Activity ID Activity Name Original Start Finish Total Resources Calendar 2022 2023
Duration Float
Nov Dec Jan
FHDL Farm House Design at Lahore 60 01-Nov-22 30-Dec-22 0 5 Days Work 30-Dec-22, FHDL Farm House
Week
FHDL.1 Desk Study 3 01-Nov-22 03-Nov-22 0 5 Days Work 03-Nov-22, FHDL.1 Desk Study
Week
A1040 Preliminary Study for Requirements Collection 1 01-Nov-22 01-Nov-22 0 Chief 5 Days Work Preliminary Study for Requirements Collection
Architect, Week
Senior
A1050 Finalization of Requirement Collection Tools 2 02-Nov-22 03-Nov-22 0 Chief 5 Days Work Finalization of Requirement Collection Tools
Architect, Week
Senior
FHDL.2 Requirement Collection 6 04-Nov-22 09-Nov-22 0 5 Days Work 09-Nov-22, FHDL.2 Requirement Collection
Week
A1000 Kickoff Meeting 1 04-Nov-22 04-Nov-22 0 Chief 5 Days Work Kickoff Meeting
Architect, Week
Senior
A1010 Requirement Collection from Client 2 05-Nov-22 06-Nov-22 0 Senior 5 Days Work Requirement Collection from Client
Architect Week
A1020 Finalization of Requirement Tracability Matrix 2 07-Nov-22 08-Nov-22 0 Senior 5 Days Work Finalization of Requirement Tracability Matrix
Architect Week
A1030 Signing off Scope Finalization Docs 1 09-Nov-22 09-Nov-22 0 Senior 5 Days Work Signing off Scope Finalization Docs
Architect Week
FHDL.3 Field Testing 11 10-Nov-22 20-Nov-22 0 5 Days Work 20-Nov-22, FHDL.3 Field Testing
Week
A1060 Mobilization for Geotechnical Isvestigations 1 10-Nov-22 10-Nov-22 0 Geotech 5 Days Work Mobilization for Geotechnical Isvestigations
engr, Week
Laboratory
A1070 SPT Test for Borehole-1 3 11-Nov-22 13-Nov-22 0 Geotech 5 Days Work SPT Test for Borehole-1
engr, Week
Laboratory
A1080 SPT Test for Broehole-2 3 14-Nov-22 16-Nov-22 0 Geotech 5 Days Work SPT Test for Broehole-2
engr, Week
Laboratory
A1090 Laboratory Testing & Finalization of Results 3 17-Nov-22 19-Nov-22 0 Geotech 5 Days Work Laboratory Testing & Finalization of Results
engr, Week
Laboratory
A1100 Submission of Results 1 20-Nov-22 20-Nov-22 0 Geotech 5 Days Work Submission of Results
engr, Week
Laboratory
Activity ID Activity Name Original Start Finish Total Resources Calendar 2022 2023
Duration Float
Nov Dec Jan
FHDL.4 Architecture Design 15 21-Nov-22 05-Dec-22 0 5 Days Work 05-Dec-22, FHDL.4 Architecture Design
Week
A1110 Preparation & Submission of Concept Design 4 21-Nov-22 24-Nov-22 0 Architect 5 Days Work Preparation & Submission of Concept Design
Week
A1120 Approval of Concept Design 4 23-Nov-22 26-Nov-22 0 Architect 5 Days Work Approval of Concept Design
Week
A1130 Preparation & Submission of Detailed Layout 2 27-Nov-22 28-Nov-22 0 Architect 5 Days Work Preparation & Submission of Detailed Layout Design
Design Week
A1140 Approval of Detailed Layout Design 2 29-Nov-22 30-Nov-22 0 Architect 5 Days Work Approval of Detailed Layout Design
Week
A1150 Preparation & Submission of Furtniture Layout 4 01-Dec-22 04-Dec-22 0 Interior 5 Days Work Preparation & Submission of Furtniture Layout Desig
Design designer Week
A1160 Approval of Furniture Layout Design 4 02-Dec-22 05-Dec-22 0 Interior 5 Days Work Approval of Furniture Layout Design
designer Week
FHDL.5 Structure Design 5 06-Dec-22 10-Dec-22 0 5 Days Work 10-Dec-22, FHDL.5 Structure Design
Week
A1180 Finalization of Design Loads 1 06-Dec-22 06-Dec-22 0 Lead 5 Days Work Finalization of Design Loads
Structrue Week
Engineer
A1190 Calculation & Design Analysis 2 07-Dec-22 08-Dec-22 0 Structure 5 Days Work Calculation & Design Analysis
Engr Week
A1200 Preparation & Submission of Structure Design 2 09-Dec-22 10-Dec-22 0 Structure 5 Days Work Preparation & Submission of Structure Design
Engr Week
FHDL.6 MEP Design 6 11-Dec-22 16-Dec-22 0 5 Days Work 16-Dec-22, FHDL.6 MEP Design
Week
A1210 Preparation & Submission of Fresh Water 2 11-Dec-22 12-Dec-22 0 Hydraulic 5 Days Work Preparation & Submission of Fresh Water Sup
Supply Design Calculations Engr Week
A1220 Preparation & Submission of Sewerage 2 13-Dec-22 14-Dec-22 0 Hydraulic 5 Days Work Preparation & Submission of Sewerage Sys
System Design Drawings Calculations Engr Week
A1230 Preparation & Submission of Electrical 2 15-Dec-22 16-Dec-22 0 MEP 5 Days Work Preparation & Submission of Electrical Sys
Systems Design Calculations Designer Week
Activity ID Activity Name Original Start Finish Total Resources Calendar 2022 2023
Duration Float
Nov Dec Jan
FHDL.7 Land Scape Design 8 17-Dec-22 24-Dec-22 0 5 Days Work 24-Dec-22, FHDL.7 Land Scape De
Week
A1240 Preparation & Submission Concept Design 5 17-Dec-22 21-Dec-22 0 Landscape 5 Days Work Preparation & Submission Concept De
Expert Week
A1250 Approval of Concept Design 5 18-Dec-22 22-Dec-22 0 Landscape 5 Days Work Approval of Concept Design
Expert Week
A1260 Preparation & Submission of Final Landscape 2 23-Dec-22 24-Dec-22 0 Landscape 5 Days Work Preparation & Submission of Final L
Design Expert Week
FHDL.8 Drawings & Docs Submission 6 25-Dec-22 30-Dec-22 0 5 Days Work 30-Dec-22, FHDL.8 Drawings
Week
A1270 Submission of Construction Drawings forArchi 1 25-Dec-22 25-Dec-22 0 Draftsman 5 Days Work Submission of Construction Drawin
Construction Drawings Archi Week
A1280 Submission of Structure Drawings 1 26-Dec-22 26-Dec-22 0 Draftsman 5 Days Work Submission of Structure Drawings
Structure Week
A1290 Submission of Plumbing Drawings 1 27-Dec-22 27-Dec-22 0 Draftsman 5 Days Work Submission of Plumbing Drawing
MEP Week
A1300 Submission of Sewerage Drawings 1 28-Dec-22 28-Dec-22 0 Draftsman 5 Days Work Submission of Sewerage Drawin
MEP Week
A1310 Submission of Land Scape Drawings 1 29-Dec-22 29-Dec-22 0 Draftsman 5 Days Work Submission of Land Scape Dra
Archi Week
A1320 Submission of Specifications 1 30-Dec-22 30-Dec-22 0 Lead 5 Days Work Submission of Specifications
Structrue Week
Engineer