Contractual - Overall Schedule - PEMEX - 17months - CDU Heaters - R9

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Project Duration: 17Months -Modularisation (CIF) Prepared by : AS/ DBH1

Document No: P1-201-03-H-22501-10002


PEMEX PROJECT ‐ 04 NOS. CRUDE HEATERS Checked by : MS/DB
Document name : Overall Schedule Rev No. : 09

ID TaskTask Name Duration Start Finish Predecessors Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mod Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
1 PEMEX PROJECT 529 day Wed 09‐12‐20 Sat 21‐05‐22
2 PO 0 days Wed 09‐12‐20 Wed 09‐12‐20 09‐12
3 CRUDE OIL HEATERS ‐ 04 NOS.( BA‐11101 A/B & BA‐11201 A/B ) 1 day Wed 09‐12‐20 Wed 09‐12‐20 2
4  KOM  3 days Wed 13‐01‐21 Fri 15‐01‐21
5  ENGINEERING 236 day Wed 09‐12‐20 Sun 01‐08‐21
6  Basic Design, Data Sheets, GAD, P & ID 60 days Wed 09‐12‐20 Sat 06‐02‐21 2
7  Structural Calculation, Foundation Load Plan 45 days Tue 29‐12‐20 Thu 11‐02‐21 2FS+20 days
8  Steel Detail Drawing  120 day Wed 13‐01‐21 Wed 12‐05‐21 7SS+15 days
9  Piping Engineering  120 day Sat 27‐02‐21 Sat 26‐06‐21 8SS+45 days
10  E & I Engineering  120 day Sat 27‐02‐21 Sat 26‐06‐21 9SS
11 30% Model Review  7 days Tue 13‐04‐21 Mon 19‐04‐21 9SS+45 days
12 60% Model Review 7 days Fri 04‐06‐21 Thu 10‐06‐21 11FS+45 days
13 90% Model Review 7 days Mon 26‐07‐21 Sun 01‐08‐21 12FS+45 days
14  PROCUREMENT 454 day Mon 22‐02‐21 Sat 21‐05‐22
15  Mechanical   450 day Mon 22‐02‐21 Tue 17‐05‐22
16  Structural Steel to Fabricator  121 day Sun 14‐03‐21 Mon 12‐07‐21 8SS+60 days
17  Pressure Part Pipes 151 day Mon 22‐02‐21 Thu 22‐07‐21 6SS+75 days
18  Pressure Parts Fittings (Wrought) 151 day Mon 22‐02‐21 Thu 22‐07‐21 6SS+75 days
19  Pressure Part Fittings (Forged) 151 day Mon 22‐02‐21 Thu 22‐07‐21 6SS+75 days
20 Piping Material for Fuel Skid 166 day Sat 12‐06‐21 Wed 24‐11‐21 9SS+105 days
21  Finned tubes 91 days Sun 18‐04‐21 Sat 17‐07‐21 17SS+55 days
22  Refractory Anchors‐ SS 85 days Mon 29‐03‐21 Mon 21‐06‐21 6SS+110 days
23  Refractory ‐ Castable 146 day Mon 29‐03‐21 Sat 21‐08‐21 6SS+110 days
24  Refractory ‐ Blankets 146 day Mon 29‐03‐21 Sat 21‐08‐21 6SS+110 days
25  Burners 205 day Wed 14‐04‐21 Thu 04‐11‐21 6SS+126 days
26 CAPH 306 day Sun 18‐04‐21 Thu 17‐02‐22 6SS+130 days
27 ID‐FD Fan 380 day Mon 03‐05‐21 Tue 17‐05‐22 6SS+145 days
28 Dampers w/ Actuator and Shut of  Blind 226 day Wed 28‐04‐21 Thu 09‐12‐21 6SS+140 days
29 Expansion Joint 341 day Tue 13‐04‐21 Sat 19‐03‐22 6SS+125 days
30  Cast Tube Supports 121 day Wed 24‐03‐21 Thu 22‐07‐21 6SS+105 days
31  Gratings 116 day Thu 13‐05‐21 Sun 05‐09‐21 8SS+120 days
32  Electrical & Instrumentation 401 day Fri 16‐04‐21 Sat 21‐05‐22
33  On‐Off Valve 272 day Sun 16‐05‐21 Fri 11‐02‐22 10SS+78 days
34  Control Valve 271 day Mon 17‐05‐21 Fri 11‐02‐22 10SS+79 days
35  O2 Analysers 392 day Tue 20‐04‐21 Mon 16‐05‐22 10SS+52 days
36 CO Analysers 361 day Wed 21‐04‐21 Sat 16‐04‐22 10SS+53 days
37  Transmitters (Pressure, Flow , Temp) 181 day Fri 11‐06‐21 Wed 08‐12‐21 10SS+104 days
38  Temperature Element  131 day Thu 13‐05‐21 Mon 20‐09‐21 10SS+75 days
39  Pressure Regulators 91 days Fri 14‐05‐21 Thu 12‐08‐21 10SS+76 days
40  Gauges (Pressure and Temp) 61 days Wed 14‐07‐21 Sun 12‐09‐21 10SS+137 days
41 Skin Thermocouple 121 day Fri 16‐04‐21 Sat 14‐08‐21 10SS+48 days
42 Flow Element 122 day Mon 12‐07‐21 Wed 10‐11‐21 10SS+135 days
43 Mass Flowmeter 181 day Sun 18‐04‐21 Fri 15‐10‐21 10SS+50 days
44 Loop Power Indicator 116 day Sun 18‐07‐21 Wed 10‐11‐21 10SS+141 days
45 Multiplexer 179 day Wed 12‐05‐21 Sat 06‐11‐21 10SS+74 days
46 Electrical Bulk 249 day Wed 15‐09‐21 Sat 21‐05‐22 10FS+80 days
47 Instrumentation Bulk 249 day Wed 15‐09‐21 Sat 21‐05‐22 10FS+80 days
48 DELIVERY TO DOS BOCAS PORT ‐ CDU TRAIN 1 & 2 ‐ TOTAL 04 NOS. HEATERS 374 day Thu 13‐05‐21 Sat 21‐05‐22
49  SHOP FABRICATION ‐ PACKAGE "TRAIN 1" ‐ CRUDE OIL HEATERS ‐ BA‐11101 A/B  374 day Thu 13‐05‐21 Sat 21‐05‐22
50  FOUNDATION TEMPLATE  120 day Thu 13‐05‐21 Thu 09‐09‐21
51  Fabrication Of Foundation Template 58 days Thu 13‐05‐21 Fri 09‐07‐21 16SS+60 days
52 Final Inspection 2 days Sat 10‐07‐21 Sun 11‐07‐21 51
53  LOT 1‐Dispatch to Site (CIF) 60 days Mon 12‐07‐21 Thu 09‐09‐21 52
54 A) RADIANT MODULE ‐ 04 NOS. 364 day Sun 23‐05‐21 Sat 21‐05‐22
55 A‐1) FLOOR 90 days Sun 23‐05‐21 Fri 20‐08‐21
56   Steel Structure Fabrication  90 days Sun 23‐05‐21 Fri 20‐08‐21 16SS+70 days
57   Anchor Welding 25 days Tue 22‐06‐21 Fri 16‐07‐21 56SS+30 days,22
58  Blasting,Primer & Painting 10 days Wed 07‐07‐21 Fri 16‐07‐21 57SS+15 days
59 A‐2) SIDE WALL PANELS 120 day Fri 28‐05‐21 Fri 24‐09‐21
60   Steel Structure Fabrication  120 day Fri 28‐05‐21 Fri 24‐09‐21 56SS+5 days
61   Anchor Welding 60 days Sun 27‐06‐21 Wed 25‐08‐21 60SS+30 days,22
62  Blasting,Primer & Painting 45 days Mon 12‐07‐21 Wed 25‐08‐21 61SS+15 days
63 A‐3) END WALL PANELS 120 day Fri 28‐05‐21 Fri 24‐09‐21
64   Steel Structure Fabrication  120 day Fri 28‐05‐21 Fri 24‐09‐21 56SS+5 days
65   Anchor Welding 60 days Sun 27‐06‐21 Wed 25‐08‐21 64SS+30 days,22
66  Blasting,Primer & Painting 45 days Mon 12‐07‐21 Wed 25‐08‐21 65SS+15 days
67 A‐4) ARCH PANELS 90 days Fri 28‐05‐21 Wed 25‐08‐21
68   Steel Structure Fabrication  90 days Fri 28‐05‐21 Wed 25‐08‐21 56SS+5 days
69   Anchor Welding 30 days Sun 27‐06‐21 Mon 26‐07‐21 68SS+30 days,22
70  Blasting,Primer & Painting 15 days Mon 12‐07‐21 Mon 26‐07‐21 69SS+15 days
71 A‐5) HEADER BOX FRONT 80 days Fri 28‐05‐21 Sun 15‐08‐21
72 Steel Structure Fabrication  60 days Fri 28‐05‐21 Mon 26‐07‐21 56SS+5 days
73 Anchor Welding 30 days Sun 27‐06‐21 Mon 26‐07‐21 72SS+30 days
74 Blasting,Primer & Painting 15 days Mon 12‐07‐21 Mon 26‐07‐21 73SS+15 days
75 Refractory Application 15 days Tue 27‐07‐21 Tue 10‐08‐21 74
76 Dry out 5 days Wed 11‐08‐21 Sun 15‐08‐21 75
77 A‐6) TAKE OF DUCTS 143 day Thu 21‐10‐21 Sat 12‐03‐22
78   Steel Structure Fabrication  60 days Thu 21‐10‐21 Sun 19‐12‐21 56SS+151 days
79 Anchor Welding 45 days Fri 05‐11‐21 Sun 19‐12‐21 78SS+15 days
80  Blasting,Primer & Painting 35 days Mon 15‐11‐21 Sun 19‐12‐21 79SS+10 days
81 Refractory Application 16 days Mon 20‐12‐21 Tue 04‐01‐22 80
82 Dry out 5 days Wed 05‐01‐22 Sun 09‐01‐22 81
83 Final Inspection  2 days Mon 10‐01‐22 Tue 11‐01‐22 82
84  LOT 2‐Dispatch to Site (CIF) 60 days Wed 12‐01‐22 Sat 12‐03‐22 83
85 A‐7)PRESSURE PART 45 days Fri 23‐07‐21 Sun 05‐09‐21
86  Pre‐ fabrication 45 days Fri 23‐07‐21 Sun 05‐09‐21 17
87  Fabrication on Jig 30 days Fri 23‐07‐21 Sat 21‐08‐21 86SS
88 A‐8) PLATFORM/HANDRAIL/LADDER/STAIRCASE 322 day Tue 22‐06‐21 Mon 09‐05‐22
89   Steel Structure Fabrication 160 day Tue 22‐06‐21 Sun 28‐11‐21 56SS+30 days
90   Blasting & Priming 130 day Thu 22‐07‐21 Sun 28‐11‐21 89SS+30 days
91   Layout Assembly 65 days Mon 29‐11‐21 Tue 01‐02‐22 90
92  Painting 35 days Wed 02‐02‐22 Tue 08‐03‐22 91
93 Final Inspection 2 days Wed 09‐03‐22 Thu 10‐03‐22 92
94  LOT 3‐Dispatch to Site (CIF) 60 days Fri 11‐03‐22 Mon 09‐05‐22 93
95 A‐9) RADIANT MODULE ASSEMBLY (RM 1) 269 day Thu 26‐08‐21 Sat 21‐05‐22
96 Installation of Stools 2 days Thu 26‐08‐21 Fri 27‐08‐21 66
97 Floor Assembly 15 days Sat 28‐08‐21 Sat 11‐09‐21 96
98 Assembly of side wall panels 20 days Sun 12‐09‐21 Fri 01‐10‐21 97
99 Assembly of end wall panels 15 days Sat 02‐10‐21 Sat 16‐10‐21 98
100 Internal & External Seal Welding 7 days Sun 17‐10‐21 Sat 23‐10‐21 99
101 Tube Support Installation 9 days Sun 24‐10‐21 Mon 01‐11‐21 100,30
102 Refractory Application for Side Wall / End Wall 30 days Tue 02‐11‐21 Wed 01‐12‐21 23,24,101
103 Refractory Application for Arch 15 days Thu 02‐12‐21 Thu 16‐12‐21 102
104 Arch Installation and Seal Welding  10 days Fri 17‐12‐21 Sun 26‐12‐21 103
105 Refractory dryout 15 days Mon 27‐12‐21 Mon 10‐01‐22 104
106 Coil insersion and  welding 35 days Tue 11‐01‐22 Mon 14‐02‐22 105,86
107 Installation of Transporation Jig 15 days Tue 15‐02‐22 Tue 01‐03‐22 106,87
108 Hydrotest 5 days Wed 02‐03‐22 Sun 06‐03‐22 107
109 Installation of Header Box 8 days Mon 07‐03‐22 Mon 14‐03‐22 108
110 Final touch‐up painting 5 days Tue 15‐03‐22 Sat 19‐03‐22 109

Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start‐only Deadline Baseline Milestone Progress
Project: Overall Schedule ‐ PEMEX
Split Summary External Tasks Inactive Task Inactive Summary Duration‐only Manual Summary Finish‐only Baseline Baseline Summary Manual Progress

 Page 1  JNK INDIA PVT LTD


Project Duration: 17Months -Modularisation (CIF) Prepared by : AS/ DBH2
Document No: P1-201-03-H-22501-10002
PEMEX PROJECT ‐ 04 NOS. CRUDE HEATERS Checked by : MS/DB
Document name : Overall Schedule Rev No. : 09

ID TaskTask Name Duration Start Finish Predecessors Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mod Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
111 Final Inspection all  3 days Sun 20‐03‐22 Tue 22‐03‐22 110
112  LOT 4‐Dispatch to Site (CIF) 60 days Wed 23‐03‐22 Sat 21‐05‐22 111
113 A‐10) RADIANT MODULE ASSEMBLY (RM 2) 269 day Thu 26‐08‐21 Sat 21‐05‐22
114 Installation of Stools 2 days Thu 26‐08‐21 Fri 27‐08‐21 66
115 Floor Assembly 15 days Sat 28‐08‐21 Sat 11‐09‐21 114
116 Assembly of side wall panels 20 days Sun 12‐09‐21 Fri 01‐10‐21 115
117 Assembly of end wall panels 15 days Sat 02‐10‐21 Sat 16‐10‐21 116
118 Internal & External Seal Welding 7 days Sun 17‐10‐21 Sat 23‐10‐21 117
119 Tube Support Installation 9 days Sun 24‐10‐21 Mon 01‐11‐21 118,30
120 Refractory Application for Side Wall / End Wall 30 days Tue 02‐11‐21 Wed 01‐12‐21 119,23,24
121 Refractory Application for Arch 15 days Thu 02‐12‐21 Thu 16‐12‐21 120
122 Arch Installation and Seal Welding  10 days Fri 17‐12‐21 Sun 26‐12‐21 121
123 Refractory dryout 15 days Mon 27‐12‐21 Mon 10‐01‐22 122
124 Coil insersion and  welding 35 days Tue 11‐01‐22 Mon 14‐02‐22 123,86
125 Installation of Transporation Jig 15 days Tue 15‐02‐22 Tue 01‐03‐22 124,87
126 Hydrotest 5 days Wed 02‐03‐22 Sun 06‐03‐22 125
127 Installation of Header Box 8 days Mon 07‐03‐22 Mon 14‐03‐22 126
128 Final touch‐up painting 5 days Tue 15‐03‐22 Sat 19‐03‐22 127
129 Final Inspection all  3 days Sun 20‐03‐22 Tue 22‐03‐22 128
130  LOT 5‐Dispatch to Site (CIF) 60 days Wed 23‐03‐22 Sat 21‐05‐22 129
131 A‐11) RADIANT MODULE ASSEMBLY (RM 3) 269 day Thu 26‐08‐21 Sat 21‐05‐22
132 Installation of Stools 2 days Thu 26‐08‐21 Fri 27‐08‐21 66
133 Floor Assembly 15 days Sat 28‐08‐21 Sat 11‐09‐21 132
134 Assembly of side wall panels 20 days Sun 12‐09‐21 Fri 01‐10‐21 133
135 Assembly of end wall panels 15 days Sat 02‐10‐21 Sat 16‐10‐21 134
136 Internal & External Seal Welding 7 days Sun 17‐10‐21 Sat 23‐10‐21 135
137 Tube Support Installation 9 days Sun 24‐10‐21 Mon 01‐11‐21 136,30
138 Refractory Application for Side Wall / End Wall 30 days Tue 02‐11‐21 Wed 01‐12‐21 137,23,24
139 Refractory Application for Arch 15 days Thu 02‐12‐21 Thu 16‐12‐21 138
140 Arch Installation and Seal Welding  10 days Fri 17‐12‐21 Sun 26‐12‐21 139
141 Refractory dryout 15 days Mon 27‐12‐21 Mon 10‐01‐22 140
142 Coil insersion and  welding 35 days Tue 11‐01‐22 Mon 14‐02‐22 141,86
143 Installation of Transporation Jig 15 days Tue 15‐02‐22 Tue 01‐03‐22 142,87
144 Hydrotest 5 days Wed 02‐03‐22 Sun 06‐03‐22 143
145 Installation of Header Box 8 days Mon 07‐03‐22 Mon 14‐03‐22 144
146 Final touch‐up painting 5 days Tue 15‐03‐22 Sat 19‐03‐22 145
147 Final Inspection all  3 days Sun 20‐03‐22 Tue 22‐03‐22 146
148  LOT 6‐Dispatch to Site (CIF) 60 days Wed 23‐03‐22 Sat 21‐05‐22 147
149 A‐12) RADIANT MODULE ASSEMBLY (RM 4) 269 day Thu 26‐08‐21 Sat 21‐05‐22
150 Installation of Stools 2 days Thu 26‐08‐21 Fri 27‐08‐21 66
151 Floor Assembly 15 days Sat 28‐08‐21 Sat 11‐09‐21 150
152 Assembly of side wall panels 20 days Sun 12‐09‐21 Fri 01‐10‐21 151
153 Assembly of end wall panels 15 days Sat 02‐10‐21 Sat 16‐10‐21 152
154 Internal & External Seal Welding 7 days Sun 17‐10‐21 Sat 23‐10‐21 153
155 Tube Support Installation 9 days Sun 24‐10‐21 Mon 01‐11‐21 154,30
156 Refractory Application for Side Wall / End Wall 30 days Tue 02‐11‐21 Wed 01‐12‐21 155,23,24
157 Refractory Application for Arch 15 days Thu 02‐12‐21 Thu 16‐12‐21 156
158 Arch Installation and Seal Welding  10 days Fri 17‐12‐21 Sun 26‐12‐21 157
159 Refractory dryout 15 days Mon 27‐12‐21 Mon 10‐01‐22 158
160 Coil insersion and  welding 35 days Tue 11‐01‐22 Mon 14‐02‐22 159,86
161 Installation of Transporation Jig 15 days Tue 15‐02‐22 Tue 01‐03‐22 160,87
162 Hydrotest 5 days Wed 02‐03‐22 Sun 06‐03‐22 161
163 Installation of Header Box 8 days Mon 07‐03‐22 Mon 14‐03‐22 162
164 Final touch‐up painting 5 days Tue 15‐03‐22 Sat 19‐03‐22 163
165 Final Inspection all  3 days Sun 20‐03‐22 Tue 22‐03‐22 164
166  LOT 7‐Dispatch to Site (CIF) 60 days Wed 23‐03‐22 Sat 21‐05‐22 165
167 B ) CONVECTION MODULE'S ‐ 02 NOS. 286 day Fri 06‐08‐21 Wed 18‐05‐22
168 B‐1)  CONVECTION MODULE‐1 276 day Fri 06‐08‐21 Sun 08‐05‐22
169   Casing Steel Str Fabrication 85 days Fri 06‐08‐21 Fri 29‐10‐21 16FS+24 days
170   ETS Fabrication 25 days Wed 11‐08‐21 Sat 04‐09‐21 169SS+5 days
171   HB Fabrication 40 days Wed 11‐08‐21 Sun 19‐09‐21 170SS
172   Anchor Welding 12 days Sun 05‐09‐21 Thu 16‐09‐21 169SS+30 days,22
173   Blasting & Priming 8 days Sat 30‐10‐21 Sat 06‐11‐21 169
174   Module Assembly 15 days Mon 20‐09‐21 Mon 04‐10‐21 170,171,172
175   Refractory Application 25 days Wed 06‐10‐21 Sat 30‐10‐21 23,174FS+1 day
176   Dry out 5 days Sun 31‐10‐21 Thu 04‐11‐21 175
177   Coil U Pin Welding ( Shop )  45 days Sat 11‐09‐21 Mon 25‐10‐21 18,19,21FS+55 da
178   Coil & U Pin Insertion 35 days Fri 05‐11‐21 Thu 09‐12‐21 176,177
179 Convection coil bend welding  40 days Fri 10‐12‐21 Tue 18‐01‐22 178,18
180 Manifold inlet Header Welding 30 days Wed 19‐01‐22 Thu 17‐02‐22 179
181   Hydrotest 8 days Fri 18‐02‐22 Fri 25‐02‐22 180
182   Final Painting 10 days Sat 26‐02‐22 Mon 07‐03‐22 181
183 Final Inspection 2 days Tue 08‐03‐22 Wed 09‐03‐22 182
184  LOT 8‐Dispatch to Site (CIF) 60 days Thu 10‐03‐22 Sun 08‐05‐22 183
185 B‐2)  CONVECTION MODULE‐2 276 day Mon 16‐08‐21 Wed 18‐05‐22
186   Casing Steel Str Fabrication 85 days Mon 16‐08‐21 Mon 08‐11‐21 169SS+10 days
187   ETS Fabrication 25 days Sat 21‐08‐21 Tue 14‐09‐21 186SS+5 days
188   HB Fabrication 40 days Sat 21‐08‐21 Wed 29‐09‐21 187SS
189   Anchor Welding 12 days Wed 15‐09‐21 Sun 26‐09‐21 186SS+30 days,22
190   Blasting & Priming 8 days Tue 09‐11‐21 Tue 16‐11‐21 186
191   Module Assembly 15 days Thu 30‐09‐21 Thu 14‐10‐21 187,188,189
192   Refractory Application 25 days Sat 16‐10‐21 Tue 09‐11‐21 191FS+1 day,23
193   Dry out 5 days Wed 10‐11‐21 Sun 14‐11‐21 192
194   Coil U Pin Welding ( Shop )  45 days Wed 22‐09‐21 Fri 05‐11‐21 18,19,21FS+66 da
195   Coil & U Pin Insertion 35 days Mon 15‐11‐21 Sun 19‐12‐21 193,194
196 Convection coil bend welding  40 days Mon 20‐12‐21 Fri 28‐01‐22 195,18
197 Manifold inlet Header Welding 30 days Sat 29‐01‐22 Sun 27‐02‐22 196
198   Hydrotest 8 days Mon 28‐02‐22 Mon 07‐03‐22 197
199   Final Painting 10 days Tue 08‐03‐22 Thu 17‐03‐22 198
200 Final Inspection 2 days Fri 18‐03‐22 Sat 19‐03‐22 199
201  LOT 9‐Dispatch to Site (CIF) 60 days Sun 20‐03‐22 Wed 18‐05‐22 200
202 B‐3) PLATFORM/HANDRAIL/LADDER 224 day Sat 25‐09‐21 Fri 06‐05‐22
203   Steel Structure Fabrication 120 day Sat 25‐09‐21 Sat 22‐01‐22 169SS+50 days
204   Blasting & Priming 95 days Sun 10‐10‐21 Wed 12‐01‐22 203SS+15 days
205   Layout Assembly 30 days Thu 13‐01‐22 Fri 11‐02‐22 204
206  Painting 22 days Sat 12‐02‐22 Sat 05‐03‐22 205
207 Final Inspection 2 days Sun 06‐03‐22 Mon 07‐03‐22 206
208  LOT 10‐Dispatch to Site (CIF) 60 days Tue 08‐03‐22 Fri 06‐05‐22 207
209 C ) FG DUCT 239 day Sun 22‐08‐21 Sun 17‐04‐22
210   Steel Str Fabrication 150 day Sun 22‐08‐21 Tue 18‐01‐22 16FS+40 days
211   Anchor Welding 120 day Tue 21‐09‐21 Tue 18‐01‐22 210SS+30 days,22
212   Blasting & Priming 105 day Wed 06‐10‐21 Tue 18‐01‐22 211SS+15 days
213   Refractory Application 21 days Wed 19‐01‐22 Tue 08‐02‐22 212
214   Dry out 7 days Wed 09‐02‐22 Tue 15‐02‐22 213
215 Final Inspection 1 day Wed 16‐02‐22 Wed 16‐02‐22 214
216  LOT 11‐Dispatch to Site (CIF) 60 days Thu 17‐02‐22 Sun 17‐04‐22 215
217 D ) AIR DUCT / CA DUCT 231 day Wed 01‐09‐21 Tue 19‐04‐22
218 Steel Str Fabrication 130 day Wed 01‐09‐21 Sat 08‐01‐22 16FS+50 days
219 Blasting & Priming 40 days Sun 09‐01‐22 Thu 17‐02‐22 218
220 Final Inspection 1 day Fri 18‐02‐22 Fri 18‐02‐22 219

Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start‐only Deadline Baseline Milestone Progress
Project: Overall Schedule ‐ PEMEX
Split Summary External Tasks Inactive Task Inactive Summary Duration‐only Manual Summary Finish‐only Baseline Baseline Summary Manual Progress

 Page 2  JNK INDIA PVT LTD


Project Duration: 17Months -Modularisation (CIF) Prepared by : AS/ DBH3
Document No: P1-201-03-H-22501-10002
PEMEX PROJECT ‐ 04 NOS. CRUDE HEATERS Checked by : MS/DB
Document name : Overall Schedule Rev No. : 09

ID TaskTask Name Duration Start Finish Predecessors Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mod Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
221 LOT 12‐Dispatch to Site (CIF) 60 days Sat 19‐02‐22 Tue 19‐04‐22 220
222 E ) STACK MODULE.S ‐ 5 NOS. 218 day Mon 11‐10‐21 Mon 16‐05‐22
223 E‐1) STACK MODULE‐1 178 day Mon 11‐10‐21 Wed 06‐04‐22
224   Casing Fabrication 70 days Mon 11‐10‐21 Sun 19‐12‐21 16FS+90 days
225   Anchor Welding 15 days Mon 20‐12‐21 Mon 03‐01‐22 224,22
226   Blasting & Priming 10 days Tue 04‐01‐22 Thu 13‐01‐22 225
227   Refractory Application 10 days Fri 14‐01‐22 Sun 23‐01‐22 226
228   Dry Out 7 days Mon 24‐01‐22 Sun 30‐01‐22 227
229   Final Painting 4 days Mon 31‐01‐22 Thu 03‐02‐22 228
230 Final Inspection 2 days Fri 04‐02‐22 Sat 05‐02‐22 229
231  LOT 13‐Dispatch to Site (CIF) 60 days Sun 06‐02‐22 Wed 06‐04‐22 230
232 E‐2) STACK MODULE‐2 178 day Thu 21‐10‐21 Sat 16‐04‐22
233   Casing Fabrication 70 days Thu 21‐10‐21 Wed 29‐12‐21 224SS+10 days
234   Anchor Welding 15 days Thu 30‐12‐21 Thu 13‐01‐22 233,22
235   Blasting & Priming 10 days Fri 14‐01‐22 Sun 23‐01‐22 234
236   Refractory Application 10 days Mon 24‐01‐22 Wed 02‐02‐22 235
237   Dry Out 7 days Thu 03‐02‐22 Wed 09‐02‐22 236
238   Final Painting 4 days Thu 10‐02‐22 Sun 13‐02‐22 237
239 Final Inspection 2 days Mon 14‐02‐22 Tue 15‐02‐22 238
240  LOT 14‐Dispatch to Site (CIF) 60 days Wed 16‐02‐22 Sat 16‐04‐22 239
241 E‐3) STACK MODULE‐3 178 day Sun 31‐10‐21 Tue 26‐04‐22
242   Casing Fabrication 70 days Sun 31‐10‐21 Sat 08‐01‐22 233SS+10 days
243   Anchor Welding 15 days Sun 09‐01‐22 Sun 23‐01‐22 242,22
244   Blasting & Priming 10 days Mon 24‐01‐22 Wed 02‐02‐22 243
245   Refractory Application 10 days Thu 03‐02‐22 Sat 12‐02‐22 244
246   Dry Out 7 days Sun 13‐02‐22 Sat 19‐02‐22 245
247   Final Painting 4 days Sun 20‐02‐22 Wed 23‐02‐22 246
248 Final Inspection 2 days Thu 24‐02‐22 Fri 25‐02‐22 247
249  LOT 15‐Dispatch to Site (CIF) 60 days Sat 26‐02‐22 Tue 26‐04‐22 248
250 E‐4) STACK MODULE‐4 178 day Wed 10‐11‐21 Fri 06‐05‐22
251   Casing Fabrication 70 days Wed 10‐11‐21 Tue 18‐01‐22 242SS+10 days
252   Anchor Welding 15 days Wed 19‐01‐22 Wed 02‐02‐22 251,22
253   Blasting & Priming 10 days Thu 03‐02‐22 Sat 12‐02‐22 252
254   Refractory Application 10 days Sun 13‐02‐22 Tue 22‐02‐22 253
255   Dry Out 7 days Wed 23‐02‐22 Tue 01‐03‐22 254
256   Final Painting 4 days Wed 02‐03‐22 Sat 05‐03‐22 255
257 Final Inspection 2 days Sun 06‐03‐22 Mon 07‐03‐22 256
258  LOT 16‐Dispatch to Site (CIF) 60 days Tue 08‐03‐22 Fri 06‐05‐22 257
259 E‐5) STACK MODULE‐5 178 day Sat 20‐11‐21 Mon 16‐05‐22
260   Casing Fabrication 70 days Sat 20‐11‐21 Fri 28‐01‐22 251SS+10 days
261   Anchor Welding 15 days Sat 29‐01‐22 Sat 12‐02‐22 260,22
262   Blasting & Priming 10 days Sun 13‐02‐22 Tue 22‐02‐22 261
263   Refractory Application 10 days Wed 23‐02‐22 Fri 04‐03‐22 262
264   Dry Out 7 days Sat 05‐03‐22 Fri 11‐03‐22 263
265   Final Painting 4 days Sat 12‐03‐22 Tue 15‐03‐22 264
266 Final Inspection 2 days Wed 16‐03‐22 Thu 17‐03‐22 265
267  LOT 17‐Dispatch to Site (CIF) 60 days Fri 18‐03‐22 Mon 16‐05‐22 266
268 E‐6) PLATFORM/HANDRAIL/LADDER 177 day Thu 21‐10‐21 Fri 15‐04‐22
269    Steel Structure Fabrication 75 days Thu 21‐10‐21 Mon 03‐01‐22 233SS
270    Blasting & Priming 65 days Sun 31‐10‐21 Mon 03‐01‐22 269SS+10 days
271    Layout Assembly 30 days Tue 04‐01‐22 Wed 02‐02‐22 270
272   Painting 10 days Thu 03‐02‐22 Sat 12‐02‐22 271
273 Final Inspection 2 days Sun 13‐02‐22 Mon 14‐02‐22 272
274   LOT 18‐Dispatch to Site (CIF) 60 days Tue 15‐02‐22 Fri 15‐04‐22 273
275 F ) FUEL SKID ‐ 2 NOS. 198 day Thu 21‐10‐21 Fri 06‐05‐22
276 F‐1) FUEL SKID ‐1  184 day Thu 21‐10‐21 Fri 22‐04‐22
277  Steel Frame Fabrication 50 days Thu 21‐10‐21 Thu 09‐12‐21 16FS+100 days
278  Pipe Support 25 days Fri 10‐12‐21 Mon 03‐01‐22 277
279  Piping Spool 18 days Tue 04‐01‐22 Fri 21‐01‐22 278
280  Assembly of Skid 20 days Sat 22‐01‐22 Thu 10‐02‐22 279
281  Hydrotest 5 days Fri 11‐02‐22 Tue 15‐02‐22 280
282  Painting 4 days Wed 16‐02‐22 Sat 19‐02‐22 281
283 Final Inspection 2 days Sun 20‐02‐22 Mon 21‐02‐22 282
284  LOT 19‐Dispatch to Site (CIF) 60 days Tue 22‐02‐22 Fri 22‐04‐22 283
285 F‐1) FUEL SKID ‐2 184 day Thu 04‐11‐21 Fri 06‐05‐22
286  Steel Frame Fabrication 50 days Thu 04‐11‐21 Thu 23‐12‐21 277SS+14 days
287  Pipe Support 25 days Fri 24‐12‐21 Mon 17‐01‐22 286,16,20
288  Piping Spool 18 days Tue 18‐01‐22 Fri 04‐02‐22 287
289  Assembly of Skid 20 days Sat 05‐02‐22 Thu 24‐02‐22 288
290  Hydrotest 5 days Fri 25‐02‐22 Tue 01‐03‐22 289
291  Painting 4 days Wed 02‐03‐22 Sat 05‐03‐22 290
292 Final Inspection 2 days Sun 06‐03‐22 Mon 07‐03‐22 291
293  LOT 20‐Dispatch to Site (CIF) 60 days Tue 08‐03‐22 Fri 06‐05‐22 292
294  SHOP FABRICATION ‐ PACKAGE "TRAIN 2" ‐ CRUDE OIL HEATERS ‐  BA‐11201 A/B 374 day Thu 13‐05‐21 Sat 21‐05‐22
295  FOUNDATION TEMPLATE  120 day Thu 13‐05‐21 Thu 09‐09‐21
296  Fabrication Of Foundation Template 58 days Thu 13‐05‐21 Fri 09‐07‐21 16SS+60 days
297 Final Inspection 2 days Sat 10‐07‐21 Sun 11‐07‐21 296
298  LOT 1‐Dispatch to Site (CIF) 60 days Mon 12‐07‐21 Thu 09‐09‐21 297
299 A) RADIANT MODULE ‐ 04 NOS. 364 day Sun 23‐05‐21 Sat 21‐05‐22
300 A‐1) FLOOR 90 days Sun 23‐05‐21 Fri 20‐08‐21
301   Steel Structure Fabrication  90 days Sun 23‐05‐21 Fri 20‐08‐21 16SS+70 days
302   Anchor Welding 25 days Tue 22‐06‐21 Fri 16‐07‐21 301SS+30 days,22
303  Blasting,Primer & Painting 10 days Wed 07‐07‐21 Fri 16‐07‐21 302SS+15 days
304 A‐2) SIDE WALL PANELS 120 day Fri 28‐05‐21 Fri 24‐09‐21
305   Steel Structure Fabrication  120 day Fri 28‐05‐21 Fri 24‐09‐21 301SS+5 days
306   Anchor Welding 60 days Sun 27‐06‐21 Wed 25‐08‐21 305SS+30 days,22
307  Blasting,Primer & Painting 45 days Mon 12‐07‐21 Wed 25‐08‐21 306SS+15 days
308 A‐3) END WALL PANELS 120 day Fri 28‐05‐21 Fri 24‐09‐21
309   Steel Structure Fabrication  120 day Fri 28‐05‐21 Fri 24‐09‐21 301SS+5 days
310   Anchor Welding 60 days Sun 27‐06‐21 Wed 25‐08‐21 309SS+30 days,22
311  Blasting,Primer & Painting 45 days Mon 12‐07‐21 Wed 25‐08‐21 310SS+15 days
312 A‐4) ARCH PANELS 90 days Fri 28‐05‐21 Wed 25‐08‐21
313   Steel Structure Fabrication  90 days Fri 28‐05‐21 Wed 25‐08‐21 301SS+5 days
314   Anchor Welding 30 days Sun 27‐06‐21 Mon 26‐07‐21 313SS+30 days,22
315  Blasting,Primer & Painting 15 days Mon 12‐07‐21 Mon 26‐07‐21 314SS+15 days
316 A‐5) HEADER BOX FRONT 80 days Fri 28‐05‐21 Sun 15‐08‐21
317 Steel Structure Fabrication  60 days Fri 28‐05‐21 Mon 26‐07‐21 301SS+5 days
318 Anchor Welding 30 days Sun 27‐06‐21 Mon 26‐07‐21 317SS+30 days
319 Blasting,Primer & Painting 15 days Mon 12‐07‐21 Mon 26‐07‐21 318SS+15 days
320 Refractory Application 15 days Tue 27‐07‐21 Tue 10‐08‐21 319
321 Dry out 5 days Wed 11‐08‐21 Sun 15‐08‐21 320
322 A‐6) TAKE OF DUCTS 143 day Thu 21‐10‐21 Sat 12‐03‐22
323   Steel Structure Fabrication  60 days Thu 21‐10‐21 Sun 19‐12‐21 301SS+151 days
324 Anchor Welding 45 days Fri 05‐11‐21 Sun 19‐12‐21 323SS+15 days
325  Blasting,Primer & Painting 35 days Mon 15‐11‐21 Sun 19‐12‐21 324SS+10 days
326 Refractory Application 16 days Mon 20‐12‐21 Tue 04‐01‐22 325
327 Dry out 5 days Wed 05‐01‐22 Sun 09‐01‐22 326
328 Final Inspection  2 days Mon 10‐01‐22 Tue 11‐01‐22 327
329  LOT 2‐Dispatch to Site (CIF) 60 days Wed 12‐01‐22 Sat 12‐03‐22 328
330 A‐7)PRESSURE PART 45 days Fri 23‐07‐21 Sun 05‐09‐21

Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start‐only Deadline Baseline Milestone Progress
Project: Overall Schedule ‐ PEMEX
Split Summary External Tasks Inactive Task Inactive Summary Duration‐only Manual Summary Finish‐only Baseline Baseline Summary Manual Progress

 Page 3  JNK INDIA PVT LTD


Project Duration: 17Months -Modularisation (CIF) Prepared by : AS/ DBH4
Document No: P1-201-03-H-22501-10002
PEMEX PROJECT ‐ 04 NOS. CRUDE HEATERS Checked by : MS/DB
Document name : Overall Schedule Rev No. : 09

ID TaskTask Name Duration Start Finish Predecessors Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mod Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
331  Pre‐ fabrication 45 days Fri 23‐07‐21 Sun 05‐09‐21 17
332  Fabrication on Jig 30 days Fri 23‐07‐21 Sat 21‐08‐21 331SS
333 A‐8) PLATFORM/HANDRAIL/LADDER/STAIRCASE 322 day Tue 22‐06‐21 Mon 09‐05‐22
334   Steel Structure Fabrication 160 day Tue 22‐06‐21 Sun 28‐11‐21 301SS+30 days
335   Blasting & Priming 130 day Thu 22‐07‐21 Sun 28‐11‐21 334SS+30 days
336   Layout Assembly 65 days Mon 29‐11‐21 Tue 01‐02‐22 335
337  Painting 35 days Wed 02‐02‐22 Tue 08‐03‐22 336
338 Final Inspection 2 days Wed 09‐03‐22 Thu 10‐03‐22 337
339  LOT 3‐Dispatch to Site (CIF) 60 days Fri 11‐03‐22 Mon 09‐05‐22 338
340 A‐9) RADIANT MODULE ASSEMBLY (RM 1) 269 day Thu 26‐08‐21 Sat 21‐05‐22
341 Installation of Stools 2 days Thu 26‐08‐21 Fri 27‐08‐21 311
342 Floor Assembly 15 days Sat 28‐08‐21 Sat 11‐09‐21 341
343 Assembly of side wall panels 20 days Sun 12‐09‐21 Fri 01‐10‐21 342
344 Assembly of end wall panels 15 days Sat 02‐10‐21 Sat 16‐10‐21 343
345 Internal & External Seal Welding 7 days Sun 17‐10‐21 Sat 23‐10‐21 344
346 Tube Support Installation 9 days Sun 24‐10‐21 Mon 01‐11‐21 345,30
347 Refractory Application for Side Wall / End Wall 30 days Tue 02‐11‐21 Wed 01‐12‐21 346,23,24
348 Refractory Application for Arch 15 days Thu 02‐12‐21 Thu 16‐12‐21 347
349 Arch Installation and Seal Welding  10 days Fri 17‐12‐21 Sun 26‐12‐21 348
350 Refractory dryout 15 days Mon 27‐12‐21 Mon 10‐01‐22 349
351 Coil insersion and  welding 35 days Tue 11‐01‐22 Mon 14‐02‐22 331,350
352 Installation of Transporation Jig 15 days Tue 15‐02‐22 Tue 01‐03‐22 332,351
353 Hydrotest 5 days Wed 02‐03‐22 Sun 06‐03‐22 352
354 Installation of Header Box 8 days Mon 07‐03‐22 Mon 14‐03‐22 353
355 Final touch‐up painting 5 days Tue 15‐03‐22 Sat 19‐03‐22 354
356 Final Inspection all  3 days Sun 20‐03‐22 Tue 22‐03‐22 355
357  LOT 4‐Dispatch to Site (CIF) 60 days Wed 23‐03‐22 Sat 21‐05‐22 356
358 A‐10) RADIANT MODULE ASSEMBLY (RM 2) 269 day Thu 26‐08‐21 Sat 21‐05‐22
359 Installation of Stools 2 days Thu 26‐08‐21 Fri 27‐08‐21 311
360 Floor Assembly 15 days Sat 28‐08‐21 Sat 11‐09‐21 359
361 Assembly of side wall panels 20 days Sun 12‐09‐21 Fri 01‐10‐21 360
362 Assembly of end wall panels 15 days Sat 02‐10‐21 Sat 16‐10‐21 361
363 Internal & External Seal Welding 7 days Sun 17‐10‐21 Sat 23‐10‐21 362
364 Tube Support Installation 9 days Sun 24‐10‐21 Mon 01‐11‐21 363,30
365 Refractory Application for Side Wall / End Wall 30 days Tue 02‐11‐21 Wed 01‐12‐21 364,23,24
366 Refractory Application for Arch 15 days Thu 02‐12‐21 Thu 16‐12‐21 365
367 Arch Installation and Seal Welding  10 days Fri 17‐12‐21 Sun 26‐12‐21 366
368 Refractory dryout 15 days Mon 27‐12‐21 Mon 10‐01‐22 367
369 Coil insersion and  welding 35 days Tue 11‐01‐22 Mon 14‐02‐22 331,368
370 Installation of Transporation Jig 15 days Tue 15‐02‐22 Tue 01‐03‐22 332,369
371 Hydrotest 5 days Wed 02‐03‐22 Sun 06‐03‐22 370
372 Installation of Header Box 8 days Mon 07‐03‐22 Mon 14‐03‐22 371
373 Final touch‐up painting 5 days Tue 15‐03‐22 Sat 19‐03‐22 372
374 Final Inspection all  3 days Sun 20‐03‐22 Tue 22‐03‐22 373
375  LOT 5‐Dispatch to Site (CIF) 60 days Wed 23‐03‐22 Sat 21‐05‐22 374
376 A‐11) RADIANT MODULE ASSEMBLY (RM 3) 269 day Thu 26‐08‐21 Sat 21‐05‐22
377 Installation of Stools 2 days Thu 26‐08‐21 Fri 27‐08‐21 311
378 Floor Assembly 15 days Sat 28‐08‐21 Sat 11‐09‐21 377
379 Assembly of side wall panels 20 days Sun 12‐09‐21 Fri 01‐10‐21 378
380 Assembly of end wall panels 15 days Sat 02‐10‐21 Sat 16‐10‐21 379
381 Internal & External Seal Welding 7 days Sun 17‐10‐21 Sat 23‐10‐21 380
382 Tube Support Installation 9 days Sun 24‐10‐21 Mon 01‐11‐21 381,30
383 Refractory Application for Side Wall / End Wall 30 days Tue 02‐11‐21 Wed 01‐12‐21 382,23,24
384 Refractory Application for Arch 15 days Thu 02‐12‐21 Thu 16‐12‐21 383
385 Arch Installation and Seal Welding  10 days Fri 17‐12‐21 Sun 26‐12‐21 384
386 Refractory dryout 15 days Mon 27‐12‐21 Mon 10‐01‐22 385
387 Coil insersion and  welding 35 days Tue 11‐01‐22 Mon 14‐02‐22 331,386
388 Installation of Transporation Jig 15 days Tue 15‐02‐22 Tue 01‐03‐22 332,387
389 Hydrotest 5 days Wed 02‐03‐22 Sun 06‐03‐22 388
390 Installation of Header Box 8 days Mon 07‐03‐22 Mon 14‐03‐22 389
391 Final touch‐up painting 5 days Tue 15‐03‐22 Sat 19‐03‐22 390
392 Final Inspection all  3 days Sun 20‐03‐22 Tue 22‐03‐22 391
393  LOT 6‐Dispatch to Site (CIF) 60 days Wed 23‐03‐22 Sat 21‐05‐22 392
394 A‐12) RADIANT MODULE ASSEMBLY (RM 4) 269 day Thu 26‐08‐21 Sat 21‐05‐22
395 Installation of Stools 2 days Thu 26‐08‐21 Fri 27‐08‐21 311
396 Floor Assembly 15 days Sat 28‐08‐21 Sat 11‐09‐21 395
397 Assembly of side wall panels 20 days Sun 12‐09‐21 Fri 01‐10‐21 396
398 Assembly of end wall panels 15 days Sat 02‐10‐21 Sat 16‐10‐21 397
399 Internal & External Seal Welding 7 days Sun 17‐10‐21 Sat 23‐10‐21 398
400 Tube Support Installation 9 days Sun 24‐10‐21 Mon 01‐11‐21 399,30
401 Refractory Application for Side Wall / End Wall 30 days Tue 02‐11‐21 Wed 01‐12‐21 400,23,24
402 Refractory Application for Arch 15 days Thu 02‐12‐21 Thu 16‐12‐21 401
403 Arch Installation and Seal Welding  10 days Fri 17‐12‐21 Sun 26‐12‐21 402
404 Refractory dryout 15 days Mon 27‐12‐21 Mon 10‐01‐22 403
405 Coil insersion and  welding 35 days Tue 11‐01‐22 Mon 14‐02‐22 331,404
406 Installation of Transporation Jig 15 days Tue 15‐02‐22 Tue 01‐03‐22 332,405
407 Hydrotest 5 days Wed 02‐03‐22 Sun 06‐03‐22 406
408 Installation of Header Box 8 days Mon 07‐03‐22 Mon 14‐03‐22 407
409 Final touch‐up painting 5 days Tue 15‐03‐22 Sat 19‐03‐22 408
410 Final Inspection all  3 days Sun 20‐03‐22 Tue 22‐03‐22 409
411  LOT 7‐Dispatch to Site (CIF) 60 days Wed 23‐03‐22 Sat 21‐05‐22 410
412 B ) CONVECTION MODULE'S ‐ 02 NOS. 286 day Fri 06‐08‐21 Wed 18‐05‐22
413 B‐1)  CONVECTION MODULE‐1 276 day Fri 06‐08‐21 Sun 08‐05‐22
414   Casing Steel Str Fabrication 85 days Fri 06‐08‐21 Fri 29‐10‐21 16FS+24 days
415   ETS Fabrication 25 days Wed 11‐08‐21 Sat 04‐09‐21 414SS+5 days
416   HB Fabrication 40 days Wed 11‐08‐21 Sun 19‐09‐21 415SS
417   Anchor Welding 12 days Sun 05‐09‐21 Thu 16‐09‐21 414SS+30 days,22
418   Blasting & Priming 8 days Sat 30‐10‐21 Sat 06‐11‐21 414
419   Module Assembly 15 days Mon 20‐09‐21 Mon 04‐10‐21 415,416,417
420   Refractory Application 25 days Wed 06‐10‐21 Sat 30‐10‐21 419FS+1 day,23
421   Dry out 5 days Sun 31‐10‐21 Thu 04‐11‐21 420
422   Coil U Pin Welding ( Shop )  45 days Sat 11‐09‐21 Mon 25‐10‐21 18,19,21FS+55 da
423   Coil & U Pin Insertion 35 days Fri 05‐11‐21 Thu 09‐12‐21 421,422
424 Convection coil bend welding  40 days Fri 10‐12‐21 Tue 18‐01‐22 423,18
425 Manifold inlet Header Welding 30 days Wed 19‐01‐22 Thu 17‐02‐22 424
426   Hydrotest 8 days Fri 18‐02‐22 Fri 25‐02‐22 425
427   Final Painting 10 days Sat 26‐02‐22 Mon 07‐03‐22 426
428 Final Inspection 2 days Tue 08‐03‐22 Wed 09‐03‐22 427
429  LOT 8‐Dispatch to Site (CIF) 60 days Thu 10‐03‐22 Sun 08‐05‐22 428
430 B‐2)  CONVECTION MODULE‐2 276 day Mon 16‐08‐21 Wed 18‐05‐22
431   Casing Steel Str Fabrication 85 days Mon 16‐08‐21 Mon 08‐11‐21 414SS+10 days
432   ETS Fabrication 25 days Sat 21‐08‐21 Tue 14‐09‐21 431SS+5 days
433   HB Fabrication 40 days Sat 21‐08‐21 Wed 29‐09‐21 432SS
434   Anchor Welding 12 days Wed 15‐09‐21 Sun 26‐09‐21 431SS+30 days,22
435   Blasting & Priming 8 days Tue 09‐11‐21 Tue 16‐11‐21 431
436   Module Assembly 15 days Thu 30‐09‐21 Thu 14‐10‐21 432,433,434
437   Refractory Application 25 days Sat 16‐10‐21 Tue 09‐11‐21 436FS+1 day,23
438   Dry out 5 days Wed 10‐11‐21 Sun 14‐11‐21 437
439   Coil U Pin Welding ( Shop )  45 days Wed 22‐09‐21 Fri 05‐11‐21 18,19,21FS+66 da
440   Coil & U Pin Insertion 35 days Mon 15‐11‐21 Sun 19‐12‐21 438,439

Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start‐only Deadline Baseline Milestone Progress
Project: Overall Schedule ‐ PEMEX
Split Summary External Tasks Inactive Task Inactive Summary Duration‐only Manual Summary Finish‐only Baseline Baseline Summary Manual Progress

 Page 4  JNK INDIA PVT LTD


Project Duration: 17Months -Modularisation (CIF) Prepared by : AS/ DBH5
Document No: P1-201-03-H-22501-10002
PEMEX PROJECT ‐ 04 NOS. CRUDE HEATERS Checked by : MS/DB
Document name : Overall Schedule Rev No. : 09

ID TaskTask Name Duration Start Finish Predecessors Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mod Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
441 Convection coil bend welding  40 days Mon 20‐12‐21 Fri 28‐01‐22 440,18
442 Manifold inlet Header Welding 30 days Sat 29‐01‐22 Sun 27‐02‐22 441
443   Hydrotest 8 days Mon 28‐02‐22 Mon 07‐03‐22 442
444   Final Painting 10 days Tue 08‐03‐22 Thu 17‐03‐22 443
445 Final Inspection 2 days Fri 18‐03‐22 Sat 19‐03‐22 444
446  LOT 9‐Dispatch to Site (CIF) 60 days Sun 20‐03‐22 Wed 18‐05‐22 445
447 B‐3) PLATFORM/HANDRAIL/LADDER 224 day Sat 25‐09‐21 Fri 06‐05‐22
448   Steel Structure Fabrication 120 day Sat 25‐09‐21 Sat 22‐01‐22 414SS+50 days
449   Blasting & Priming 95 days Sun 10‐10‐21 Wed 12‐01‐22 448SS+15 days
450   Layout Assembly 30 days Thu 13‐01‐22 Fri 11‐02‐22 449
451  Painting 22 days Sat 12‐02‐22 Sat 05‐03‐22 450
452 Final Inspection 2 days Sun 06‐03‐22 Mon 07‐03‐22 451
453  LOT 10‐Dispatch to Site (CIF) 60 days Tue 08‐03‐22 Fri 06‐05‐22 452
454 C ) FG DUCT 239 day Sun 22‐08‐21 Sun 17‐04‐22
455   Steel Str Fabrication 150 day Sun 22‐08‐21 Tue 18‐01‐22 16FS+40 days
456   Anchor Welding 120 day Tue 21‐09‐21 Tue 18‐01‐22 455SS+30 days,22
457   Blasting & Priming 105 day Wed 06‐10‐21 Tue 18‐01‐22 456SS+15 days
458   Refractory Application 21 days Wed 19‐01‐22 Tue 08‐02‐22 457
459   Dry out 7 days Wed 09‐02‐22 Tue 15‐02‐22 458
460 Final Inspection 1 day Wed 16‐02‐22 Wed 16‐02‐22 459
461  LOT 11‐Dispatch to Site (CIF) 60 days Thu 17‐02‐22 Sun 17‐04‐22 460
462 D ) AIR DUCT / CA DUCT 231 day Wed 01‐09‐21 Tue 19‐04‐22
463 Steel Str Fabrication 130 day Wed 01‐09‐21 Sat 08‐01‐22 16FS+50 days
464 Blasting & Priming 40 days Sun 09‐01‐22 Thu 17‐02‐22 463
465 Final Inspection 1 day Fri 18‐02‐22 Fri 18‐02‐22 464
466 LOT 12‐Dispatch to Site (CIF) 60 days Sat 19‐02‐22 Tue 19‐04‐22 465
467 E ) STACK MODULE.S ‐ 5 NOS. 218 day Mon 11‐10‐21 Mon 16‐05‐22
468 E‐1) STACK MODULE‐1 178 day Mon 11‐10‐21 Wed 06‐04‐22
469   Casing Fabrication 70 days Mon 11‐10‐21 Sun 19‐12‐21 16FS+90 days
470   Anchor Welding 15 days Mon 20‐12‐21 Mon 03‐01‐22 469,22
471   Blasting & Priming 10 days Tue 04‐01‐22 Thu 13‐01‐22 470
472   Refractory Application 10 days Fri 14‐01‐22 Sun 23‐01‐22 471
473   Dry Out 7 days Mon 24‐01‐22 Sun 30‐01‐22 472
474   Final Painting 4 days Mon 31‐01‐22 Thu 03‐02‐22 473
475 Final Inspection 2 days Fri 04‐02‐22 Sat 05‐02‐22 474
476  LOT 13‐Dispatch to Site (CIF) 60 days Sun 06‐02‐22 Wed 06‐04‐22 475
477 E‐2) STACK MODULE‐2 178 day Thu 21‐10‐21 Sat 16‐04‐22
478   Casing Fabrication 70 days Thu 21‐10‐21 Wed 29‐12‐21 469SS+10 days
479   Anchor Welding 15 days Thu 30‐12‐21 Thu 13‐01‐22 478,22
480   Blasting & Priming 10 days Fri 14‐01‐22 Sun 23‐01‐22 479
481   Refractory Application 10 days Mon 24‐01‐22 Wed 02‐02‐22 480
482   Dry Out 7 days Thu 03‐02‐22 Wed 09‐02‐22 481
483   Final Painting 4 days Thu 10‐02‐22 Sun 13‐02‐22 482
484 Final Inspection 2 days Mon 14‐02‐22 Tue 15‐02‐22 483
485  LOT 14‐Dispatch to Site (CIF) 60 days Wed 16‐02‐22 Sat 16‐04‐22 484
486 E‐3) STACK MODULE‐3 178 day Sun 31‐10‐21 Tue 26‐04‐22
487   Casing Fabrication 70 days Sun 31‐10‐21 Sat 08‐01‐22 478SS+10 days
488   Anchor Welding 15 days Sun 09‐01‐22 Sun 23‐01‐22 487,22
489   Blasting & Priming 10 days Mon 24‐01‐22 Wed 02‐02‐22 488
490   Refractory Application 10 days Thu 03‐02‐22 Sat 12‐02‐22 489
491   Dry Out 7 days Sun 13‐02‐22 Sat 19‐02‐22 490
492   Final Painting 4 days Sun 20‐02‐22 Wed 23‐02‐22 491
493 Final Inspection 2 days Thu 24‐02‐22 Fri 25‐02‐22 492
494  LOT 15‐Dispatch to Site (CIF) 60 days Sat 26‐02‐22 Tue 26‐04‐22 493
495 E‐4) STACK MODULE‐4 178 day Wed 10‐11‐21 Fri 06‐05‐22
496   Casing Fabrication 70 days Wed 10‐11‐21 Tue 18‐01‐22 487SS+10 days
497   Anchor Welding 15 days Wed 19‐01‐22 Wed 02‐02‐22 496,22
498   Blasting & Priming 10 days Thu 03‐02‐22 Sat 12‐02‐22 497
499   Refractory Application 10 days Sun 13‐02‐22 Tue 22‐02‐22 498
500   Dry Out 7 days Wed 23‐02‐22 Tue 01‐03‐22 499
501   Final Painting 4 days Wed 02‐03‐22 Sat 05‐03‐22 500
502 Final Inspection 2 days Sun 06‐03‐22 Mon 07‐03‐22 501
503  LOT 16‐Dispatch to Site (CIF) 60 days Tue 08‐03‐22 Fri 06‐05‐22 502
504 E‐5) STACK MODULE‐5 178 day Sat 20‐11‐21 Mon 16‐05‐22
505   Casing Fabrication 70 days Sat 20‐11‐21 Fri 28‐01‐22 496SS+10 days
506   Anchor Welding 15 days Sat 29‐01‐22 Sat 12‐02‐22 505,22
507   Blasting & Priming 10 days Sun 13‐02‐22 Tue 22‐02‐22 506
508   Refractory Application 10 days Wed 23‐02‐22 Fri 04‐03‐22 507
509   Dry Out 7 days Sat 05‐03‐22 Fri 11‐03‐22 508
510   Final Painting 4 days Sat 12‐03‐22 Tue 15‐03‐22 509
511 Final Inspection 2 days Wed 16‐03‐22 Thu 17‐03‐22 510
512  LOT 17‐Dispatch to Site (CIF) 60 days Fri 18‐03‐22 Mon 16‐05‐22 511
513 E‐6) PLATFORM/HANDRAIL/LADDER 177 day Thu 21‐10‐21 Fri 15‐04‐22
514    Steel Structure Fabrication 75 days Thu 21‐10‐21 Mon 03‐01‐22 478SS
515    Blasting & Priming 65 days Sun 31‐10‐21 Mon 03‐01‐22 514SS+10 days
516    Layout Assembly 30 days Tue 04‐01‐22 Wed 02‐02‐22 515
517   Painting 10 days Thu 03‐02‐22 Sat 12‐02‐22 516
518 Final Inspection 2 days Sun 13‐02‐22 Mon 14‐02‐22 517
519   LOT 18‐Dispatch to Site (CIF) 60 days Tue 15‐02‐22 Fri 15‐04‐22 518
520 F ) FUEL SKID ‐ 2 NOS. 198 day Thu 21‐10‐21 Fri 06‐05‐22
521 F‐1) FUEL SKID ‐1  184 day Thu 21‐10‐21 Fri 22‐04‐22
522  Steel Frame Fabrication 50 days Thu 21‐10‐21 Thu 09‐12‐21 16FS+100 days
523  Pipe Support 25 days Fri 10‐12‐21 Mon 03‐01‐22 522
524  Piping Spool 18 days Tue 04‐01‐22 Fri 21‐01‐22 523
525  Assembly of Skid 20 days Sat 22‐01‐22 Thu 10‐02‐22 524
526  Hydrotest 5 days Fri 11‐02‐22 Tue 15‐02‐22 525
527  Painting 4 days Wed 16‐02‐22 Sat 19‐02‐22 526
528 Final Inspection 2 days Sun 20‐02‐22 Mon 21‐02‐22 527
529  LOT 19‐Dispatch to Site (CIF) 60 days Tue 22‐02‐22 Fri 22‐04‐22 528
530 F‐1) FUEL SKID ‐2 184 day Thu 04‐11‐21 Fri 06‐05‐22
531  Steel Frame Fabrication 50 days Thu 04‐11‐21 Thu 23‐12‐21 522SS+14 days
532  Pipe Support 25 days Fri 24‐12‐21 Mon 17‐01‐22 531,16,20
533  Piping Spool 18 days Tue 18‐01‐22 Fri 04‐02‐22 532
534  Assembly of Skid 20 days Sat 05‐02‐22 Thu 24‐02‐22 533
535  Hydrotest 5 days Fri 25‐02‐22 Tue 01‐03‐22 534
536  Painting 4 days Wed 02‐03‐22 Sat 05‐03‐22 535
537 Final Inspection 2 days Sun 06‐03‐22 Mon 07‐03‐22 536
538  LOT 20‐Dispatch to Site (CIF) 60 days Tue 08‐03‐22 Fri 06‐05‐22 537

Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start‐only Deadline Baseline Milestone Progress
Project: Overall Schedule ‐ PEMEX
Split Summary External Tasks Inactive Task Inactive Summary Duration‐only Manual Summary Finish‐only Baseline Baseline Summary Manual Progress

 Page 5  JNK INDIA PVT LTD