OSBL Site

Weekly Site Progress Report


Week Ending 09-Dec-2022

A. Mechanical:

Mechanical - Static 6-Week Look Ahead Plan


PERECENT
UNIT Completed Total COMPLETED
Week 2 (Previous) Week 3 (This week)
Total Scope
This Week Completed Plan Actual Plan Actual
319 14 0 8 43.18% 0 0 0 0
320 47 0 12 26.37% 0 0 0 0
321                
323 21 0 0 0.00% 0 0 0 0
325 10 0 0 0.00% 0 0 0 0
332 34 0 0 0.00% 0 0 0 0
333                
334 82 0 0 0.00% 0 0 0 0
337 28 0 11 0.00% 0 0 0 0
315 8 0 2 0.00% 0 0 0 0
331 72 3 62 67.52% 0 0 0 0
335 89 0 30 29.71% 0 0 0 0
337 - SWI 9 0 0 33.52% 0 0 0 0
TOTAL (This Week) 384 3 125 32,65% 0 0 0 0
TOTAL (Last Week) 384 4 121 30,04%        

Mechanical - Rotating 6-Week Look Ahead Plan


PERECENT
UNIT Completed Total COMPLETED
Week 2 (Previous) Week 3 (This week)
Total Scope
This Week Completed Plan Actual Plan Actual
319 13 0 8 46.15% 0 0 0 0
320 89 0 8 8.99% 0 0 0 0
321                
323 23 0 0 13.04% 0 0 0 0
325 14 0 0 0.00% 0 0 0 0
332 53 2 18 19.00% 0 0 0 0
333                
334 183 0 31 14.82% 0 0 0 0
337 - SWI 21 1 11 30.02% 0 0 0 0
315 8 0 0 0.00% 0 0 0 0
331 216 4 179 88.79% 0 0 0 0
335 11 0 6 9.09% 0 0 0 0
337 - SWRO 142 0 8 4.52% 0 0 0 0
TOTAL (This Week) 773 7 269 34.80% 0 0 0 0
TOTAL (Last Week) 773 5  265 34.47%        

1
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022

Major activities achieved this week

 Tag-weld on bolts of GT air plenum and HEPA module at GTG package A-331-07A-GT-01.
 Bolt torque on centrifugal fan of GT enclosure ventilation outlet tower (SAG) A-331-07A-GT-01.
 Vertical alignment, install v-belt and bolt torque on lubrication oil cooler unit (MBV) for GTG
package A-331-07B-GT-01.
 Installation of CO2 bottle to fire extinguishing unit (SGJ10) A-331-07A-GT-01.
 Installation of wall sound enclosure in left / right side at GTG Package A-331-07C-GT-01.
 Installation of GT air plenum to silencer on GTG package A-331-07D-GT-01.
 Centre line, orientation and grouting base plate on GT purge ai cooler unit (MBH20) for GTG
package A-331-07C-GT-01.
 Fit up and setting of interconnecting panels to evaporator module (M1) and economizer module
(M2) at HRSG package A-331-07A-WHB-01.
 Replace new mineral insulation and cladding on boiler Economizer casing A-331-01D/E.
 Installation of boiler feed water preheater to foundation E-331-02.
 Installation of HHP BFW pump to foundation G-331-01A.
 Welding washer plate of anchor bolt on ring base frame at HSN liquid storage A-335-03-C3A,
liquid nitrogen storage A-335-03-C3B/C and instrument air receiver C-335-02A/B/C/D.
 Cleaning, repair welding and touch up on the outer shell at purge nitrogen vaporizer A-335-03-
E4A/B.
 Installation of process side filter pumps to foundation G-332-07A/B.
 Pre alignment and grouting anchor box for utility cooling water pumps G-332-01A/B/C.
 Installation of valve skid to foundation for PSA unit A-068-02.
 Setting and plumbness of APH M1 / M 2 in support column at WHRS unit and Installation of steam
reformer casing El 16.000 F-068-01.
 Center line, elevation and grouting base plate of condensate pumps A-331-03D-G01A/B and
installation of soleplate WKTR 100 to foundation for condensate pumps A-331-03E-G01A/B.

Issues/Concerns

 JO immediately started construction of cooling system on the step-up transformer unit at GTG A-
331-07A-GT-01.
 Its not possible for new expansion joint to arrive from Sweden, JO immediately requested a
method statement document from SIEMENS to repair the thermal expansion joint unit for GTG A-
331-07A-GT-01.
 JO brought a Macchi vendor and speed up the mechanical construction of HRSG bypass stack
system.
 JO speed up installation of liquid fuel system for GTG A start up.

B. Activity & Progress Photos:

Mechanical Construction Activity

2
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022

Bolt torque on centrifugal fan of GT ventilation outlet tower (SAG), Replace new mineral insulation and cladding on boiler Economizer
Tag-weld on bolts of GT air plenum and HEPA module and CO2 casing A-331-01D/E.
bottle to fire extinguishing unit (SGJ10) A-331-07A-GT-01.

Fit up and setting of interconnecting panels to evaporator module Grouting base plate A-331-03D-G01A/B and installation of soleplate
(M1) and economizer module (M2) at HRSG A-331-07A-WHB-01. WKTR 100 for condensate pumps A-331-03E-G01A/B.

3
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022

Installation of boiler feed water preheater to foundation E-331-02. Installation of HHP BFW pump to foundation G-331-01A.

Welding washer plate of anchor bolt on ring base frame at HSN Vertical alignment, install v-belt and bolt torque on lubrication oil
liquid storage A-335-03-C3A, liquid nitrogen storage A-335-03- cooler unit (MBV) for GTG package A-331-07B-GT-01.
C3B/C and instrument air receiver C-335-02A/B/C/D.

Installation of valve skid to foundation for PSA unit A-068-02. Setting and plumbness of APH M1 / M 2 in support column at WHRS
unit and Installation of steam reformer casing El 16.000 F-068-01.

4
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022

Pre-alignment and grouting anchor box for utility cooling water Installation of process side filter pumps to foundation G-332-07A/B.
pumps G-332-01A/B/C.

5
OSBL Site
Weekly Site Progress Report
Week Ending 09-Dec-2022

Melihat kemajuan konstruksi pada GTG A-331-07A-GT-01 untuk kesiapan start up di maret 2023, IPMT memohon
kepada JO untuk mempercepat pemasangan diantaranya.

1. Seel structure untuk GTG bush duct


2. Kelanjutan pemasangan pada Step up transformer TR