Professional Documents
Culture Documents
Corrosion Under Insulation Inspection in Ammonia Urea Plant
Corrosion Under Insulation Inspection in Ammonia Urea Plant
Inspection in Ammonia
Urea Plant
CO2 absorber
CUI near
bottom skirt,
2010
CUI
Carbon Stainless
Steel Steel
Mechanical
Insulation Technician for
Operator from
NH3/ Urea &
Technician for scaffolding, Civil contactor
Insulation surface for repainting
Utility Plant
removal preparation for
NDT
Work Organization (cont.)
CUI inspection is a multi disciplinary work. Good
communication & understanding is required between group
members.
Best time to execute such inspection is during plant shut
down period and dry season.
Insulation is hazardous material so proper safety
supervision is also important.
Work Schedule
Job Tasks Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Study CUI as per API 510, 571 & RBI
recommendation
Preparation of CUI Job volume
Assessment of material and Job by
maintenance
Inspection Checklist preparation
Ultrasonic Thickness
Uniform Oxidation & Thinning Measurement (UT)
Stainless Steel
7 2-E-802 Desorber Heat Exchanger Stainless Steel Thickness check near saddle
support and perform
thickness monitoring
Urea Plant Equipment
RBI Approach of Pipeline CUI Inspection
Critical Areas for Pipeline CUI
Common Locations of pipeline CUI
1. Pipes those are in intermittent service
2. Steam tracing pipe lines
(sometimes in Urea plant SS pipe is steam traced by CS tracing
line- Introduce risk of external Cl-SCC)
3. Termination of insulation in a vertical pipe.
4. Bulges or staining of the insulation or jacketing system or
missing bands.
5. Low points in piping systems that have a known breach in
the insulation system
Pipeline CUI
Vertical run pipeline partially
insulated are very prone for
CUI at the lower portion of
the pipe.
4”-LA-60007-A2-C55
4”-LA-60020-A2-C55
12”-GA-60009-A2-C55
To 6-K-201 B inlet line
Conclusion
Atmospheric corrosion is a serious threat to the safe
operation of older, petro-chemical process plant.
CUI detection is a challenging job; it is highly
unpredictable
Reduce use of insulation as much as possible
Avoid insulation where it is not a process requirements
Design modification, apply suitable coating, surface
preparation, use suitable aluminum cover sheet etc.
Prepare painting surface and apply coating as per
internationally acceptable codes & standard.
Q&A Session