NAGAR PARISHAD BHIND HEAVENS DESIGN BHOPAL

RENOVATION WORKS OF AUDITORIUM WORKS AT BHIND

UADD SOR
S.no Vol. 2 . 2021 Description of Items Unit Quantity Rate Amount
Item no
Dismantling doors, windows, and clerestory windows
(steel or wood ) shutter including chowkhats,
1 15.10
architrave, holdfasts etc. complete and stacking
within 50 meters lead.
15.10.1 Of area 3 Sq meters and below EACH 45.00 99.00 4455.00

2 15.10.2 Of area beyond 3 sq. meters EACH 6.00 127.00 762.00

Dismantling stone slab flooring laid in cement mortar


3 15.23
including stacking servicable material and disposal of
unservicable material within 50 meters lead. Sqm 1141.82 79.00 90203.87

Dismantling G.I pipes (external work) including


excavation and refilling trenches after taking out the
4 15.39 pipes, manually by mechanical means including
stacking of pipes withing 50 mts lead as per direction
of Engineer -in charge
15.39.1 Upto 40 mm nominal bore Meter 60.00 44.00 2640.00

Dismantling of road gully chamber of various sizes


including CI grating with frame including stacking of
5 15.41
useful materials near the site and disposal of
unservicable material into municipal dumps within 50
mts lead including refilling the excavated gap. Each 15.00 275.00 4125.00

Dismantling of flushing cistern of any size including


6 15.42
stacking of useful materials near the site and disposal
of unservicable material within 50 mts lead. Each 12.00 287.00 3444.00
Dismantling Old plaster or skirting upto 15 mm thick
ness raking out joints amd cleaning the surface for
7 15.45 plater upto Two Floor level including disposal of
rubbish within 50 meters lead and including
scaffolding etc. Sqmt 0.00 19.00 0.00
Dismantling of existing light/fan/Bell/ Socket out let
UADD SOR point on seprate board / wiring with insulated wire in
13
VOL 4 12.1 casing / conduit / Batten complete with fitting and
accessories. Each 280.00 17.00 4760.00
NAGAR PARISHAD BHIND HEAVENS DESIGN BHOPAL

UADD SOR Dismantlinf of existing socket outlet point on same


14
VOL 4 12.3 board in any sytem of wiring Each 100.00 14.00 1400.00
Dismantling the existing armoured/unarmoured cable
UADD SOR
14 or single core of submain , main, circuit, in any system
VOL 4 12.4
of wiring including reciling meter 250.00 15.00 3750.00

UADD SOR Dismantling of existing underground cable saftly with


15
VOL 4 12.5 its accessories amd refilling the trench to ground level
including recoiling of dismentalled cable. meter 150.00 29.00 4350.00
UADD SOR Dismantling of D.F, Board , D.P Swicth, T.P & T.P.N
16
VOL 4 12.7 Swicth or DB of any size only Each 80.00 16.00 1280.00
UADD SOR
17 Dismantling the existing Ceiling / exhaust/ cabin fan
VOL 4 12.8
with complete accessories qand making the site clear Each 75.00 32.00 2400.00

TOTAL 123569.87