
more than 5 percent of clay. In exposed work fine aggregates shall be free from any substance, which will
discolor the concrete surface.
Coarse aggregate shall consist of crushed stones, gravel or other approved inert materials with similar
characteristics or a combination thereof, having clean, hard, strong, durable, uncoated particles, free from
injurious amount of soft, elongated and laminated pieces organic or other matter.
Coarse aggregate shall be well graded as to size, ranging from 6mm up to size which will readily pass
between all reinforcing bars and between reinforcements and forms, but not to exceed 25mm in size for
reinforced beams, floor slabs, columns, etc. and may range up to 50mm for less highly reinforced parts of
structure such as footing.
Gravel under concrete slab shall be river run gravel with a maximum size of 50mm. A minimum size
of 12.50mm.
Placing concrete- concrete shall be rapidly handled from the mixing site to forms and deposited as
early as possible in its final position without loss of ingredients. Concrete shall be spaded and worked by
hand to assure close contact to surfaces of forms and reinforcement. Concrete shall not be dropped freely
more than 1.22520mm (5ft.) for columns and not more than 920mm (3ft.) for footings and slabs.
Preparation for placing concrete- Before placing concrete, remove all sawdust, chips and other
construction debris from the places to be occupied by the concrete. Reinforcement shall be secured in
position and inspected by the authorized representative.
Curing shall be started as soon as free water has disappeared from the surface of the concrete. The
entire surface of the concrete shall be covered with canvass, straw, jute sack or other satisfactory materials
and kept moist by flushing or sprinkling water. Curing shall continue for a period of not less than 7 days after
placing the concrete.
Mixing concrete/materials shall be measured, batched and mixed in a mixer or by hand in a
watertight wooden platform at the job site.
This item of work includes furnishing, fabrication and installation of ASTM grade 60, ASTM grade 40 and
ASTM grade 33 deformed steel bars comprising of wall footings, columns, beams, transformer platform, and pathwalk.
This item of work also includes the rental of cut-out machine and bar cutter as necessary as
possible to finish the work.
Reinforcing bars shall be standard commercial deformed type.
Use 10mmØ steel bars spaced at 1200mm on center both ways for ceiling hangers.
Tie wire shall be local standard commercial G.I. wire gauge 16.
Placing steel reinforcements – Place reinforcements securely fastened and support it to prevent
displacement before or during placing of concrete. Bars shall be bent cold. Bars shall be free from rust, scales
and oil. Splices in bars shall be made at critical points of maximum stresses.
Deformation of reinforcing bars shall conform to ASTM A615-68
Unless otherwise noted in the plans the minimum yield strength of the main reinforcing bars shall be
as follows:
10 mm fy = 230 MPa (Grade 33)
12 mm fy = 275 MPa (Grade 40)
16 mm and larger fy = 415 MPa (Grade 60)
Development length requirements (ld) shall be as tabulated in standard details.
Splice and anchorages shall follow those set from development length (ld) unless otherwise shown in
the plans or approved by the Engineer.
Standard hook for re-bars if required shall be either of the following:
Semicircular turns plus an extension of at least 4 bar diameters but not less than 65mm at free end of
the bar.
90 degree turn plus an extension of at least 12 bar diameters at free end of the bar.
Minimum diameter of bend measured on the inside of the bar be as follows:
10 mm to 25 mm - 6 bar diameter
This item of work includes furnishing and installation of machine pressed Concrete Hollow Blocks 150mm
for exterior walls and concrete pathway; and machine pressed Concrete Hollow Blocks 100mm for the stairs and
interior partition walls, reinforced with 10 mm diameter rebars spaced at 600 mm on center bothways. Concrete
Hollow Blocks shall be filled with mortar and must be plain cement plaster finished.
This item of work also includes completion of plastering of all exterior and interior wall surfaces, columns,
beams, canopies, paraphets, and gutters.
All masonry surfaces shall be cement plastered smooth finish ready to accept painting works.
All concrete hollow blocks for use in masonry works shall be load bearing-concrete hollow blocks
with a minimum strength of 4.85 MPa.
All masonry shall be laid true, level, plumb and neat in accordance with the plans.
Units shall be cut accurately to fit all plumbing ducts, opening, electrical works, etc. and all holes shall
be neatly patched.
Reinforcing bar shall conform to the provisions provided for the structural notes and their installation
shall be in accordance with standard details provided for. All provisions for dowels shall properly laid in place
prior to laying of masonry units. Splicing of bars shall conform to splicing standards set forth in the structural
notes.
Unless otherwise shown on the drawings, all cells shall be filled with mortar mixture consisting part
cement and three parts of sand.
All control joints shall be laid in accordance with the plans or as directed by the Engineer.
All exterior walls above grade which are not to be painted shall be waterproof with three coats of
cement sealant which is one component colorless preparation on base of Alkoxy-Silan. The sample of the
cement sealant shall be submitted to the Engineer for approval.
All masonry units shall be sound and free from cracks and other defects. Defective units shall be
subject to rejection by the Engineer and shall be removed from the project site immediately upon receipt.
This item of works includes the furnishing and installation of 1/4" thk. Marine plywood, 2"x 2" coco
lumber, 2" x 3" coco lumber, tiewire, and assorted nails.
This item of work also includes rental of GI Pipe H-frame scaffolding needed to complete the said item
in this project.
Construction of forms – Construct forms sufficiently tight to prevent leakage, securely brace and shore
forms to prevent displacement and to safely support construction loads. Forms shall not be removed until
concrete is set.
This item of work includes the installation of ceiling in the Ground Floor and Second Floor classrooms,
computer rooms, laboratory rooms, comfort rooms, admin office, janitor's room, electrical room, and storage
room using 3.5mm thk. fiber cement board, 1" x 2" x 0.4mm double metal furring spaced at 600mm o.c. bothways, 1"
x 2" x 0.7mm carrying channel, 25mm x 25mm x 0.5mm wall angle, blind revits, s-furring clips, hangers at 1200mm
spacing, and 50cm x 50 cm manholes with metal frames.
This item of work also includes the installation of ceiling in the Ground Floor corridors and lobby; and
Second Floor corridors, and stairs using 6.0mm thk. fiber cement board, 38mm x 38mm x 3mm angle bar ceiling joist
spaced at 600mm o.c. bothways, hangers at 1200mm spacing, 200mm x 2400mm PVC ceiling vent, epoxy primer
paint, and 50cm x 50cm manholes w/ metal frames.
This item of work includes fabrication and installation of the following doors and windows for the Ground
Floor and Second Floor of the Building
(Please refer to the plan)
GROUND FLOOR 16.00 sets
Doors
D2 - 2.5m x 0.9m Hardwood Panel Type Door 7.00 sets
Windows
W1 - 1.2m x 2.4m Steel Casement Swing Type Window w/ 24.00 sets
1/4" Thk. Clear Glass Panel and Security Grills
All doors and windows shall be done as specified and shown on the detailed drawings.
Windows shall be installed without forcing or distortion so that sills and heads are level and jambs are
plumb.
Each panel of hinged door shall be hung on 88.92mm x 88.92mm (3.5" x 3.5") pin hinges. All hinges shall
be of heavy duty stainless steel.
All doors shall be duty and of approved good quality.
All locks shall be installed in door frames at the same height of 0.90 meter from finished floor line.
Please refer to the plan.
This item of work includes furnishing and installation of the following tiles for the Ground Floor and
Second Floor of the building.
(Please refer to the plan)
GROUND FLOOR 354.53 m2
a. Stairs (4-Units) 116.70 m2
300mm x 300mm Ceramic Floor Tiles, Non-Skid 1,036.00 pcs
400mm x 400mm Ceramic Floor Tiles 220.00 pcs
Use tile adhesive for bonding, and grout for filling joints.
Use grinder and diamond blade, anti-microbial tile sealer, masking tape, spacer, sleeves, and other
consumable hardwares necessary for the completion of work.
Please refer to the Tiles Layout Plan and Perspective for complete details.
This item of work includes the painting of exterior surfaces using concrete neutralizer, one (1) coat
elastomeric latex primer paint, two (2) coats elastomeric latex topcoat, patching compound, tinting color, and
paint thinner.
This item of work also includes the painting of ceiling and interior walls/surfaces using concrete neutralizer,
one (1) coat flat latex paint undercoat, two (2) coats semi-gloss latex paint topcoat, patching compound, tinting
color, and paint thinner.
This item of work also includes painting of installed doors and windows using one (1) coat epoxy primer,
two (2) coats quick dry enamel, and paint thinner.
Also included in this item of work is grouting/patching of all cracks in the interior and exterior surfaces
of the Ground Floor using cement epoxy before application of paints.
Use only premium quality paint.
Use rollers & tray, brushes, old newspaper, sandpapers and rugs as necessary.
The painting contractor shall supply all labor, tool and equipment necessary and shall perform all
painting and finishing works as shown in the schedule of painting and other surfaces to render ready to use.
Painting materilas shall be stored in one place in the building to be kept neat and clean.
Before any painting is done all surfaces shall be cleaned, smoothed and free from dust. Dirt, grease,
mortar, rust and other foreign substances and all parts where paint remover has been used shall be washed off
with paint or laquer thinner.
All paints shall be spread evenly and carefully.
No painting shall be done on outside work extremely cold, frosty, foggy or damp weather.
E. PARTITIONS 104.40 m2
This item of work also includes rental of welding machine, cut-off machine, use of E-70 welding rod
and all other equipments needed to complete welding works.
(Please refer to the plan)
This item of work includes fabrication and installation of the following items listed below:
Please refer to the Stairs and Railings Layout Plan for complete details.
This item of work includes furnishing and installation of the following items listed below:
This item of work includes the manhole size cutting at the ceiling and restoration, chipping
works if needed, and voltage test and megger testing. Also includes the supply and installation of the
following electrical materials;
GROUND FLOOR
Pinlight housing 6" dia with 15W led bulb 70.00 sets
daylight, cylindrical recessed type
15W LED Compact Bulb, Daylight 68.00 pcs
ceiling fan, 16" dia. 4.00 sets
electrical tape 10.00 rolls
Rubber tape 3.00 roll
PVC 20 mm dia conduit 25.00 pcs
3.5 sq. mm THHN wire 1.00 bx
50 sq. mm THHN wire 60.00 m
5.5 sq. mm THHN wire 2.00 bxs
5.5 sq. mm TW wire (grounding) 1.00 bxs
14.0 sq. mm TW wire (grounding) 15.00 m
PVC 50 mm dia conduit 3.00 pcs
PVC 50 mm dia elbow 2.00 pcs
SECOND FLOOR
Pinlight housing 6" dia with 22W led bulb 162.00 sets
daylight, cylindrical recessed type
duplex convenience outlet with grounding 66.00 sets
universal type, heavy duty, 16A
Duplex socket outlet FM Grounding Type 16.00 sets
Enclosed circuit breaker, 30AT, 2P, single 10.00 sets
phase in Nema 3R, metal enclosure with grounding lug(for accu)
ceiling fan, 16" dia. 26.00 sets
one gang switch 2.00 sets
two gang switch 17.00 sets
three gang switch 5.00 sets
two gang three way switch 2.00 sets
utility box, sch. 40 123.00 pcs
junction box with cover, sch. 40 193.00 pcs
pullbox 12" x 12" x 4" 1.00 pcs
electrical tape 50.00 rolls
Rubber tape 20.00 roll
Mica tube 1/4" 200.00 m
tie wire 5.00 kls
PVC solvent 3.00 can
PVC 20 mm dia conduit 886.00 pcs
3.5 sq. mm THHN wire 18.00 bxs
5.5 sq. mm THHN wire 17.00 bxs
5.5 sq. mm TW wire (grounding) 9.00 bxs
60 sq. mm THHN wire 100.00 m
22 sq. mm TW wire (grounding) 25.00 m
PVC 50 mm dia conduit 10.00 pcs
PVC 50 mm dia elbow 4.00 pcs
grounding rod with clamp 5/8" x 10' 2.00 set
other miscellaneous items 1.00 lot
and consumables such as bolts, cable tie,
terminal lugs, tagging tape, compression tap,
solderless connector etc.
This item of work includes furnishing and installation of the following plumbing materials and fire protection
system for the Ground Floor and Second Floor of the building.
E. Vent Line
3"Ø x 3m PVC Pipe 2.00 pcs
3"Ø Coupling 1.00 pc
4"Ø x 3"Ø Wye Reducer 1.00 pc
4"Ø x 2"Ø Wye Reducer 5.00 pcs
3"Ø 45° Elbow 1.00 pc
3"Ø x 2"Ø Coupling Reducer 9.00 pcs
2"Ø PVC Pipes 17.00 pcs
2"Ø Coupling 13.00 pcs
2"Ø 45° Elbow 20.00 pcs
PVC Solvent cement 2.00 liters
This item of work also includes the rental of 1-bagger concrete mixers and other equipments necessary to
finish the work.
This item of work also includes rental of welding machine, cut-off machine, use of E-70 welding rod
and all other equipments needed to complete welding works.
Please refer to plan for details.
Approved:
d. Transformer Platform
Excavation 20.90 m3 @ 200.00 / m3 4,180.00
Backfilling and Compaction 17.42 m3 @ 250.00 / m3 4,355.63
Gravel Bedding (Material & Labor) 2.09 m3 @ 780.00 / m3 1,630.20
l. Equipment Rental
Plate Compactor 10.00 units @ 1,000.00 / day 10,000.00
Hauling Truck 5.00 days @ 7,500.00 / day 37,500.00
(A) Direct Cost ₱ 408,590.97
(B) Indirect Cost 81,718.19
Vat (5% of A & B) 24,515.46
Sub-Total Cost ₱ 514,824.62
B. CONCRETE WORKS #REF! m3
a. Column Footing
a.1 Concrete Works 5.42 m3
Portland Cement 49.00 bags @ 260.00 / bag ₱ 12,740.00
Sand 2.80 cu. m. @ 500.00 / cu. m. 1,400.00
Gravel 5.50 cu. m. @ 600.00 / cu. m. 3,300.00
b Column
a.1 Concrete Works 4.76 m3
Portland Cement 43.00 bags @ 260.00 / bag ₱ 11,180.00
Sand 2.40 cu. m. @ 500.00 / cu. m. 1,200.00
Gravel 4.80 cu. m. @ 600.00 / cu. m. 2,880.00
c. Wall Footing
a.1 Concrete Works 4.76 m3
Portland Cement 43.00 bags @ 260.00 / bag ₱ 11,180.00
Sand 2.40 cu. m. @ 500.00 / cu. m. 1,200.00
Gravel 4.80 cu. m. @ 600.00 / cu. m. 2,880.00
b. Slanted Canopy [Along gridlines B' (3' to 6), & F' (3' to 6)]
b.1 Concrete Works 2.28 m3
Portland Cement 21.00 bags @ 265.00 / bag ₱ 5,565.00
Sand 1.20 cu. m. @ 500.00 / cu. m. 600.00
Gravel 2.30 cu. m. @ 600.00 / cu. m. 1,380.00
c. Wall Footing
c.1 Concrete Works 3.36 m3
Portland Cement 31.00 bags @ 265.00 / bag ₱ 8,215.00
Sand 1.70 cu. m. @ 500.00 / cu. m. 850.00
Gravel 3.40 cu. m. @ 600.00 / cu. m. 2,040.00
d. Transformer Platform
d.1 Concrete Works 7.44 m3
Portland Cement 67.00 bags @ 265.00 / bag ₱ 17,755.00
Sand 3.80 cu. m. @ 500.00 / cu. m. 1,900.00
Gravel 7.50 cu. m. @ 600.00 / cu. m. 4,500.00
b. Slanted Canopy [Along gridlines B' (3' to 6), & F' (3' to 6)]
b.1 Steel Works 372.69 kgs
12 mm Ø RSB, ASTM Grade 40 x 9.0m 247.75 kgs @ 45.00 / kg ₱ 11,148.84
10 mm Ø RSB, ASTM Grade 33 x 6.0m 124.94 kgs @ 43.00 / kg 5,372.53
Tie Wire # 16 9.00 kgs @ 75.00 / kg 675.00
b.2 Equipment Rental
Bar Cutter 1.00 day/s @ 500.00 / day 500.00
Cut-Off Machine 1.00 day/s @ 1,000.00 / day 1,000.00
Material Cost ₱ 17,196.37
Labor Cost 5,158.91
Equipment 1,500.00
(A) Direct Cost ₱ 23,855.28
(B) Indirect Cost 4,771.06
VAT (5% of A and B) 1,431.32
Sub-Total Cost ₱ 30,057.65
c. Wall Footing
c.1 Steel Works 215.68 kgs
12 mm Ø RSB, ASTM Grade 40 x 9.0m 164.10 kgs @ 45.00 / kg ₱ 7,384.41
10 mm Ø RSB, ASTM Grade 33 x 6.0m 51.58 kgs @ 43.00 / kg 2,217.94
Tie Wire # 16 1.00 kg @ 75.00 / kg 75.00
d. Transformer Platform
d.1 Steel Works 926.10 kgs
20 mm Ø RSB, ASTM Grade 60 x 6.0m 549.10 kgs @ 47.00 / kg ₱ 25,807.70
16 mm Ø RSB, ASTM Grade 60 x 6.0m 205.21 kgs @ 47.00 / kg 9,644.87
12 mm Ø RSB, ASTM Grade 40 x 6.0m 45.87 kgs @ 45.00 / kg 2,064.15
10 mm Ø RSB, ASTM Grade 33 x 6.0m 125.92 kgs @ 43.00 / kg 5,414.56
Tie Wire # 16 10.00 kgs @ 75.00 / kg 750.00
b. Stairs 29.70 m2
Concrete Hollow Blocks, 100mm 390.00 pcs @ 12.00 / pc 4,680.00
Sand 1.31 m3 @ 500.00 / m3 653.40
Cement 16.00 bags @ 265.00 / bag 4,240.00
10mm dia. X 6.0m (Grade 33 ) 22.00 pcs @ 159.1 / pc 3,500.20
Tie Wire # 16 1.00 kg @ 75.00 / kg 75.00
d. Plastering [Walls along gridlines B' (3' to 6), F' (3' to 6), 226.35 m2
A (5 to 6), & H (5 to 6); Colums along gridlines B' (3' to 6),
F' (3' to 6), & 3' (B' to F'); Exposed beams along gridlines
B' (3' to 6), & F' (3' to 6); Stairs's Masonry; Canopies
along gridlines B' (4 to 6), & F' (4 to 6), and exposed
septic tank]
Sand 3.62 m3 @ 500.00 / m3 1,810.80
Cement 44.00 bags @ 265.00 / bag 11,660.00
Material Cost ₱ 53,863.90
Labor Cost 16,159.17
(A) Direct Cost ₱ 70,023.07
(B) Indirect Cost 14,008.78
VAT (5% of A and B) 4,201.59
Sub-Total Cost ₱ 88,233.44
Equipment Rental
Welding Generator Set 30.00 days @ 1,500.00 / day 45,000.00
Cut-Off Machine 30.00 days @ 1,000.00 / day 30,000.00
Material Cost ₱ 1,327,726.50
Labor Cost 398,317.95
Equipment 75,000.00
(A) Direct Cost ₱ 1,801,044.45
(B) Indirect Cost 360,182.85
VAT (5% of A and B) 108,061.36
Sub-Total Cost ₱ 2,269,288.66
Equipment Rental
Welding Generator Set 30.00 days @ 1,500.00 / day 45,000.00
Cut-Off Machine 30.00 days @ 1,000.00 / day 30,000.00
Material Cost ₱ 1,816,218.00
Labor Cost 544,865.40
Equipment 75,000.00
(A) Direct Cost ₱ 2,436,083.40
(B) Indirect Cost 487,216.68
VAT (5% of A and B) 146,165.00
Sub-Total Cost ₱ 3,069,465.08
D2a - 2.5m x 1.0m Hardwood Panel Type Door 1.00 set @ 8,750.00 / set 8,750.00
D1a - 2.5m x 1.1m Aluminum Framed Powder Coated 2.00 sets @ 12,375.00 / set 24,750.00
Dual Swing Type with Clear Glass Panel
D2 - 2.5m x 0.9m Hardwood Panel Type Door 6.00 sets @ 7,875.00 / set 47,250.00
D2a - 2.5m x 1.0m Hardwood Panel Type Door 1.00 set @ 8,750.00 / set 8,750.00
Windows
W1 - 1.2m x 2.4m Steel Casement Swing Type Window w/ 24.00 sets @ 9,875.00 / set 237,000.00
1/4" Thk. Clear Glass Panel and Security Grills
W2 - 1.2m x 1.6m Steel Casement Swing Type Window w/ 2.00 sets @ 7,301.00 / set 14,602.00
1/4" Thk. Clear Glass Panel and Security Grills
W3 - 0.4m x 2.4m Steel Casement Awning Type Window w/ 11.00 sets @ 3,653.00 / set 40,183.00
1/4" Thk. Clear Glass Panel and Security Grills
W4 - 0.4m x 1.8m Steel Casement Awning Type Window w/ 4.00 sets @ 2,736.00 / set 10,944.00
1/4" Thk. Clear Glass Panel and Security Grills
W5 - 0.4m x 1.8m Steel Casement Awning Type Window w/ 5.00 sets @ 2,746.00 / set 13,730.00
1/4" Thk. Clear Glass Panel and Security Grills
W6 - 0.4m x 1.2m Steel Casement Awning Type Window w/ 4.00 sets @ 1,824.00 / set 7,296.00
1/4" Thk. Clear Glass Panel and Security Grills
W7 - 1.5m x 3.0m Steel Casement Awning Type Window w/ 3.00 sets @ 17,100.00 / set 51,300.00
1/4" Thk. Clear Glass Panel and Security Grills
c. Ceiling 1,223.72 m2
Concrete Neutralizer 79.00 liters @ 137.65 / liter 10,874.35
Flat Latex Undercoat, White 13.00 pails @ 1,858.50 / pail 24,160.50
Semi-Gloss Acrylic Topcoat, Color 25.00 pails @ 2,215.50 / pail 55,387.50
Patching Compound 20.00 gals @ 285.00 / gal 5,700.00
Acri/Tinting Colors 392.00 qrts @ 155.00 / qrt 60,760.00
Paint Thinner 37.00 gals @ 347.00 / gal 12,839.00
Sandpapers, Rollers & Tray, Brushes, Rugs, & Newspapers 1.00 lot @ 5,000.00 / lot 5,000.00
c. Ceiling 1,424.00 m2
Concrete Neutralizer 92.00 liters @ 137.65 / liter 12,663.80
Flat Latex Undercoat, White 15.00 pails @ 1,858.50 / pail 27,877.50
Semi-Gloss Acrylic Topcoat, Color 29.00 pails @ 2,215.50 / pail 64,249.50
Patching Compound 23.00 gals @ 285.00 / gal 6,555.00
Acri/Tinting Colors 456.00 qrts @ 155.00 / qrt 70,680.00
Paint Thinner 43.00 gals @ 347.00 / gal 14,921.00
Sandpapers, Rollers & Tray, Brushes, Rugs, & Newspapers 1.00 lot @ 5,000.00 / lot 5,000.00
E. PARTITIONS 104.40 m2
Equipment Rental
Welding Generator Set 5.00 days @ 1,500.00 / day 7,500.00
Cut-Off Machine 5.00 days @ 1,000.00 / day 5,000.00
Material Cost ₱ 65,678.50
Labor Cost 19,703.55
Equipment 12,500.00
(A) Direct Cost ₱ 97,882.05
(B) Indirect Cost 19,576.41
VAT (5% of A and B) 5,872.92
Sub-Total Cost ₱ 123,331.38
GROUND FLOOR
Pinlight housing 6" dia with 15W led bulb 70.00 sets @ 750.00 / set ₱ 52,500.00
daylight, cylindrical recessed type
15W LED Compact Bulb, Daylight 68.00 pcs @ 300.00 / set 20,400.00
ceiling fan, 16" dia. 4.00 sets @ 2,500.00 / set 10,000.00
electrical tape 10.00 rolls @ 38.00 / pc 380.00
Rubber tape 3.00 roll @ 115.00 / roll 345.00
PVC 20 mm dia conduit 25.00 pcs @ 85.00 / pc 2,125.00
3.5 sq. mm THHN wire 1.00 bx @ 3,500.00 / bx 3,500.00
50 sq. mm THHN wire 60.00 m @ 450.00 / m 27,000.00
5.5 sq. mm THHN wire 2.00 bxs @ 5,500.00 / bx 11,000.00
5.5 sq. mm TW wire (grounding) 1.00 bxs @ 5,500.00 / bx 5,500.00
14.0 sq. mm TW wire (grounding) 15.00 m @ 114.00 / m 1,710.00
PVC 50 mm dia conduit 3.00 pcs @ 207.00 / pc 621.00
PVC 50 mm dia elbow 2.00 pcs @ 72.00 / pc 144.00
SECOND FLOOR
Pinlight housing 6" dia with 22W led bulb 162.00 sets @ 750.00 / set 121,500.00
daylight, cylindrical recessed type
duplex convenience outlet with grounding 66.00 sets @ 195.00 / set 12,870.00
universal type, heavy duty, 16A
Duplex socket outlet FM Grounding Type 16.00 sets @ 620.00 / set 9,920.00
Enclosed circuit breaker, 30AT, 2P, single 10.00 sets @ 1,500.00 / set 15,000.00
phase in Nema 3R, metal enclosure with grounding lug(for accu)
ceiling fan, 16" dia. 26.00 sets @ 2,500.00 / set 65,000.00
one gang switch 2.00 sets @ 150.00 / set 300.00
two gang switch 17.00 sets @ 195.00 / set 3,315.00
three gang switch 5.00 sets @ 250.00 / set 1,250.00
two gang three way switch 2.00 sets @ 217.00 / set 434.00
utility box, sch. 40 123.00 pcs @ 35.00 / pc 4,305.00
junction box with cover, sch. 40 193.00 pcs @ 35.00 / pc 6,755.00
pullbox 12" x 12" x 4" 1.00 pcs @ 550.00 / pc 550.00
electrical tape 50.00 rolls @ 38.00 / pc 1,900.00
Rubber tape 20.00 roll @ 115.00 / roll 2,300.00
Mica tube 1/4" 200.00 m @ 20.00 / m 4,000.00
tie wire 5.00 kls @ 75.00 / kl 375.00
PVC solvent 3.00 can @ 265.00 / can 795.00
PVC 20 mm dia conduit 886.00 pcs @ 85.00 / pc 75,310.00
3.5 sq. mm THHN wire 18.00 bxs @ 3,500.00 / bx 63,000.00
5.5 sq. mm THHN wire 17.00 bxs @ 5,500.00 / bx 93,500.00
5.5 sq. mm TW wire (grounding) 9.00 bxs @ 5,500.00 / bx 49,500.00
60 sq. mm THHN wire 100.00 m @ 492.00 / m 49,200.00
22 sq. mm TW wire (grounding) 25.00 m @ 157.00 / m 3,925.00
PVC 50 mm dia conduit 10.00 pcs @ 207.00 / pc 2,070.00
PVC 50 mm dia elbow 4.00 pcs @ 72.00 / pc 288.00
grounding rod with clamp 5/8" x 10' 2.00 set @ 1,500.00 / set 3,000.00
other miscellaneous items 1.00 lot @ 10,000.00 / lot 10,000.00
and consumables such as bolts, cable tie,
terminal lugs, tagging tape, compression tap,
solderless connector etc.
other miscellaneous items and consumables 1.00 lot @ 10,000.00 / lot 10,000.00
such as cable tie, terminal lugs, tagging tape,
compression tap, etc.
E. Vent Line
3"Ø x 3m PVC Pipe 2.00 pcs @ 547.00 / pc 1,094.00
3"Ø Coupling 1.00 pc @ 65.00 / pc 65.00
4"Ø x 3"Ø Wye Reducer 1.00 pc @ 190.00 / pc 190.00
4"Ø x 2"Ø Wye Reducer 5.00 pcs @ 119.00 / pc 595.00
3"Ø 45° Elbow 1.00 pc @ 43.00 / pc 43.00
3"Ø x 2"Ø Coupling Reducer 9.00 pcs @ 22.00 / pc 198.00
2"Ø PVC Pipes 17.00 pcs @ 255.00 / pc 4,335.00
2"Ø Coupling 13.00 pcs @ 15.50 / pc 201.50
2"Ø 45° Elbow 20.00 pcs @ 59.00 / pc 1,180.00
PVC Solvent cement 2.00 liters @ 420.00 / pc 840.00
Equipment Rental
2 1-Bagger Concrete Mixers 5.00 day/s @ 1,500.00 / day 15,000.00
Welding Generator Set 10.00 days @ 1,500.00 / day 15,000.00
Cut-Off Machine 10.00 days @ 1,000.00 / day 10,000.00
Material Cost ₱ 579,306.10
Labor Cost 173,791.83
Equipment 40,000.00
(A) Direct Cost ₱ 793,097.93
(B) Indirect Cost 158,625.00
VAT (5% of A and B) 47,586.15
Sub-Total Cost ₱ 999,309.08
GRAND SUMMARY
Approved:
I. Excavation = 1,026.05 m3
Summary: II. Backfill & Compaction = 968.13 m3
III. Gravel Bedding = 35.57 m3
A. SPREAD FOOTING
Designation: C4/F4
No. of Footing = 12 pcs Excavation = 206.01 m3
Length = 2.45 m Backfill = 169.46 m3
Width = 2.45 m Gravel Bed = 7.92 m3
Thickness = 0.35 m
Base depth from NGL = 2.50 m Comment/s:
Column Area = 0.16 m 2 Additional 10% volume of excavation in order to
Gravel Bed Thickness = 0.10 m accommodate the whole dimension of the footings.
B. WALL FOOTING
Designation: W1F1
Footing Length = 56 m Excavation = 17.25 m3
Footing Width = 0.40 m Backfill = 7.87 m3
Footing Thickness = 0.15 m Gravel Bed = 2.46 m3
Base depth from NGL = 0.60 m
Gravel Bed Thickness = 0.10 m Comment/s:
CHB Thickness = 0.15 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
C. SLAB ON GRADE
Overall Area = 112 m2 Excavation = 0.00 m3
Gravel Bed Thickness = 0.10 m Backfill = 0.00 m3
Gravel Bed = 11.20 m3
Comment/s: ok
D. FOOTING BEAM
Designation: FTB2
No. of Beams = 20 pcs Excavation = 59.40 m3
Length of Beam = 4.00 m Backfill = 47.40 m3
Depth = 0.40 m Gravel Bed = 2.64 m3
Base Width = 0.30 m
Base depth from NGL = 2.15 m Comment/s:
Gravel Bed Thickness = 0.10 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the beams.
E. RICE bran
Designation: rice bran
Length = 28.00 m Excavation = 743.40 m3
Width = 17.70 m Backfill = 743.40 m3
Depth = 1.50 m Gravel Bed = 0.00 m3
F. Walkway
Designation: rice hay
Length = 58.00 m Excavation = 0.00 m3
Width = 1.70 m Backfill = 0.00 m3
Depth = 0.10 m Gravel Bed = 11.34 m3
G. Demoition
G.-1
Designation: 1st Floor Line B' & F' (3'to 5)
No. of Sets = 2 sets Area of CHB = 5.20 m2
Length = 2.00 m
Height = 1.30 m Comment/s:
No. of Face(s) = 1.00
CONCRETE WORKS
A. LEAN CONCRETE
Designation: Footing C4/F4
No. of Footing = 12 pcs Volume of Concrete = 3.96 m3
Length = 2.45 m
Width = 2.45 m Comment/s: Please check the thickness of lean concrete.
Thickness of Lean = 0.05 m
B. FOOTING
Designation: C2/F2
No. of Footing = 2 pcs Volume of Concrete = 1.24 m3
Length = 1.50 m
Width = 1.50 m Comment/s:
Thickness = 0.25 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
Designation: C2/F3
No. of Footing = 3 pcs Volume of Concrete = 1.29 m3
Length = 1.25 m
Width = 1.25 m Comment/s:
Thickness = 0.25 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
Designation: C2/F1
No. of Footing = 2 pcs Volume of Concrete = 1.12 m3
Length = 1.30 m
Width = 1.30 m Comment/s:
Thickness = 0.30 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
Designation: C2/F23A
No. of Footing = 2 pcs Volume of Concrete = 0.66 m3
Length = 1.00 m
Width = 1.20 m Comment/s:
Thickness = 0.25 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
Designation: 12/F3A
No. of Footing = 1 pcs Volume of Concrete = 0.33 m3
Length = 1.00 m
Width = 1.20 m Comment/s:
Thickness = 0.25 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
Designation: 12/F3A
No. of Footing = 1 pcs Volume of Concrete = 0.33 m3
Length = 1.00 m
Width = 1.20 m Comment/s:
Thickness = 0.25 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
Designation: 12/F3A
No. of Footing = 1 pcs Volume of Concrete = 0.33 m3
Length = 1.00 m
Width = 1.20 m Comment/s:
Thickness = 0.25 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
B. COLUMNS
Designation: C1
No. of Columns = 2 pcs Volume of Concrete = 0.79 m3
Length of Column = 4.20 m
Column Width1 = 0.30 m
Column Width2 = 0.30 m
Designation: C2
No. of Columns = 10 pcs Volume of Concrete = 3.97 m3
Length of Column = 4.20 m
Column Width1 = 0.30 m
Column Width2 = 0.30 m
Designation: Wall Footing
Footing Length = 56 m Volume of Concrete = 3.70 m3
Footing Width = 0.40 m
Footing Thickness = 0.15 m Comment/s:
Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
C. SLABS
Designation: Slab on Grade
Overall Area = 0 m2 Volume of Concrete = 0.00 m3
Slab Thickness = 0.100 m
Comment/s: Di pa kasama ang flooring sa labas na part.
Designation: S2 - Suspended Slab Covered Corridor / Walkway 2nd Floor
Overall Area = 0 m2 Volume of Concrete = 0.00 m3
Slab Thickness = 0.125 m
Comment/s:
Designation: Walkway
Overall Area = 98.6 m2 Volume of Concrete = 21.69 m3
Slab Thickness = 0.200 m
D. BEAMS
Designation: FTB2 - Footing Beams
No. of Beams = 0 pcs Volume of Concrete = 0.00 m3
Length of Beam = 4.00 m
Depth = 0.40 m Comment/s:
Base Width = 0.30 m Additional 10% volume of excavation in order to
accommodate the whole dimension of the footings.
E. COLUMNS
Designation: C4 - 1st Floor
No. of Columns = 0 pcs Volume of Concrete = 0.00 m3
Length of Column = 7.70 m
Column Width1 = 0.40 m Comment/s:
Column Width2 = 0.40 m Dun palang ito sa dinagdag na building.
A. EXTERIOR WALLS
Designation: 1st Floor Line 6 (B'to F')
No. of Sets = 0 sets Area of CHB = 0.00 m2
Length = 4.00 m
Height = 2.60 m Comment/s:
Height is from top of wall footing.
B. INTERIOR WALLS
Designation: 2nd Floor masonry (classrooms and hagdan interior)
No. of Sets = 10 sets Area of CHB = 132.00 m2
Length = 4.00 m
Height = 3.30 m Comment/s:
Add the retractible partition wall in the final estimate.
Designation: stairs
No. of Sets = 4 sets Area of CHB = 29.70 m2
Length = 9.00 m
Height = 0.83 m Comment/s:
C.. PLASTERING
C.1 - WALLS
C.2 - COLUMNS
Designation: C4 - 1st Floor Line 5 & 6 (B'to F')
No. of Sets = 0 sets Area of Plastering = 0.00 m2
Height = 3.275 m
Column W = 0.40 m Comment/s: Check sa actual if 16 talaga.
No. of Face(s) = 4.00 1/2 interior, 1/2 exterior
C.3 - BEAMS
Designation: B3 - 2nd Floor
No. of Sets = 0 sets Area of Plastering = 0.00 m2
Beam Length = 4.000 m
Beam Depth = 0.450 m Comment/s:
Beam Width = 0.35 m all interior
Designation: B4 - 2nd Floor
No. of Sets = 0 sets Area of Plastering = 0.00 m2
Beam Length = 4.000 m
Beam Depth = 0.450 m Comment/s:
Beam Width = 0.30 m 1/2 interior, 1/2 exterior
C.6 - STAIRS
Designation: stairs
No. of Sets = 3 sets Area of Plastering = 44.55 m2
Length = 9.00 m
Height = 0.83 m Comment/s:
all interior
Interior
Length = 209.425 ln.m Reduced Area = 1559.365 m2
Height = 3.3 m
Total Area = 1382.205 m2
Columns
Interior
Columns = 21 pcs Total Area = 108.9 m2
Width = 0.5 m
Height = 3.3 m
Beams
Interior
Length = 296 ln.m Total Area = 355.2 m2
Depth = 0.45 m
Width = 0.3 m
PAINTING WORKS
I. = m3
Summary: II. = m3
III. = m3
Columns
C4 - 1st Floor Line 5 & 6 (B'to F') 0 m2 0 m2
C1 & C2 - 1st Floor Line 3' (B'to F') 20.4 m2 0 m2
C4 - 1st Floor Line B' & F' (3'to 5) 10.88 m2 0 m2
Beams
B3 - 2nd Floor 0 m2 0.00 m2
B4 - 2nd Floor 0 m2 0 m2
Slanted Canopy
1st flr Slanted Canopy 46.72 m2 0 m2
Stairs
3 units stairs 0 m2 44.55 m2
151.42 m2 92.55 m2
Columns
C4 - 2nd floor 13.335 m2 13.335 m2
C1 - 2nd floor 15.24 m2 25.4 m2
Beams
RB1A - Roof Beam 2.5454545 m2 5.4545455 m2
RB1 - Roof Beam 16 m2 32 m2
RB4 - Roof Beam 19.2 m2 57.6 m2
RCB1 - Roof Beam 0 m2 3.24 m2
RCB2 - Roof Beam 0 m2 11.88 m2
Concrete Gutter
Concrete Gutter 116.00 m2 0 m2
508.21 m2 540.89 m2
Walls
Exterior
Length = 136 ln.m Reduced Area = 371.4 m2
Height = 3.3 m
Total Area = 448.8 m2
Interior
Length = 209.425 ln.m Reduced Area = 1559.365 m2
Height = 3.3 m
Total Area = 1382.205 m2
Columns
Exterior
Columns = 24 pcs Total Area = 39.6 m2
Width = 0.5 m
Height = 3.3 m
Interior
Columns = 21 pcs Total Area = 108.9 m2
Width = 0.5 m
Height = 3.3 m
0 m2
0 m2
Canopy
Exterior
Length = 109.75 ln.m Total Area = 160.235 m2
Perimeter = 1.46 m
SUMMARY of C
Exterior Interior
912.28 m2
1,668.27 m2
Walls
Exterior
Length = 128 ln.m Reduced Area = 488.72 m2
Height = 4 m
Total Area = 512 m2
Columns sa porch
Exterior
Columns = 4 pcs Total Area = 32 m2
Width = 0.5 m
Height = 4 m
Canopy
Exterior
Length = 46.4 ln.m Total Area = 67.744 m2
Perimeter = 1.46 m
Columns
Interior
Inside = 13 pcs Total Area = 85 m2
Outside = 24 pcs
Width = 0.5 m
Height = 3.4 m
2nd flr computation
COLUMN FORMS
Input longer dimension: 0.4 m No. of plywoods (1.2 x 2.4):
BEAM FORMS
Input depth of beam: 0.35 m No. of plywoods (1.2 x 2.4):
SLAB FORMS
Input concrete slab area: 0 m^2 No. of plywoods (1.2 x 2.4):
COLUMN SCAFFOLDING OR STAGING
15 pcs Vertical support (2" x 3"): 162 bd.ft
Horizontal support (2" x 2"): 486 bd.ft
Brace support (2" x 2"): 271 bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
STEEL WORKS
A. FOOTINGS
Designation: C4/F4 - Spread Footing
Longer Dimension: 2.45 m Shorter Dimension: 2.45 m
No. of cut bars: 12 pcs No. of cut bars: 12 pcs
No of footings: 12 No of footings: 12
Bar Length with Hook: 2.6 m Bar Length with Hook: 2.6 m
Total number of cut bars: 144 Total number of cut bars: 144
Comment/s: ok
Comment/s: ok
C. SLABS
Designation: Slab on Grade
Longitudinal Dimension: 4 m Transverse Dimension: 4 m
Spacing of Bars: 0.4 m Spacing of Bars: 0.4 m
Number of Sets: 7 sets Number of Sets: 7 sets
Hook Length: 0.2 m Hook Length: 0.2 m
Total Number of Cut Bars: 77 Total Number of Cut Bars: 77
Bar Length with Hook 4.4 m Bar Length with Hook 4.4 m
D. BEAMS
Designation: FTB2 -Footing Beams
No. of Beams: = 0 pcs At Support: TOP Bar = 4 pcs
Beam Length (CTC): = 4.0 m BOT Bar = 2 pcs
Beam Depth: = 0.4 m
Beam Width: = 0.3 m At Midspan: TOP Bar = 4 pcs
Column 1 Dimension: = 0.4 m BOT Bar = 2 pcs
Column 2 Dimension: = 0.4 m
Main Bar Diameter = 20 mm # of Non-continuous Bar:
Hook Length: = 0.25 m At 1 Support = 0 pcs
Clear Span (L) = 3.6 m At Midspan = 0 pcs
Total Number of Cont. Bar = 195 pcs @ 6.0 m ----------> 7.3846154 pcs
Continuous Bar Length = 1.4 m @ 7.5 m ----------> 9.2307692 pcs
@ 9.0 m ----------> 11.076923 pcs
@ 6.0 m ----------> 4.2857143 pcs ADOPT: 2 pcs
@ 7.5 m ----------> 5.3571429 pcs 6.0 m
@ 9.0 m ----------> 6.4285714 pcs Total no. of bars: 0 pcs
ADOPT: 4 pcs
6.0 m RSB Ø kg/m kgs
Total no. of bars: 49 pcs 10 0.617 0.00
12 0.888 0.00
RSB Ø kg/m kgs 16 1.578 0.00
10 0.617 181.40 20 2.467 0.00
12 0.888 261.07 25 3.854 0.00
16 1.578 463.93
20 2.467 725.30 At Midspan:
25 3.854 1,133.08 Total No. of Main Bars = 0 pcs
Bar Length = 0.15 m
STIRRUPS:
Length of Stirrups = 1.25 m @ 6.0 m ----------> 40 pcs
No. of Stirrups / Beam = 10 pcs @ 7.5 m ----------> 50 pcs
Diameter of Stirrups = 10 mm @ 9.0 m ----------> 60 pcs
ADOPT: 1 pcs
@ 6.0 m ----------> 4.8 pcs 6.0 m
@ 7.5 m ----------> 6 pcs Total no. of bars: 0 pcs
@ 9.0 m ----------> 7.2 pcs
ADOPT: 6 pcs RSB Ø kg/m kgs
7.5 m 10 0.617 0.00
Total no. of bars: 30 pcs 12 0.888 0.00
16 1.578 0.00
RSB Ø kg/m kgs 20 2.467 0.00
10 0.617 138.83 25 3.854 0.00
12 0.888 199.80
WATERPROOFING
A. ROOF SLAB
Designation: Area Bounded by (5 to 6) and (B'to F')
No. of Sets = 0 sets Area of Waterproofing = 0.00 m2
Length = 4.00 m
Width = 4.00 m
B. CONCRETE GUTTER
Designation: Gutter
Linear Meter = 116.00 m Area of Waterproofing = 133.40 m2
Perimeter = 1.15 m
208 ang buong building gutter line
CEILING WORKS
A. 1st Floor
Designation: CF-2 Area Bounded by (5 to 6) and (B'to F')
No. of Sets = 7 sets Area of CHB = 112.00 m2
Length = 4.00 m
Width = 4.00 m Comment/s: CF2
B. 2nd Floor
B-1 . C1
Designation: CF-1 Area Bounded by (4 to 5) and (A to B and G to H)
No. of Sets = 8 sets Area of CHB = 128.00 m2
Length = 4.00 m
Width = 4.00 m Comment/s: CF1
B-2. C2
Designation: CF-2
2nd Floor Area = 1,536.00 m2 Area of CHB = 614.38 m2
2nd Flr CF1 Area = 921.63 m2
Comment/s: CF2
TILING WORKS
A. 2nd Floor
Designation: 2nd flr except cr
Area of Tiling = 1,452.20 m2 Area of Tiling = 1,452.20 m2
B. Stairs
Designation: all 4 stairs
Stairs = 84.70 m2 Area of Tiling = 116.70 m2
below 1 stair = 32.00 m2
C. 1t Floor
Designation: covered corridor
Area of Tiling = 112.00 m2 Area of Tiling = 112.00 m2
PLUMBING WORKS
A. CATCH BASINS
No. = 31 pcs CHB Area = 44.64 m2
Width = 0.6 m Plastering Area = 100.44 m2
Height = 0.6 m Cover & Bot Slab = 4.464 m3
Thickness = 0.1 m RCPC Concrete Cover x 2 multiplier
RCPC
Summary: = m2
C. MASONRY REDUCTION
Exterior Wall
W1 4 sets x 2.88 m2 = 11.52 m2
W5 2 sets x 0.72 m2 = 1.44 m2 22 m2 Ok na naibawas na.
W7 2 sets x 4.5 m2 = 9 m2
Interior Wall
D1 4 sets x 2.75 m2 = 11 m2
W3 2 sets x 0.86 m2 = 1.72 m2 12.7 m2 Ok na naibawas na.
Project Title: 0
###
Location: 0
ROOFING
A. TRUSSES
Designation: T2
No. of Sets = 6 sets
Designation: HT5
No. of Sets = 4 sets
WEB MEMBERS
1) Total Length = 21.159 m Summary:
Double Angle? = 2 Angles 23 pcs, 65mm x 65mm x 6mm Angle Bars
Order: 32 pcs 32 pcs, 50mm x 50mm x 6mm Angle Bars
50mm x 50mm x 6mm Angle Bars 72 connections
CONNECTIONS = 18
Designation: HT6
No. of Sets = 2 sets
WEB MEMBERS
1) Total Length = 15.238 m Summary:
Double Angle? = 2 Angles 8 pcs, 50mm x 50mm x 6mm Angle Bars
Order: 12 pcs 12 pcs, 50mm x 50mm x 4.5mm Angle Bars
50mm x 50mm x 4.5mm Angle Bars 28 connections
CONNECTIONS = 14
Designation: HT7
No. of Sets = 8 sets
WEB MEMBERS
1) Total Length = 5.361 m Summary:
Double Angle? = 2 Angles 16 pcs, 50mm x 50mm x 6mm Angle Bars
Order: 16 pcs 16 pcs, 50mm x 50mm x 4.5mm Angle Bars
50mm x 50mm x 4.5mm Angle Bars 64 connections
CONNECTIONS = 8
Designation: LB1
No. of Sets = 4 sets
TOP CHORDS BOTTOM CHORDS
1) Length of Cut = 4.000 m 1) Length of Cut = 4.000 m
No. of Cuts = 4 cuts No. of Cuts = 4 cuts
@ 6.0 m ---> 1.5 pcs @ 6.0 m ---> 1.5 pcs
ADOPT: 1 pcs ADOPT: 1 pcs
Order: 16 pcs Order: 16 pcs
50mm x 50mm x 6mm Angle Bars 50mm x 50mm x 6mm Angle Bars
exces: 2 m, 16 pcs exces: 2 m, 16 pcs
WEB MEMBERS
1) Total Length = 20.320 m Summary:
Double Angle? = 2 Angles 32 pcs, 50mm x 50mm x 6mm Angle Bars
Order: 30 pcs 30 pcs, 50mm x 50mm x 4.5mm Angle Bars
50mm x 50mm x 4.5mm Angle Bars 36 connections
CONNECTIONS = 36
Designation: LB1A
No. of Sets = 2 sets
WEB MEMBERS
1) Total Length = 10.657 m Summary:
Double Angle? = 2 Angles 0 pcs, 50mm x 50mm x 6mm Angle Bars
Order: 8 pcs 8 pcs, 50mm x 50mm x 4.5mm Angle Bars
50mm x 50mm x 4.5mm Angle Bars 40 connections
CONNECTIONS = 20
B. ROOFING AREA
Designation: Roofing Comment/s:
Area of Roofing = 392.064 m2 May 200mm na extension mula sa one end ng truss
Length of Ridge = 20.000 m dahil sa papunta sa gutter na sobra.
Length of Hip = 32.544 m
Summary:
438 ln.m 0.6mm thk. Pre-painted long-span Corrugated Roofing Sheets
10 rolls Polyethylene Double Film Foam Roof Insulation ( 1.2 meters x 40 meters x 5mm)
3099 pcs, Tekscrew s
10 pcs, Pre-painted Ridge Rolls, Ga #24
15 pcs, Pre-painted Hipped Rolls, Ga #24
C. MISC.
Designation: Purlins Summary:
Total length = 640.000 m 112 pcs, 150mm x 50mm x 2.0mm C-Purlins x 6M
Designation: Sogrods
Summary:
16 pcs, 12mm Ø Sagrods x 6M