Project: Proposed EDC Office Interior Fit-Out

Architect: Ar. June Carlo A. Zapanta


Contractor: ALZA Construction
Date of Visit: 02/28/23

CONSTRUCTION PUNCH LIST

ITEM PHOTO LOCATION REMARKS


1 Entrance  Repaint Entrance Door
Header

2 Reception  Clean Glue Marks


Counter  Clean / Retouch White Paint
 Install Drawer Pulls

3 Reception Area  House Wire in Molding


painted in Grey
4 Signage  Hide LED Driver Inside Wall
Behind Signage (make hole in
drywall to house the LED
Driver as long as the hole will
be covered by EDC Signage)

5 Work Cubicles  Apply Finishing Coat


 Install Drawer Pulls

6 Seating Area  Paint Column Face White


Column
7 Seating Area  Apply Filler and Sealant in
Gaps
 Alter Melamine Seating to
Allow Operation of Awning
Window @ Left Side

8 Pantry Shelving  Rectify Sag with Epoxy


 Rectify Delaminated Edge
Banding
9 Floating  Apply Silicone Sealant to all
Shelves Wall to Shelf Connections
 Cover Exposed Screws

10 Various  Clean / Retouch Paint Works


@ Edges and Along Conduits
11 Jr Executive  Install Melamine Board
Office Seating

You might also like