Professional Documents
Culture Documents
Flash Tank Calculation Report
Flash Tank Calculation Report
Flash Tank Calculation Report
Contractor's Name:
This document is issued by Harris Pye DMCC, Dubai UAE. The information contained in this document is the confidential property
of Harris Pye. It cannot be disclosed, copied or used for any purpose without written approval from Harris Pye. If you are not
authorised to possess this document, please destroy it immediately.
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
2 of 29___ _
PROCESS DESIGN REPORT 3 29/05/17
REVISION HISTORY
Re-Issued for - Incorporated updated information on CBD line; Inlet nozzles &
2 12/04/17
Approval tank top portion dimensions
649383605.xlsx
3 of 29___ _
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
4 of 29_ ____
PROCESS DESIGN REPORT 3 29/05/17
TABLE OF CONTENTS
Revision History 2
Contents 3
Design Input Data 4
Assumptions 5
Nozzles Sizing 6
N1/ N9 - CBD Inlet 6
N2 - Flash Steam Outlet 9
N3 - Liquid Outlet 9
N4-N5 - Level Instruments 10
N6 - Pressure Intrument 10
N7 - Vent 11
N8 - PRV 11
Vessel Sizing 13
Vessel Diameter for Gravity Separation 13
Wire Mesh Pad Mist Eliminator Sizing 14
Calculation of Vessel Height 15
References 17
Appendix- 18
Demister pad Datasheet 18
649383605.xlsx
5 of 29_ ____
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
6 of 29_ ____
PROCESS DESIGN REPORT 3 29/05/17
Rev DESIGN INPUT DATA
Liquid
Stream Description Units CBD [3] Two-Phase Inlet Flash Steam
Outlet/Liquor
2 Flow Rate [kg/h] 1,000 1,000 264.6 735.4
2 [kg/s] 0.278 0.278 0.074 0.204
2 Pressure [bar(a)] 49.79 3.52 3.51 3.51
2 Temperature [°C] 262.4 139.0 139.0 139.0
2 Enthalphy [kJ/kg] 1153.2 1153.2 2732.1 584.7
2 Quality [-] 0.000 0.265 1.000 0.000
2 Density [kg/m³] 777.8 7.20 1.9 927.1
2 Viscosity [cP] 0.100 0.198 (2) 0.014 0.198
2 Volumetric Flow [m³/s] 0.00036 0.0386 0.0384 0.00022
2 Specific Heat [kJ/kg K] 5.029 3.760 2.303 4.284
2 Thermal Conduct. [W/m K] 0.601 - 0.029 0.685
Notes:
(1) Flash Steam and liquid Outlet stream properties are calculated by heat and mass balance.
(2) Mixture viscosity approximated with saturated liquid viscosity.
2 (3) Pressure upstream of the CBD valve, including also the static head.
649383605.xlsx
7 of 29_ ____
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 3 29/05/17 8 of 29___ __
Rev ASSUMPTIONS
The following assumptions were made for the design of the blowdown flash tank:
1. The operating pressure in the flash tank is established by the downstream equipment, i.e. the deaerator. The pressure will be
the deaerator pressure plus the pressure drops of the flashed steam in the piping and vessel internals. In the following, a
0.01 bar pressure drop is assumed, to be verified after pipe routing and vessel sizing.
2. The vapor-liquid separation in the vessel is mainly achieved by gravity settling of the liquid droplets and by action of the
inlet device. A wire mesh mist eliminator is installed in the vessel to increase the separation efficiency.
3. For gravity settling, the momentum equation reduces to a balance of the gravity and drag forces at steady state. This allows
to calculate a terminal velocity, which is the superficial velocity around the liquid droplets under equilibrium conditions.
4. The typical droplet size for a flash vessel with two-phase flow inlet in similar applications is 150 micron (μm). The
blowdown flash vessel will be able to separate the liquid droplets larger than 150 μm by gravity. To achieve a higher
separation efficiency and to remove the smaller-sized droplets, a demister pad (wire mesh mist eliminator) will be used.
5. To determine the drag force, the C vs Reynolds curve is divided into three regions, corresponding to typical Re number
D
regions, where different physical laws are used to represent the CD vs Re curve (namely Stoke's, Intermediate and Newton's
Laws, respectively). This results in three different formulations of the terminal velocity, based on the Reynolds number and
thus depending on the fluid. In this work, the Intermediate Law will be used, representing the typical range encountered in
similar applications.
6. Liquid residence time in the vessel is taken as 2 min, based on level control considerations and on the surge volume to
accommodate transients in the inlet stream.
7. The vessel is vented at atmospheric pressure, with the assumption of closed flash steam output and open inlet.
2 8. The sizing calculations are done for Nozzle N1A,the same is applicable to N1B due to similar Process design parameters.
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 3 29/05/17 9 of 29___ __
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 10 of 29 _____
2 The feed inlet to the separator is, in general, a 2-phase mixture, due to the flashing of the fluid in the blowdown
line,downstream to the blowdown valve.The following is a summary of the conditions of the inlet continuous blowdown
stream to the flash tank.
Since the inlet to the vessel is a multiphase fluid, the determination of the flow regime in the inlet line is very important for
the inlet nozzle sizing and for the efficient separation of the two components. Normally, the inlet nozzle of a flash vessel is
sized for Annular or Spray flow. Other flow regimes, such as Slug, Plug and Froth are not recommended.
The existing blowdown line data from the boiler to the Flash Tank is summarized below.
Description Unit Existing Line Data Recalculated Nozzle
2 Line Number - - 01-15-BB-AS1-067 06-50-BB-6CS-H26A/B
2 Line Material - - A 335 P1 A 335 P1
Nozzle Material - - A 106 Gr.B A 106 Gr.B
Nominal Diameter DN - 15 50
Outside Diameter OD mm 21.3 60.3
Schedule Sch. - 80 80
Thickness t mm 3.7 5.5
Inside Diameter ID mm 13.9 49.3
Flow Area A m² 0.00015 0.00191
Flow Velocity v m/s 281.0 22.3 OK
A preliminary calculation of the velocity in the existing line shows that for the two-phase mixture, the velocity is
unrealistic. Therefore, the line has to be resized to avoid such high velocities.
The maximum velocity in a two-phase line is usually established by the erosional limit, which can be calculated according
to:
𝑉_𝑒𝑟=(100 ∙0.3048)/√(𝜌_𝑚 ) (100) (0.3048)
= = 45.5 m/s [Ref.5]
(7.2) (0.0624)
Taking this as a base, the new line size has been calculated iteratively, and the flow regime in the new line was determined,
using a flow map from the literature [Ref.1]. To use this map, some flow parameters must be calculated, and used as input
to the chart axes. The insersection point gives the flow regime in the pipe with sufficient accuracy for practical applications.
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN
Taking this as a base, the new line size has been calculated REPORT
iteratively, and the flow regime in2 the new line 11 of 29 _____
was determined,
29/05/17
using a flow map from the literature [Ref.1]. To use this map, some flow parameters must be calculated, and used as input
to the chart axes. The insersection point gives the flow regime in the pipe with sufficient accuracy for practical applications.
Nozzle sizing
To size the nozzle, a maximum (conservative) value for the kinetic energy per unit volume (ρv²) is usually specified, and
the nozzle diameter calculated iteratively based on this value.
The maximum value of (ρv²) is very dependent on the type of inlet device (if any) mounted on the nozzle, which usually
decrease the momentum of the inlet fluid to values not dangerous from the point of view of corrosion or liquid entrainment.
(ρv²) ≤ 3,500 kg/m s² considering an inlet baffle only.
If inlet devices, such as slotted distributors or inlet vanes are used, higher values of the (ρv²) can be accepted.
Check of (ρv²) value with chosen nozzle diameter.
(ρv²) = (7.2) (22.3)² = 3,574 kg/m s² Increase the nozzle size
Sizing of Inlet baffle
b
Given the low inlet mixture velocity with the selected nozzle size, no inlet device is required. a
However, an inlet baffle is installed to deflect the entering flow and promote an initial
Dv
separation of the two phases.
Typical dimensions for the inlet baffle/diverter are:
a ≥ max {2 D ; D + 50} ≥ 120.65 mm say 150 mm a
b ≥ 100 ≥ 100 mm say 120 mm
c ≥ max {2 D ; D + 60} ≥ 120.65 mm say 150 mm c
Following the recommendation in Ref.2, a value of X double will be used fo rthe annular and spray flow patterns.
X' = 5.00
= 5.10
4.6 〖 (𝑋^′) 〗 ^(−1.78)+12.5 〖 (𝑋^′) 〗 ^(−0.68)+0.65
YL 1+20/((𝑋^′))+1/
= 〖 (𝑋^′) 〗 ^2 = 5.04
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 13 of 29 _____
The entrance loss, with the assumption of incompressible flow (Δp≤10% Pin),and A1/A2 → 0 is given by:
(𝑉_1^2)/2 (1−𝐴_1/𝐴_2 )^2
Δpentr = = 248.21 Pa
Finally, the pressure drop due to the change in direction of the fluid due to the baffle plate would need to be estimated.
However, since the calculation of the pressure drop of a 2-phase fluid changing direction is an involved and iterative
calculation, this loss will be conservatevely estimated as 1.5 times the entrance loss.
Thus:
Δpbp = 1.5 Δpentr = 372.31 Pa
Δptotal = Δpfrict+Δpentr+Δpbp = 623.5 Pa = 0.0062 bar
2. Flash Steam Outlet Nozzle (N2)
The data on the existing flash steam line to the deaerator is shown in the table below. A preliminary calculation of the
velocity in this line shows that for the LP Flash Steam, the velocity is low compared to the usual velocities for steam (≈ 15 -
20 m/s). Therefore, a new line size was assumed and the velocity recalculated (see Table below).
Description Unit Existing Line Recalculated Line
2 Line Number - - 01-100-STM-CS1-029 06-50-STM-1CS-H28
Material - - A 106 Gr.B A 106 Gr.B
Nominal Diameter DN - 100 50
Outside Diameter OD mm 101.6 60.3
Schedule Sch. - 80 40
Thickness t mm 8.1 3.9
Inside Diameter ID mm 85.4 52.5
Flow Area A m² 0.0057 0.0022
2 Flow Velocity v m/s 7.4 19.5 OK
The nozzle size will be as per the recalculated line size. Also in this case, a check for the (ρv²) shall be made. However, for
gas/vapor outlet nozzles, this parameter can be higher, due to the single phase fluid and the relatively low erosion risk.
Check of (ρv²) value with chosen nozzle diameter.
(ρv²) = (1.9) (19.5)² = 729 kg/m s² ≤ 5,400 kg/m s² Nozzle Size is Acceptable
2 In addition, a check for sonic velocity has to be made, since the fluid in the nozzle is in the vapor phase, but for saturated
steam this velocity is usually very high (>400 m/s, for LP Steam), so the selected nozzle is acceptable.
To size the oultet liquid/liquor line, a nozzle size (and line size) is assumed and the fluid velocity is checked. The criteria
for liquid outlet nozzles is usually based on the fluid velocity, as follows:
0.6 m/s ≤ v ≤ 1.2 m/s
Description Unit Outlet Liq./Liquor Line
2 Line Number - - 06-20-BB-1CS-H27
Material - - A 106 Gr.B
Nominal Diameter DN - 20
Outside Diameter OD mm 26.7
Schedule Sch. - 80
Thickness t mm 3.9
Inside Diameter ID mm 18.8
Flow Area A m² 0.0003
2 Flow Velocity v m/s 0.9 Nozzle Size is Acceptable
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 14 of 29 _____
The vortex breaker sizing is based on rules of thumb, and a minimum fluid height above the device has to be maintained.
Minimum fluid height above vortex breaker = 150 mm
438.2 mm
Vortex Breaker height = 1.5 ODn = 40.0 mm
Vortex Breaker width = 2.5 ODn = 66.7 mm
Actual fluid height above vortex breaker = 403 mm OK LWL
250 mm 66.7 mm
403 mm
193 mm
40 mm
Figure 3 - Arrangement of Vortex Breaker.
OD = 26.7 mm
3/4" 3/4"
HHWL
Control Range
HWL
Level Transm.
Level Gauge
650
NWL
650
650
LWL
LLWL
3/4"
BTL 75
3/4"
Figure 4 - Schematic representation of Level Instruments Arrangement.
The amount of flash steam at this pressure would then be obtained, as before, by flashing of the incoming Continuous
Blowdown to the pressure of the vessel during venting. The following table gives the thermophysical properties of the inlet
CBD and the flash steam under venting conditions. With the calculated flash steam, the vent nozzle can be sized,
maintaining a fluid velocity ≤ 50 m/s.
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 16 of 29 _____
2 Backpressure - bar(a) 1.013
Relieving Temperature (sat.) T1 °C 155.5
K 428.6
To size the valve for vapor relief, a preliminary check for critical flow (or chocked flow) has to be made and the critical
pressure calculated as follows. If the downstream pressure is less than or equal to the critical pressure, critical flow will be
established in the valve.
2 𝑝_𝑐𝑟=𝑃_1 [2/(𝑘+1)]^(𝑘∕(𝑘−1) ) 2 1.135/(1.135-1)
= 5.5 = 3.18 bar(a) Critical Flow
1.135+ 1
where:
Pcr = Critical Pressure
P1 = Relief Pressure
k = 1.135 for dry saturated steam
The required effective discharge area of the pressure relief valve for vapor service is calculated according to the following
formula, from API 520-1.
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 17 of 29 _____
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 18 of 29_ ____
where:
ρl = Saturated liquid density = 927.1 kg/m³
ρg = Saturated flash steam density = 1.9 kg/m³
μg = Flash steam viscosity = 1.4E-05 kg/m s (= cP/1000)
Substituting,
(
0.154) (5.06) (4.37E-05) (127.65)
ut = = 0.446 m/s
(1.207) (0.008083)
2 Check for Intermediate Law assumption validity : (2 < Re < 500)
An alternative method to calculate the terminal velocity makes use of the following general formula:
𝑢_𝑡=1.15√(( 〖 𝜌〗 _𝑔 𝐷_𝑝
( 〖𝜌 _𝑙−𝜌 〗 _𝑔))/( 〖 𝜌〗 _𝑔 𝐶_𝐷 ))
Since CD is dependent on Re, and thus on the terminal velocity, an iterative approach would be required. However, using a
the following correlation, together with Figure 1, the terminal velocity is eliminated and the drag coefficient can be directly
calculated.
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 19 of 29_ ____
The difference between the two values of the terminal velocity calculated with the two above methods is ≈ 8.82 %, hence
acceptable.
Taking the lower value of the two terminal velocities calculated above (conservative), the required vessel diameter can be
calculated, with the vapor velocity being less than the terminal velocity, to avoid entrainment:
𝐷/1000≥√(4/𝜋∙𝑄_𝑎/𝑢_𝑡 )
(4) (0.0423)
= = 0.347 m
(3.14) (0.446)
where:
D = Minimum Inside Diameter of the flash tank vessel = 347 mm
ut = Terminal velocity for liquid droplets = 0.446 m/s
Qa = Flash steam max volumetric flow rate = 0.0384 m³/s
To size the mist eliminator, a simplified and more empirical approach is employed, due to the complexity in expressing the
mesh pad separation performance in simple mathematical terms.
Similarly to the above, a critical velocity is calculated, using the following formula:
𝑉_𝑐=𝐹 𝐾√((𝜌_𝑙−𝜌_𝑔)/𝜌_𝑔 )
where:
2
K = Sizing factor or velocity constant (0.055 - 0.110 for vertical drums) = 0.085
F = Design margin to account for surging and uncertainties in data = 0.85
Typical values for K are in the range of 0.055 - 0.110 m/s for vertical separation drums with demister pad (for flash tank
applications, a value of 0.076 is employed). In the case of a flash drum with wet steam the K value can be taken as:
925.1
K = 0.076 m/s Vc = (0.076) (0.85) = 1.42 m/s
and 1.9
The minimum required wire mesh pad diameter is then obtained:
𝐷_𝑤𝑚/1000≥√(4/𝜋∙𝑄_𝑎/𝑉_𝑐 )
(4) (0.0423)
= = 0.195 m say 200 mm
(3.14) (1.42)
where:
Dwm = Minimum Required Diameter of the Wire mesh pad = 200.0 mm
Vc = Critical velocity = 1.421 m/s
Qa = Flash steam volumetric flow rate (max) = 0.0423 m³/s
The vessel drum inside diameter shall be larger than the required pad diameter, to allow for proper installation.
Dves ≥ max{D ; Dv} = max {347 ; 300} = 347 mm say IDves = 438.2 mm
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 20 of 29_ ____
Minimum size of wire mesh pad bottom ring supports = 107.15 mm say 120 mm (on each side)
Calculated vapor velocity with the chosen diameter = 0.28 m/s ≤ ut = 0.45 m/s → OK
2 The vessel height is usually calculated as a function of the vessel diameter. In fact, an optimal H/D ratio usually exists, that
minimizes the cost of the vessel. Typically the H/D ratio for similar vessels ecountered in practice varies in the range 3.0 -
5.0, depending on the operating pressure.
The total height of the cilindrical part of the vessel can be expressed as:
Hh
Ht = HT-T + 2 Hh = H1 + H2 + H3 + twm + H4 + 2 Hh H4
twm
where:
H3
H1 = Height from bottom TL to HHWL, depending on liquid holdup time (see 3.1)
H2 = Height from HHWL to inlet nozzle CL
H3 = Vapor space disengaging height H2
HHW
twm = Wire mesh pad thickness L
HWL
H4 = Height from top of wire mesh pad to top TL LWL H1
The liquid residence time (or holdup time) was selected as 2 min from HWL to LWL.
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 21 of 29_ ____
In order to avoid entrainment of liquid in the vapor stream, a minimum distance from the nozzle centerline to the
HHWL (High High Water Level) must be respected. This distance is usually taken as:
The clearance from the top of the Wire mesh pad to the outlet nozzle is
established based on the Figure [Ref.3].
DN 50
H1 = 650 mm ± 40 mm
193 mm
H2 = 350 mm ± 40 mm
H3 = 950 mm ± 40 mm 102 mm
twm = 150 mm ± 40 mm
H4 = 102.0 mm ± 40 mm 300 mm
Hh = 193.0 mm ± 40 mm
438.2 mm
HT-T = 2,202 mm => 2200 mm ± 40 mm 950 mm
HT-T
Check for: 3 ≤ ≤ 5 DN 50 150 mm
ODves
350 mm
HT-T HHWL
= 4.8 OK
649383605.xlsx
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17 22 of 29_ ____
600 mm
LWL
LLWL
193 mm
`
649383605.xlsx
]
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
23 of 29_____
PROCESS DESIGN REPORT 2 29/05/17
INSULATION THICKNESS
Calculate the insulation thickness for PP (?), using the EN 12241 standard.
649383605.xlsx 03/08/2023
24 of 29_____
]
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 2 29/05/17
649383605.xlsx 03/08/2023
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 25 of 29
2 29/05/17
Rev REFERENCES
[1] Green, D.W.; Perry, R.H. - Perry's Chemical Engineering Handbook, 8th Ed. (2008).
[2] Ludwig, E.E. - Applied Process Design Vol. 1, 3rd Ed. (1999).
[3] GPSA Engineering Data Book, Vol. I & II, 12th Ed. (2004).
[4] Towler, G.; Sinnott, R. - Chemical Engineering Design (2008).
[5] API 14E - Recommended Practice for Design and Installation of Offshore Production Platforms and Piping Systems,
5th Ed. (1991)
[6] EN ISO 4126 Safety Devices for Protection Against Excessive Pressure.
2 [7] Drawing No. HULL_01_DWG_19_70017_C - Blowdown System P&ID
2 [8] HP Document No. MI-17085-PS-SP-001_5 - Pressure Relief Valves Datasheets
[9] API 520-1, Sizing, Selection and Installation of Pressure Relieving Devices
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
PROCESS DESIGN REPORT 26 of 29
2 29/05/17
Client: Galliford Try Doc. No. MI-17085-PR-CR-001
Project: Hull Biomass UK LLP 1 Tag No. T-06-17023
Location: Hull, United Kingdom Job No. MI-17085
BLOWDOWN FLASH TANK Rev. Date Sheet
27 of 29
PROCESS DESIGN REPORT 2 29/05/17
APPENDIX
Demister Pad Datasheet
649383605.xlsx
28 of 29
649383605.xlsx
Flash Steam NOTES
2
to Deaerator [1] Assumption of cold boiler
draining.
Intermittent Blowdown 7
Sootblower Condensate 8
Flash
Tank
Continuous Blowdown 1 T-06-
17026
6
Atmospheric
Blowdown Tank
T-06-17081
3 4
Make-up Water KEY
LCV
Preheater 12 Water
HE-06-17083 Saturated Steam
Make-up Water from Condensate
5
Treatment Plant To Drain System Intermittent Cond.
TCV
Foul Water
STREAM 1 2 3 4 5 6 7 8 9 10 11 12
Continuous Flash Tank Cold Hot Intermittent Sootblower Deaerator Blowdown
Description Flash Steam Cold Liquor Boiler Drains Vent Steam
Blowdown Liquor Make-up Make-up Blowdown Condensate Overflow Tank Outlet
Flow [kg/h] 1,000 264.6 735.4 735.4
Temperature [°C] 139.0 139.0 139.0 20
Pressure [bar(a)] 3.5 3.5 3.5 4
Density [kg/m³] 7.2 1.9 927.1 998.3
Volume Flow [ m³/h] 138.9 138.3 0.79