PT. ESKA DEKADE ELGAMA TO. PT.

JAYA TEKNIK INDONESIA


PR0JECK BX. CANGE - TANNGERANG BANTEN PENGAJUAN PROGRESS 1. BULAN ; JANUARY 2022
PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY

TOTAL BULAN LALU BULAN INI S/D BULAN INI


Item URAIAN VOL SAT
BOBOT VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS

00000 PERSIAPAN/ GUDANG / BEDENG 1.00 LOT 1.53% 0.00% 0.00% 0.00% 0.40 40% 0.61% 0.40 40% 0.61%
Biaya pembuatan gudang, listrik kerja, air kerja dan biaya keamanan

54000 JASA PEMASANGAN MATERIAL UTAMA


MATERIAL ELEKTRIKAL MALL
54001 Trafo 2500 KVA (Oil Type) Winding CU - CU 5.00 Unit 1.16% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
54002 Trafo 2500 KVA (Oil Type) (Jalur Panel Chiller) CU - CU 1.00 Unit 0.42% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Jasa Panel Utama


Include material terminasi Reychem/3m, sertifikasi
TM, penurunan dari truck hingga ke posisi pemasangan
serta alat tes yang sudah dikalibrasi
54003 PUTM 1.00 Unit 1.39% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
54004 PUTM Lengkap - Suplai Panel Chiller 2.00 Unit 0.84% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
54005 PUTR Lengkap (sesuai Gambar) 1.00 Unit 1.34% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
54006 PUTR Lengkap (untuk suplai Panel Chiller) 1.00 Unit 0.22% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
54007 Kapasitor Bank (suplai Panel Chiller) 1.00 Unit 0.23% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
54008 Panel Kontrol Genset 5.00 Unit 1.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

54009 Jasa Pemasangan Panel Distribusi Lantai


Panel Distribusi
Lantai B2
1 P-B2-A 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
2 P-B2-B 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
3 SDP-VAC.B2-A 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
4 SDP-VAC.B2-B 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
5 SDP-FAN.B2-A 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
7 P.FAN-B2-2 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai B1
8 P-B1-A 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
9 P-B1-B 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
10 P-OCEANARIUM-B1 1.00 Unit 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
11 SDP-TATA UDARA-OCENARIUM 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
12 SDP-VAC.B1-A 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
13 SDP-VAC.B1-B 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
14 P- AHU-B1-1 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
15 P- AHU-B1-2 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
16 P- AHU-B1-3 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
17 P- AHU-B1-4 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
18 P- AHU-B1-5 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
19 P- AHU-B1-6 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
20 P- AHU-B1-7 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
27 P-FAN-B1-1 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
28 P-T.B1-A 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
29 P-T.B1-B 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
30 SDP.POMPA (LANTAI B1) 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
31 SDP-FIRE (LANTAI B1) 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
32 P-O.B1-FIRE 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
35 PANEL-TATA UDARA-POWER HOUSE 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai LG
36 P-1-A 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
37 P-1-B 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
38 SDP-VAC.1-A 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
39 SDP-VAC.1-B 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
40 P-AHU-1-1 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
41 P-AHU-1-2 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
42 P-AHU-1-3 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
43 P-AHU-1-4 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
44 P-AHU-1-5 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
45 P-AHU-1-6 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
46 P-AHU-1-7 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
47 P-AHU-1-8 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
52 P-T.1-A 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
53 P-T.1-B 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
55 P-P.PT-1 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
56 P-P.WTP-1 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai GF
59 P-2A 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
60 P-2B 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
61 SDP-VAC.2-A 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
62 SDP-VAC.2-B 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
63 P-AHU-2-1 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
64 P-AHU-2-2 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
65 P-AHU-2-3 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
66 P-AHU-2-4 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
67 P-AHU-2-5 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
68 P-AHU-2-6 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
69 P-AHU-2-7 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
70 P-AHU-2-8 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
71 P-AHU-2-9 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
79 P-T.2-A 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
80 P-T.2-B 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai UG
83 P-3A 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
84 P-3B 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
85 P-AHU-3-1 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
86 P-AHU-3-2 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
87 P-AHU-3-3 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
88 P-AHU-3-4 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
89 P-AHU-3-5 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
90 P-AHU-3-6 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
91 P-AHU-3-7 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
92 P-AHU-3-8 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
93 P-AHU-3-9 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
102 P-T.3-A 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
103 P-T.3-B 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
106 SDP-VAC.3-A 1.00 Unit 0.07% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
107 SDP-VAC.3-B 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

DKD-808 | Hal :1/7


PT. ESKA DEKADE ELGAMA TO. PT. JAYA TEKNIK INDONESIA
PR0JECK BX. CANGE - TANNGERANG BANTEN PENGAJUAN PROGRESS 1. BULAN ; JANUARY 2022
PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY

TOTAL BULAN LALU BULAN INI S/D BULAN INI


Item URAIAN VOL SAT
BOBOT VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS

Lantai LH1
108 P-4A 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
109 P-4B 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
110 SDP-VAC.4-A 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
111 SDP-VAC.4-B 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
112 P-AHU-4-1 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
113 P-AHU-4-2 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
114 P-AHU-4-3 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
115 P-AHU-4-4 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
116 P-AHU-4-5 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
117 P-AHU-4-6 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
118 P-AHU-4-7 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
125 P-T.4-A 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
126 P-T.4-B 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai 2F
129 P-5 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
130 P-FAN-5-1 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
131 P-FAN-5-2 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
132 P-FAN-5-3 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
133 P-FAN-5-4 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai ATAP
134 P-PRESS. FAN-1 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
135 P-PRESS. FAN-2 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
136 SDP-VAC.ATAP 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
137 P-FAN-ATAP 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Panel Escalator dan Lift


138 SDP-ESC.B2-A 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
140 SDP-ESC.B1-A 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
142 SDP-ESC.1A 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
143 SDP-ESC.1B 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
151 SDP-ESC.2A 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
152 SDP-ESC.2B 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
153 SDP-ESC.3A 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
154 SDP-ESC.3B 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
157 SDP-LIFT-A 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
158 PP-LIFT FIRE.A 1.00 Unit 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
159 PP-LIFT FIRE.B 1.00 Unit 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
167 PANEL LIFT PENUMPANG MALL 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
168 PANEL LIFT SERVICE/FIRE-OCEANARIUM 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

P.Chiller dan Colling Tower


169 SDP-COOLING TOWER 1.00 Unit 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
171 P.CWP 1.00 Unit 0.13% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
172 P.CHWP 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
173 P.CHILLER-1 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
174 P.CHILLER-2 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
175 P.CHILLER-3 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
176 P.CHILLER-4 1.00 Unit 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
177 P-FAN-R. CHILLER 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
178 P.COOLING TOWER-1 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
179 P.COOLING TOWER-2 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
180 P.COOLING TOWER-3 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
181 P.COOLING TOWER-4 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

P. Smoke Extrak dan Press. Fan


182 P-PRESS. FAN-3 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
183 P-PRESS. FAN-4 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
184 P-PRESS. FAN-5 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
185 P-PRESS. FAN-6 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
186 P-PRESS. FAN-7 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
187 P-PRESS. FAN-8 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
188 P-SMOKE EXTRACT FAN-1 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
189 P-SMOKE EXTRACT FAN-2 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

P.Tangga Kebakaran
196 SDP- TK-A 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
197 SDP- TK-B 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
198 P-TK.1 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
199 P-TK.2 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
200 P-TK.3 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
201 P-TK.4 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
202 P-TK.5 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
203 P-TK.6 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

P.Utilitas
207 PP-KKO (OCENARIUM) 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
208 P-LAMP.O (OCENARIUM) 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
209 PANEL UTILITAS 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
210 P-FH 1.00 Unit 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
211 P-KONTROL 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

P.Plumbing
212 SDP STP / PP. STP 1.00 Unit 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
213 PP-P.SUMPPIT-A 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
214 PP-P.SUMPPIT-B 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
215 P-P.PT-2 1.00 Unit 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

BQ Tambah Kurang Material Panel


1 Panel AHU.B2 OC-1 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
2 Panel AHU.B2 OC-2 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
3 Panel AHU.B1 OC-1 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
4 Panel AHU.B1 OC-2 1.00 Unit 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
5 PP SUMPPIT OCEANARIUM MALL 1.00 Unit 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

54010 Jasa Pemasagan Kabel

DKD-808 | Hal :2/7


PT. ESKA DEKADE ELGAMA TO. PT. JAYA TEKNIK INDONESIA
PR0JECK BX. CANGE - TANNGERANG BANTEN PENGAJUAN PROGRESS 1. BULAN ; JANUARY 2022
PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY

TOTAL BULAN LALU BULAN INI S/D BULAN INI


Item URAIAN VOL SAT
BOBOT VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS
Include material bantu perapihan kabel (Kabel ties
hitam 30cm), penurunan dari truck hingga ke posisi
gudang.
Kabel dari PLN ke MVMDP N2XSEBY 3x120mm2 185.00 mtr 0.39% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Galian (termasuk timbunan tanah kembali + bak kon 1.00 ls 0.87% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
N2XSY 3x1x120mm2 422.80 mtr 0.77% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
N2XSY 3x1x120mm2 (Prov Sum) 52.00 mtr 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYYHY 2x2,5 mm2 84.60 mtr 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 185 mm2 514.60 mtr 1.91% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 95 mm2 695.40 mtr 1.32% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 120 mm2 358.20 mtr 0.86% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 150 mm2 536.50 mtr 1.62% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 240 mm2 639.00 mtr 3.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 300 mm2 325.07 mtr 1.55% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 (1x240) mm2 72.70 mtr 0.32% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 8x(1x240)mm2 163.40 mtr 1.44% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 25 mm2 702.30 mtr 0.42% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 25 mm2 (Prov Sum) 100.00 mtr 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 50 mm2 987.30 mtr 1.15% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 16 mm2 2,621.10 mtr 0.97% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 16 mm2 (Prov Sum) 376.10 mtr 0.14% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 35 mm2 1,188.90 mtr 0.99% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 12 x (1x400)mm2 (Prov Sum) 72.10 mtr 1.57% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 8 x (1x400)mm2 224.30 mtr 3.25% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 16x(1x400)mm2 102.40 mtr 2.96% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 8x(1x300)mm2 168.10 mtr 1.83% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 5 X 6 mm2 3,599.00 mtr 0.67% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x10 mm2 851.57 mtr 0.20% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x10 mm2 (Prov Sum) 20.10 mtr 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 3x4mm2 11,798.00 mtr 1.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 3x6mm2 2,205.90 mtr 0.31% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 5 x 4 mm2 3,053.90 mtr 0.43% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4 x 70 mm2 250.00 mtr 0.41% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 5 X 16 mm2 623.90 mtr 0.29% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 5 X 10 mm2 1,008.40 mtr 0.33% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
NYY 4x(1x400) mm2 76.90 mtr 0.56% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
FRC 4x240 mm2 336.40 mtr 1.86% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
FRC 4 x 25 mm2 1,018.40 mtr 0.61% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
FRC 4 x 95 mm2 95.80 mtr 0.21% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
FRC 4x50 mm2 (Provsum) 100.00 mtr 0.12% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
FRC 4 x 10 mm2 235.40 mtr 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
FRC 5x6 mm2 1,940.80 mtr 0.36% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
FRC 5x4 mm2 8.00 mtr 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

54011 Jasa Pemasangan Busduct


Include material support longdrat 10mm, Hollow
galvanized 60x60 tebal 2mm dan mur baut, penurunan
dari truck hingga ke posisi gudang dan area pemasangan
Busduct 3500A LVMDP-05 ke PCG-4 14.40 mtr 0.37% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LVMDP-9 ke PCG-3 14.40 mtr 0.43% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LVMDP-15 ke PCG-2 17.20 mtr 0.45% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LVMDP-23 ke PCG-1 23.40 mtr 0.67% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PCG 4 ke Genset 4 38.80 mtr 1.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PCG 3 ke Genset 3 35.60 mtr 0.92% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PCG 2 ke Genset 2 33.30 mtr 0.96% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PCG 1 ke Genset 1 24.90 mtr 0.74% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Busduct 4000A Trafo 1 ke LVMDP-8 33.00 mtr 1.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Trafo 2 ke LVMDP-4 36.30 mtr 1.08% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Trafo 3 ke LVMDP-22 41.70 mtr 1.51% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Trafo 4 ke LVMDP-14 38.20 mtr 1.33% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Prov Sum Trafo 5 (Step Up) 5.00 mtr 0.15% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Prov Sum Kabel dari Trafo S 5.00 mtr 0.20% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

LAMPU, TITIK LAMPU, SAKLAR, STOP KONTAK, TRAY & RAK KABEL

54012 Jasa Pemasangan Kabel Instalasi


Include material bantu fischer dan staping, lasdop, isolasi
Kabel Instalasi LT.B2
Kabel NYA 3x2.5mm² + PVC Conduit ø ¾" untuk Instalasi Lampu 1,069.00 ttk 1.88% 0 0% 0.0% 150.00 14% 0.26% 150.00 14% 0.26%
Kabel NYA 3x4mm² + PVC Conduit ø ¾" untuk Instalasi Stop Kontak 108.00 ttk 0.31% 0 0% 0.0% 40.00 37% 0.12% 40.00 37% 0.12%

Kabel Instalasi LT.B1


Kabel NYA 3x2.5mm² + PVC Conduit ø ¾" untuk Instalasi Lampu 503.00 ttk 0.89% 0 0% 0.0% 100.00 20% 0.18% 100.00 20% 0.18%
Kabel NYA 3x4mm² + PVC Conduit ø ¾" untuk Instalasi Stop Kontak 78.00 ttk 0.22% 0 0% 0.0% 40.00 51% 0.12% 40.00 51% 0.12%

Kabel Instalasi LT.LG


Kabel NYA 3x2.5mm² + PVC Conduit ø ¾" untuk Instalasi Lampu 356.00 ttk 0.63% 0 0% 0.0% 90.00 25% 0.16% 90.00 25% 0.16%
Kabel NYA 3x4mm² + PVC Conduit ø ¾" untuk Instalasi Stop Kontak Publik 54.00 ttk 0.16% 0 0% 0.0% 20.00 37% 0.06% 20.00 37% 0.06%

Kabel Instalasi LT.GF


Kabel NYA 3x2.5mm² + PVC Conduit ø ¾" untuk Instalasi Lampu 238.00 ttk 0.42% 0 0% 0.0% 48.00 20% 0.08% 48.00 20% 0.08%
Kabel NYA 3x4mm² + PVC Conduit ø ¾" untuk Instalasi Stop Kontak Publik 52.00 ttk 0.15% 0 0% 0.0% 10.00 19% 0.03% 10.00 19% 0.03%

Kabel Instalasi LT.UG


Kabel NYA 3x2.5mm² + PVC Conduit ø ¾" untuk Instalasi Lampu 129.00 ttk 0.23% 0 0% 0.0% 32.00 25% 0.06% 32.00 25% 0.06%
Kabel NYA 3x4mm² + PVC Conduit ø ¾" untuk Instalasi Stop Kontak 55.00 ttk 0.16% 0.0% 0.0% 0.0% 20.00 2.75 0.44% 20.00 2.75 0.44%

Kabel Instalasi LT.LH1


Kabel NYA 3x2.5mm² + PVC Conduit ø ¾" untuk Instalasi Lampu 140.00 ttk 0.25% 0 0% 0.0% 10.00 14.00 3.46% 10.00 1400% 3.46%
Kabel NYA 3x4mm² + PVC Conduit ø ¾" untuk Instalasi Stop Kontak 44.00 ttk 0.13% 0 0% 0.0% 5.00 11% 0.01% 5.00 11% 0.01%

Kabel Instalasi LT.2F


Kabel NYA 3x2.5mm² + PVC Conduit ø ¾" untuk Instalasi Lampu 92.00 ttk 0.16% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Kabel NYA 3x4mm² + PVC Conduit ø ¾" untuk Instalasi Stop Kontak 41.00 ttk 0.12% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Kabel Instalasi LT.ATAP


Kabel NYA 3x2.5mm² + PVC Conduit ø ¾" untuk Instalasi Lampu 10.00 ttk 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Kabel NYA 5x4mm² + PVC Conduit ø ¾" untuk Instalasi Stop Konta 15.00 ttk 0.07% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

54013 Jasa Pemasangan Typical Box Retail Tenant/ Retail


Include Bobokan dan perapihan kembali, terminasi,
labelling group instalasi
Typical Box Panel 10A 23.00 bh 0.32% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Typical Box Panel 16A 125.00 bh 1.97% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Typical Box Panel 20A 24.00 bh 0.38% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Typical Box Panel 40A 1.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

DKD-808 | Hal :3/7


PT. ESKA DEKADE ELGAMA TO. PT. JAYA TEKNIK INDONESIA
PR0JECK BX. CANGE - TANNGERANG BANTEN PENGAJUAN PROGRESS 1. BULAN ; JANUARY 2022
PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY

TOTAL BULAN LALU BULAN INI S/D BULAN INI


Item URAIAN VOL SAT
BOBOT VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS
Typical Box Panel 63A 2.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Typical Box Panel 100A 2.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Typical Box Panel 160A 2.00 bh 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Typical Box Panel 500A 1.00 bh 0.07% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Typical Box Panel 125A 1.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Typical Box Panel 250A 2.00 bh 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Typical Box Panel 350A 1.00 bh 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai LG
LAK 100 mm 108.29 mtr 0.29% 0 0% 0.0% 60.00 55% 0.16% 60.00 55% 0.16%
LAK 200 mm 385.00 mtr 1.04% 0 0% 0.0% 120.00 31% 0.33% 120.00 31% 0.33%
LAL 200 mm 289.00 mtr 0.78% 0 0% 0.0% 150.00 52% 0.41% 150.00 52% 0.41%
LAK 300 mm 36.00 mtr 0.10% 0 0% 0.0% 20.00 56% 0.06% 20.00 56% 0.06%
Cable Ladder 600 mm 182.00 mtr 0.55% 0 0% 0.0% 40.00 22% 0.12% 40.00 22% 0.12%

Lantai GF
LAK 100 mm 174.00 mtr 0.47% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAK 200 mm 438.00 mtr 1.19% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAL 200 mm 436.00 mtr 1.18% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAK 300 mm 66.00 mtr 0.19% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAL 300 mm 82.00 mtr 0.23% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai UG
LAK 200 mm 109.00 mtr 0.30% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAL 200 mm 574.00 mtr 1.56% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAK 300 mm 552.00 mtr 1.55% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAL 300 mm 84.00 mtr 0.24% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAK 400 mm 89.00 mtr 0.25% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai LH.1
LAK 100 mm 206.00 mtr 0.56% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAK 200 mm 466.00 mtr 1.26% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAL 200 mm 412.00 mtr 1.12% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAK 300 mm 85.00 mtr 0.23% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAL 300 mm 90.00 mtr 0.25% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAK 400 mm 10.00 mtr 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Jasa Kabel Tray & Kabel Ladder Tambahan


Tray Data 100 mm 3,500.00 mtr 9.50% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Tray Kabel TM 200 mm 76.24 mtr 0.21% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Jasa Pemasangan Lampu lengkap peralatan bantu


54015 sesuai spesifikasi dan gambar Include material longdrat
meyesuaikan level balok

Lantai B2
TL BALOK LED 1 x 14.5 WATT 465.00 bh 0.88% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 1 x 14.5 WATT c/w Batere Nicad 90.00 bh 0.17% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT 7.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT c/w Batere Nicad 7.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 2 x 14.5 WATT c/w Batere Nicad 18.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAMPU EXIT 2 x 8 WATT 27.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT 96.00 bh 0.18% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT c/w Batere Nicad 28.00 bh 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT 25.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT Batere 9.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Wall Lamp PL 18 W 29.00 bh 0.17% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 600 LUMEN 8 WATT 17.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 600 LUMEN 8 WATT c/w Batere 3.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT, Dichroic 7 WATT - 12 VOLT (Eye Ball 48.00 bh 0.08% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai B1
Downlight LED 2300 L 22W 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Downlight LED 2300 L 22W c/w Batere 1.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Downlight LED 1100 L 11,5W 10.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Downlight LED 1100 L 11,5W c/w Batere 5.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Downlight LED 600 L 8W 35.00 bh 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Downlight LED 600 L 8W c/w Batere 15.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Downlight Dicroic 7W 12 V Eye Ball 10.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL Balok LED 1x14,5 Watt 160.00 bh 0.30% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL Balok LED 1x14,5 Watt c/w Batere 48.00 bh 0.09% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL Bracket LED 2x14,5 Watt c/w Batere 20.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Wall Lamp PL 18 W 12.00 bh 0.07% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL Bracket LED 1x14,5 Watt c/w Batere 8.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL Balok LED 2x14,5 Watt c/w Batere 20.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL Balok LED 2x14,5 Watt 32.00 bh 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL Bracket LED 1x14,5 Watt 7.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Lampu Exit 2x8 W 18.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai LG
TL BALOK LED 1 x 14.5 WATT 16.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 1 x 14.5 WATT c/w Batere Nicad 7.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT 8.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT c/w Batere Nicad 8.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 2 x 14.5 WATT c/w Batere Nicad 26.00 bh 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BOX ARMATURE LED 2 x 14.5 WATT C/W LOUV 7.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BOX ARMATURE LED 2 x 14.5 WATT C/W LOUVE 4.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAMPU EXIT 2 x 8 WATT 9.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT 10.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT c/w Batere Nicad 4.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT 33.00 bh 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT c/w Bate 17.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 2300 LUMEN 22 WATT 87.00 bh 0.14% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 2300 LUMEN 22 WATT c/w Bater 20.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai GF
TL BALOK LED 1 x 14.5 WATT 27.00 bh 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 1 x 14.5 WATT c/w Batere Nicad 13.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT 8.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT c/w Batere Nicad 8.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 2 x 14.5 WATT c/w Batere Nicad 16.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAMPU EXIT 2 x 8 WATT 8.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT 3.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DKD-808 | Hal :4/7
PT. ESKA DEKADE ELGAMA TO. PT. JAYA TEKNIK INDONESIA
PR0JECK BX. CANGE - TANNGERANG BANTEN PENGAJUAN PROGRESS 1. BULAN ; JANUARY 2022
PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY

TOTAL BULAN LALU BULAN INI S/D BULAN INI


Item URAIAN VOL SAT
BOBOT VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS
TL BALOK LED 2 x 14.5 WATT c/w Batere Nicad 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 600 LUMEN 8 WATT 4.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 600 LUMEN 8 WATT c/w Batere 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT 15.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT c/w Bate 11.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 2300 LUMEN 22 WATT 11.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 2300 LUMEN 22 WATT c/w Bater 4.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT, Dichroic 7 WATT - 12 VOLT (Eye Ball 6.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai UG
TL BALOK LED 1 x 14.5 WATT 23.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 1 x 14.5 WATT c/w Batere Nicad 13.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT 9.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT c/w Batere Nicad 9.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 2 x 14.5 WATT c/w Batere Nicad 18.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAMPU EXIT 2 x 8 WATT 9.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT c/w Batere Nicad 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 600 LUMEN 8 WATT 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 600 LUMEN 8 WATT c/w Batere 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT 12.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT c/w Bate 10.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 2300 LUMEN 22 WATT 10.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 2300 LUMEN 22 WATT c/w Bater 5.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT, Dichroic 7 WATT - 12 VOLT (Eye Ball 3.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai LH1
TL BALOK LED 1 x 14.5 WATT 21.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 1 x 14.5 WATT c/w Batere Nicad 8.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT 9.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT c/w Batere Nicad 9.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 2 x 14.5 WATT c/w Batere Nicad 18.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAMPU EXIT 2 x 8 WATT 9.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT c/w Batere Nicad 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 600 LUMEN 8 WATT 5.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 600 LUMEN 8 WATT c/w Batere 3.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT 23.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 1100 LUMEN 11.5WATT c/w Bate 11.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 2300 LUMEN 22 WATT 10.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT LED 2300 LUMEN 22 WATT c/w Bater 5.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
DOWN LIGHT, Dichroic 7 WATT - 12 VOLT (Eye Ball 5.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai 2F
TL BRACKET LED 1 x 14.5 WATT 4.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 1 x 14.5 WATT c/w Batere Nicad 7.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BRACKET LED 2 x 14.5 WATT c/w Batere Nicad 8.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
LAMPU EXIT 2 x 8 WATT 5.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT 20.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL BALOK LED 2 x 14.5 WATT c/w Batere Nicad 16.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
SPOT LIGHT LED 90 WATT 32.00 bh 0.19% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai Atap
Tambahan Jasa Lampu lengkap peralatan bantu sesuai
spesifikasi dan gambar
Downlight LED 2300 L 22W c/w Batere 1.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Downlight LED 1100 L 11,5W 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Downlight LED 1100 L 11,5W c/w Batere 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Downlight LED 600 L 8W 4.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
TL Bracket LED 2x14,5 Watt c/w Batere 5.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

54016 Jasa Pemasangan Kotak kontak


Lantai B2
Stop Kontak 16 A/1P 300mm AFF 106.00 bh 0.08% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Tunggal 16.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Ganda 49.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Grid Switch 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai B1
Stop Kontak 16A/1P 300 mm 72.00 bh 0.05% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Stop Kontak 16A/1P 1200 mm 5.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Tunggal 13.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Ganda 39.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Grid Switch 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai LG
Stop Kontak 16 A/1P 300mm AFF 28.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Stop Kontak 16A/1P 1200mm AFF 3.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Stop Kontak Lantai 20A/1P (1 Modular) 8.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Tunggal 4.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Ganda 26.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Grid Switch 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai GF
Stop Kontak 16 A/1P 300mm AFF 43.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Stop Kontak 16A/1P 1200mm AFF 9.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Tunggal 6.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Ganda 21.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Grid Switch 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai UG
Stop Kontak 16 A/1P 300mm AFF 47.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Stop Kontak 16A/1P 1200mm AFF 8.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Tunggal 3.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Ganda 24.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Grid Switch 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Lantai LH1
Stop Kontak 16 A/1P 300mm AFF 39.00 bh 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Stop Kontak 16A/1P 1200mm AFF 5.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Tunggal 4.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Ganda 22.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Grid Switch 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

DKD-808 | Hal :5/7


PT. ESKA DEKADE ELGAMA TO. PT. JAYA TEKNIK INDONESIA
PR0JECK BX. CANGE - TANNGERANG BANTEN PENGAJUAN PROGRESS 1. BULAN ; JANUARY 2022
PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY PEKERJAAN ELECTRICAL SYSTEM - LAK DAN CABLE TRAY

TOTAL BULAN LALU BULAN INI S/D BULAN INI


Item URAIAN VOL SAT
BOBOT VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS VOLUME PRESTASI PROGRESS
Lantai 2F
Stop Kontak 16 A/1P 300mm AFF 24.00 bh 0.02% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Stop Kontak Gondola 16A/3P (Waterproofing) 17.00 bh 0.04% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Tunggal 6.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Ganda 9.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Grid Switch 1.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

Jasa Kotak kontak tambahan


Stop Kontak 16A/1P 1200 mm 2.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Tunggal 7.00 bh 0.01% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Saklar Ganda 6.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Grid Switch 1.00 bh 0.00% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

54017 JASA PERALATAN UTAMA GROUNDING


Include Dinabold, sepatu kabel/schoon kabel, vinyl
kabel, alat torsi, penurunan dari truck hingga ke posisi
pemasangan serta alat tes yang sudah dikalibrasi

MPEB LV 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%


MPEB MV 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
SPEB 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
MPEB 1.00 Unit 0.03% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PEB B2 2.00 Unit 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PEB B1 2.00 Unit 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PEB LG 2.00 Unit 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PEB GF 2.00 Unit 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PEB UG 2.00 Unit 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PEB 1 2.00 Unit 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PEB Atap 2.00 Unit 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
PEB MV (di lantai atap) 2.00 Unit 0.06% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%
Bak Kontrol 18.00 Unit 0.63% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

54017 JASA PEMASANGAN KABEL BC UNTUK INSTALASI GROUNDING


Include material bantu perapihan kabel (Kabel ties
hitam 30cm), penurunan dari truck hingga ke posisi
gudang.
Kabel BC 70mm2 untuk instalasi grounding : 11,453.30 mtr 2.28% 0 0% 0.0% 0.00 0% 0.00% 0.00 0% 0.00%

TOTAL JUMLAH 100.00% 0.00% 955.40 21.91 6.65% 955.40 21.91 6.65%

6.65%
13.30%

TANGERANG 20 - 01 - 2022 TANGERANG 20 - 01 - 2022


DI BUAT OLEH : DI AJUKAN OLEH :
SUB KONTRAKTOR SUB KONTRAKTOR

-
ACH. IQBAL H.NASRUDDIN ZAINI
PT. ESKA DEKADE ELGAMA PT. ESKA DEKADE ELGAMA

DKD-808 | Hal :6/7


PERHITUNGAN BOBOT DAN PRESTASI
PEKERJAAN INSTALASI LISTRIK
PROGRESS KE :1
BULAN : DESEMBER

PROGRESS BULAN LALU PROGRESS BULAN INI TOTAL


PENJUMLAHAN TOTAL TOTAL BOBOT
BOBOT BOBOT BOBOT

DAFTATR NO 1 PEKERJAAN PERSIAPAN 1.53% 0.00% 0.61% 0.61%

DAFTATR NO 2 PEKERJAAN INSTALASI LISTRIK 98.47% 0.00% 6.04% 6.04%

TOTAL REKAPUTILASI PROGRESS 100.00% 0.00% 6.65% 6.65%

TANGERANG 21 - 01 - 2022
DI AJUKAN OLEH :
SUB KONTRAKTOR

H. NASRUDIN
PT. DEKADE ESKA ELGAMA

PT.DEKADE ESKA ELGAMA


H.NASRUDIN