On Hand (t ) = On Hand(t-1) + Scheduled Receipts(t) + Planned Order Receipt(t) -Gross Requirements(t)

ORDEN lxl
Net Requirements (t) = Gross Requirements(t) + Safety Stock - On Hand(t-1) - Scheduled Receipts(t)
LT 1
SS 0
A 1 2 3 4 5 6 7 8
Gross requirements 300
Scheduled receipts
On-Hand 0 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 0 0 0 300
Planned order receipt 300
Planned order release 300

ORDEN LXL
LT 0
SS 0
B 1 2 3 4 5 6 7 8
Gross requirements 0 0 0 0 0 0 300 0
Scheduled receipts
On-Hand 0 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 0 0 300 0
Planned order receipt 300
Planned order release 300

ORDEN lxl
LT 0
SS 0
C 1 2 3 4 5 6 7 8
Gross requirements 0 0 0 0 0 0 300 0
Scheduled receipts
On-Hand 0 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 0 0 300 0
Planned order receipt 300
Planned order release 300

ORDEN lxl
LT 1
SS 0
D 1 2 3 4 5 6 7 8
Gross requirements 0 0 0 0 0 900 0 0
Scheduled receipts
On-Hand 0 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 0 900 0 0
Planned order receipt 900
Planned order release 900

ORDEN lxl
LT 1
SS 0
E 1 2 3 4 5 6 7 8
Gross requirements 0 0 0 0 0 300 0 0
Scheduled receipts
On-Hand 0 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 0 300 0 0
Planned order receipt 300
Planned order release 300

ORDEN LXL
LT 1
SS 0
F 1 2 3 4 5 6 7 8
Gross requirements 0 0 0 0 0 900 0 0
Scheduled receipts
On-Hand 0 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 0 900 0 0
Planned order receipt 900
Planned order release 900