Page | 1
PROJECT: Ref. No.:
METHOD STATEMENT FOR TESTING AND Rev : 00
COMMISSIOING OF UNINTERRUPTED
POWER SUPPLY (UPS) Date: 15.02.2023
METHOD STATEMENT
METHOD STATEMENT
FOR TESTING AND COMMISSIOING OF
TITLE
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
01
02
03
CONTENT
1. PURPOSE .................................................................................................................................................... 4
2. SCOPE ......................................................................................................................................................... 4
3. REFERENCES ............................................................................................................................................ 4
4. DEFINITIONS & ABBREVATIONS ......................................................................................................... 5
5. WORKING ACCESS .................................................................................................................................. 6
6. LIGHTING .................................................................................................................................................. 6
7. PLANT & EQUIPMENT ............................................................................................................................ 6
8. MATERIALS ............................................................................................................................................... 8
9. SEQUENCE / METHOD OF WORK ......................................................................................................... 8
10. PROGRAMME .......................................................................................................................................... 16
11. RISKS & CONTROLS .............................................................................................................................. 17
12. TECHNICAL INFORMATION ................................................................................................................ 17
13. EMERGENCY ARRANGEMENTS ......................................................................................................... 18
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
1. PURPOSE:
The purpose of this Method Statement to ensure safe working practice during Testing & Commissioning of
UPS installed at Al Anantara Project. It gives details of how the Testing & commissioning procedure will be
carried out in a safe manner and identifies any health & safety issues and respective controls that need to
be in place for a safe working environment.
The content of this method statement reflects the findings of the relevant risk assessment.
2. SCOPE:
This method statement details the method of testing and commissioning of the UPS as per manufacturer
recommendations.
3. REFERENCES:
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
5. WORKING ACCESS:
The access / egress for the construction vehicles for the installation of activities to be as per the logistic Plan.
Ensure Proper coordination with all interfacing contractors for Logistics, access prior to commencement of all
activities.
6. LIGHTING:
i. Safety Lighting:
The minimum safety lighting as per general requirements (Minimum 50 lux) will be provided.
Task lighting to be provided in addition to the safety lighting to undertake the task with the proper level of
lighting to meet acceptable safety and quality of workmanship standards.
i. General:
Appropriate plants and equipment to be used for the execution of the activity. The plant, tools and
equipment to be checked visually prior to use.
Only authorized applicator approved and trained by the manufacturer to install manufacturer's products
All Operators to be trained and certified by the 3rd party where required
No defective plant and equipment to be allowed to use on site
5 Screw driver
6 Set of Spanner
7 Pliers
8 Clamp meter
9 Laptop
Note: All valid calibration certificates shall be available on site during testing and witnessing activities.
iii. Personal Protective Equipment:
(Refer Attachment for Risk Assessment)
All operatives involved in the activity to be provided with Job Specific Personal Protective equipment which
are and but not limited as mentioned below
Polycarbonate Safety Helmet
Safety boots with steel toe
Coverall with high visibility strips
Hand Gloves
Ear Plugs
Eye protection / Goggles
iv. Power:
The Power supply used on site for power tools to be 230V. 230V or higher voltage power supply to be
provide to site welfare areas and other site establishment.
v. Working Platforms:
All working platforms shall be designed and comply with UAE code of construction practice. All work
at height to follow the project fall prevention plan and UAE code of construction practice.
All scaffoldings shall be recorded in the temporary works register / scaffolding log and coordinated
with the TC coordinator. The contractor shall refrain from using step ladders as working platforms
for installation works and shall use scaffoldings or podium steps.
The working platforms for the task to be firm and stable.
The elevated working platforms for the activity (if used) to be provided by means of cup lock
scaffold system.
The scaffolds for the activity to be built by competent scaffolders trained by third party.
The built scaffolds to be inspected and signed off by a third party trained inspectors / supervisors.
Where necessary access to be provide by means of scaffold
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
The working platforms to be used as only platforms for working and shall not be used for loading
heavy material or equipment on to it.
8. MATERIALS:
SL No. Material Description
1 UPS, VRLA Batteries and its accessories (as per approved material submittal)
The above listed materials/items to be in line with the approved material submittal and requirement of the
project.
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
PRE-Commissioning:
Preliminary Activities:
PM//PE/QHS PROJECT
Submit material submission for all materials related to the task for Engineer
E/Specialist SPEC
approval and obtain approval.
As per approved material submittal and IFC drawings/specification prepare and
submits shop drawing and obtain approval from the relevant project authorities
and local regulatory body.
Method statement, inspection & test plan and Risk Assessment to be submitted
for Engineer approval and obtain approval. Authorities (as applicable)
Implement the risk mitigation actions as per the approved risk assessment and
ensure that the risk is as low as reasonably practicable.
Approval for the installation to be achieved prior start the T&C of the System.
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
Delivery notes to be obtained for materials delivered to site and stored in the PM/PE/QHSE
designated areas as per manufacturer recommendations. / Specialist Project
Submit MIR for delivered materials on site SPEC/
Ensure that all materials are approved prior to using the material on site. MSS/ITP/
Ensure that method statement, ITP and shop drawing approved prior to starting RA/PTW
any activity on site.
Adequate lighting to be provided in the work areas to execute the task.
All risk hazards on operations have been identified and precautions are taken.
Ensure that all necessary personnel, plant, equipment and services are required
for the works is in place.
Implement employee induction procedure and tool box talks for ongoing risk
assessment and identification of hazards.
Ensure RFI is raised and approved for technical clarification and modification
as/if required.
Ensure work area is clear and safe for working
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
1.Check the absence of short circuit on Input and Output power terminals
2.Provide voltages on the power terminals (input rectifier and auxiliary)
3.Check that voltages respect the limits of the Unit
4. Check the correct working of manual by-pass Q6 different positions
5. Close the input breaker and check on mimic panel the measurements and absence of
alarms related to this input
6. Close the auxiliary mains input breaker and check on mimic panel that all is OK (i.e. no
alarm about phase rotation)
7. Close the battery breaker and verify the battery measurements on mimic panel
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
• The load shall be energized with zero loads and checked for functionality If satisfactory
the UPS shall be energized and switched to support the actual bank.
• Load shall be applied to the KVA rating of the UPS, Observe and record the UPS
measurements of volt, temperature, and frequency WITH (0,100%) Load.
C- Functional Test:
1. From UPS Display: Load to static BYPASS: UPS shall transfer the load to static bypass
(high efficiency mode) without interruption upon user command
2. From UPS Display: Load to Inverter: UPS shall transfer the load back to inverter (UPS
mode) without interruption upon user command
3. From UPS Display: Load to manual bypass: UPS shall transfer the load to manual bypass
(bypass mode) without interruption upon user command
4. Open input breaker: Main’s failure (ON BATTERY): Battery shall be able to supply the
load without interruption (battery mode)
5. Close input breaker: Mains restore UPS shall transfer the load back to UPS mode without
interruption.
• On starting the battery discharge test the mains shall be failed at the closest isolation
point upstream of the UPS to simulate mains failure at 100% Load (as per approved battery
calculation). Battery voltage and current will be recorded from the UPS display at 5 min
intervals until cut-off voltage is achieved.
• The mains supply shall be re-installed and the UPS allowed restarting, Recharge voltage
and current shall be recorded and the battery allowed recharging.
• Before disconnecting the load it shall be allowed to cool off load and then switched off.
The output of the UPS will be isolated to allow the load to be disconnected.
• On completion of the load test; all connections, power and control, shall be remade and
checked.
• If the battery still requires re-charging the UPS shall be started and left to recharge either
supplying the load or isolated from it.
• The load shall be packed for removal and stored safely until dispatched.
• All barriers / signs removed leaving the workplace as it was found
• Results shall be drawn up into a report and check list.
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
D- Battery:
• Battery parameters/Main Battery Config/Battery-Elements = n° of elements per 1 branch
• Battery parameters/Main Battery Config/Battery-Blocks = 12V corresponding n° of blocks
• Battery parameters/Main Battery Config/Battery-Position = internal/external
• Battery parameters/Recharging Config/Temperature-Compensation = enable if external
temp. probe present and connected on ADC+SL card
• Battery parameters/Batt. Temperature Config/Battery-Temperature-Gap = must be set Project
to 0 PM/PE/SE/Q SPEC/
E- UPS ALARMS VERIFICATION. CM/HSEM/ MSS/ITP/
• Observe and record the alarms appeared during the functional test performed to make specialist Manual
sure UPS is monitoring all alarms and status.
• Include missing Alarm check lists, check list/test report for start-up test, normal
operation test, battery operation test, static bypass operation test, maintenance by pass
testing, battery discharge test, load test, Interface/communication test, over all
functioning test, etc.
Quality Control
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
10. PROGRAMME
As per the site construction programme.
i. Hazards / Risks
In addition to the requirements indicated in the specification mentioned under section 7., drawings, schedules,
the work will be in accordance with recommendations and requirements of the following standards, codes and
bodies. The current editions of publications being those applicable:
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
i. General
The Site HSE department to be responsible to arrange and coordinate with site execution teams in arranging
Day & Night emergency procedures
In case of any emergency the HSEM will be informed about the emergency
Emergency assembly point to be allotted and communicated to all the operatives involved in the job
Ensure clear access to the emergency assembly area with signage’s in place.
No construction activity shall block the access leading to the emergency assembly point. In case of any
deviation the access has to divert and the same to be communicated to all the operatives on site.
Fire extinguishers to be put in place in each working zone and a clear access to be provided to the
location
All the operatives to be trained for fire precautions on site
A fire warden is appointed and trained from each team of operatives
iii. Communication
The communication on site to be through mobile provided by the contractor or by two-way wireless radio
systems
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
14. TRAINING
Necessary safety or operational training to be provided to the operatives involved in the activities
15. SUPERVISION
Site working hours to be 06:30 AM to 05:30 PM. Authority regulations for the working hours will be
followed. Mid-day break between 12:30 PM to 3:00 PM will be followed during summer as per
regulation.
17. HOUSEKEEPING
1. Risk Assessment
2. UPS pre-commissioning check list
3. UPS Commissioning – Testing check list
4. Manufacturer recommendations for UPS.
a. Operating manual
b. Quick start guide
CONTRACTOR: Delta Electrical & Sanitary Contracting & Safety Equipment LLC
Page | 1
PRE-COMMISSIONING REPORT
Page 1 of 1
Date - Time
Unit model
Serial Number
Configuration
Unit Location
Engineer
Witnessed by
SUPPLIER MEP MAIN CONSULTANT
CONTRACTOR CONTRACTOR
Name
Date
Signature
Page | 1
COMMISSIONING CHECKLIST (LOAD & BATTERY DISCHARGE TEST)
Date - Time
Unit model
Serial Number
Configuration
Unit Location
Engineer
TESTING PROCEDURE:
STEP DESCRIPTION
ENVIRONMENTAL CHECK-UP
1 Obverse and record the UPS surroundings i.e. temperature, humidity, availability of air condition
etc. in section step-1
UPS UPSTREAM MEASUREMENT
2
Obverse and record the UPS upstream readings i.e. mains & auxiliary in section step-2
MEASUREMENT OF UPS OUTPUT WITHOUT load – zero load
3 Obverse and record the UPS output readings WITHOUT LOAD on various modes i.e. UPS mode,
static bypass mode, battery mode etc. in section step-3.
MEASUREMENT OF UPS OUTPUT WITH______________ LOAD
4 Obverse and record the UPS output readings WITH LOAD on various modes i.e. UPS mode,
static bypass mode, battery mode etc. in section step-4.
FUCTIONAL TEST
5 Observe and record the performance of the UPS as per specification for the deep discharge test,
load on static bypass, load back on inverter etc. under section step-5.
UPS ALARMS VERIFICATION.
6 Observe and record under the section step-5 the alarms appeared during the functional test
performed in step-6.
STEP -1
TEMPERATURE (0 TO 40°C) HUMIDITY (95% MAX)
AIR CONDITION DUST-FREE
STEP -3
PERCENTAGE OF LOAD ZERO%
LOAD IN kW Zero
LOAD TYPE
UPS
ITEM DESIGN VALUES TOLERANCE REMARKS
READING
L1 230 V
L2 230 V
Output voltage (Vac) on L3 230 V
L12 400 V ±1%
inverter mode
L23 400 V
L31 400 V
STEP -4
LOAD IN kW
LOAD TYPE
UPS
ITEM DESIGN VALUES TOLERANCE REMARKS
READING
L1 230 V
L2 230 V
Output voltage (Vac) on L3 230 V
±1%
inverter mode L12 400 V
L23 400 V
L31 400 V
LOAD IN kW
LOAD TYPE
S.NO. DESCRIPTION EXPECTED RESULTS REMARKS
UPS SHALL TRANSFER THE
LOAD TO STATIC BYPASS (HIGH
1 LOAD TO STATIC BYPASS EFFICIENCY MODE) WITHOUT
INTERRUPTION UPON USER
COMMAND
UPS SHALL TRANSFER THE
LOAD BACK TO INVERTER (UPS
2 LOAD TO INVERTER MODE) WITHOUT
INTERRUPTION UPON USER
COMMAND
UPS SHALL TRANSFER THE
LOAD TO MANUAL BYPASS
7 LOAD TO MANUAL BYPASS (BYPASS MODE) WITHOUT
INTERRUPTION UPON USER
COMMAND
8 OTHER:
9 OTHER:
STEP -6
OBSERVE AND COMMENT ON THE ALARMS WHICH APPEARED ON THE MIMIC PANEL
-
-
-
-
-
-
-
-
-
Witnessed by
SUPPLIER MEP MAIN CONSULTANT
CONTRACTOR CONTRACTOR
Name
Date
Signature
Page | 12
DOC No HSE-RA-01
PAGE No 1 of 14
RISK ASSESSMENT REV 1
DATE 26-08-2021
RISK ASSESSMENT
MAIN ACTIVITY: Installation of Uninterrupted Power Supply (UPS) RA No BMTS/012
LOCATION:
Al Anantara-RAK PROJECT: Al Anantara-RAK DATE: 11-11-2021
EQUIPMENT TO BE USED SUBSTANCES TO BE USED REVISION STATUS
Cutting tools, Manual Crimping Tools, Tools set N/A REVISION NUMBER REVISED DATE
00 First Issue
WORKING FROM HEIGHT ELECTRICITY HAND TOOLS MATERIAL HANDLING CONFINED SPACE
□EXCAVATION/BACK FILLING EMPLOYEES PUBLIC
Potential Residual
Risk H / M
Demonstrated
Risk H /
Consequence / L With Existing Barrier or M/L
ALARP
Hazard Cause Recommended Controls with
Job Step s no Controls
Sequence of controls controls
# The potential to Possible causes in place
Action By in place
working The harm which Describe all existing Describe additional controls that are
activities cause harm. that will
could possibly barriers /controls for each required
Health, Injury, potentially Yes
occur S P PR hazard S P RR
Property damage, release a hazard /No
environment etc.
Unplanned Obstructed • Ensure all the work • Close effective supervision of Site Manager/
movement of visibility of the crews including the activity Supervisor/HSE
vehicles operator delivery drivers are • Additional refresher training O/Operator/
adequately trained Flag man
to Drivers, Operators and
Overturning -In- through induction.
• Segregation of Flagman.
competency of • Pre-Task Briefing to task team
Collision with pedestrians from
pedestrians / operator prior to the commencement
moving plant /
operatives equipment where of work.
-Operator possible
-Serious • Trained banksman for
Collision with under the injuries can
structures • Suitable signage in controlling all vehicle
influence of be movements
Mobilization place to warn of
drugs / alcohol sustained
Collision with vehicle movement • Work will be planned
of Materials to by person if
01 5 3 15 5 1 5 Yes
Site other vehicles struck by • TBT to explain the between normal work hours
-Over speeding
moving dangers of working (daylights), otherwise
Overloading and -Defective next to vehicles,
plant, adequate lighting will be
falling from warning plant &
vehicles provided
devices Fatality equipment’s
• Banksman shall maintain a
Drivers • Competent drivers / suitable safe position in order
-Sleeping or operators with valid
unfamiliar with to maintain good and
resting under / UAE driving licenses
the site constant communication with
near plant / / 3rd party
competency the mobile plant operator
Unsafe delivery equipment
certificates • Close and effective
/ pick up point
supervision of the work
-Breakdown / • Flagman in place to
activity by the construction
malfunctioning control all reversing
DOC No HSE-RA-01
PAGE No 3 of 14
RISK ASSESSMENT REV 1
DATE 26-08-2021
• Competent
Supervision in place
Unsafe Elimination: • Pre-task briefing to be Supervisor/Oper
offloading/loadi discussed to all persons ator/Rigger/HSE
ng area • Do not work or involved in the task prior to O/Lifting
walk under the works commencing. supervisor
Unexpected suspended load • Trained and certified lifting
movements Isolation: supervisor and riggers must
deploy for the lifting activity
• Provide exclusion
Fall / Roll Over • Permit shall be obtaining
zone(s) where the
activity is occurring. from HSE dept prior to
Loads not
• All personnel on commence the lifting
properly
foot must be clear operation
restrained
of the loading zone • All lifting equipment to have
Unsafe Work Injury during operations. current test certificates
Exceeding safe
working limits Practice Engineering Controls: certified by approved third
Loading & Fatality party and to be inspected
02 Offloading of 4 3 12 daily and before use by the 4 1 4 Yes
Person hit in Lack of
Material Property • Ladder to be slinger/signaller who is
swing zone Supervision
damage provided when responsible for the operation.
accessing the trailer
Loads not • Certified lifting supervisor
from ground
properly must be present for lifting
• If multiple items or
restrained operations.
loads that shall be
shifted are moved, • Always maintain the
Falling objects
these must be adequate exclusion zone with
properly secured isolation, signages and
Person struck by
with straps, bands watchmen.
moving object /
or other means
load / • Material must be offloaded in
prior to works
equipment a designated material storage
commencing.
area along with barricading
Unsecured loads and signages.
DOC No HSE-RA-01
PAGE No 5 of 14
RISK ASSESSMENT REV 1
DATE 26-08-2021
-Flying particles -Use of poor- -Internal / in quarantine for • Check tool before using.
from the tool. quality tools. external burns repair before issue. • Never wear loose clothing
whilst working near or with
-Vibration. - Using the - rotating tools.
tools without Fatality/death, • Ensure correct PPE is worn
-Tripping inspection whilst using power tools,
• All power tools
hazard. periodically. -Secondary goggles and eye protection
should be fitted
injury (e.g. must be always worn during
with guards and
Fall from height - Not using falling from a use.
operated only by
gloves. ladder).
competent trained • Check tool at end of shift
persons. prior to handover to
-Using -Eye injuries colleague
• Electric tool should
damaged • Disconnect electric tool when
be regularly
tools. -Sprain not in use
inspected and
Injuries • Check blade, disc or bit for
maintained by
competent person. signs of damage prior to start
-Muscular- (damage tools can break up at
• A periodic check by
skeletal high speed and cause serious
electrician is
injuries injury to users and others
required every
three months. working close by).
-Hand/arm • Always have a good footing,
• Only competent
injury do not overreach.
Injury person to change
the blades, disc or • Return electrical tools to
following trips electrician or pneumatic tools
bits.
and falls. to mechanic when finished.
• Ensure all cables,
plugs and switches • When cutting, grinding and
-Respiratory drilling beware that contact
injury from are sound and
working properly. of the tool to other hidden
airborne dust material such as steel in
• All electric cables
off the ground/floor concrete can cause the tool to
to avoid trip hazard jam, overheat.
and damage to • Ensure correct type of
cables. blade/disk, fit for purpose, is
• Avoid standing in selected and used for the
damp or wet task.
DOC No HSE-RA-01
PAGE No 8 of 14
RISK ASSESSMENT REV 1
DATE 26-08-2021
• Ensure operators
are trained on
power tools either
DM approved third
party or by the
Manufacturer
• Ensure ladder must
hold by helper and
ladder use for short
time activity.
-Falling PMT/Site
• Suspend the • Training and toolbox talk on
Engineer /
-Injuries. activities in extreme adverse weather condition.
Forman &
weather conditions.
-Poor visibility -Sunburn and • Welfare facilities to be Workforce
-Falling from due to dehydration • Assess situation arranged -Chemical Toilets
height. mist/fog/ etc. (sunstroke) before carrying out shall be arranged as per the
so unable to the activity and strength of work force
-Lifting failure, -Respiratory
see warning cancel activities if working.
signs and and hearing conditions deemed
-Flying objects, • Cold drinking water must be
dangers. problem too hazardous to go
provided for all workforces on
out on Nature
site. ORS powder shall be
Hot Weather -Extreme high Reserve. Check site
provided in-case of high
winds. regularly
06 Adverse Ill Health (Heat 3 4 humidity. 3 1 3 Yes
weather 12 • Remove all
-Extreme Heat stress, Heat • Daily activity briefing.
conditions Stroke) hazardous materials
/ sunlight. • PPE to be provided to the
through felling
-Lack of regime during the workers.
heavy wind.
welfare Dehydration • Summer working uniforms to
conditions. • Cordon off be provided.
hazardous areas
-Dust, Noise. • Adequate supervision and
where possible
monitoring.
Inadequate • Reduce the time of • Engineer to monitor weather
supervision exposure from conditions.
direct sun light • Supervisor to ensure workers
are hydrated and healthy.
DOC No HSE-RA-01
PAGE No 10 of 14
RISK ASSESSMENT REV 1
DATE 26-08-2021
Poor Yes
housekeeping Environmental
Poor material damage SUP/S
stacking All empty containers of • Clear briefing to workforce to E/PE
Lack of chemicals will be sent to dispose of waste materials in
supervision lay down storage area. the designated areas only
Waste materials 3 3 9 and send them to laydown 3 1 3
DM approved waste
transported will carry all storage area on daily basis
the chemical waste from after usage.
the laydown storage area.
RISK LEVEL
H(HIGH-Potential to cause death, permanent injury or M (MEDIUM – Potential to cause loss time injury or Long Term L(LOW – An injury treatable with First Aid or Short Term Environmental Impact)
Severe Permanent Environmental Harm) Environmental Impact)
SEVERITY (S)
LIKELIHOOD (L) CLASS OF RISK (L X S) RISK MATRIX
Health & Safety Environmental Impact
5 5 10 15 20 25
0 = Impossible 0 = No injury
LIKELIHOOD (L)
Short Term < less than 1 month
4 4 8 12 16 20
1 = Improbable 1 = Minor – (FAC) 0 = No harm HIGH = 15 – 25 3 3 6 9 12 15
2 = Remote 2 = Major - (MTC) 3 = Minor 2 2 4 6 8 10
3 = Probable 3 = LTI (Lost Time Incident) Long Term > Greater than 1 Month MEDIUM = 07 – 14 1 1 2 3 4 5
NOTE: 1. Risk assessment must be addressed to workers by work in charge before starting job.
2. Risk assessment is a continuous process hence to be reviewed depending on activity and risk involved
1. OBJECTIVE
2. PROCEDURE
1. Do pre-use inspection of all equipment to be used and replace or repair faulty items.
2. Use trained competent employees only.
3. Use appropriate Personal Protective Equipment i.e.:
DOC No HSE-RA-01
PAGE No 14 of 14
RISK ASSESSMENT REV 1
DATE 26-08-2021
3.1. Hardhat.
3.2. Safety boots.
3.3. Overalls.
3.4. Ear Protection.
3.5. Masks
3.6. Safety Glasses
3.7. Hand gloves
2.1. Appropriate PPE must be worn by all workers on site & special PPE should be provided for those who are directly
involved in this activity.
2.2. Site Induction and toolbox talks should be given prior to start job.
2.3. Equipment to be used should be inspected and must be safe for use.
2.4. Materials be properly secured while being transported and during offloading.
2.5. Employees shall be educated in keeping out of possible crush of wall or collapse of the excavation.
2.6. All the underground utility services must be protected and secure.
2.7. Permit to work system should be followed by all supervisors and engineers.
2.8. Daily, weekly and monthly inspection to be done regularly any defect found must be reported immediately.
2.9. Physical barricade to installed and maintained with entry and exit points.
2.10. Only personnel involve in the activities are allowed inside the barricaded area.
2.11. Enforce the use of competent persons only.
2.12. All hand and power tools must be inspected before use
2.13. All hand and power tools must be safe for use
2.14. All type of power tools must be colour coded and tagged as safe for use also must be entered in register.
2.15. Permit to work system should be in place.
2.16. PPE should be worn by all operators as per the job nature.
2.17. Maintain work area isolated with means of barricade and appropriate signage should be in place.
2.18. Remind personnel through toolbox talk to observe proper positioning when working
2.19. All the work should be done under the competent supervision.
ITP
Page | 1
Document No : ITP-No
Inspection and Test Plan: Rev. No. : 00
BAHRI & MAZROEI TECHNICAL SYSTEMS CO. L.L.C Commissioning of ATS Date :
Page : 1 of 1
Project:-
ITP Inspection Points Verifying /
Clause Inspection Description Type of Reference Testing Requirement/ MEP Consul Client Control
No Inspection Document. Acceptance Criteria tant Data forms.
1.0 GENERAL
1.1 Relevant shop drawings, material submittal, Review of ATS System All documents are to have a H R R
method statement, ITP and Risk Assessment Documents Tender minimum of status B No objections.
are submitted and approved prior to the start Specifications
of commissioning.
1.2 Project common approval for the entire UPS Review & Final Approved Full approval with no objections. H R R
system from the Consultant Approve Submittal
entire scheme.
2.0 TESTING PLAN
2.1 Installation of ATS panels, ,incoming and Installation Shop drawings. Installation signed off with no H W W
outgoing cables (By Contractor) Inspection snags.(By Contractor)
2.2 Cable Continuity test(By Contractor) Continuity Shop drawings. Cables identified and continuity H W W
checked.(By Contractor)
2.3 System pre commissioning and Visual/Commi Method System is fully commissioned as per H W W
commissioning. ssioning Statement the method statement and is fault SR
free
2.4 Final Testing Visual Method Inspection by the W W SR
statement Consultant(Visual) and method
statement document sign off
LEGENDS: MEP Contractor H-hold point, W- Witness Point,
R- Review Documents only, S- Surveillance Inspection, SR- Submit for Records