Professional Documents
Culture Documents
WE 09-Dec-2022 - Mechanical - OSBL Weekly Report
WE 09-Dec-2022 - Mechanical - OSBL Weekly Report
A. Mechanical:
1
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022
Tag-weld on bolts of GT air plenum and HEPA module at GTG package A-331-07A-GT-01.
Bolt torque on centrifugal fan of GT enclosure ventilation outlet tower (SAG) A-331-07A-GT-01.
Vertical alignment, install v-belt and bolt torque on lubrication oil cooler unit (MBV) for GTG
package A-331-07B-GT-01.
Installation of CO2 bottle to fire extinguishing unit (SGJ10) A-331-07A-GT-01.
Installation of wall sound enclosure in left / right side at GTG Package A-331-07C-GT-01.
Installation of GT air plenum to silencer on GTG package A-331-07D-GT-01.
Centre line, orientation and grouting base plate on GT purge ai cooler unit (MBH20) for GTG
package A-331-07C-GT-01.
Fit up and setting of interconnecting panels to evaporator module (M1) and economizer module
(M2) at HRSG package A-331-07A-WHB-01.
Replace new mineral insulation and cladding on boiler Economizer casing A-331-01D/E.
Installation of boiler feed water preheater to foundation E-331-02.
Installation of HHP BFW pump to foundation G-331-01A.
Welding washer plate of anchor bolt on ring base frame at HSN liquid storage A-335-03-C3A,
liquid nitrogen storage A-335-03-C3B/C and instrument air receiver C-335-02A/B/C/D.
Cleaning, repair welding and touch up on the outer shell at purge nitrogen vaporizer A-335-03-
E4A/B.
Installation of process side filter pumps to foundation G-332-07A/B.
Pre alignment and grouting anchor box for utility cooling water pumps G-332-01A/B/C.
Installation of valve skid to foundation for PSA unit A-068-02.
Setting and plumbness of APH M1 / M 2 in support column at WHRS unit and Installation of steam
reformer casing El 16.000 F-068-01.
Center line, elevation and grouting base plate of condensate pumps A-331-03D-G01A/B and
installation of soleplate WKTR 100 to foundation for condensate pumps A-331-03E-G01A/B.
Issues/Concerns
JO immediately started construction of cooling system on the step-up transformer unit at GTG A-
331-07A-GT-01.
Its not possible for new expansion joint to arrive from Sweden, JO immediately requested a
method statement document from SIEMENS to repair the thermal expansion joint unit for GTG A-
331-07A-GT-01.
JO brought a Macchi vendor and speed up the mechanical construction of HRSG bypass stack
system.
JO speed up installation of liquid fuel system for GTG A start up.
2
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022
Bolt torque on centrifugal fan of GT ventilation outlet tower (SAG), Replace new mineral insulation and cladding on boiler Economizer
Tag-weld on bolts of GT air plenum and HEPA module and CO2 casing A-331-01D/E.
bottle to fire extinguishing unit (SGJ10) A-331-07A-GT-01.
Fit up and setting of interconnecting panels to evaporator module Grouting base plate A-331-03D-G01A/B and installation of soleplate
(M1) and economizer module (M2) at HRSG A-331-07A-WHB-01. WKTR 100 for condensate pumps A-331-03E-G01A/B.
3
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022
Installation of boiler feed water preheater to foundation E-331-02. Installation of HHP BFW pump to foundation G-331-01A.
Welding washer plate of anchor bolt on ring base frame at HSN Vertical alignment, install v-belt and bolt torque on lubrication oil
liquid storage A-335-03-C3A, liquid nitrogen storage A-335-03- cooler unit (MBV) for GTG package A-331-07B-GT-01.
C3B/C and instrument air receiver C-335-02A/B/C/D.
Installation of valve skid to foundation for PSA unit A-068-02. Setting and plumbness of APH M1 / M 2 in support column at WHRS
unit and Installation of steam reformer casing El 16.000 F-068-01.
4
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022
Pre-alignment and grouting anchor box for utility cooling water Installation of process side filter pumps to foundation G-332-07A/B.
pumps G-332-01A/B/C.
5
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022
Melihat kemajuan konstruksi pada GTG A-331-07A-GT-01 untuk kesiapan start up di maret 2023, IPMT memohon
kepada JO untuk mempercepat pemasangan diantaranya.