COST ESTIMATE FOR SINGLE STOREY BUILDING ( ABSTRACT)

Sl. No. Description of Works No. Amount in Rs.


A. CIVIL WORKS.
i. CONSTRUCTION OF BUILDING(GF) 1 2435492.64

Sub Total (A) 2435492.6

Provision for un-forseen items and periphery


B. development (CIVIL COST)@5% 5% 121774.63
Sub Total(B) 121774.63

P.H. WORKS.(INTERNAL & EXTERNAL P.H. &


C. SANITARY WORK) 10% 243549.26

Sub Total(C) 243549.26

D. INTERNAL & EXTERNAL ELECTRICAL WORK 10% 243549.26

Sub Total(D) 243549.26

E. TOTAL = (A+B+C+D) 30,44,365.75


F. Add GST @ 18% on TOTAL (E) 18% 547985.835
G. TOTAL = (E+F) 3592351.585
H. Add Contigency @ 2% on TOTAL (E) 0.02 60887.315
GRAND TOTAL = (G+H) Rs. 36,53,238.90
SAY Rs. 3653000
Rupees Thirty Six Lakhs Fifty Three Thousand Only
COST ESTIMATE FOR SINGLE STOREY BUILDING ( ABSTRACT)
Sl. No. Description of Works No. Amount in Rs.
A. CIVIL WORKS.
i. CONSTRUCTION OF BUILDING(GF) 1 2435492.64

Sub Total (A) 2435492.6

Provision for un-forseen items and periphery


B. development (CIVIL COST)@5% 5% 121774.63
Sub Total(B) 121774.63

P.H. WORKS.(INTERNAL & EXTERNAL P.H. &


C. SANITARY WORK) 10% 243549.26

Sub Total(C) 243549.26

D. INTERNAL & EXTERNAL ELECTRICAL WORK 10% 243549.26

Sub Total(D) 243549.26

E. TOTAL = (A+B+C+D) 30,44,365.75


F. Add GST @ 18% on TOTAL (E) 18% 547985.835
G. TOTAL = (E+F) 3592351.585
H. Add Contigency @ 2% on TOTAL (E) 0.02 60887.315
GRAND TOTAL = (G+H) Rs. 36,53,238.90
SAY Rs. 3653000
Rupees Thirty Six Lakhs Fifty Three Thousand Only