Professional Documents
Culture Documents
CDR - Damish - 230223 - 223031
CDR - Damish - 230223 - 223031
CDR - Damish - 230223 - 223031
The report is my own work and is a true representation of my personal competence in written
English.
I confirm that I understand that members of the engineering team in Australia are required to
display a commitment to exercising professional and ethical responsibility in all aspects of their
work ’.
Signature: ___________________________________________________________________
Date: _______________________________________________________________________
b) Background
Engro Chemicals Pakistan Limited (now Engro Fertilizer Pakistan Limited) is one of the
leading Fertilizer producing companies currently operating in Pakistan. In order to cater
for the increasing demand for chemical Fertilizer in Pakistan and abroad, Engro ventured
for the largest Ammonia / Urea complex in Pakistan, with the largest Heat Train in Asia.
It’s designed at a tremendous capacity of 2,194 MTPD (metric tons per day) of Ammonia
& 3,834 MTPD of Urea.
My responsibilities for the Daharki Site Expansion Project included but were not limited
to the following:
• Area Planning for Reformer Unit (Furnace, Heat Effluent Exchangers, Steam Drum,
Waste Heat Boiler).
• Monitoring and updating Daily / Weekly Progress Reports and Weekly Level 4 Plan
for Reformer Unit.
• Supervision of Field Execution Team, and coordination with QA/QC and HSE
Departments for efficient time management.
• Administering consumable and non-consumable material status and utilization.
• Launching material Indents, Technical Queries in coordination with Procurement
Department.
• Maintaining direct contact with Client as well as Engineering Consultant and
Vendors.
• Provision of work to Sub-contractors and Third Parties.
• Maintaining and Expediting Welding inspection and Radiographic / Ultrasound Test
Reports.
• Providing Work-front to Welding, Rigging and Refractory Teams, such as Weld
Procedure Specification / PQR, Refractory Calculations.
• Studying and expedition of engineering design material such as Equipment and
Layout drawings, Isometric Drawings, Plot Plans, and other relevant technical
Documents.
C.E. 1.1 My preliminary goal on arrival on site was to get acquainted with the basics, then
gradually get a thorough understanding of the activities involved in the construction of
the Reformer Unit, the area I was deployed to mostly throughout my tenure on site. As
this was my first construction project, these few initial steps were critical for me and the
project as they would prove to be advantageous in my later role as acting site in-charge
for this unit. My personal engineering activities consisted included but not limited to the
following:
C.E. 1.2.1 I had to learn and assimilate these policies and procedures as safety always comes first.
Also I had to provide an exemplary role as an engineer in-order to implement and
maintain the strictest attitude towards HSE. I learned and advocated the;
C.E. 1.2.2 As an example of strict safety policies followed at site, I reviewed and modified the JSA
(Joint Safety Analysis) mandatory for entry of Vessels for work, in this case the
Secondary Reformer, for safe execution of work inside the vessel.
C.E. 1.3.1 It was a challenge to acquaint myself with fine details of every module of the unit. I set
myself to study the layouts, mechanical drawings and design parameters of the following
equipment:
• Primary Reformer
• Secondary Reformer
• Fuel Gas System (including Burners)
• Flue Gas System (including Blowers)
• Pneumatically actuated Damping System
• Cold & Hot Collectors
• Catalytic Convertor Tubes
• Effluent Heat Exchangers Package, including
o Waste Heat Boiler
o Ammonia Synthesis Heat Exchangers
o Steam Drum
C.E. 1.3.2 In doing so, I made it mandatory upon myself to get accustomed with the necessary
Codes and Standards, for instance for refractory works of the start-up heater, anchor
pins had to be welded to the panels of the heater. The pins carried the code TP 310,
whereas the panel plates were of AISI 304 (Stainless Steel), this is where I intervened
with the welding team to point out that in-fact ER Ni-Cr-3, a filler wire used for Gas Metal
Arc Welding, should be used in place of E-309, an electrode used for Shield Metal Arc
Welding. This was critical for the final firing of the heater, as the joint would have been
too weak to hold the 25mm ceramic fiber insulation sheets against the heater panels. In-
order to proceed I asked the QA/QC department to develop a Weld Procedure
Specification to complete the work on time, to avoid any delays.
C.E. 1.3.3 Each equipment had associated drawings and documents (such as data sheets), which I
studied in-order to guide the field execution team towards systemized installation of the
equipment. For example, the Cold Collector had 12 segments in total, of which 6 had to
be placed on slide supports. However, the base plate of the cold collector segment had
to be welded with a 5 mm stainless steel plate, which then had to be placed on top of a
Teflon plate (to minimize friction) and was finally placed on the sliding support.
C.E. 1.3.4 As I was in-charge of the area at that time it was my responsibility, so I guided the
execution team to carefully fabricate the plates and place the cylindrical cold collector
segments such that they are completely in-line with the supports.
C.E. 1.4.1 This is where I worked hard to gain insight into the proper engineering practices to
successfully plan and execute (supervise) the job at hand.
C.E. 1.5.2 Moreover, time and budget were my primary concerns for the efficient completion of the
project. Due to constraints, these parameters had to be monitored on a daily basis so as
not to exceed the allotted estimation.
C.E. 1.5.3 I thoroughly familiarized myself with the governing codes and standards as it would
prove to be essential in some cases. As an example, the Risers and Downcomers
(Waste heat Boiler components) materials specifications were in accordance with a
different standard being followed by BORSIG (vendor).
C.E. 1.5.4 Therefore, I requested the QA/QC department of Engro and Descon to formulate a
standard WPS in lieu of the ones already being followed, such as the one specified by
GRANZIERA (Vendor) for the Cold Collector. For instance the filler wire for an A-105 to
A-105 valve / 16Mo3 Reducer was specified as EML 5 / Argon, in terms of the WPS
already being followed, this was equivalent to ER-70 S3. This helped in clarification of
the general uncertainties faced by not only me and my team, but the client as well.
C.E. 1.6.1 I had to maintain constant correspondence with QA/QC department throughout the
project tenure, not only because it was essential in terms of contractual agreement but
because I was obligated to uphold the highest level of quality in my teams work.
C.E. 1.6.2 I requested the QA/QC department by filing a Request for Inspection and Testing (RIT)
form for a whole range of inspection activities including:
C.E. 1.7.1 Although the E&I department was separately responsible for its activities, I had to help
my team in paving the way for its activities, as E&I activities preceded, succeeded or ran
in parallel with mechanical ones. This required tremendous planning and
correspondence with E&I department to ensure timely and conflict-free installation of:
• Pressure / Temperature / Level Transmitters
• Control Valves
• Actuating Equipment
• Cable Trenches / Trays
C.E. 1.8.1 The area I was working in comprised pupils from different ethnic and language
backgrounds, such as Italians, Germans, Australians, and most from different regions of
C.E. 1.8.2 For instance, RCR Heat Treatment Pty. Ltd. (Australian) was hired for the dry out of
refractory of Secondary Reformer, Waste Heat Boiler and Cold Collector. A team of four
persons (English Speaking) along with the blower heat train equipment arrived to carry
out this procedure. Most of the supervisors and workers at site could only communicate
in Urdu (a native language). Therefore, I proceeded to take the role of an interpreter
between the two teams.
C.E. 1.8.3 The first layer of refractory had to be dried out at 250 C and the final layer at 450 C.
Therefore, I planned and supervised my team for the timely completion of casting of
refractory, this included;
• Calculating total tons of refractory for each layer and;
• Distributing it over the duration between dry-outs.
C.E. 1.8.4 The shuttering, a very critical part of the casting, had to fabricated and installed at exact
dimensions. Moreover, the casting had to be done overnight so as to cure for certain
time and temperature. Furthermore, the shuttering had to be fabricated using Low
Carbon Steel (ASTM A-53) sheets of different thicknesses. Therefore, I deduced a re-
order level of different materials (consumable and non-consumable) and tools required
along with the total required over the time period. This brought about a target and
forecasted status for the items.
C.E. 1.9.1 I had to bear not one but many challenging situations as I was site in-charge of the
whole Reformer Unit, with manpower ranging from 250 to 350 at a time. During this time
any loss of time and money was to be on my shoulders. Therefore, I fulfilled my job with
zeal and dedication gaining a complete contentment in my capabilities from the company
as well as client.
d) Summary
This project was my first construction project and to be able to lead a very large team of
experience personnel has been very beneficial experience for me. I coordinated
between disciplines, client and vendors continuously through the tenure and have
gained a wider knowledge and know-how of activities and challenges of executing large
scale projects. In a nutshell, my work experience on the project strengthened my abilities
both as a planning and a mechanical engineer.
b) Background
I was recruited in ARL primarily as a Senior Management Trainee (Mechanical),
however, I was performing my duties as a Mechanical / Planning Engineer. The
maintenance department was distributed into different sections, I was designated to
Plant Maintenance 2 which included the following areas:
Plant Area:
• 5,500 BPD Crude Distillation Unit.
• 10,000 BPD Heavy Crude Unit (2 - STAGE i.e. Atmospheric and Vacuum).
Utilities Area:
• 7.5 MW Power Plant (included three 2.5 MW Gensets) running on Furnace Fuel Oil.
• Boilers (2 x 12 ton per hour Superheated Steam Boilers and 3 x 10 ton per hour
saturated steam Boilers).
• Air Compressor House (one 2-phase multistage compressor at 350 m3 per hour).
I performed numerous tasks through the duration of my tenure there; however, I will
narrate my account through the major activities I performed.
My responsibilities included:
• Study of Equipment and Layout drawings, Piping Isometric Drawings, Operation &
Maintenance Manuals and other technical Documents.
• Feasibility, supervision and monitoring of; Corrective / Routine / Preventive
Maintenance and Trouble-Shooting of various Plant equipment.
• Coordination of Projects; Planning and Supervision of Maintenance / Installation
activities in addition to Shutdowns / Turnaround jobs of refinery plants.
• Study and Management of Equipment hierarchy, Assets Catalogue and its
classifications, and Equipment History documentation.
• Development of Preventive Maintenance Schedules and Standard Operating
Procedures.
• Expedition and Management of Work Orders, Job plans, Job tasks, Job material,
Safety plans and Tools.
• Administration of Inventory records for equipment spare parts.
• Study basic refinery chemical processes.
• Launching Purchase Inquiries, Material Requisitions and Purchase Orders.
Projects Executed:
• Shutdown of Lummus (5,000 BPD) Distillation Plant; repair of Atmospheric Tower
Heater Tubes and Burner
• Shutdown of Heavy Crude Unit (10,000 BPD); complete unit inspection and
replacement of Exchanger Bundle
• 2.5 MW Diesel GenSet: 48,000 hrs Major Maintenance / Overhaul
• Annual Turnaround of Babcock & Wilcox Water Tube Boiler (Superheated Steam: 20
ton/h) and Descon Fire Tube Boiler(Saturated Steam: 12 ton/h)
C.E. 2.1 As an engineer, I was determined to get accustomed to Health, Safety and Environment
standards particularly in my line of work. The refinery is a potentially hazardous work
place, where a life threatening incident can take place following a slight mishap. My
priority was to learn and promote:
C.E. 2.2 I discovered earlier on that in-order to apply engineering knowledge and skills, especially
on a pragmatic level, I not only had to suffice my superior but myself as well. Therefore, I
studied the design and operation of all the mechanical equipment (static and rotary
present in my area such as;
• Pumps
• Compressors
• Heat Exchangers
• Valves
• Boilers
• Cooling Towers
• Power generators (Engine Operated)
C.E. 2.4.2 For instance, during a simple startup of the Diesel engine the control panel indicated a
pressure drop in the lube oil system. Upon query by my superior I pointed out that there
can only be two causes, one; a malfunction in the Lube Oil Purifier, and two; a blockage
in the Lube Oil / Cooling water heat exchanger. Thus, he instructed the team to explore
both options. The problem was eventually identified in the Lube Oil Purifier.
C.E. 2.5.2 I documented all the plant equipment in my area, the information included operating /
design parameters and preventive maintenance procedures, along with the necessary
documents which I then handed over to the CMMS department. They stored it into the
MAXIMO database, which later help me in recording and monitoring Key Performance
Index for a particular Plant asset.
C.E. 2.6.2 On the instructions of my superior, I identified all the main problems which needed to be
attended to. I asked the Operations department to provide a list of all equipment with
discrepancies in regard to operational procedure. On basis of that list I devised a
possible scenario for each problem; this was done with the help of a senior maintenance
supervisor whose job was to aid me in formulating a solution to these specific problems
on the basis of past experience.
C.E. 2.6.3 For example, the operations department identified an inconsistency in the Naptha
stabilizer unit, mainly; tremendous surge of flow and pressure of stabilized Naptha and
inclusion of impurities. Upon further investigation the problem was identified in the heat
in which raw water (fluid in the tubes) was being mixed with Naptha (fluid in the shell,
recovered from atmospheric tower). This required immediate bypassing of the
C.E. 2.6.4 I supervised and monitored the maintenance activities, besides performing the
preliminary studies and ordering of parts for equipments according to the required
design conditions, such as tube material, design tempurature / pressure etcetera. Major
activities performed during shutdown included:
C.E. 2.7.1 I corresponded with many departments and sections of the refinery including but not
limited to:
• Operations department
• E&I department
• HSE department.
C.E. 2.7.2 I maintained direct contact with all the personnel for smooth and efficient completion of
the governing activities including Managers, Foremen / Supervisors, Fitters etcetera.
C.E. 2.8.1 Attock Refinery Limited requires its employees, especially of the Senior Management
cadre to be acquainted with Management Systems of International Standards which are
a vital part of its business strategy.
C.E. 2.8.2 Therefore, as a Trainee I learnt and understood the ISO Management Systems which,
mainly ISO 9001:2000 Quality Management System, ISO 14001:2004 Environment
Management System and OHSAS 18001:1999 Occupational Health and Safety.
C.E. 2.8.3 During the external audit held in October-November 2008 by SGS, I developed an action
list, which identified the key corrections made against the objections (identified by the
audit team for the previous year, i.e. 2007). I performed the necessary activities to
improve this list such as:
C.E. 2.9.1 Aside from the shutdown activities, which required careful technical and communication
skills, I studied the piping networks and configurations, prepared BOQs and cost
estimates, performed line tracing of the plant which was essential for gaining a complete
understanding and working principle of the plant.
C.E. 2.9.3 I studied the original design of the machinery and proposed any modifications to the
material, dimensions and working cycle to reduce any chances of machinery failure.
Some maintenance activities had to be anticipated (Predictive Maintenance) beforehand
to reduce downtime such as draining / venting / cleaning of Strainers, Valve seats and
spring mechanisms, steam traps, steam ejectors, de-aerators etcetera.
C.E. 2.9.4 On various occasions the plant machinery required replacing parts such as Bearings,
Mechanical Seals (bellows, dry-gas), piston rings, Impellers, rotating shafts etcetera. I
supervised these activities and maintained an inventory record for each part.
d) Summary
I had the tremendous opportunity to work for a well established and experienced
Industry with a wide array of professional engineers and technicians. This contributed
greatly in my understanding of mechanical equipment and machinery on a more
practical level.
b) Background
Due to the recent importance of considering product life cycle and the dynamic change
in the manufacturing paradigm from the current mass production to sustainable
production, I envisaged the immense importance of Modular Design.
Initially, the priority between each interface is introduced. Then this priority information is
available for stepwise modular breakdown considering the design intention from the
upper design stage to the lower design stage. A module is any functionally complete
device, or sub-assembly, that can be independently operated and can be readily fitted
and connected to, or in combination with, additional modules to comprise a complete
and functionally reliable system.
In this project, I identified ‘Drones’ as a potential product after survey, for the application
of Modular Design Approach. This need was validated by my advisor and the personnel
at AMF alike. The Drones manufactured at Kamra have a part count of 31 in their
existing design. My advisor advised me that a further decrease in the part count will
bring about a larger change in the manufacturing and assembly cost and time. The
application tools used such as DFA (Design for ease of Assembly) and DFM (Design for
Manufacturing) help to bring about this change to the benefit of the company and the
clients.
Besides reduction in cost (due to lesser customization, and less learning time), and
flexibility in design, modularity offers other benefits such as augmentation (adding new
solution by merely plugging in a new module), and exclusion. As I, alongside my
colleague, justified this when I looked at the bottle necks in the manufacturing and
assembly operations that lead to a loss in revenue by stretching the lead time.
My advisor for this project was Dr. Muhammad Abid, who currently is an associate
professor in the Faculty of Mechanical Engineering at Ghulam Khan Ishaq Khan Institute
of Engineering Sciences and Technology, one of the most prestigious engineering
institutes of Pakistan.
C.E 3.3 Design development for concurrent engineering was conceded with the following
objectives:
C.E. 3.5 On the advice of my advisor, I studied on the subject in the local university library and
acquired a complete detailed reference book on the subject. Actually, my complete
project thesis was based on the material provided in the book; ‘Product Design for
Manufacturing and Assembly’ by G. Boothroyd, P.Dewhurst.
C.E. 3.6 It was imperative that I along with my project partner distribute work evenly between us
for an efficient time managed project. Therefore, I identified key responsibilities, which
later we discussed and adopted in unison.
C.E. 3.7 Defining Module Specifications:
C.E. 3.7.1 While researching on the subject, I requested my project partner to study and define the
Modules, Functionalities and Specifications.
C.E. 3.7.2 The next step I took was to identify the detail for the process along with the plan layouts
and time / material consumption. This was accomplished with the help of the personnel
present at the site.
C.E. 3.8.3 The Design Review carried the following crucial steps:
• A complete analysis of the drone modular system was undertaken for the proposed
design modifications. It showed in detail the existing weaknesses against the impact
of proposed modifications for the modules and manufacturing processes. This
C.E. 3.8.4 Upon satisfaction over the positive results gained on calculation of the Design Efficiency,
I then asked my colleague to perform the cost estimation for labor, tools and over-heads,
while I estimated the cost for material for both existing and proposed design.
C.E. 3.9 Finally, I along with my project partner gave presentations on our Final Year Project, its
implications, design improvements and overall cost / time benefits to AMF, our project
advisory committee and various companies during 2010 university Open House.
d) Summary
The project was a great success in the light of the detailed study improvements as
summarized below:
• Design Efficiency improved 25%
• Part Count Reduction 55%
• Production time reduction 37%
• Production Cost reduction 20%
This concluded that modular design approach was successful tool not only in this project
but in any other Engineering organization or Industry to improve resource utilization and
to gain an edge in the today’s competitive market.
Moreover, the personnel from AMF karma were delighted with the results, as they took
the high recommendations to adopt Modular Designing Approach for Drones with keen
interest and fervor.