Professional Documents
Culture Documents
EN - Project-Management-Prepcast - Com-Free PMP Practice Exam Questions 120 Sample Test Questions PDF
EN - Project-Management-Prepcast - Com-Free PMP Practice Exam Questions 120 Sample Test Questions PDF
Questions
project-management-prepcast.com/pmp-practice-exam-questions-sample-test
Home
Corporate Training
Forum
Log in
For your Project Management Professional (PMP)® exam using A Guide to the Project
Management Body of Knowledge (PMBOK® Guide):
Based on the PMBOK® Guide Exam 6th Edition, and updated for
the most current PMP Exam!
*** Updated 2020-Nov-16 - We are proud to have this up-to-date list of free questions
for the latest PMP exam!
Note: The exam results created by this page are temporary. If you restart your browser, or
reload, close or move away from this page in any way, then your results will disappear.
Where in the project life cycle will the overall project risk be the lowest?
(Please note that on the real PMP exam you may be asked to provide your answer by
clicking the correct area in the image. But here in the simulator, we are asking you to
select the answer below.)
1/29
Question 2 - Qid 6110002, Cost Management, 3. Business
Environment, 4.1 Develop Project Charter
A company is considering two projects, Alpha and Beta. Project Alpha is expected to result
in a $50 million net profit, while project Beta and is expected to net $45 million. Both
projects could be very lucrative and rewarding. However, the financial controller has
stated that the company can only invest in one of these projects.
After the first phase of the project is complete, which process group of the second phase
should follow?
2/29
Question 5 - Qid 6110006, Stakeholder Management, 2. Process,
13.1 Identify Stakeholders
You are managing a software upgrade project for your company. Your project sponsor has
a great deal of authority regarding project decisions, but you recently discovered that he
doesn't have much interest in your project. To complete the project successfully, you need
your project sponsor's continuous support.
What stakeholder management strategy should you use with your project sponsor?
As a starting point for initial project planning, what is the first thing you should do?
3/29
Recently, you promoted your star programmer, Sam, to lead the agile development team.
Sam was a fantastic software coder, and you thought the promotion would mean that he
could now share his expertise with the other development team members. However, you
are surprised to learn that the performance of Sam in his new role is not meeting your
expectations.
Which empirical rule did you forget while considering the promotion of Sam?
Which of the following components did the project manager most likely notice?
Which of the following activities might be carried out during this process?
4/29
Question 15 - Qid 6110040, Integration Management, 2. Process,
4.6 Perform Integrated Change Control
An organization has a policy that a change control board (CCB) must review all change
requests for every project in the organization, and that the CCB follows the recommended
activities outlined in the PMBOK® Guide. Project managers and the project team do not
serve as members of the CCB.
Based on this scenario, which of the following activities might be performed by members
of the CCB?
If the project sponsor is a member of the CCB, which of the following best describes an
individual or group that can request a change on a project?
What should the project manager review first to identify stakeholders for a newly started
project?
5/29
Question 20 - Qid 6112348, Schedule Management, 2. Process, 6.5
Develop Schedule
The following table is an activity list that includes the duration and predecessor for a
series of project activities.
6/29
Which of the following is not considered one of these techniques?
The methods the team is using are representative of which tool and technique?
What would likely have helped avoid this conflict had it been properly created first?
7/29
What estimation technique does the project manager use?
Which of the following documents would you primarily refer to for this purpose?
8/29
Question 33 - Qid 6112005, Procurement Management, 2. Process,
12.3 Control Procurements
You are managing a project that is nearing its end and planning to settle all pending
claims with the vendors. In one case, you are not satisfied with the delivery of their final
product. All conversations with the vendor have ended in an impasse.
What is the best course of action for you to increase the chances of receiving the bonus?
Which of the following tools or techniques should be used to comply with the plan?
9/29
needs to be reworked to ensure it can be operated safely.
Which of the following was most likely the element the PMO requested to remove?
(Please note that on the real PMP exam you may be asked to provide your answer by
clicking the correct area in the image. But here in the simulator, we are asking you to
select the answer below.)
10/29
Question 41 - Qid 6112039, Scope Management, 2. Process, 5.3
Define Scope
To define the product that will be produced by the project, the project team is using a
product analysis technique that helps with breaking down the high-level requirements
into the level of detail needed to design the product.
Which of the following is the product analysis technique used by the team?
What might have the manager of the project done differently in this situation?
11/29
Question 46 - Qid 6112064, Schedule Management, 2. Process, 6.0
Project Schedule Management
A project is underway to construct a wind farm in an area with no communication
infrastructure. The plan is to monitor progress and coordinate the scheduling of the
project activities using project management software and provide daily status updates to
the project sponsor at the home office. Two project teams will work and reside onsite in
rotating seven-day tours.
Which of the following is the most likely challenge the teams will face while controlling
the schedule?
What conflict resolution technique did you most likely employ in this situation?
What does the project manager need to obtain first to make this determination?
12/29
approved to repair the defect. After discussing the issue with the team, the project
manager learns that the team never implemented the approved change request.
13/29
You are in the process of establishing a knowledge management system for your project.
Which of the following actions will be the least beneficial in this process?
Which of the following documents would you leave out of the package?
14/29
The following Gantt chart displays the schedule for a software upgrade project. The
system analysis was completed on August 12th, but the system design and development
activities are still in process as of October 3rd. Once the product is developed, the project
team will need to test and deploy it, which must be completed by October 17th. The
method used to determine the earned value is based on percent complete.
15/29
Which of the following would be the most beneficial for this project?
What is the best way for the project manager to address this situation with the team
member?
Which of the following actions is the project manager least likely to perform in this
situation?
16/29
During a bidder conference, a supplier asks why a section is missing from the request for
quotation (RFQ). Upon realizing that the section is indeed missing, the project manager
becomes flustered and stumbles through a brief reply. When the seller responses were
received, all but three prospective suppliers fail to address the missing section.
Which of the following processes describes the work you are performing?
Which of the following components of the template are you likely to tailor the most?
17/29
You meet with your team to determine the life cycle for your project. After analyzing the
best way to define and manage requirements, develop deliverables, handle changes,
control risk and cost, and engage key stakeholders, the decision is made to select a hybrid
life cycle.
With the project life cycle selected, how will the product be delivered?
What is the best approach to determine the team resource requirements for the project?
What action is the project team least likely to take in selecting the best risk response?
18/29
Question 79 - Qid 6113042, Resource Management, 2. Process, 9.3
Acquire Resources
To acquire resources for the project, the project manager consults the resource
management plan. The plan calls for the scrum master to be assigned to the team.
However, the only individual in the company qualified to serve as a scrum master has
already started working on another project, and her functional manager does not
cooperate on a potential resolution.
Where on the Stacey Complexity Model did the team most likely map the project?
(Please note that on the real PMP exam you may be asked to provide your answer by
clicking the correct area in the image. But here in the simulator, we are asking you to
select the answer below.)
19/29
Question 81 - Qid 6113060, Quality Management, 2. Process, 8.3
Control Quality
Your project team members are writing software code together as a pair and reviewing
each other's work to determine if the code conforms to the requirements documentation.
20/29
The scrum master, business analyst, programmers, and testers have been assigned to a
product development project. The performing organization is well-versed with the
traditional waterfall framework but will incorporate scrum for the software development
phase of the project.
What is the best strategy to ensure that all of the scrum roles and responsibilities are
served in the project?
Which agile ceremony can this project incorporate to increase timely cross-functional
communication?
What is the best option to confirm that the information is received and understood?
How might the project manager's role change with respect to integration management?
21/29
A project manager is leading a daily standup meeting with a scrum team as part of the
Direct and Manage Project Work process. A developer raises an impediment stating that
he is struggling with the software code necessary to authenticate users on the sign-in
page. The developer indicates that the impediment could result in a schedule delay to the
current sprint.
Before mandating any agile methods to be used in a project, what should be done first?
Which of the following tasks is the least likely to impact this prioritization?
22/29
Team members are frequently changing during the long timeline of a multi-phase project.
The project manager is questioning whether to include agile practices to accommodate the
changes.
What is the best way for the project manager and team to address the risk of audits
disrupting the project plans?
Which agile practices can the project manager recommend to the team to make certain
that the deliverables are completed and delivered as expected?
What can the project manager suggest the project team members do prior to the daily
standup?
23/29
Question 98 - Qid 6113143, Integration Management, 2. Process,
2.4 Organizational Systems
Projects in a program are using various project management approaches, such as plan-
driven, agile, hybrid. The project teams are complaining that because of that, the team
members must enter the same work, hours, risks, and other data in multiple tools. The
redundant work is impeding on their productivity time.
Which project management approach should the project manager select for this project?
Given the costs, odds, and rewards of high demand and low demand of each route in this
decision tree, what is the expected monetary value of the route to Brazos?
24/29
Senior leadership has returned from a conference where they have learned about the agile
practice of retrospectives. Even though the organization does not manage any projects in
an agile manner, they mandate that from now on this ceremony is included in all projects.
How should the outputs from the retrospectives be stored and managed?
After the team begins working remotely, what will be the best method to understand the
impact of the change on the team's productivity?
What might have been done differently during project planning to avoid this situation?
25/29
Question 106 - Qid 6113623, Schedule Management, 2. Process,
6.3 Sequence Activities
Two team members are arguing over how to organize the work packages in the work
breakdown structure (WBS). One says the work packages should be arranged in the order
the work is planned to be carried out, while the other insists the order of the work
packages in the WBS does not matter. The two ask the project manager for advice.
What is the best course of action for the project manager to address the issues?
How much more will it cost to complete the project if the cost performance remains
unchanged?
26/29
Question 111 - Qid 6125212, Procurement Management, 2.
Process, 12.3 Control Procurements
A major dispute arises with a vendor on a project. The project manager claims that the
vendor has failed to perform its contractual obligations, while the vendor complains that
the project is behind on payments.
What is the best course of action for the project manager in this situation?
Which of the following do you need to guide you through this process?
27/29
Question 116 - Qid 6151383, Cost Management, 3. Business
Environment, 7.2 Estimate Costs
You are in the process of developing an approximation of the monetary resources needed
to complete project work for a large-scale multinational project which will take at least
seven years to complete. Your previous projects have all been domestic with short
timeframes.
As part of the process you are currently performing, what might you need to do differently
compared with your past projects?
28/29
29/29