SPEEDWELL STANDARD PROJECT DEVELOPMENT SCHEDULE

ID WBS Task Name Duration Start Finish Resource Names Year 1 Year 2 Year 3 Year 4
Month -1 Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 21 Month 22 Month 23 Month 24 Month 25 Month 26 Month 27 Month 28 Month 29 Month 30 Month 31 Month 32 Month 33 Month 34 Month 35 Month 36 Month 37 Month 38 Month 39 Month 40 Month 41
1 0 Speedwell_standard project development 831 days Wed 01/01/20 Wed 08/03/23
schedule
2 1.1 Call to action/Start of the project 0 days Wed 01/01/20 Wed 01/01/20 01/01
3 1.2 Strategic Definition 65 days Wed 01/01/20 Tue 31/03/20
4 1.2.1 Project appraisal 50 days Wed 01/01/20 Tue 10/03/20
5 1.2.1.1 Appoint Client Team 1 day Wed 01/01/20 Wed 01/01/20 Board of Directors
6 1.2.1.2 Legal Due Diligence report 20 days Wed 01/01/20 Tue 28/01/20 Legal
7 1.2.1.3 Technical Due Diligence report 20 days Wed 01/01/20 Tue 28/01/20 Technical
8 1.2.1.4 Preliminary Topographic survey 5 days Wed 01/01/20 Tue 07/01/20 Technical
9 1.2.1.5 Preliminary Geotehnical survey 20 days Wed 01/01/20 Tue 28/01/20 Technical
10 1.2.1.6 Feasibility study (including concept 20 days Wed 29/01/20 Tue 25/02/20 Design,Financial,Operational,Technical,Commercial
study, existing urban planning
regulations, presentations, project
risks, project budget)
11 1.2.1.7 Preliminary Concept 0 days Wed 12/02/20 Wed 12/02/20 12/02
12 1.2.1.8 Business Case (including Budget, 5 days Wed 12/02/20 Tue 18/02/20 Board of
Cash Flow, IRR, ROE, ROI) Directors,Financial,Operational
13 1.2.1.9 Set up and register SPV 15 days Wed 19/02/20 Tue 10/03/20 Financial,Legal
14 1.2.1.10 Land acquisition contract approved 2 days Mon 09/03/20 Tue 10/03/20 Legal,Board of Directors
15 1.2.1.11 Land acquisition 0 days Tue 10/03/20 Tue 10/03/20 10/03
16 1.2.2 Client's requirements 15 days Wed 11/03/20 Tue 31/03/20
17 1.2.2.1 Review feedback from previous 10 days Wed 11/03/20 Tue 24/03/20 Commercial,Design,Financial,Legal,Operational,Permitting,Technical,FM
projects
18 1.2.2.2 Define Client's requirements 5 days Wed 25/03/20 Tue 31/03/20 Operational
19 1.2.2.3 Strategic appraisal of planning 1 day Wed 25/03/20 Wed 25/03/20 Commercial,Design,Financial,Legal,Operational,Permitting,Technical
considerations
20 1.2.2.4 Client's information requirements 0 days Tue 31/03/20 Tue 31/03/20 31/03
21 1.3 Preparation and Briefing 65 days Wed 11/03/20 Tue 09/06/20
22 1.3.1 Project Brief (including project 65 days Wed 11/03/20 Tue 09/06/20
outcomes and sutainability
outcomes, quality aspirations and
spatial requierements)
23 1.3.1.1 Hiring 2 employees and changing 3 days Wed 11/03/20 Fri 13/03/20 Financial
the tax status
24 1.3.1.2 Land registration/advertisement at 10 days Mon 16/03/20 Fri 27/03/20 Financial
local taxes
25 1.3.1.3 Define project phasing (including 5 days Wed 01/04/20 Tue 07/04/20 Board of
land split proposal) Directors,Commercial,Design,Operational,Technical
26 1.3.1.4 Agree Project Budget 10 days Wed 01/04/20 Tue 14/04/20 Board of Directors,Commercial,Design,Financial,Legal,Operational,Permitting,Technical
27 1.3.1.5 Prepare project execution plan 5 days Wed 15/04/20 Tue 21/04/20 Operational
28 1.3.1.6 Define scope of work for Design Team 15 days Wed 08/04/20 Tue 28/04/20 Design,Technical,FM
29 1.3.1.7 Procurement strategy 5 days Wed 22/04/20 Tue 28/04/20 Financial,Operational,Technical
30 1.3.1.8 Responsibility matrix 2 days Wed 22/04/20 Thu 23/04/20 Operational
31 1.3.1.9 Appoint Urban Planner 20 days Wed 29/04/20 Tue 26/05/20 Design,Technical,Board of Directors
32 1.3.1.10 Appoint General Designer 30 days Wed 29/04/20 Tue 09/06/20 Design,Technical,Board of Directors
33 1.3.1.11 Topographic Study 10 days Wed 11/03/20 Tue 24/03/20 Technical,Permitting
34 1.3.1.12 Geotechincal Study 30 days Wed 11/03/20 Tue 21/04/20 Technical,Permitting
35 1.3.1.13 Traffic Study 30 days Wed 11/03/20 Tue 21/04/20 Technical,Permitting
36 1.3.1.14 Project Brief 0 days Tue 28/04/20 Tue 28/04/20 28/04
37 1.3.1.15 Urban Planner contract signed 0 days Tue 26/05/20 Tue 26/05/20 26/05
38 1.3.1.16 General Designer contract signed 0 days Tue 09/06/20 Tue 09/06/20 09/06
39 1.3.2 Maketing and Sales 30 days Wed 15/04/20 Tue 26/05/20
40 1.3.2.1 Appoint Marketing Agency 30 days Wed 15/04/20 Tue 26/05/20 Commercial
41 1.3.2.2 Appoint Sales Broker Agency 20 days Wed 15/04/20 Tue 12/05/20 Commercial
42 1.3.2.3 Market Analysis 5 days Wed 13/05/20 Tue 19/05/20 Commercial
43 1.3.2.4 Prepare commercial analysis for 5 days Wed 15/04/20 Tue 21/04/20 Commercial
mix between units types and
44 1.3.2.5 Marketing Agency contract signed 0 days Tue 26/05/20 Tue 26/05/20 26/05
45 1.3.2.6 Sales Broker Agency contract signed0 days Tue 12/05/20 Tue 12/05/20 12/05
46 1.4 Concept Design & Urban Planning 246 days Wed 15/04/20 Wed 24/03/21
47 1.4.1 Urban planning 206 days Wed 15/04/20 Wed 27/01/21
48 1.4.1.1 PUZ documentation (Plans, land 90 days Wed 22/07/20 Tue 24/11/20 Design,Legal,Permitting,Technical
split, mentions, RLU, Memoair,
49 1.4.1.2 Certificat de urbanism (CU) 30 days Wed 15/04/20 Tue 26/05/20 Design,Permitting,Technical
50 1.4.1.3 Aviz de oportunitate 20 days Wed 27/05/20 Tue 23/06/20 Design,Permitting,Technical
51 1.4.1.4 Aviz Unic 60 days Wed 27/05/20 Tue 18/08/20 Design,Permitting,Technical
52 1.4.1.5 Aviz MAPN 60 days Wed 27/05/20 Tue 18/08/20 Design,Permitting,Technical
53 1.4.1.6 Aviz Sanitar 30 days Wed 27/05/20 Tue 07/07/20 Design,Permitting,Technical
54 1.4.1.7 Aviz Politia Rutiera 10 days Wed 27/05/20 Tue 09/06/20 Design,Permitting,Technical
55 1.4.1.8 Aviz Protectie Civila 20 days Wed 27/05/20 Tue 23/06/20 Design,Permitting,Technical
56 1.4.1.9 Aviz CFR 20 days Wed 27/05/20 Tue 23/06/20 Design,Permitting,Technical
57 1.4.1.10 Aviz Apele Romane 40 days Wed 22/07/20 Tue 15/09/20 Design,Permitting,Technical
58 1.4.1.11 Aviz Cultura 90 days Wed 22/07/20 Tue 24/11/20 Design,Permitting,Technical
59 1.4.1.12 Aviz Mediu Urban si Gest. Deseuri 20 days Wed 27/05/20 Tue 23/06/20 Design,Permitting,Technical
60 1.4.1.13 Aviz Mediu 40 days Wed 16/09/20 Tue 10/11/20 Design,Permitting,Technical
61 1.4.1.14 Aviz Comisia de Circulatie 30 days Wed 22/07/20 Tue 01/09/20 Design,Permitting,Technical
62 1.4.1.15 Aviz C.J.T. 40 days Wed 22/07/20 Tue 15/09/20 Design,Permitting,Technical
63 1.4.1.16 Certificate Legal Disputes 2 days Wed 25/11/20 Thu 26/11/20 Design,Permitting,Technical,Legal
64 1.4.1.17 CTATU 30 days Fri 27/11/20 Thu 07/01/21 Design,Permitting,Technical
65 1.4.1.18 HCL 14 days Fri 08/01/21 Wed 27/01/21 Design,Permitting,Technical
66 1.4.1.19 PUZ approval 0 days Wed 27/01/21 Wed 27/01/21 27/01
67 1.4.2 Concept Design 80 days Wed 10/06/20 Tue 29/09/20
68 1.4.2.1 Preliminary Concept 30 days Wed 10/06/20 Tue 21/07/20 Design,FM,Technical
69 1.4.2.2 Detailed Concept 20 days Wed 12/08/20 Tue 08/09/20 Design,FM,Technical
70 1.4.2.3 Existing building surveys 30 days Wed 10/06/20 Tue 21/07/20 Design,Technical
71 1.4.2.4 Technical expertise 30 days Wed 22/07/20 Tue 01/09/20 Design,Technical
72 1.4.2.5 Sustainability certification 15 days Wed 22/07/20 Tue 11/08/20 Design,FM,Technical
pre-assessment
73 1.4.2.6 Blue table (surfaces, BOMA, etc) 10 days Wed 09/09/20 Tue 22/09/20 Design
74 1.4.2.7 Preliminary Execution Budget 15 days Wed 09/09/20 Tue 29/09/20 Commercial,Financial,Operational,Technical
75 1.4.2.8 Concept Design approved 0 days Tue 08/09/20 Tue 08/09/20 08/09
76 1.4.3 Marketing and Sales 216 days Wed 27/05/20 Wed 24/03/21
77 1.4.3.1 Copwriting and Content writing 30 days Wed 09/09/20 Tue 20/10/20 Commercial
78 1.4.3.2 Project identity (Name, Logo) 20 days Wed 27/05/20 Tue 23/06/20 Commercial,Board of Directors,Operational
79 1.4.3.3 Project Brochure 60 days Wed 07/10/20 Tue 29/12/20 Commercial,Design,Technical
80 1.4.3.4 Project Website 60 days Wed 07/10/20 Tue 29/12/20 Commercial
81 1.4.3.5 Social Media pages 10 days Wed 07/10/20 Tue 20/10/20 Commercial
82 1.4.3.6 Project site banners 40 days Thu 28/01/21 Wed 24/03/21 Commercial,Design,Permitting,Technical
83 1.4.3.7 Online strategy campaign 30 days Wed 16/12/20 Tue 26/01/21 Commercial
84 1.4.3.8 Sales office concept 10 days Wed 09/09/20 Tue 22/09/20 Commercial,Design,Technical
85 1.4.3.9 Sales strategy and procedures 40 days Wed 23/09/20 Tue 17/11/20 Board of
(including contracts drafts, Directors,Commercial,Financial,Legal,Operational,Technical
technical specs)
86 1.4.3.10 Sales Price list 20 days Wed 18/11/20 Tue 15/12/20 Board of Directors,Commercial
87 1.4.3.11 Press realese 5 days Thu 04/02/21 Wed 10/02/21 Commercial

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Wed 25/03/20 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress

Page 1
SPEEDWELL STANDARD PROJECT DEVELOPMENT SCHEDULE

ID WBS Task Name Duration Start Finish Resource Names Year 1 Year 2 Year 3 Year 4
Month -1 Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 21 Month 22 Month 23 Month 24 Month 25 Month 26 Month 27 Month 28 Month 29 Month 30 Month 31 Month 32 Month 33 Month 34 Month 35 Month 36 Month 37 Month 38 Month 39 Month 40 Month 41
88 1.4.3.12 Project Indenty 0 days Tue 26/01/21 Tue 26/01/21 26/01
89 1.4.3.13 Sales Launch 0 days Wed 10/02/21 Wed 10/02/21 10/02
90 1.5 Technical Design 336 days Wed 21/10/20 Wed 02/02/22
91 1.5.1 Design 110 days Thu 28/01/21 Wed 30/06/21
92 1.5.1.1 PAC & POE (Building permit design) 20 days Thu 28/01/21 Wed 24/02/21 Design,Permitting,Technical
93 1.5.1.2 Tender Documentation 60 days Thu 25/02/21 Wed 19/05/21 Design,FM,Technical
94 1.5.1.3 PT (Technical design) 60 days Thu 25/02/21 Wed 19/05/21 Design,FM,Technical
95 1.5.1.4 DDE (Detailed design) 30 days Thu 20/05/21 Wed 30/06/21 Design,FM,Technical
96 1.5.2 Building Permit 130 days Thu 28/01/21 Wed 28/07/21
97 1.5.2.1 CU 60 days Thu 28/01/21 Wed 21/04/21 Design,Operational,Permitting,Technical
98 1.5.2.2 Environment 20 days Thu 22/04/21 Wed 19/05/21 Design,Permitting,Technical
99 1.5.2.3 Water 15 days Thu 22/04/21 Wed 12/05/21 Design,Permitting,Technical
100 1.5.2.4 Sewage 15 days Thu 22/04/21 Wed 12/05/21 Design,Permitting,Technical
101 1.5.2.5 Electricity 15 days Thu 22/04/21 Wed 12/05/21 Design,Permitting,Technical
102 1.5.2.6 Gas 20 days Thu 22/04/21 Wed 19/05/21 Design,Permitting,Technical
103 1.5.2.7 Salubrity 5 days Thu 22/04/21 Wed 28/04/21 Design,Permitting,Technical
104 1.5.2.8 Telephony 10 days Thu 22/04/21 Wed 05/05/21 Design,Permitting,Technical
105 1.5.2.9 Public heating 20 days Thu 22/04/21 Wed 19/05/21 Design,Permitting,Technical
106 1.5.2.10 Fire permit 40 days Thu 22/04/21 Wed 16/06/21 Design,Permitting,Technical
107 1.5.2.11 Civilian safety shelter 40 days Thu 22/04/21 Wed 16/06/21 Design,Permitting,Technical
108 1.5.2.12 Public health 40 days Thu 22/04/21 Wed 16/06/21 Design,Permitting,Technical
109 1.5.2.13 Metropolitan and Urban Planning 15 days Thu 22/04/21 Wed 12/05/21 Design,Permitting,Technical
Center of Bucharest
110 1.5.2.14 Technical traffic commission 40 days Thu 22/04/21 Wed 16/06/21 Design,Permitting,Technical
111 1.5.2.15 Road network Police Brigade 12 days Thu 22/04/21 Fri 07/05/21 Design,Permitting,Technical
112 1.5.2.16 Environmental Department of PMB 30 days Thu 22/04/21 Wed 02/06/21 Design,Permitting,Technical
113 1.5.2.17 Romanian Civil Aeronautical Authority
30 days Thu 22/04/21 Wed 02/06/21 Design,Permitting,Technical
114 1.5.2.18 Building permit 30 days Thu 17/06/21 Wed 28/07/21 Design,Permitting,Technical
115 1.5.2.19 Building Permit approval 0 days Wed 28/07/21 Wed 28/07/21 28/07
116 1.5.3 General Contractor 75 days Thu 22/04/21 Wed 04/08/21
117 1.5.3.1 List of selected Contractors 2 days Thu 22/04/21 Fri 23/04/21 Board of Directors,Technical
118 1.5.3.2 CG contract draft 5 days Thu 22/04/21 Wed 28/04/21 Legal,Operational,Technical
119 1.5.3.3 Verify tender design and BOQ's 10 days Thu 20/05/21 Wed 02/06/21 Design,Technical
120 1.5.3.4 Tender specifications and procedure5 days Thu 20/05/21 Wed 26/05/21 Design,Technical
121 1.5.3.5 Ivitation to tender 1 day Thu 27/05/21 Thu 27/05/21 Technical
122 1.5.3.6 RFI's 30 days Fri 28/05/21 Thu 08/07/21 Design,Technical
123 1.5.3.7 Offers Analsys 10 days Fri 09/07/21 Thu 22/07/21 Operational,Technical
124 1.5.3.8 Short List 2 days Fri 23/07/21 Mon 26/07/21 Operational,Technical
125 1.5.3.9 Award of General Contractor 5 days Thu 29/07/21 Wed 04/08/21 Board of Directors,Operational,Technical
126 1.5.3.10 Sign contract with General Contractor
0 days Wed 04/08/21 Wed 04/08/21 04/08
127 1.5.4 Health & Saftey Coordinator 112 days Thu 25/02/21 Fri 30/07/21
128 1.5.4.1 List of selected Contractors 2 days Thu 25/02/21 Fri 26/02/21 Operational,Technical
129 1.5.4.2 Invitation to tender 1 day Mon 01/03/21 Mon 01/03/21 Operational,Technical
130 1.5.4.3 Short List 10 days Tue 02/03/21 Mon 15/03/21 Operational,Technical
131 1.5.4.4 Award H & S Coordinator 2 days Thu 29/07/21 Fri 30/07/21 Operational,Technical,Legal
132 1.5.5 Site inspector 112 days Thu 25/02/21 Fri 30/07/21
133 1.5.5.1 List of selected Contractors 2 days Thu 25/02/21 Fri 26/02/21 Operational,Technical
134 1.5.5.2 Invitation to tender 1 day Mon 01/03/21 Mon 01/03/21 Operational,Technical
135 1.5.5.3 Short List 10 days Tue 02/03/21 Mon 15/03/21 Operational,Technical
136 1.5.5.4 Award of Site Inspector 2 days Thu 29/07/21 Fri 30/07/21 Operational,Technical,Legal
137 1.5.6 Breeam Consultant 15 days Wed 21/10/20 Tue 10/11/20
138 1.5.6.1 List of selected Contractors 2 days Wed 21/10/20 Thu 22/10/20 Operational,Technical
139 1.5.6.2 Invitation to tender 1 day Fri 23/10/20 Fri 23/10/20 Operational,Technical
140 1.5.6.3 Short List 10 days Mon 26/10/20 Fri 06/11/20 Operational,Technical
141 1.5.6.4 Award of Breeam Consultant 2 days Mon 09/11/20 Tue 10/11/20 Operational,Technical,Legal
142 1.5.7 Electricity connection Contractor 112 days Thu 25/02/21 Fri 30/07/21
143 1.5.7.1 List of selected Contractors 2 days Thu 25/02/21 Fri 26/02/21 Operational,Technical
144 1.5.7.2 Invitation to tender 1 day Mon 01/03/21 Mon 01/03/21 Operational,Technical
145 1.5.7.3 Short List 10 days Tue 02/03/21 Mon 15/03/21 Operational,Technical
146 1.5.7.4 Award of Electricity connection 2 days Thu 29/07/21 Fri 30/07/21 Operational,Technical,Legal
Contractor
147 1.5.8 Gas connection Contractor 112 days Thu 25/02/21 Fri 30/07/21
148 1.5.8.1 List of selected Contractors 2 days Thu 25/02/21 Fri 26/02/21 Operational,Technical
149 1.5.8.2 Invitation to tender 1 day Mon 01/03/21 Mon 01/03/21 Operational,Technical
150 1.5.8.3 Short List 10 days Tue 02/03/21 Mon 15/03/21 Operational,Technical
151 1.5.8.4 Award of Gas connection Contractor2 days Thu 29/07/21 Fri 30/07/21 Operational,Technical,Legal
152 1.5.9 Sewage and Water network 112 days Thu 25/02/21 Fri 30/07/21
connection Contractor
153 1.5.9.1 List of selected Contractors 2 days Thu 25/02/21 Fri 26/02/21 Operational,Technical
154 1.5.9.2 Invitation to tender 1 day Mon 01/03/21 Mon 01/03/21 Operational,Technical
155 1.5.9.3 Short List 10 days Tue 02/03/21 Mon 15/03/21 Operational,Technical
156 1.5.9.4 Award of S &W network 2 days Thu 29/07/21 Fri 30/07/21 Operational,Technical,Legal
connection Contractor
157 1.5.10 Roads Contractor 111 days Thu 25/02/21 Thu 29/07/21
158 1.5.10.1 List of selected Contractors 2 days Thu 25/02/21 Fri 26/02/21 Operational,Technical
159 1.5.10.2 Invitation to tender 1 day Mon 01/03/21 Mon 01/03/21 Operational,Technical
160 1.5.10.3 Short List 10 days Tue 02/03/21 Mon 15/03/21 Operational,Technical
161 1.5.10.4 Award of Roads Contractor 1 day Thu 29/07/21 Thu 29/07/21 Operational,Technical,Legal
162 1.5.11 Operational 245 days Thu 25/02/21 Wed 02/02/22
163 1.5.11.1 Agree Execution Budget 10 days Thu 05/08/21 Wed 18/08/21 Board of Directors,Operational,Technical
164 1.5.11.2 Agree Execution Schedule 10 days Thu 05/08/21 Wed 18/08/21 Operational,Board of Directors,Technical
165 1.5.11.3 Agree Project Implementation Plan 10 days Thu 05/08/21 Wed 18/08/21 Board of Directors,Operational,Technical
166 1.5.11.4 Obtain Bank Loan 120 days Thu 29/07/21 Wed 12/01/22 Board of Directors,Financial,Operational,Legal
167 1.5.11.5 Sign contract with Technical Adviser15 days Thu 13/01/22 Wed 02/02/22 Financial,Operational,Legal
168 1.5.11.6 BREEAM Design Stage 120 days Thu 25/02/21 Wed 11/08/21 Design,FM,Technical
169 1.5.12 Marketing and Sales 20 days Thu 11/02/21 Wed 10/03/21
170 1.5.12.1 Sales office execution 20 days Thu 11/02/21 Wed 10/03/21 Commercial,Technical
171 1.6 Manufacturing and Construction 365 days Thu 05/08/21 Wed 28/12/22
172 1.6.1 Execution 365 days Thu 05/08/21 Wed 28/12/22
173 1.6.1.1 Site setup 15 days Thu 05/08/21 Wed 25/08/21 Design,Technical
174 1.6.1.2 Slurry walls & dewatering works 50 days Thu 26/08/21 Wed 03/11/21 Design,Technical
175 1.6.1.3 Earth works 40 days Thu 07/10/21 Wed 01/12/21 Design,Technical
176 1.6.1.4 Infrastructure 100 days Thu 02/12/21 Wed 20/04/22 Design,Technical
177 1.6.1.5 Superstructure 100 days Thu 21/04/22 Wed 07/09/22 Design,Technical
178 1.6.1.6 Arhitectural works 100 days Thu 16/06/22 Wed 02/11/22 Design,Technical,FM
179 1.6.1.7 MEP 80 days Thu 14/07/22 Wed 02/11/22 Design,Technical,FM
180 1.6.1.8 Exterior works 60 days Thu 08/09/22 Wed 30/11/22 Design,Technical
181 1.6.1.9 As Build Design 20 days Thu 01/12/22 Wed 28/12/22
182 1.6.1.10 End of works 0 days Wed 30/11/22 Wed 30/11/22 30/11
183 1.6.2 Operational recurring processes 346 days Mon 30/08/21 Mon 26/12/22
184 1.6.2.1 Updating Execution Budget 346 days Mon 30/08/21 Mon 26/12/22 Commercial,Financial,Technical
202 1.6.2.2 TA Monitoring Reports 233 days Thu 03/02/22 Mon 26/12/22 Financial,Operational,Technical
215 1.6.2.3 Sales Reports 346 days Mon 30/08/21 Mon 26/12/22 Commercial
Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Wed 25/03/20 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress

Page 2
SPEEDWELL STANDARD PROJECT DEVELOPMENT SCHEDULE

ID WBS Task Name Duration Start Finish Resource Names Year 1 Year 2 Year 3 Year 4
Month -1 Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 21 Month 22 Month 23 Month 24 Month 25 Month 26 Month 27 Month 28 Month 29 Month 30 Month 31 Month 32 Month 33 Month 34 Month 35 Month 36 Month 37 Month 38 Month 39 Month 40 Month 41
233 1.7 Handover 90 days Thu 03/11/22 Wed 08/03/23
234 1.7.1 Execution 50 days Thu 03/11/22 Wed 11/01/23
235 1.7.1.1 Snag List 20 days Thu 03/11/22 Wed 30/11/22 Technical
236 1.7.1.2 Commissioning 40 days Thu 03/11/22 Wed 28/12/22 FM,Technical
237 1.7.1.3 Remedial Works 30 days Thu 01/12/22 Wed 11/01/23 Technical
238 1.7.1.4 Reception of works (PVRTL) 0 days Thu 29/12/22 Thu 29/12/22 Design,Technical 29/12
239 1.7.1.5 Reception of works (PVRTL) 0 days Thu 29/12/22 Thu 29/12/22 29/12
240 1.7.2 Operational 70 days Thu 01/12/22 Wed 08/03/23
241 1.7.2.1 Declaring the value of the project 2 days Thu 01/12/22 Fri 02/12/22 Financial
at local taxes
242 1.7.2.2 Registering the reception and end 5 days Thu 01/12/22 Wed 07/12/22 Financial
of project in accounting
243 1.7.2.3 Closing the financing contract with 40 days Thu 29/12/22 Wed 22/02/23 Financial
the bank / changing it into an
investment or refinancing loan
244 1.7.2.4 CF Registration 25 days Thu 29/12/22 Wed 01/02/23 Financial,Legal,Operational,Permitting
245 1.7.2.5 Split per Levels 15 days Thu 02/02/23 Wed 22/02/23 Operational,Permitting,Technical
246 1.7.2.6 CF Apartments 10 days Thu 23/02/23 Wed 08/03/23 Legal,Operational
247 1.8 Use 30 days Thu 29/12/22 Wed 08/02/23
248 1.8.1 Obtaining function permits 30 days Thu 29/12/22 Wed 08/02/23
249 1.8.1.1 Fire Saftey Permit 30 days Thu 29/12/22 Wed 08/02/23 Design,Permitting,Technical
250 1.8.1.2 Health Department Permit 30 days Thu 29/12/22 Wed 08/02/23 Design,Permitting,Technical
251 1.8.2 Operational 30 days Thu 29/12/22 Wed 08/02/23
252 1.8.2.1 Assign Facility Management Company 30 days Thu 29/12/22 Wed 08/02/23 FM,Operational

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Wed 25/03/20 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress