FULL CONCRETE JACKETING

Bent No. Pile ID Original Add: Cover+bottom Length (m)


3 A 3.1 2.1 5.20
4 A 6.6 2.1 8.70
4 B 6.6 2.1 8.70
4 D 5.8 2.1 7.90
4 F 5.8 2.1 7.90
5 A 6.9 2.1 9.00
5 E 8.3 2.1 10.40
5 F 8.3 2.1 10.40
6 A 8.5 2.1 10.60
6 B 8.5 2.1 10.60
6 C 8 2.1 10.10
7 D 8.75 2.1 10.85
7 E 8.3 2.1 10.40
12 D 8.1 2.1 10.20
12 G 7.9 2.1 10.00
SECTIONAL CONCRETE JACKETING
Bent No. Pile ID Original Add: Cover Length (m) Notes
3 C 0.90 0.20 1.10 Crack above water
8 A 0.80 0.20 1.00 Crack above water
10 A 0.90 0.20 1.10 Crack above water
11 B 0.70 0.20 0.90 1.3 from ceiling on south side
11 E 0.90 0.20 1.10 Crack above water
12 A1 2.00 0.20 2.20 Crack above and below water
12 F 2.90 0.20 3.10 Crack above and below water
13 E 0.60 0.20 0.80 Crack above water
13 E 0.36 0.20 0.56 Exposed rebar 5.70 m from ceiling
14 A1 0.80 0.20 1.00 Crack above water
14 A1 5.70 0.20 5.90 Crack below water
15 A 0.90 0.20 1.10 Crack above water
15 B 0.60 0.20 0.80 Crack above water
15 E 0.70 0.20 0.90 Crack above water
16 B 0.40 0.20 0.60 Crack above water
16 C 0.80 0.20 1.00 Crack above water
16 C 0.60 0.20 0.80 Crack underwater 2m from ceiling
17 C 1.00 0.20 1.20 Crack above water
18 A 0.90 0.20 1.10 Crack above water
18 A 0.40 0.20 0.60 Crack underwater 1.2m from ceiling
19 B 2.20 0.20 2.40 Crack above water and below water
19 E 0.80 0.20 1.00 Crack above water
19 E 0.60 0.20 0.80 Exposed rebar above water
20 C 0.80 0.20 1.00 Crack above water
20 C 1.00 0.20 1.20 Crack below water
20 C 0.70 0.20 0.90 Exposed rebar
20 G1 1.60 0.20 1.80 Crack above water
20 G1 5.60 0.20 5.80 Northeast corner crack
20 G1 5.40 0.20 5.60 Northwest corner crack
20 G1 1.50 0.20 1.70 Southeast corner crack
21 A1 6.75 0.20 6.95 Midsection crack
21 B 1.50 0.20 1.70 Crack above water
21 B 0.90 0.20 1.10 Crack below water
21 B 1.50 0.20 1.70 Crack below water
21 B 0.80 0.20 1.00 Crack at the bottom
21 G1 3.00 0.20 3.20 Crack above water
21 G1 0.80 0.20 1.00 Crack 1.8m from the ceiling
21 G1 1.00 0.20 1.20 Crack below water
22 E 1.20 0.20 1.40 Crack above water
22 E 0.12 0.20 0.32 Horizontal crack
22 G 1.10 0.20 1.30 Crack below water
22 G 1.40 0.20 1.60 Crack at the bottom
24 B 1.60 0.20 1.80 Crack above water
24 B 0.77 0.20 0.97 Crack below water
24 C 0.90 0.20 1.10 Crack above water
24 E 0.90 0.20 1.10 Crack above water
24 E 0.40 0.20 0.60 Crack below water
24 E 3.00 0.20 3.20 Crack at the bottom
25 A1 2.10 0.20 2.30 Crack from the ceiling
25 A1 0.17 0.20 0.37 Crack below water
25 B 2.10 0.20 2.30 Crack above water
25 B 2.10 0.20 2.30 Crack at midsection
25 B 2.90 0.20 3.10 Crack at the bottom
25 C 0.70 0.20 0.90 Crack above water
25 F 2.30 0.20 2.50 Crack above water
25 F 1.00 0.20 1.20 Crack at midsection
25 G 0.60 0.20 0.80 Crack above water
25 G 0.25 0.20 0.45 Crack at midsection
25 G 3.50 0.20 3.70 Crack at midsection
26 A 3.30 0.20 3.50 Crack above water
26 A 1.80 0.20 2.00 Crack at midsection
26 C 1.20 0.20 1.40 Crack above water
26 C 1.60 0.20 1.80 Crack at midsection
26 C 1.90 0.20 2.10 Crack at 4m from the ceiling
26 G1 1.40 0.20 1.60 Crack above water
26 G1 0.20 0.20 0.40 Crack at 1.8m from ceiling
27 G1 1.50 0.20 1.70 Crack above water
28 A1 0.40 0.20 0.60 Crack below water
28 E 0.40 0.20 0.60 Crack at midsection
28 F 1.10 0.20 1.30 Crack above water
28 F 0.40 0.20 0.60 Crack below water
29 B 1.15 0.20 1.35 Crack above water
29 G 1.10 0.20 1.30 Crack below water
30 G 1.00 0.20 1.20 Crack above water
30 G 1.60 0.20 1.80 Crack below water
31 B 1.00 0.20 1.20 Crack above water
31 B 0.70 0.20 0.90 Crack below water
31 C 0.90 0.20 1.10 Crack below water
31 C 0.70 0.20 0.90 Crack at midsection
31 C 1.80 0.20 2.00 Crack below water, bottom
31 E 1.00 0.20 1.20 Crack above water
31 E 1.70 0.20 1.90 Crack below water
31 F 0.90 0.20 1.10 Crack at midsection
31 F 0.90 0.20 1.10 Crack below water, bottom
31 G 0.90 0.20 1.10 Crack above water
31 G 0.60 0.20 0.80 Crack below water
31 G1 0.80 0.20 1.00 Crack above water
31 G1 6.50 0.20 6.70 Crack below water, bottom
32 A1 0.70 0.20 0.90 Crack above water
32 E 0.40 0.20 0.60 Crack above water
32 G 0.60 0.20 0.80 damage below water, exposed rebar
33 A 1.10 0.20 1.30 Crack above water
33 A 1.30 0.20 1.50 Crack below water
33 C 1.70 0.20 1.90 Crack above and below water
33 C 0.70 0.20 0.90 Crack below water
33 G 1.10 0.20 1.30 Crack above water
33 G 1.50 0.20 1.70 Crack below water
33 G1 0.40 0.20 0.60 Crack above water
33 G1 7.10 0.20 7.30 Crack below water
34 A 1.00 0.20 1.20 Crack above water
34 A 0.70 0.20 0.90 Crack at midsection
35 A 0.90 0.20 1.10 Crack above water
35 A 1.10 0.20 1.30 Crack below water
36 A 0.95 0.20 1.15 Crack above water
36 A2 1.50 0.20 1.70 Crack above water, exposed rebar
36 A2 0.90 0.20 1.10 Crack below water
36 A2 0.40 0.20 0.60 Crack at midsection
37 A 2.20 0.20 2.40 Crack above water
37 A 1.50 0.20 1.70 Crack below water
37 A1 1.10 0.20 1.30 Crack above water
37 A1 1.40 0.20 1.60 Crack below water
37 A1 0.55 0.20 0.75 Crack below water
37 B 1.70 0.20 1.90 Crack above water
37 B 0.50 0.20 0.70 Crack below water
37 D1 1.40 0.20 1.60 Crack above water, exposed rebar
37 D1 0.80 0.20 1.00 Crack below water
37 D2 1.10 0.20 1.30 Crack above water
37 D2 0.80 0.20 1.00 Crack below water
37 D2 1.50 0.20 1.70 Crack at midsection
37 D2 0.50 0.20 0.70 Crack below water, bottom
37 G1 1.20 0.20 1.40 Crack above water
37 G1 8.00 0.20 8.20 Crack below water
37 G2 0.10 0.20 0.30 Crack below water
37 G3 0.90 0.20 1.10 Crack above water
37 G3 1.60 0.20 1.80 Crack at midsection
37 G3 1.20 0.20 1.40 Crack below water, bottom
37 G4 1.90 0.20 2.10 Crack below water
37 G4 7.60 0.20 7.80 Crack at midsection
37 G4 0.70 0.20 0.90 Crack below water
37 G5 1.50 0.20 1.70 Crack above water
37 G5 0.70 0.20 0.90 Crack below water
37 G5 0.40 0.20 0.60 Crack at midsection
MDA-1 D 0.40 0.20 0.60 Crack above water
MDA-1 D 0.40 0.20 0.60 Crack below water
MDA-3 B 0.40 0.20 0.60 Crack above water
MDA-3 B 0.40 0.20 0.60 Crack below water
MDA-3 B 0.20 0.20 0.40 Crack below water
MDA-7 C 0.70 0.20 0.90 Crack above water
MDA-7 C 0.30 0.20 0.50 Crack at midsection
MDA-7 C 0.30 0.20 0.50 Crack below water, bottom
MDB-1 A 0.50 0.20 0.70 Crack above water
MDB-1 A 0.50 0.20 0.70 Crack below water
MDB-1 A 0.80 0.20 1.00 Crack at midsection
MDB-1 A 0.55 0.20 0.75 Crack below water
MDB-1 B 0.30 0.20 0.50 Crack above water
MDB-1 B 0.80 0.20 1.00 Crack below water
MDB-1 D 1.00 0.20 1.20 Crack above water
MDB-1 D 0.50 0.20 0.70 Crack at midsection
MDB-2 C 0.40 0.20 0.60 Crack above water
MDB-3 D 0.40 0.20 0.60 Crack above water
MDB-3 D 0.70 0.20 0.90 Crack at midsection
MDB-3 D 2.70 0.20 2.90 Crack below water, bottom
MDB-4 B 0.70 0.20 0.90 Crack above water
MDB-4 B 0.65 0.20 0.85 Crack at midsection
MDB-6 B 0.30 0.20 0.50 Crack above water
MDB-6 C 0.70 0.20 0.90 Crack above water
MDB-7 B 0.90 0.20 1.10 Crack above water
MDB-7 B 0.70 0.20 0.90 Crack below water
MDC-1 D 0.60 0.20 0.80 Crack above water
MDC-1 D 9.20 0.20 9.40 Crack at midsection
MDC-3 C 0.75 0.20 0.95 Crack above water
MDC-3 D 0.80 0.20 1.00 Crack above water
MDC-5 A 0.70 0.20 0.90 Crack above water
MDC-6 C 0.40 0.20 0.60 Crack below water
MDC-6 C 8.50 0.20 8.70 Crack below water
MDC-7 D 8.30 0.20 8.50 Crack below water
MDC-7 E 8.00 0.20 8.20 Crack below water
MDC-7 F 9.50 0.20 9.70 Crack below water
MDC-8 D 2.50 0.20 2.70 Crack at midsection
MDC-8 D 1.40 0.20 1.60 Crack below water
MDC-9 E 0.30 0.20 0.50 Crack below water
MDC-9 F 8.50 0.20 8.70 Crack below water
MDC-10 C 8.40 0.20 8.60 Crack below water
MDC-11 B 7.10 0.20 7.30 Crack below water
MDC-11 D 0.30 0.20 0.50 Crack above water
MDC-11 D 9.90 0.20 10.10 Crack below water
HAIRLINE CRACKS 98.45 Cracks above water
SECTIONAL CONCRETE JACKETING
Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
3 C 0.90 0.20 1.10 Crack above water Epoxy Injection 1.5 5 780 x 780 @ 2-3 meters from under slab
8 A 0.80 0.20 1.00 Crack above water Epoxy Injection 2.5 3 780 x 780 @ 2-3 meters from under slab
10 A 0.90 0.20 1.10 Crack above water Epoxy Injection 1.2 9 780 x 780 @ 2-3 meters from under slab
11 B 0.70 0.20 0.90 1.3 from ceiling on south side Epoxy Injection 2.15 4 780 x 780 @ 2-3 meters from under slab
11 E 0.90 0.20 1.10 Crack above water Epoxy Injection 0.9 1 780 x 780 @ 2-3 meters from under slab
12 A1 2.00 0.20 2.20 Crack above water Epoxy Injection 4 3 780 x 780 @ 2-3 meters from under slab
12 F 2.90 0.20 3.10 Crack above water Epoxy Injection 4.9 5 780 x 780 @ 2-3 meters from under slab
13 E 0.60 0.20 0.80 Crack above water Epoxy Injection 0.6 3 780 x 780 @ 2-3 meters from under slab
13 E 0.36 0.20 0.56 Exposed rebar 5.70 m from ceiling Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
14 A1 0.80 0.20 1.00 Crack above water Epoxy Injection 2.4 5 780 x 780 @ 2-3 meters from under slab
14 A1 5.70 0.20 5.90 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
15 A 0.90 0.20 1.10 Crack above water Epoxy Injection 0.9 3 780 x 780 @ 2-3 meters from under slab
15 B 0.60 0.20 0.80 Crack above water Epoxy Injection 0.6 2 780 x 780 @ 2-3 meters from under slab
15 E 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 2 780 x 780 @ 2-3 meters from under slab
16 B 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 3 780 x 780 @ 2-3 meters from under slab
16 C 0.80 0.20 1.00 Crack above water Epoxy Injection 2.3 4 780 x 780 @ 2-3 meters from under slab
16 C 0.60 0.20 0.80 Crack underwater 2m from ceiling Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
17 C 1.00 0.20 1.20 Crack above water Epoxy Injection 2.7 5 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack above water 1.8 3
18 A Epoxy Injection 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack underwater 1.2m from ceiling 0.4 3
19 B 2.20 0.20 2.40 Crack above water Epoxy Injection 4.7 3 780 x 780 @ 2-3 meters from under slab
19 B 2.20 0.20 2.40 Crack above water and below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.80 0.20 1.00 Crack above water
19 E Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.60 0.20 0.80 Exposed rebar above water
0.80 0.20 1.00 Crack above water
20 C 1.00 0.20 1.20 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.70 0.20 0.90 Exposed rebar
20 G1 1.60 0.20 1.80 Crack above water Epoxy Injection 1.6 5 780 x 780 @ 2-3 meters from under slab
5.60 0.20 5.80 Northeast corner crack
20 G1 5.40 0.20 5.60 Northwest corner crack Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.50 0.20 1.70 Southeast corner crack
21 A1 6.75 0.20 6.95 Midsection crack Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
21 B 1.50 0.20 1.70 Crack above water Epoxy Injection 1.5 3 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack below water
21 B 1.50 0.20 1.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.80 0.20 1.00 Crack at the bottom
3.00 0.20 3.20 Crack above water
21 G1 0.80 0.20 1.00 Crack 1.8m from the ceiling Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.00 0.20 1.20 Crack below water
22 E 1.20 0.20 1.40 Crack above water Epoxy Injection 2.3 5 780 x 780 @ 2-3 meters from under slab
22 E 0.12 0.20 0.32 Horizontal crack Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.10 0.20 1.30 Crack below water
22 G Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.40 0.20 1.60 Crack at the bottom
SECTIONAL CONCRETE JACKETING
Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
24 B 1.60 0.20 1.80 Crack above water Epoxy Injection 1.6 4 780 x 780 @ 2-3 meters from under slab
24 B 0.77 0.20 0.97 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
24 C 0.90 0.20 1.10 Crack above water Epoxy Injection 0.9 3 780 x 780 @ 2-3 meters from under slab
24 E 0.90 0.20 1.10 Crack above water Epoxy Injection 1.3 3 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack below water
24 E Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
3.00 0.20 3.20 Crack at the bottom
25 A1 2.10 0.20 2.30 Crack from the ceiling Epoxy Injection 2.1 5 780 x 780 @ 2-3 meters from under slab
25 A1 0.17 0.20 0.37 Crack below water Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
25 B 2.10 0.20 2.30 Crack above water Epoxy Injection 2.1 3 780 x 780 @ 2-3 meters from under slab
2.10 0.20 2.30 Crack at midsection
25 B Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
2.90 0.20 3.10 Crack at the bottom
25 C 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 1 780 x 780 @ 2-3 meters from under slab
2.30 0.20 2.50 Crack above water 4.3 3
25 F Epoxy Injection 780 x 780 @ 2-3 meters from under slab
1.00 0.20 1.20 Crack at midsection 1.75 4
25 G 0.60 0.20 0.80 Crack above water Epoxy Injection 0.6 3 780 x 780 @ 2-3 meters from under slab
0.25 0.20 0.45 Crack at midsection
25 G Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
3.50 0.20 3.70 Crack at midsection
3.30 0.20 3.50 Crack above water 3.3 3
26 A Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.80 0.20 2.00 Crack at midsection 1.8 6
26 C 1.20 0.20 1.40 Crack above water Epoxy Injection 3.1 3 780 x 780 @ 2-3 meters from under slab
1.60 0.20 1.80 Crack at midsection
26 C Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.90 0.20 2.10 Crack at 4m from the ceiling
1.40 0.20 1.60 Crack above water 1.4 2
26 G1 Epoxy Injection 780 x 780 @ 2-3 meters from under slab
0.20 0.20 0.40 Crack at 1.8m from ceiling 0.2 4
27 G1 1.50 0.20 1.70 Crack above water Epoxy Injection 4.9 5 780 x 780 @ 2-3 meters from under slab
28 A1 0.40 0.20 0.60 Crack above water Epoxy Injection 0.7 3 450 x 450
28 E 0.40 0.20 0.60 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
28 F 1.10 0.20 1.30 Crack above water Epoxy Injection 2 2 780 x 780 @ 2-3 meters from under slab
28 F 0.40 0.20 0.60 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
29 B 1.15 0.20 1.35 Crack above water Epoxy Injection 2.15 5 780 x 780 @ 2-3 meters from under slab
29 G 1.10 0.20 1.30 Crack below water Epoxy Injection 3.1 12 780 x 780 @ 2-3 meters from under slab
30 G 1.00 0.20 1.20 Crack above water Epoxy Injection 1 3 780 x 780 @ 2-3 meters from under slab
30 G 1.60 0.20 1.80 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
31 B 1.00 0.20 1.20 Crack above water Epoxy Injection 1.8 5 780 x 780 @ 2-3 meters from under slab
31 B 0.70 0.20 0.90 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack above water Epoxy Injection 1.4 3
31 C 0.70 0.20 0.90 Crack at midsection 450 x 450
Epoxy Injection and Concrete Jacketing
1.80 0.20 2.00 Crack below water, bottom
31 E 1.00 0.20 1.20 Crack above water Epoxy Injection 1.9 3 780 x 780 @ 2-3 meters from under slab
31 E 1.70 0.20 1.90 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack at midsection
31 F Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack below water, bottom
SECTIONAL CONCRETE JACKETING
Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
31 G 0.90 0.20 1.10 Crack above water Epoxy Injection 2.3 4 780 x 780 @ 2-3 meters from under slab
31 G 0.60 0.20 0.80 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
31 G1 0.80 0.20 1.00 Crack above water Epoxy Injection 2.15 4 780 x 780 @ 2-3 meters from under slab
31 G1 6.50 0.20 6.70 Crack below water, bottom Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
32 A1 0.70 0.20 0.90 Crack above water Epoxy Injection 1.2 3 780 x 780 @ 2-3 meters from under slab
32 E 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
32 G 0.60 0.20 0.80 Damage below water, exposed rebar Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
33 A 1.10 0.20 1.30 Crack above water Epoxy Injection 2.1 3 780 x 780 @ 2-3 meters from under slab
33 A 1.30 0.20 1.50 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
33 C 1.70 0.20 1.90 Crack above water Epoxy Injection 3.7 3 780 x 780 @ 2-3 meters from under slab
33 C 0.70 0.20 0.90 Crack above and below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
33 G 1.10 0.20 1.30 Crack above water Epoxy Injection 7.8 6 780 x 780 @ 2-3 meters from under slab
33 G 1.50 0.20 1.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack above water 1.3 12
33 G1 Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
7.10 0.20 7.30 Crack below water
34 A 1.00 0.20 1.20 Crack above water Epoxy Injection 2 2 780 x 780 @ 2-3 meters from under slab
34 A 0.70 0.20 0.90 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
35 A 0.90 0.20 1.10 Crack above water Epoxy Injection 3.7 5 780 x 780 @ 2-3 meters from under slab
35 A 1.10 0.20 1.30 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
36 A 0.95 0.20 1.15 Crack above water Epoxy Injection 2.25 5 780 x 780 @ 2-3 meters from under slab
1.50 0.20 1.70 Crack above water, exposed rebar
36 A2 0.90 0.20 1.10 Crack below water Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack at midsection
37 A 2.20 0.20 2.40 Crack above water Epoxy Injection 3.3 3 780 x 780 @ 2-3 meters from under slab
37 A 1.50 0.20 1.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
37 A1 1.10 0.20 1.30 Crack above water Epoxy Injection 1.7 2 780 x 780 @ 2-3 meters from under slab
1.40 0.20 1.60 Crack below water
37 A1 Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.55 0.20 0.75 Crack below water
1.70 0.20 1.90 Crack above water 3.05 3
37 B Epoxy Injection 780 x 780 @ 2-3 meters from under slab
0.50 0.20 0.70 Crack above water 0.5 1
1.40 0.20 1.60 Crack above water, exposed rebar
37 D1 Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.80 0.20 1.00 Crack below water
37 D2 1.10 0.20 1.30 Crack above water Epoxy Injection 4 3 780 x 780 @ 2-3 meters from under slab
0.80 0.20 1.00 Crack below water
37 D2 1.50 0.20 1.70 Crack at midsection Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.50 0.20 0.70 Crack below water, bottom
37 G1 1.20 0.20 1.40 Crack above water Epoxy Injection 1.6 1 780 x 780 @ 2-3 meters from under slab
37 G1 8.00 0.20 8.20 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
37 G2 0.10 0.20 0.30 Crack below water Epoxy Injection 0.7 1 780 x 780 @ 2-3 meters from under slab
37 G3 0.90 0.20 1.10 Crack above water Epoxy Injection 3.2 3 780 x 780 @ 2-3 meters from under slab
1.60 0.20 1.80 Crack at midsection
37 G3 Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.20 0.20 1.40 Crack below water, bottom
SECTIONAL CONCRETE JACKETING
Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
1.90 0.20 2.10 Crack below water
37 G4 7.60 0.20 7.80 Crack at midsection Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.70 0.20 0.90 Crack below water
37 G5 1.50 0.20 1.70 Crack above water Epoxy Injection 3.4 3 780 x 780 @ 2-3 meters from under slab
0.70 0.20 0.90 Crack below water
37 G5 Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack at midsection
MDA-1 D 0.40 0.20 0.60 Crack above water Epoxy Injection 0.7 4 780 x 780 @ 2-3 meters from under slab
MDA-1 D 0.40 0.20 0.60 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDA-3 B 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack below water
MDA-3 B Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.20 0.20 0.40 Crack below water
MDA-7 C 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 1 780 x 780 @ 2-3 meters from under slab
0.30 0.20 0.50 Crack at midsection
MDA-7 C Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.30 0.20 0.50 Crack below water, bottom
MDB-1 A 0.50 0.20 0.70 Crack above water Epoxy Injection 0.8 2 780 x 780 @ 2-3 meters from under slab
0.50 0.20 0.70 Crack below water
MDB-1 A 0.80 0.20 1.00 Crack at midsection Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.55 0.20 0.75 Crack below water
MDA-1 B 0.30 0.20 0.50 Crack above water Epoxy Injection 0.3 1 780 x 780 @ 2-3 meters from under slab
MDA-1 B 0.80 0.20 1.00 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDB-1 D 1.00 0.20 1.20 Crack above water Epoxy Injection 1.6 1 780 x 780 @ 2-3 meters from under slab
MDB-1 D 0.50 0.20 0.70 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDB-2 C 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
MDB-3 D 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
0.70 0.20 0.90 Crack at midsection
MDB-3 Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
2.70 0.20 2.90 Crack below water, bottom
MDB-4 B 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 1 780 x 780 @ 2-3 meters from under slab
MDB-4 B 0.65 0.20 0.85 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDB-6 B 0.30 0.20 0.50 Crack above water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDB-6 C 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 2 780 x 780 @ 2-3 meters from under slab
MDB-7 B 0.90 0.20 1.10 Crack above water Epoxy Injection 2.2 1 780 x 780 @ 2-3 meters from under slab
MDB-7 B 0.70 0.20 0.90 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-1 D 0.60 0.20 0.80 Crack above water Epoxy Injection 1.5 1 780 x 780 @ 2-3 meters from under slab
MDC-1 D 9.20 0.20 9.40 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-3 C 0.75 0.20 0.95 Crack above water Epoxy Injection 1.65 1 780 x 780 @ 2-3 meters from under slab
MDC-3 D 0.80 0.20 1.00 Crack above water Epoxy Injection 1.5 1 780 x 780 @ 2-3 meters from under slab
MDC-5 A 0.70 0.20 0.90 Crack above water Epoxy Injection 0.6 3 780 x 780 @ 2-3 meters from under slab
MDC-6 C 0.40 0.20 0.60 Crack below water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
MDC-6 C 8.50 0.20 8.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
SECTIONAL CONCRETE JACKETING
Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
MDC-6 D 8.30 0.20 8.50 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-7 E 8.00 0.20 8.20 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-7 F 9.50 0.20 9.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
2.50 0.20 2.70 Crack at midsection
MDC-8 D Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.40 0.20 1.60 Crack below water
MDC-9 E 0.30 0.20 0.50 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-9 F 8.50 0.20 8.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-10 C 8.40 0.20 8.60 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-11 B 7.10 0.20 7.30 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-13 D 0.30 0.20 0.50 Crack above water Epoxy Injection 0.3 1 780 x 780 @ 2-3 meters from under slab
MDC-13 D 9.90 0.20 10.10 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
HAIRLINE CRACKS 330.72

Total No. of Piles per original contract: 97


No. of Piles for Epoxy Injection: 71
Quantity (l.m.): 137.75

Prepared by: Noted by: Check and recommending Approval:

Aries C. Hawan John Mark A. Catayong Randy B. Novicio / Napoleon C. Ablaza


Diving Supervisor Project Manager Diving Inspector / Team Lead
HSSC HSSC DCCD - Consultant
HAIRLINE CRACK LENGTH (ABOVE WATER) HAIRLINE CRACK AREA

BENT NO. PILE ID LENGTH (cm) COVER TOTAL LENGTH (m) SURFACE WIDTH (m) AREA (sq.m)
2 C 50.00 20.00 70.00 0.50 0.5 0.25
2 E 20.00 20.00 40.00 0.20 0.5 0.10
2 G 20.00 20.00 40.00 0.20 0.5 0.10
4 A1 20.00 20.00 40.00 0.20 0.5 0.10
4 C 10.00 20.00 30.00 0.10 0.5 0.05
5 A 50.00 20.00 70.00 0.50 0.5 0.25
5 C 30.00 20.00 50.00 0.30 0.5 0.15
6 A 40.00 20.00 60.00 0.40 0.5 0.20
6 B 50.00 20.00 70.00 0.50 0.5 0.25
6 E 20.00 20.00 40.00 0.20 0.5 0.10
6 F 20.00 20.00 40.00 0.20 0.5 0.10
7 B 20.00 20.00 40.00 0.20 0.5 0.10
8 C 100.00 20.00 120.00 1.00 0.5 0.50
8 G 80.00 20.00 100.00 0.80 0.5 0.40
9 A 80.00 20.00 100.00 0.80 0.5 0.40
9 B 100.00 20.00 120.00 1.00 0.5 0.50
9 C 30.00 20.00 50.00 0.30 0.5 0.15
9 G 80.00 20.00 100.00 0.80 0.5 0.40
9 G1 130.00 20.00 150.00 1.30 0.5 0.65
10 C 40.00 20.00 60.00 0.40 0.5 0.20
10 G 20.00 20.00 40.00 0.20 0.5 0.10
13 F 30.00 20.00 50.00 0.30 0.5 0.15
14 A1 50.00 20.00 70.00 0.50 0.5 0.25
14 F 40.00 20.00 60.00 0.40 0.5 0.20
15 G 30.00 20.00 50.00 0.30 0.5 0.15
15 G1 60.00 20.00 80.00 0.60 0.5 0.30
18 C 30.00 20.00 50.00 0.30 0.5 0.15
20 A 50.00 20.00 70.00 0.50 0.5 0.25
20 G 30.00 20.00 50.00 0.30 0.5 0.15
21 D 30.00 20.00 50.00 0.30 0.5 0.15
21 F 50.00 20.00 70.00 0.50 0.5 0.25
23 A1 30.00 20.00 50.00 0.30 0.5 0.15
24 G 50.00 20.00 70.00 0.50 0.5 0.25
25 A 30.00 20.00 50.00 0.30 0.5 0.15
25 D 50.00 20.00 70.00 0.50 0.5 0.25
25 E 30.00 20.00 50.00 0.30 0.5 0.15
25 G1 30.00 20.00 50.00 0.30 0.5 0.15
26 A1 20.00 20.00 40.00 0.20 0.5 0.10
26 B 20.00 20.00 40.00 0.20 0.5 0.10
26 E 20.00 20.00 40.00 0.20 0.5 0.10
27 E 20.00 20.00 40.00 0.20 0.5 0.10
28 A 80.00 20.00 100.00 0.80 0.5 0.40
28 B 100.00 20.00 120.00 1.00 0.5 0.50
28 C 40.00 20.00 60.00 0.40 0.5 0.20
29 A 40.00 20.00 60.00 0.40 0.5 0.20
29 C 100.00 20.00 120.00 1.00 0.5 0.50
29 E 100.00 20.00 120.00 1.00 0.5 0.50
29 G1 80.00 20.00 100.00 0.80 0.5 0.40
30 A1 40.00 20.00 60.00 0.40 0.5 0.20
30 A 100.00 20.00 120.00 1.00 0.5 0.50
30 B 20.00 20.00 40.00 0.20 0.5 0.10
30 C 30.00 20.00 50.00 0.30 0.5 0.15
30 D 40.00 20.00 60.00 0.40 0.5 0.20
30 F 30.00 20.00 50.00 0.30 0.5 0.15
32 C 30.00 20.00 50.00 0.30 0.5 0.15
33 A1 100.00 20.00 120.00 1.00 0.5 0.50
33 B 20.00 20.00 40.00 0.20 0.5 0.10
33 D 40.00 20.00 60.00 0.40 0.5 0.20
33 E 20.00 20.00 40.00 0.20 0.5 0.10
33 F 100.00 20.00 120.00 1.00 0.5 0.50
34 A1 100.00 20.00 120.00 1.00 0.5 0.50
34 B 100.00 20.00 120.00 1.00 0.5 0.50
34 C 40.00 20.00 60.00 0.40 0.5 0.20
34 F 100.00 20.00 120.00 1.00 0.5 0.50
35 E 100.00 20.00 120.00 1.00 0.5 0.50
35 G 80.00 20.00 100.00 0.80 0.5 0.40
36 A3 100.00 20.00 120.00 1.00 0.5 0.50
36 D2 80.00 20.00 100.00 0.80 0.5 0.40
36 E 20.00 20.00 40.00 0.20 0.5 0.10
37 D2 130.00 20.00 150.00 1.30 0.5 0.65
37 E 40.00 20.00 60.00 0.40 0.5 0.20
MP-A2 B 70.00 20.00 90.00 0.70 0.5 0.35
MP-A3 A 30.00 20.00 50.00 0.30 0.5 0.15
MP-A3 D 30.00 20.00 50.00 0.30 0.5 0.15
MP-A5 C 30.00 20.00 50.00 0.30 0.5 0.15
MP-A6 A 50.00 20.00 70.00 0.50 0.5 0.25
MP-A6 D 50.00 20.00 70.00 0.50 0.5 0.25
MP-A7 B 50.00 20.00 70.00 0.50 0.5 0.25
MP-B2 B 20.00 20.00 40.00 0.20 0.5 0.10
MP-B3 B 50.00 20.00 70.00 0.50 0.5 0.25
MP-B6 A 60.00 20.00 80.00 0.60 0.5 0.30
MP-B7 C 30.00 20.00 50.00 0.30 0.5 0.15
MP-C2 C 80.00 20.00 100.00 0.80 0.5 0.40
MP-C2 D 20.00 20.00 40.00 0.20 0.5 0.10
MP-C4 B 80.00 20.00 100.00 0.80 0.5 0.40
MP-C13 C 20.00 20.00 40.00 0.20 0.5 0.10
SECTIONAL PILE FOR REPAIR

Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
3 C 0.90 0.20 1.10 Crack above water Epoxy Injection 1.5 5 780 x 780 @ 2-3 meters from under slab
8 A 0.80 0.20 1.00 Crack above water Epoxy Injection 2.5 3 780 x 780 @ 2-3 meters from under slab
10 A 0.90 0.20 1.10 Crack above water Epoxy Injection 1.2 9 780 x 780 @ 2-3 meters from under slab
11 B 0.70 0.20 0.90 1.3 from ceiling on south side Epoxy Injection 2.15 4 780 x 780 @ 2-3 meters from under slab
11 E 0.90 0.20 1.10 Crack above water Epoxy Injection 0.9 1 780 x 780 @ 2-3 meters from under slab
12 A1 2.00 0.20 2.20 Crack above water Epoxy Injection 4 3 780 x 780 @ 2-3 meters from under slab
12 F 2.90 0.20 3.10 Crack above water Epoxy Injection 4.9 5 780 x 780 @ 2-3 meters from under slab
E 0.60 0.20 0.80 Crack above water Epoxy Injection 0.6 3 780 x 780 @ 2-3 meters from under slab
13
E 0.36 0.20 0.56 Exposed rebar 5.70 m from ceiling Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
A1 0.80 0.20 1.00 Crack above water Epoxy Injection 2.4 5 780 x 780 @ 2-3 meters from under slab
14
A1 5.70 0.20 5.90 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
15 A 0.90 0.20 1.10 Crack above water Epoxy Injection 0.9 3 780 x 780 @ 2-3 meters from under slab
15 B 0.60 0.20 0.80 Crack above water Epoxy Injection 0.6 2 780 x 780 @ 2-3 meters from under slab
15 E 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 2 780 x 780 @ 2-3 meters from under slab
16 B 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 3 780 x 780 @ 2-3 meters from under slab
C 0.80 0.20 1.00 Crack above water Epoxy Injection 2.3 4 780 x 780 @ 2-3 meters from under slab
16
C 0.60 0.20 0.80 Crack underwater 2m from ceiling Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
17 C 1.00 0.20 1.20 Crack above water Epoxy Injection 2.7 5 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack above water 1.8 3
18 A Epoxy Injection 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack underwater 1.2m from ceiling 0.4 3
B 2.20 0.20 2.40 Crack above water Epoxy Injection 4.7 3 780 x 780 @ 2-3 meters from under slab
19
B 2.20 0.20 2.40 Crack above water and below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.80 0.20 1.00 Crack above water
19 E Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.60 0.20 0.80 Exposed rebar above water
0.80 0.20 1.00 Crack above water
20 C 1.00 0.20 1.20 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.70 0.20 0.90 Exposed rebar
G1 1.60 0.20 1.80 Crack above water Epoxy Injection 1.6 5 780 x 780 @ 2-3 meters from under slab
5.60 0.20 5.80 Northeast corner crack
20
G1 5.40 0.20 5.60 Northwest corner crack Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.50 0.20 1.70 Southeast corner crack
21 A1 6.75 0.20 6.95 Midsection crack Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
B 1.50 0.20 1.70 Crack above water Epoxy Injection 1.5 3 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack below water
21
B 1.50 0.20 1.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.80 0.20 1.00 Crack at the bottom
3.00 0.20 3.20 Crack above water
21 G1 0.80 0.20 1.00 Crack 1.8m from the ceiling Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.00 0.20 1.20 Crack below water
SECTIONAL PILE FOR REPAIR

Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
E 1.20 0.20 1.40 Crack above water Epoxy Injection 2.3 5 780 x 780 @ 2-3 meters from under slab
22
E 0.12 0.20 0.32 Horizontal crack Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
SECTIONAL PILE FOR REPAIR

Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
1.10 0.20 1.30 Crack below water
22 G Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.40 0.20 1.60 Crack at the bottom
B 1.60 0.20 1.80 Crack above water Epoxy Injection 1.6 4 780 x 780 @ 2-3 meters from under slab
24
B 0.77 0.20 0.97 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
24 C 0.90 0.20 1.10 Crack above water Epoxy Injection 0.9 3 780 x 780 @ 2-3 meters from under slab
E 0.90 0.20 1.10 Crack above water Epoxy Injection 1.3 3 780 x 780 @ 2-3 meters from under slab
24 0.40 0.20 0.60 Crack below water
E Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
3.00 0.20 3.20 Crack at the bottom
A1 2.10 0.20 2.30 Crack from the ceiling Epoxy Injection 2.1 5 780 x 780 @ 2-3 meters from under slab
25
A1 0.17 0.20 0.37 Crack below water Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
B 2.10 0.20 2.30 Crack above water Epoxy Injection 2.1 3 780 x 780 @ 2-3 meters from under slab
25 2.10 0.20 2.30 Crack at midsection
B Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
2.90 0.20 3.10 Crack at the bottom
25 C 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 1 780 x 780 @ 2-3 meters from under slab
2.30 0.20 2.50 Crack above water 4.3 3
25 F Epoxy Injection 780 x 780 @ 2-3 meters from under slab
1.00 0.20 1.20 Crack at midsection 1.75 4
G 0.60 0.20 0.80 Crack above water Epoxy Injection 0.6 3 780 x 780 @ 2-3 meters from under slab
25 0.25 0.20 0.45 Crack at midsection
G Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
3.50 0.20 3.70 Crack at midsection
3.30 0.20 3.50 Crack above water 3.3 3
26 A Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.80 0.20 2.00 Crack at midsection 1.8 6
C 1.20 0.20 1.40 Crack above water Epoxy Injection 3.1 3 780 x 780 @ 2-3 meters from under slab
26 1.60 0.20 1.80 Crack at midsection
C Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.90 0.20 2.10 Crack at 4m from the ceiling
1.40 0.20 1.60 Crack above water 1.4 2
26 G1 Epoxy Injection 780 x 780 @ 2-3 meters from under slab
0.20 0.20 0.40 Crack at 1.8m from ceiling 0.2 4
27 G1 1.50 0.20 1.70 Crack above water Epoxy Injection 4.9 5 780 x 780 @ 2-3 meters from under slab
28 A1 0.40 0.20 0.60 Crack above water Epoxy Injection 0.7 3 450 x 450
28 E 0.40 0.20 0.60 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
F 1.10 0.20 1.30 Crack above water Epoxy Injection 2 2 780 x 780 @ 2-3 meters from under slab
28
F 0.40 0.20 0.60 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
29 B 1.15 0.20 1.35 Crack above water Epoxy Injection 2.15 5 780 x 780 @ 2-3 meters from under slab
29 G 1.10 0.20 1.30 Crack below water Epoxy Injection 3.1 12 780 x 780 @ 2-3 meters from under slab
G 1.00 0.20 1.20 Crack above water Epoxy Injection 1 3 780 x 780 @ 2-3 meters from under slab
30
G 1.60 0.20 1.80 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
B 1.00 0.20 1.20 Crack above water Epoxy Injection 1.8 5 780 x 780 @ 2-3 meters from under slab
31
B 0.70 0.20 0.90 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack above water Epoxy Injection 1.4 3
31 C 0.70 0.20 0.90 Crack at midsection 450 x 450
Epoxy Injection and Concrete Jacketing
SECTIONAL PILE FOR REPAIR

Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
31 C (m) (mm) 450 x 450
Epoxy Injection and Concrete Jacketing
1.80 0.20 2.00 Crack below water, bottom
E 1.00 0.20 1.20 Crack above water Epoxy Injection 1.9 3 780 x 780 @ 2-3 meters from under slab
31
SECTIONAL PILE FOR REPAIR

Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
31
E 1.70 0.20 1.90 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack at midsection
31 F Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.90 0.20 1.10 Crack below water, bottom
G 0.90 0.20 1.10 Crack above water Epoxy Injection 2.3 4 780 x 780 @ 2-3 meters from under slab
31
G 0.60 0.20 0.80 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
G1 0.80 0.20 1.00 Crack above water Epoxy Injection 2.15 4 780 x 780 @ 2-3 meters from under slab
31
G1 6.50 0.20 6.70 Crack below water, bottom Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
32 A1 0.70 0.20 0.90 Crack above water Epoxy Injection 1.2 3 780 x 780 @ 2-3 meters from under slab
32 E 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
32 G 0.60 0.20 0.80 Damage below water, exposed rebar Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
A 1.10 0.20 1.30 Crack above water Epoxy Injection 2.1 3 780 x 780 @ 2-3 meters from under slab
33
A 1.30 0.20 1.50 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
C 1.70 0.20 1.90 Crack above water Epoxy Injection 3.7 3 780 x 780 @ 2-3 meters from under slab
33
C 0.70 0.20 0.90 Crack above and below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
G 1.10 0.20 1.30 Crack above water Epoxy Injection 7.8 6 780 x 780 @ 2-3 meters from under slab
33
G 1.50 0.20 1.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack above water 1.3 12
33 G1 Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
7.10 0.20 7.30 Crack below water
A 1.00 0.20 1.20 Crack above water Epoxy Injection 2 2 780 x 780 @ 2-3 meters from under slab
34
A 0.70 0.20 0.90 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
A 0.90 0.20 1.10 Crack above water Epoxy Injection 3.7 5 780 x 780 @ 2-3 meters from under slab
35
A 1.10 0.20 1.30 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
36 A 0.95 0.20 1.15 Crack above water Epoxy Injection 2.25 5 780 x 780 @ 2-3 meters from under slab
1.50 0.20 1.70 Crack above water, exposed rebar
36 A2 0.90 0.20 1.10 Crack below water Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack at midsection
A 2.20 0.20 2.40 Crack above water Epoxy Injection 3.3 3 780 x 780 @ 2-3 meters from under slab
37
A 1.50 0.20 1.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
A1 1.10 0.20 1.30 Crack above water Epoxy Injection 1.7 2 780 x 780 @ 2-3 meters from under slab
37 1.40 0.20 1.60 Crack below water
A1 Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.55 0.20 0.75 Crack below water
1.70 0.20 1.90 Crack above water 3.05 3
37 B Epoxy Injection 780 x 780 @ 2-3 meters from under slab
0.50 0.20 0.70 Crack above water 0.5 1
1.40 0.20 1.60 Crack above water, exposed rebar
37 D1 Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.80 0.20 1.00 Crack below water
D2 1.10 0.20 1.30 Crack above water Epoxy Injection 4 3 780 x 780 @ 2-3 meters from under slab
0.80 0.20 1.00 Crack below water
37
D2 1.50 0.20 1.70 Crack at midsection Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.50 0.20 0.70 Crack below water, bottom
SECTIONAL PILE FOR REPAIR

Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
G1 1.20 0.20 1.40 Crack above water Epoxy Injection 1.6 1 780 x 780 @ 2-3 meters from under slab
37
G1 8.00 0.20 8.20 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
SECTIONAL PILE FOR REPAIR

Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
37 G2 0.10 0.20 0.30 Crack below water Epoxy Injection 0.7 1 780 x 780 @ 2-3 meters from under slab
G3 0.90 0.20 1.10 Crack above water Epoxy Injection 3.2 3 780 x 780 @ 2-3 meters from under slab
37 1.60 0.20 1.80 Crack at midsection
G3 Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.20 0.20 1.40 Crack below water, bottom
1.90 0.20 2.10 Crack below water
37 G4 7.60 0.20 7.80 Crack at midsection Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.70 0.20 0.90 Crack below water
G5 1.50 0.20 1.70 Crack above water Epoxy Injection 3.4 3 780 x 780 @ 2-3 meters from under slab
37 0.70 0.20 0.90 Crack below water
G5 Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.40 0.20 0.60 Crack at midsection
D 0.40 0.20 0.60 Crack above water Epoxy Injection 0.7 4 780 x 780 @ 2-3 meters from under slab
MDA-1
D 0.40 0.20 0.60 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
B 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
MDA-3 0.40 0.20 0.60 Crack below water
B Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.20 0.20 0.40 Crack below water
C 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 1 780 x 780 @ 2-3 meters from under slab
MDA-7 0.30 0.20 0.50 Crack at midsection
C Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.30 0.20 0.50 Crack below water, bottom
A 0.50 0.20 0.70 Crack above water Epoxy Injection 0.8 2 780 x 780 @ 2-3 meters from under slab
0.50 0.20 0.70 Crack below water
MDB-1
A 0.80 0.20 1.00 Crack at midsection Epoxy Injection and Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
0.55 0.20 0.75 Crack below water
B 0.30 0.20 0.50 Crack above water Epoxy Injection 0.3 1 780 x 780 @ 2-3 meters from under slab
MDA-1
B 0.80 0.20 1.00 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
D 1.00 0.20 1.20 Crack above water Epoxy Injection 1.6 1 780 x 780 @ 2-3 meters from under slab
MDB-1
D 0.50 0.20 0.70 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDB-2 C 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
D 0.40 0.20 0.60 Crack above water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
MDB-3 0.70 0.20 0.90 Crack at midsection
D Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
2.70 0.20 2.90 Crack below water, bottom
B 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 1 780 x 780 @ 2-3 meters from under slab
MDB-4
B 0.65 0.20 0.85 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDB-6 B 0.30 0.20 0.50 Crack above water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDB-6 C 0.70 0.20 0.90 Crack above water Epoxy Injection 0.7 2 780 x 780 @ 2-3 meters from under slab
B 0.90 0.20 1.10 Crack above water Epoxy Injection 2.2 1 780 x 780 @ 2-3 meters from under slab
MDB-7
B 0.70 0.20 0.90 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
D 0.60 0.20 0.80 Crack above water Epoxy Injection 1.5 1 780 x 780 @ 2-3 meters from under slab
MDC-1
D 9.20 0.20 9.40 Crack at midsection Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-3 C 0.75 0.20 0.95 Crack above water Epoxy Injection 1.65 1 780 x 780 @ 2-3 meters from under slab
SECTIONAL PILE FOR REPAIR

Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
MDC-3 D 0.80 0.20 1.00 Crack above water Epoxy Injection 1.5 1 780 x 780 @ 2-3 meters from under slab
MDC-5 A 0.70 0.20 0.90 Crack above water Epoxy Injection 0.6 3 780 x 780 @ 2-3 meters from under slab
SECTIONAL PILE FOR REPAIR

Crack Crack
Bent No. Pile ID Original Add: Cover Length (m) Notes Remarks Length Width Dimensions
(m) (mm)
C 0.40 0.20 0.60 Crack below water Epoxy Injection 0.4 1 780 x 780 @ 2-3 meters from under slab
MDC-6
C 8.50 0.20 8.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-6 D 8.30 0.20 8.50 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-7 E 8.00 0.20 8.20 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-7 F 9.50 0.20 9.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
2.50 0.20 2.70 Crack at midsection
MDC-8 D Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
1.40 0.20 1.60 Crack below water
MDC-9 E 0.30 0.20 0.50 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-9 F 8.50 0.20 8.70 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-10 C 8.40 0.20 8.60 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
MDC-11 B 7.10 0.20 7.30 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
D 0.30 0.20 0.50 Crack above water Epoxy Injection 0.3 1 780 x 780 @ 2-3 meters from under slab
MDC-13
D 9.90 0.20 10.10 Crack below water Concrete Jacketing 780 x 780 @ 2-3 meters from under slab
HAIRLINE CRACKS

Total No. of Piles per original contract: 97 361


No. of Piles both for Epoxy Injection and Concrete Jacketing: 42 Note:
No. of Piles for Concrete Jacketing: 25 241.47 Final count is 96 since there was no damage
No. of Piles for Epoxy Injection: 137.75 found at Pile 27-G
Quantity (l.m.): 137.75

Prepared by: Noted by: Check and recommending Approval:

Aries C. Hawan John Mark A. Catayong Randy B. Novicio / Napoleon C. Ablaza


Diving Supervisor Project Manager Diving Inspector / Team Lead
HSSC HSSC DCCD - Consultant