Invitation to Tender
22 November 2022
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
Page 2 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
1.2 The successful Tenderer will, inter alia, be required to carry out the works (the “Works”) as further
described in Section 2 and Appendix A.
1.3 By this Invitation to Tender (“ITT”), the Employer invites pre-qualified firms (each a “Tenderer”) to
submit tenders (each a “Tender”) in accordance with this ITT for the execution of the Works.
1.4 The Works shall be carried out in accordance with the terms and conditions of the works contract
set out in Appendix C (as ultimately executed with the successful Tenderer, the “Contract”).
1.5 Each Tenderer must submit one Tender, which shall fully comply with all requirements of this ITT,
including those set out in the Tender Content attached hereto in Appendix B.
1.6 Tenderers shall focus on the submission requirements set out in Section 3, however they may
also integrate any other information that is deemed relevant by the Tenderer. Each Tender will be
evaluated on its own merits but will, ultimately, be at the sole discretion of the Employer to accept
or reject.
1.7 The Project Manager for the Project is Faithful+Gould (the “Project Manager”) who shall act for
and on behalf of the Employer in accordance with the terms of the Agreement.
1.8 Words and expressions used but not defined in this ITT shall have the meaning attributed to them
in the Contract. Unless specified otherwise, references to sections, paragraphs and Appendices
are references to sections, paragraphs and Appendices of this ITT.
Page 3 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
2.2 The Successful Tenderer will become an integral part of the Employer’s team and will be expected
to co-ordinate closely its work with that of any other contractors and/or consultants engaged by
the Employer.
2.3 The works will be located at Erth Hotel, Abu Dhabi, Dubai.
2.4 The appointed Contractor shall comply in full with the procedures stipulated by the Employer and
Operator teams.
2.5 Refer to Appendix H for a detailed overview of the site constraints and proposed working hours
which is to accepted by the contractor.
2.6 Refer to Appendix A for detailed description of the Works. A summary of the Works included in
the appointed fit out contractor’s scope is:
General
• Full design completion, responsibility and ownership (to the extent specified in the
Contract)
• Application and gaining approvals from all required authorities, Landlord’s and institutions
– post award
• Applications and issuance of post construction authority, Landlord, institutional approvals
to allow Client operations – post completion
• Testing of all base-build services and production of reports
• Conducting all necessary surveys to produce required drawings and to commence the
works successfully
• Full coordination of design and contractors for any Client direct works
• Demolition, modifications and associated works as required
• The contractor is to propose a phased approach to the project specified in Appendix A,
preferably over five (5) phases spread over eighteen months (18).
Page 4 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
Each Tenderer must include within its returned submission confirmation of any additional
approvals required that are not stipulated in the above list.
2.7 The programme for the works shall be in accordance with the master programme, which indicates
the completion of the works over an 17 - 24 month period preferably divided into phases. This is
to be reviewed by the contractor in accordance with the hotels expectations, which is summarised
as follows;
Page 5 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
Page 6 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
• Financial Offer
• Cash flow (3 Years Audited Financial Records)
3.3.3 In respect of sub-section 1.1.1(a), the original of the Form of Tender attached in Appendix D must
be signed by a person or persons duly authorised to bind the Tenderer to the Tender and the
Contract, if the Tenderer is selected as the Successful Tenderer. Powers of attorney authorising
such person to sign the Form of Tender shall be provided.
Page 7 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
4.1.5 The front cover of the Tender should state “Erth Hotel Guest Arrival Experience
Refurbishment – Main Contractor Contract Tender” and each set of the Tender required by
Sub-section 4.1.4 should be contained in a box labelled the same.
4.1.6 Tenders must be delivered by courier and the Tenderer must obtain written confirmation of such
delivery. Tenders received by any other means will not be accepted.
4.1.7 All queries related to this ITT must be submitted in writing via e-mail no later than COB on 10
December 2022 to jack.delaney@fgould.com and ehab.elbehairy@atkinsglobal.com Requests
for clarification from a Tenderer shall be sequentially numbered (starting from #001) and shall
clearly reference the section number in this ITT to which the request for clarification relates. The
Employer (or the Project Manager on its behalf) reserves the right, where appropriate, to make all
significant clarifications available to all Tenderers.
4.1.8 Except as provided above, Tenderers are not permitted to contact or communicate with any
member of the Employer, its advisors or the Project Manager with regard to any matter relating to
this ITT.
Page 8 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
4.2.3 At any time following the Submission Date, during the Period of Validity, Tenderers’
representatives shall make themselves available to meet with the Employer and its advisers and/or
the Project Manager to finalise and/or clarify any aspect of the Tender, such meeting to be held in
Abu Dhabi (or elsewhere) and with such reasonable notice as is practicable in the circumstances.
All such attendance shall be at the cost of the Tenderer.
4.2.4 The Employer may at any time request clarification, verification or additional information in respect
of any item contained in a Tender. The Tenderer shall be required to respond to any such request
from the Employer within five (5) days of receipt of the request or such shorter or longer period as
may be specified in the request. The Tenderer shall be responsible for all costs associated with
the submission of any requested additional information.
Page 9 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
5.2 The Employer reserves the absolute right to accept or reject any Tender or to annul or cancel the
bidding process and reject all Tenders at any time without any liability to the Tenderer(s) or any
other person and without any obligation to inform the Tenderer of the grounds for its action. Should
the Employer choose to reject any Tender or annul or cancel the bidding process the Employer
shall notify the Tender.
5.3 Should a Tender, as may be modified or amended in accordance with this ITT, prove acceptable
to the Employer, the Employer reserves the right to accept such Tender (but shall be under no
obligation to do so). Such acceptance shall be by way of both the Employer and the Contractor
executing the Contract. The Successful Tenderer will enter into the Contract with the Employer
promptly. Failure to promptly execute the Contract will lead to the Successful Tenderer’s
immediate disqualification.
Page 10 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
6.2 The Employer reserves the right in its absolute discretion, to reject any Tender that it deems not
to be substantially responsive.
6.3 All substantially responsive Tenders will be considered on the basis of amongst other things,
economic merit, technical merit, time for completion and delivery, experience of the Tenderer and
comments made on the Contract. The Employer will take a quality balanced selection approach
to the assessment of all Tenders, considering each Tender as a whole, and shall seek out the
Tender it deems to be the most economically advantageous.
6.4 The Employer, when making a comparative assessment of each Tender, shall take into account
all information provided and all relevant circumstances and shall consider, inter alia, the following:
Criterion
TECHNICAL
Appendix B Reference
Page 11 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
Page 12 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
purpose of preparing a Tender and entering into the Contract. All costs and charges in connection
with the above-mentioned visits shall be borne by the Tenderer.
7.3.2 The Tenderer must examine and consider the Site and its surroundings and must satisfy itself as
to the nature of the existing works and buildings in the vicinity of the proposed Works, the nature
of the existing roads or other means of communication, the access to and egress from the Site
and Works, the available accommodation as regards land for temporary purposes (inside or
outside the Site), the buildings that may be required for temporary purposes, and must make its
own enquiries as to work yard sites and such other additional areas as it may require for temporary
occupation of all the construction, completion and maintenance of the Works described in the
Specification.
7.8 Amendments
The Employer (or the Project Manager on its behalf) reserves the right to issue by addendum
changes to the ITT and/or changes to the Contract, including requiring the Tenderer to provide
the price impact for each requested change in order to permit fair comparison between the
Tenders received from all the Tenderers and/or a BAFO in accordance with sub-section 4.2.5.
Page 13 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
7.11 Confidentiality
The Tenderer acknowledges that all information relating to this ITT comprises confidential
information under the terms of the non-disclosure agreement executed by the Tenderer as a pre-
condition to receipt of this ITT.
Page 14 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
7.12.3 In the event that any Prohibited Act is or has been committed by an employee, servant, agent or
Affiliate of the Tenderer, the Employer, or the Project Manager on its behalf, may give written
notice to the Tenderer of its intention to reject the Tenderer’s Tender and disqualify the Tenderer
from any further involvement in this ITT process, as if the Prohibited Act had been committed by
the Tenderer itself, unless the Tenderer terminates that employee, servant, agent or Affiliate’s
involvement in the Component Project and/or the Project and promptly procures a suitably
qualified and experienced replacement. In the event that the Tenderer fails to do so, the Employer,
or the Project Manager on its behalf, shall proceed to reject the Tenderer’s Tender and disqualify
the Tenderer from any further involvement in this ITT process.
Page 15 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
8.0 Appendices
Page 16 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
Appendix A
SPECIFICATIONS, DRAWINGS AND GUIDELINES
Content:
Items included in this RFP which are to be priced as a tender addendum. Tenderers to review and
familiar with the proposed works.
Page 17 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
Appendix B
TENDER CONTENT
The Tenderer shall submit its Tender and provide all relevant information in accordance with the requirements
of this Appendix B. The Tenderer shall address individually in its Tender the requirements of each of
paragraphs 1 to 3 of this Appendix B, and in the case of paragraph 1 and paragraph 2 the Tenderer shall clearly
reference the responses set out in its Tender to each of paragraphs 1.2.1 to 1.2.10 and paragraphs 2.3.1 to 1
respectively.
1. Volume 1: Executive Summary and Experience
1.1 A brief executive summary setting out the key features and highlighting the main points of the Tender
and the key reasons the Tenderer believes that it should be awarded the Contract.
1.2 The Tenderer should set out the following requested information in a precise and fully responsive
format. In addition to providing the requested information other materials that illustrate the
Tenderer’s professional skills with similar developments would be appreciated. Required information
includes:
1.2.1 full name of Tenderer and address of Tenderer and any affiliated offices;
1.2.2 a project specific organisation diagram of the Tenderer’s proposed organisation and project
resourcing (and in the case of a Joint Tenderer an organisation diagram indicating the relationship
between the joint venture parties) and the curricula vitae of the key members of staff who it is
anticipated will take a position of responsibility in connection with the Component Project;
1.2.3 certified copies of any powers of attorney that are relevant to the ITT or affect the Tenderer, including
a specimen signature in each case of the attorney;
1.2.4 details of the Tenderer’s experience in the Middle East with developments of a size, nature and
complexity similar to that of the Project, including the name of the project, the location, name of client,
references, size of project, use and type of project, date of assignment and status of project;
1.2.5 details of the Tenderer’s current commitments. The original of the Summary of Current Commitments
attached in Appendix F must be signed by a person or persons duly authorised to bind the Tenderer to
the Tender and the Contract, if the Tenderer is selected as the Successful Tenderer.
1.2.6 details of any potential conflict of interest or appearance of impropriety that could be created by the
Tenderer or any potential subcontractors performing the Works and an indication of the procedures will
be followed to detect, notify the Employer of, and resolve, any such conflicts;
1.2.7 details of any pending litigation, regulatory action or other contingent liability that could have an adverse
impact on the Tenderer’s ability to complete the Works; and
1.2.8 the Tenderer must include either: (i) a statement that it accepts the Contract in its entirety, or (ii) an
electronically marked-up (black lined) copy of the Contract, which clearly indicates all deletions and/or
additions desired by the Tenderer and fully explains the Tenderer’s reasons for such deletions and/or
additions.
2. Volume 2: Technical Tender
2.1 Tenderers must set out in their Technical Tender detailed requirements as to how they intend to carry
out the Component Project in accordance with the requirements of the Specification set out in Appendix
A.
2.2 The Technical Tender should demonstrate how the Tenderer intends to use good engineering practice
in the design, procurement and construction of the Works. All proposed equipment and materials
Page 18 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
should be newly manufactured by reputable manufacturers with sufficient operating experience with
regard to the specific equipment / material
2.3 The Technical Tender shall include the following information as a minimum:
2.3.1 an outline methodology statement for carrying out the Construction Works, including:
(a) a complete list of all works and services that will be required for the purposes of carrying out the
Works and details of the Tenderer’s proposed method of carrying out major items of Works.
(b) a proposed approach to risk management including details of a proposed risk management system
and a key risk register;
(c) a list of the identity (including name, address and contact details) and nature of any sub-contractor or
sub-consultant that the Tenderer proposes would undertake any part of the Works as well as a
definition of the proposed sub-contract package.
(d) the Tenderer’s approach to the management and co-ordination of the Tenderer’s own team (including
sub-contractors, sub-consultants and any novated consultants), and management of interfaces with
any other contractors or third parties working on site;
(e) demonstrate it’s ability to sufficiently source such equipment and materials for the purposes of
carrying out the Works
(f) total number of staff members that will be assigned to each major stage of the Component Project,
including proposed numbers of off-site and on-site personnel, to demonstrate the Tenderer’s ability to
source the required level of personnel in terms of quantity and qualifications;
2.3.2 a Works programme (the “Programme”) which will set out all the activities and milestones to be
completed by the Tenderer for the design (to the extent specified in the Contract), execution and
completion of the Works and will include:
(a) the order in which the Tenderer proposes to carry out the Construction Works, including the
anticipated timing of each major stage of the Works;
(b) the key deliverables and milestones required during the preconstruction phase;
(c) the sequence and timing of inspections and testing specified in the Contract;
(d) a detailed critical path programme, using [Primavera Planner Version 3.0 and above or Microsoft
Project 2007] which shall show the critical path, the float and all dependencies and links as well as
early start dates, late start dates, early completion dates and late completion dates;
(e) in developing the Tenderer’s Programme the Tenderer should respect the Component Project Master
Programme included as Appendix E. Any recommended modifications, revisions or improvements (if
needed or desirable for the purposes of ensuring good utility practice) to the Specification as set out
in Appendix A which for the avoidance of doubt the Employer shall be under no obligation to take
account of in the event that the Tenderer becomes the Successful Tenderer;
2.3.3 a draft operational health safety and environmental plan for use in connection with the Works;
2.3.4 a statement to the effect that the Tenderer (or an appropriate representative) has visited the Site and
that the Tenderer has no queries or qualifications on any matter concerning the Tender in connection
with the prevailing Site conditions.
3.1 Payment for the Works will be on the basis of a lump sum fixed price (the “Contract Price”) for the
design (to the extent specified in the Contract), construction and execution of the Works and the
remedying of any defects therein which shall be payable in monthly instalments based on valuation of
the Works carried out each month or percentage of Works complete verified by inspection of the
Works.
Page 19 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
3.2 For the purpose of ascertaining its proposed Contract Price the Tenderer shall complete and provide
a Bill of Quantities (“BoQ”) by completing the format Bill of Quantities included as Appendix G. Note
that the Tenderer shall update, amend or modify the format Bill of Quantities as required to submit its
lump sum fixed price to comply with the ITT requirements.
3.3 The Tender shall provide a forecast cash flow broken down into estimated monthly instalments from
the date of execution of the Contract up to the Time for Completion.
The Tenderer should take care not to make any arithmetical errors in arriving at its Contract Price. If
errors are made, the Tenderer will be obliged to stand by its quoted Contract Price even if this total is
less than the actual sum of all individual prices. However, should the quoted Contract Price be more
than the arithmetically corrected sum, the Tender will be accepted on the basis of the arithmetically
corrected Contract Price.
Page 20 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
Appendix C
FORM OF CONTRACT
Page 21 of 28
CONTRACT AGREEMENT
BETWEEN
AND
_________________________
FOR
____________________________________
Page 1 of 5
____________________________ CONTRACT AGREEMENT
Between
M/s. The Armed Forces Officer Club Hotel (“the Employer") duly licensed under the Laws of
Abu Dhabi, pursuant to License No [CN-2240700], whose address is Al Khaleej Al Arabi
Street, P.O. Box: 29810 Abu Dhabi, UAE (which expression shall include its successors in title
and permitted assignees) of the one part
And
_________________ (the "Contractor") duly licensed under the laws of the Emirate of Dubai,
UAE, pursuant to license No. [__________], and whose address
__________________________________________
Whereas
2. The Employer hereby covenants to pay the Contractor in consideration of the execution
and completion of the Works and remedying any defects therein the Contract Price of
AED ______________ (UAE Dirhams ________________________ only ) or such other
sums as may become payable under the provisions of the Contract at the times and in
the manner prescribed by the Contract. AED ______________ (UAE Dirhams
_______________________________________only) of this Contract Price is Provisional
Sums, as further detailed in the Bill of Quantities (Volume 4). These Provisional Sums
may or may not be instructed to be expended, if for any reason any of the Provisional
Sums is not instructed to be expended then that amount shall not be paid to Contractor
and the Contract Price will be reduced by the same amount.
3. The following documents shall be deemed to form and be read and construed as part of
the Agreement, viz.
Page 2 of 5
(a) Contract Agreement
(b) Appendix to Tender
(c) The Letter of Acceptance
(d) The Particular Conditions;
(e) The General Conditions (The Conditions of Contract- FIDIC Condition of Contract
Red Book 1st Edition 1999);
(f) The Specification - /RFIs / Post Tender Clarifications
(g) The Drawings
(h) Bills of Quantities
(a) this Contract will be interpreted in accordance with the Terms and Conditions.
(b) Capitalised terms have the meaning given in the General Conditions of Contract
as amended in the Particular Conditions; and
2. CONTRACT DOCUMENTS
This Contract consists of the following documents. Such documents shall be deemed to
form and be read and construed as part of this Contract Agreement. Any inconsistency
or discrepancy between the documents shall be resolved in the following order of
priority:
(a) Contract Agreement;
(b) The Appendix to Tender;
(c) The Letter of Acceptance and its Annexures (other than the Appendix to Tender);
(d) The Particular Conditions;
(e) The General Conditions (The Conditions of Contract- FIDIC Condition of Contract
Red Book 1st Edition 1999);
(f) The Specification clarifications and communications (Volume 2);
(g) The Drawings (Volume 3); and
(h) The Bill of Quantities (Volume 4).
3. TERM
4. CONSIDERATION
In consideration of the Contractor's satisfactory performance and successful completion
of Works as required under the Contract, the Employer shall pay the Contractor the
Contract Price as adjusted in accordance with the Contract.
Page 3 of 5
In consideration of the payments the Employer shall pay to the Contractor, the
Contractor accepts all risks and all costs of executing and completing the Works,
remedying any defects and otherwise complying with its obligations under the Contract,
except to the extent the Contract expressly provides otherwise.
5. WORKS
a) The Contractor shall carry out the Works in accordance with this Contract.
b) If before this Contract becomes effective, the Contractor performs any of the
Works following instruction to do so from the Employer, those works shall be
governed by this contract and shall be included in the Contract Price.
8. BASE DATE
The Base Date is _____________________.
9. ENTIRE AGREEMENT
The Contract Constitutes the entire agreement between the Client and the Contractor
with respect to the subject matter of the Contract and supersedes all prior arrangements,
representations communications negotiations agreements and contracts (whether written
or oral) made between or entered into by Parties prior to the date of execution of
Contract.
This Contract is governed by the laws of the Emirate of Abu Dhabi and the federal laws
of the UAE applicable to Abu Dhabi.
Page 4 of 5
In witness whereof the Parties hereto have caused this Agreement to be executed the day and year
first before written.
Executed as an agreement
Name: Signature:
Title: Stamp:
Name:
Address:
The Contractor
Name: Signature:
Title: Stamp:
Name:
Address:
Page 5 of 5
APPENDIX TO TENDER
The Employer 1.1.2.2 &1.3 Armed Forces Officers’ Club & Hotel,
P.O. Box 29810,
Abu Dhabi, UAE
Tel. +971 2 441 5900
Time for Completion 1.1.3.3 The time for completion for the
entirety of the work is ______
calendar days from ______
Address for the Recipients 1.3 The Employer +971 2 441 5900
Communications The Engineer +971 2 627 0999
Law and Language 1.4 This Contract is governed by the laws of the
Emirate of Abu Dhabi and the federal laws of
the UAE applicable to Abu Dhabi.
The language shall be English.
Delay Damages for the Works 8.7 AED _________ per day
Limit of Retention Money 14.3 10% (ten percent) of the Contract Price
The following Particular Conditions supplement, amended and, in case of any contradiction, take precedence over the Conditions of
Contract for Building & Civil Engineering Works Designed by the Employer First Edition 1999 (FIDIC Red Book 1999 General
Conditions).
1.1.1.4 “Letter of Tender” Replace all references to “Letter of Tender” with “Form of Tender to which
the completed Appendix to Tender is affixed”.
1.1.1.7 “Schedules” Delete and replace with “means the documents in Part 1 and 2 of the Tender
Documents completed by the Contractor and submitted with the Form of Tender as
included in the Contract, including data, lists, Bill of Quantities and schedules of
payments and/or prices.”
1.1.1.11 “Collateral Warranty” Add new definition “means an agreement, in the form as found in Appendix F of Part
2 of the Tender Documents, pursuant to which the Contractor or a Subcontractor
warrants to a third party or the Employer respectively that its obligations and duties in
respect of the Works arising pursuant to a primary contract and/or at law have been
fully and properly performed in accordance with such contract and laws.”
1.1.1.12 “Rules” Add new definition “means the Arbitration Rules of the Abu Dhabi
Commercial Conciliation and Arbitration Centre.”
1.1.3.1 “Base Date” Replace “28 days prior to the latest date for submission of the
Tender” with “set out in the Contract Agreement.
1.1.6.5 “Laws” Replace with “means any government legislation, statutes, ordinances, decrees and
the like and the regulations and bylaws of any legally constituted authority of the
Country, applicable in the Emirate of Abu Dhabi.”
Replace with “means not reasonably foreseeable as at the date of submission the
1.1.6.8 “Unforeseeable” Tender by a competent contractor experienced in carrying out works of a similar size,
type, nature and complexity to the Works. The term of Unforecastable doesn’t include
any existing MEP services for the already constructed buildings or for buildings under
construction "
1.1.6.10 “Milestones”
“Milestones” means the milestones for the completion of the Works or part of the
Works as identified in Appendix to Tender.
1.1.6.11 “Project Manager” “Project Manager” means a person responsible for managing the Project on behalf
of the Employer.
(a) the form and nature of the Site, including ground surface
conditions, physical obstructions and pollutants, sub-surface geology and
conditions and all other physical conditions and
1 of 26
characteristics on, above or below the surface which may affect
the performance by the Contractor of its obligations under this Contract;
(b) the general and local conditions for environment, meteorological, seismic
activity, hydrological, hydrographic, climatic conditions, ocean and sub-sea
conditions; and
(c) the availability and quality of both permanent and temporary access,
accommodation, facilities, personnel, labour, power, transport, water, waste
disposal, storage or materials and all other services and utilities, necessary
for the performance of the Works
in accordance with the Contract.
1.4 Law and Language Delete sub-clause and replace with “The Contract Documents shall be drawn up in
the English language and the ruling language shall be English. Notwithstanding the
ruling language of the Contract, wherever any Contract Documents or any other
documents received or to be submitted by the Contractor are written in any other
language or are required to be so written, the Contractor shall procure a translation
thereof and shall bear the costs associated therewith.
The Contract shall be governed by and construed in accordance with the Laws.”
1.5 Priority of Documents Delete the existing clause and replace with the following:
“The Employer and the Contractor confirm that they are not aware of any ambiguities
or discrepancies in the several documents forming the Contract Documents. Without
prejudice to the Employer’s and Contractor’s confirmation that they are not aware of
any ambiguities or discrepancies, the several documents forming the Contract are to
be taken as mutually explanatory of one another but in the event that the Employer or
the Contractor become aware of ambiguities or discrepancies the same shall be
notified by the Party discovering the ambiguity or discrepancy to the other Party and
the Engineer shall issue any clarification or instruction using the following order of
priority of documents, which clarification or
2 of 26
instruction shall be complied with by the Contractor at no cost to the Employer:
1.7 Assignment Delete this clause in its entirety and replace with:
Neither Party shall assign the whole or any part of the Agreement or any benefit or
interest in or under the Agreement, except that:
(a) either Party may assign the whole or any part of the Agreement or any
benefit or interest in or under the Agreement with the prior agreement
of the other Party, at the sole discretion of such other Party; and
(b) the Employer may, without the consent of the Contractor assign or
novate the whole or any part of the Agreement or any of its benefit or
interest in or under the Contract at its sole discretion in favour of:
(i) any of its
(ii) Affiliates;
(iii) any entity established for the purpose of executing the Project or
any other purchaser of the Works or any part thereof;
(iv) any contractor engaged to execute the Works or any part
thereof; or
(v) any lenders providing financing for the Project; (Each of the
above a "Permitted Assignee").
1.8 Care and Supply of In the second line, after the words “two copies” add the words “plus a printable
Documents electronic copy”.
1.9 Errors in the Employer’s Add the following paragraph in the beginning of the clause:
Requirements
The Contractor acknowledges and agrees that it has checked the Employer’s
Requirements and the Contractor’s Proposal consider all necessary corrections and
rectifications for any error that experienced contractor may find in the Employer’s
Requirements; and that the Contractor has allowed for all related risks of errors or
omissions in the Employer’s Requirements in the Contract Price.
Delete the words “plus reasonable profit” at Sub-Clause (b).
1.13 Compliance with Laws Deleted “the Employer shall indemnify and hold the contractor harmless against and
from the consequences of any failure to do so”
3 of 26
Insert after the word Laws in (b) the second line “and any other statutory, municipal
rules and regulations, and any other laws of other countries which have a connection
with the Works.
1.14 Joint and Several liability Add after the last paragraph:
“The Employer shall not be bound by any terms or provisions of any joint venture
agreement”
1.16 Confidentiality “All information obtained by the Contractor in the course or conduct of the
contract shall be held confidential and shall not be divulged by the contractor to any third party
save to the extent necessary, to effect the execution of the contract and then only on the basis
that the recipient of such information shall be bound by similar confidentiality obligations to
those undertaken by the contractor hereunder. Provided that the contractor notifies the
Employer with the details of such information and obtains his approval on such disclosure.
Provided however that this obligation shall not apply to information which is or shall become
part of the public domain otherwise than in consequence of a breach of the Contractor of its
obligations under this clause;
The Contractor is deemed aware about the specialty and security rules, of the Project, hence
any photos or videos are not allowed to be published without a written approval from the
Employer.
The Contractor is obliged to disclose to the Employer or the Engineer all documents and
information required for the purpose to verify the Contractor's compliance with the laws and
Contract
The Contractor shall ensure that the provisions of this clause are incorporated in any sub-
contracts or supply orders and that the employees, agents or representatives of all or any of
the sub-contractors or suppliers comply with the same. This clause shall remain binding on the
Contractor notwithstanding the completion or termination or determination of this Contract for
any reasons.”
1.17 Third Party Right The Contractor acknowledges that it provides the Works to the benefit of Third
Parties which will be but not limited to the facility management company, subsidiary, a
company the Employer is a partner in it, any other beneficiary that has rented or acquired
part of the Works .The Contractor warrants the Third Parties that as at the date of the issue
of the Taking over Certificate that the Contractor has completed the Works in accordance
with the Contract, and in case of any defect or breach to this Clause, the Contractor shall be
liable to the Third Parties for the costs of the repair, renewal, reconstruction, or
reinstatement of any part of the Works.
2.1 Right of Access to the Add “sufficient” before the right of access in paragraph 1 and 2.
Site
Delete the words “plus reasonable profit” at Sub-Clause (b).
4 of 26
2.2 Permits, Licences or Add “the Contractor is responsible for obtaining all and any municipal and
Approvals authorities approvals on the design, certificate of occupation and any other similar
approvals, permits, certificates and licenses regarding the design and construction,
completion and I or occupation of the Works. The Contractor shall however be deemed
to have satisfied himself as to which permits, licenses and approvals may be required by
the laws and regulations of Abu Dhabi and UAE that fit into the purpose.”
2.4 Employer’s Financial Delete Sub-Clause as well as all references made to it in the general and particular
Arrangements conditions.
2.5 Employer’s Claim Delete the words "only" and "or to otherwise claim against the Contractor, in
accordance with this Sub-Clause" in the last paragraph.
3.1 Engineer’s Duties and Delete the second sentence of the third paragraph “If the Engineer required to obtain
Authority the approval of the Employer before exercising a specified authority, the requirements
shall be as stated in the Particular Conditions.”
“Notwithstanding the obligation of the Engineer, as set out above, to obtain approval,
if, in the opinion of the Engineer, an emergency occurs affecting the safety of life or of
the Works or of adjoining property, he may, without relieving the Contractor of any of
his duties and responsibilities under the Contract, instruct the Contractor to execute all
such work or to do all such things as may, in the opinion of the Engineer, be necessary
to abate or reduce the risk. The Contractor shall forthwith comply, despite the absence
of approval of the Employer, with any such instruction of the Engineer. The Engineer
shall determine an addition to the Contract Price and Contract Period, in respect of
such instruction, in accordance with Sub-Clause 3.5 [Determinations] and shall notify
the Contractor accordingly, with a copy to the Employer.”
“The Engineer is required to obtain the written approval of the Employer before
exercising the following authority:
7. issuing the Final Payment Certificate under Sub-Clause 14.13 [Issue of Final
Payment Certificate]
5 of 26
8. determining and / or awarding any extension to the Time for
Completion; settling any claims
3.2 Delegation by the Engineer In the second line, after the first sentence add the following:
“The Engineer shall notify to the Contractor the names, duties and scope of authority of
such persons.”
In the first line, insert “upon Employer’s Approval” after the words “from time to time”
3.4 Replacement of the Delete Sub-Clause 3.4 in its entirety and replace with the following:
Engineer " If the Employer intends to replace the Engineer, the Employer shall, not less than 14
days before the date of replacement, give notice to the Contractor of the name,
address and relevant experience of the intended replacement Engineer. If the
Contractor reasonably objects to such replacement engineer, the Contractor shall
within 7 days of receipt of the Employer's notice provide to the Employer a detailed
substantiation in writing of such objection. Upon receipt by the Employer of such
detailed substantiation, the Employer shall in its sole discretion make a determination
regarding the suitability of the replacement engineer.
The Employer may from time to time employ a Project Manager who shall, in addition to
the Engineer, be responsible for managing the Project on behalf of the Employer. The
nature and scope of the Project Manager shall be determined by the Employer from time
to time and will be notified to the Contractor. The Contractor shall comply with any and all
directions and instructions of the Project Manager regarding the performance of the
Works."
“the Engineer shall not be bound to seek agreement unless the Contractor has complied
with the procedure set out in Clause 20.1.”
“The Contractor shall allow for the provision, erection, maintenance, daily
operation and dismantling of Offices for the Engineer in accordance with the
Specification.”
6 of 26
4.1 Contractor’s General Insert the words "exercising the skill, care and diligence reasonably to
Obligations be expected of an appropriately qualified contractor with experience in carrying
out and properly completing works of a similar type, purpose, nature and
complexity to the Works and otherwise" after the
words "execute and complete the Works" in paragraph 1. At the
“The Contractor shall notify the Engineer, with a copy to the Employer of any
facts, matters or circumstances of which the Contractor becomes aware and
which the Contractor knows or reasonably to know, threaten the Employer with
loss or damage or threaten the health, safety or welfare of any person engaged in
connection with the performance of the Works or any user of the Works. Such
notification shall not prejudice the liability or responsibility of the Parties for or in
respect of the facts, matters or circumstances so notified.
In the event that the Contractor has or believes to have any right or entitlement
pursuant to the Contract or otherwise, the Contractor shall in all cases take such
steps (if any) which can reasonably be taken to eliminate or mitigate any such
entitlement and any additional losses may be incurred by the Employer, to the
extent that such elimination or mitigation can be achieved without any additional
Cost to the Contractor.
"(e) the Contractor shall ensure that any design is prepared by suitably qualified
designers who are engineers or other relevant professionals;
the Contractor shall obtain the Engineer's consent to the Contractor's appointment of
any designer and/or design sub-contractor before such parties undertake any design
works;
(f) the Contractor shall be solely responsible for the design regard less of
whether such design is prepared by any sub-contractor;
(g) the Contractor shall ensure that the designers are available to attend
discussions with the Engineer at all reasonable times during performance of
the works;
(h) subject to Sub Clause 18.5, the Contractor shall effect and maintain, and
shall ensure any design sub-contractor effects and maintains, professional
indemnity insurance on terms reasonably acceptable to the Employer with a
limit of indemnity not less than the amount stated in the Appendix to Tender;
(i) the Contractor must maintain such professional indemnity insurance in
full force and effect throughout the period of its liability under the Contract
and under any Laws; and
(h) The Contractor shall procure a collateral warranty in a form attached here in
Appendix F, from the sub-consultant , or sub- contractor who has completed the
design in favour of the Third Parties and the Employer"
4.2 Performance Security Revise second paragraph from “the Particular Conditions” to “Annex of these
Particular Conditions”.
7 of 26
The Contractor shall deliver the Performance Security to the Employer within 14
days of the date of the Contract Agreement and shall send a copy to the Engineer.
The Performance Security shall be issued by an entity and from within a country (or
other jurisdiction) to be approved by the Employer.
"The amount of the Performance Security shall be increased within 28 days of the
written request of the Engineer, so that it corresponds to any increase in the amount
of the Contract Price and adjusted pursuant to the Contract and in such
circumstances the Contractor shall provide an amended Performance Security in
the correct amount within such period. The cost shall be borne by the Contractor,
including any extensions to the period of validity of the guarantee and increases in
the amount of the guarantee."
4.2C Contractors Further “The Contractor warrants to the Employer and the Third Parties (as defined by:
Warranties facility management, maintenance company, a contractor performing other works
related to the Works, that In carrying out the execution and completion of the works,
and any design which is the responsibility of the contractor, he has exercised and
shall exercise the skill, care and diligence reasonably to be expected of an
appropriate qualified contractor with experience in carrying out such work for
projects of an similar type, nature and complexity to the works. In carrying out the
execution and completion of the works and any design which is the responsibility of
the contractor he has not, and shall not, specify for use of permit to be used any
materials which at the time the works are being carried out are generally accepted
or reasonably suspected of being prohibited materials, and shall, when requested
issue to the employer may require a certificate that no such materials have been
specified for use or permitted to be used;
8 of 26
The design, execution and completion of the works will be carried out in such a way
as to ensure the full, efficient, economic and safe commercial operation with the
minimum interruption for maintenance or repair.”
4.4 Subcontractors Add the words “Materials and Plant supplied by and” after the words “responsible
for the” in the second paragraph. Add the words in brackets “(including a nominated
sub-contractor)” after the words “any Sub-contractor” in the second paragraph.
Add the words “The following condition shall apply to sub-contracting” in the second
paragraph.
Add new paragraph “The contractor shall be responsible for the payment of all sub-
contractors pursuant to the terms of the relevant subcontracts and evidence of
payment at the Engineer’s request.
“For the avoidance of doubt the Contractor shall be responsible for the acts
of defaults of any nominated Sub-contractor, his agents or
employees, as if they were the acts or defaults of the Contractor”.
4.6 Co-operation Add the words “of the Country” after the words “public authorities” in
sub-section (c) and add the words “whether or” after the word “work” in the sentence
after sub-section (c).
Add “subject to prior approval of the Employer” after “any such instruction.”
“The Contractor has acknowledged that other contractors and consultants work in
areas within the vicinity of or inside the Site; and that he can and could reasonably
foresee the activities of the Employer’s personnel, and the other contractors and
personnel of public authorities or public utility service providers, referred to in the
Contract.
9 of 26
The Contractor shall co-operate fully and pro-actively with, and co- ordinate his
activities with, all contractors, consultants and suppliers employed by the Employer
in relation to the project. The Contractor acknowledges that the Employer may
engage other contractors,
consultants and suppliers identified by the Employer or the Engineer, or
subsequently notified to the Contractor by the Employer or the Engineer, who may
be employed in the execution of works or services on or near the Site and that the
Contractor reasonably foresees the activities and/or works and services of those
other contractors, consultants and suppliers. The Contractor shall attend the
Employer's project meetings at the time and venues specified by the Engineer, the
Employer or the Project Manager. The Contractor shall ensure that the
Contractor's Representative attends all such meetings, together with all of the
Contractor's other personnel and/or the Subcontractor's personnel as are
necessary to resolve the issues raised in any agenda for such meetings."
4.7 Setting Out Delete the words “plus reasonable profit” in Sub-Clause (b). Insert at
“In the inspection of the Site, the Contractor will be deemed to have conducted a
visual survey of the site to determine the physical condition of the site, including the
position of any underground and above ground services and drainage visible from
a visual survey and will carry out the works as per client’s design.” The Contract
Price shall be deemed to be inclusive of all costs which may be incurred in carrying
out the Works including any diversions thereof and the costs of the Contractor's
operations in the vicinity of any such services, unless otherwise provided for in the
Employer's requirements as set out in the Drawings or the Specification.”
4.10 Site Data Delete the following from the first line of the second paragraph:
“To the extent which is practical (taking account of cost and time), the” Add to the first
“The”
“The Contractor shall be deemed to have obtained and allowed for all information
as to the risks and other contingencies in connection with the Works; and inspected
and examined the Site and its surroundings and conditions and to have satisfied
himself before the date of the Contract as to the form and nature of the Site, the
nature and difficulty of the work and Materials necessary for the completion of the
Works (any information in connection therewith may have been provided by or on
behalf of the Employer being provided by way of information only without warranty
or representation as to its accuracy, reliability or completeness), the means of
communication with and restrictions of access to the Site, the accommodation he
may require, and in general to have obtained for himself all necessary information
as to risks, contingencies and all other circumstances influencing or affecting the
Works. The Contractor shall not be entitled to any extension of time or
10 of 26
to any additional payment on grounds of any misunderstanding or misinterpretation
of any such matter, nor shall the Contractor be released from any of the risks
accepted or the obligations undertaken by him under the Contract on the grounds
that he did not or could not have foreseen any matter which might affect or have
affected the execution of the Works.”
(a) the form and nature of the Site, including Site Conditions;
(b) the extent and nature of the work and Goods necessary for the execution and
completion of the Works and the remedying of any defects;
(c) the Laws, procedures and labour practices of the Emirate of Abu Dhabi, the
United Arab Emirates and relevant Authorities; and
(d) the Contractor's requirements for access, accommodation, facilities, personnel,
power, transport, water and other services.
4.12 Unforeseeable Physical To the end of the second paragraph, add the words “but, in any event, not later than
Conditions 5 days after first encountering the adverse physical condition”.
“In the inspection of the Site, the Contractor will be deemed to have conducted a
survey of the site to determine the physical condition of the site, including the
position of any underground and above ground services and drainage visible from
a visual survey and will carry out the works as per design documents.” The Contract
Price shall be deemed to be inclusive of all costs which may be incurred in carrying
out the Works including any diversions thereof and the costs of the Contractor's
operations in the vicinity of any such services, unless otherwise provided for in the
Employer's requirements as set out in the Drawings or the Specification.”
“The Contractor shall co-operate with the relevant traffic authorities including,
without limitation, the Abu Dhabi Municipality and Department of Civil Aviation to
accomplish the foregoing”.
“Any failure by the Contractor to comply with this Sub-Clause shall, without
prejudice to any other remedies and/or provisions of the Contract, be taken into
account by the Engineer in any assessment of the Contractor’s entitlement to an
extension of the Time for Completion and/or any additional payment.”
“Any other matters set out in the Contract and other information reasonably required
by the Employer and notified to the Contractor in
advance of the relevant monthly report."
11 of 26
4.23 Contractor’s Operations Add "within 7 days." after the end of "The Contractor shall leave that
on Site part of the Site and the Works in a clean and safe condition." in the second third
paragraph.
"The Contractor shall not use any part of the Site for any purpose not connected
with the execution of the Works without the prior approval of the Employer. The
Contractor shall not destroy, damage or pull down any plant, wall or building outside
the area where the Works are being performed (but within the Site) without the prior
consent of the Employer.”
“The Contractor shall treat the details of the Contract as private and confidential,
save in so far as may be necessary for the purposes thereof, and shall not publish
or disclose the same or any particulars thereof in any trade or technical paper or
elsewhere without the previous consent in writing of the Employer or the Engineer.
If any dispute arises as to the necessity of any publication or disclosure for the
purpose of the Contract the same shall be referred to the Employer whose
determination shall be final.”
“The Contractor shall provide Site Notice Boards in accordance with the
Specification.”
“Contractor/ suppliers/ bidders acknowledge that the import and Custom laws and
regulations of the United Arab Emirates shall apply to the furnishing and shipment of any
products thereof to the United Arab Emirates.”
4.28 Product Guarantees As a precondition to the issue of a Taking Over Certificate, the Contractor shall provide
the Employer with product guarantees/warranties for all significant items of Plant,
Materials and equipment installed as part of the Works as prescribed or required by the
Specification. The coverage period of such guarantees/warranties shall be in line with
required period set out in the Specifications, the product guarantees shall be in favour of
the Employer and any Beneficiaries specified by the
Employer. Without prejudice to any other right or remedy the Employer may have, the
Employer shall be entitled to withhold the sum often percent (10%) of the value of the
works or goods to which a product guarantee relates from any Payment Certificate for
each and every product guarantee which has not been provided by the Contractor.
4.29 Employer’s policies The Contractor acknowledges that it has received copies of the Employer's policies. In
carrying out its obligations under the Contract, the Contractor
shall comply with the Employer's policies.
12 of 26
5.1 General Design Delete “within the period stated in the Appendix to Tender, calculated
Obligations from the Commencement Date” in the third paragraph and replace it by “within 14
days from the Commencement Date” Delete “(taking account of cost and time)”
after the word “that” in the last paragraph. Insert the following after “Tender,” in the
last paragraph:
“and the Employer’s personnel have done material change in the Site after the Base
Date”
6.6 Facilities for Staff and Add new paragraph at the end of the clause:
Labour
“Facilities for the use of persons employed on the Works shall be provided and
maintained by the Contractor to the extent and in such a manner and at such
places as shall be approved by the Engineer, Authorities, HSE, etc. and all
persons connected with the Works shall be required to use them. The Contractor
shall make all temporary arrangements for the proper discharge and removal of
sewage, and shall maintain the same to the satisfaction of the Engineer as long
as they may be required.
The Contractor shall, having regard to local conditions, provide on Site adequate
supply of drinking water and other water for use of his staff, labour and Engineer’s
/ Employer’s staff.”
13 of 26
“The Contractor shall ensure that his Sub-contractors also familiarise themselves
with these Particular Conditions.”
8.1 Commencement of Delete the first paragraph and replace with the following:
Works
"The Commencement Date shall be the date stated in the Appendix to Tender."
“the order in which the Contractor intends to carry out the Works high lighting all
critical activities, including all Milestones and Milestone
14 of 26
Dates, the anticipated timing of each stage of design (where relevant to the
Works), Contractor's Documents, procurement, manufacture,
inspection, delivery to Site, construction, erection, testing,
commissioning and trial operation.”
“Failure of the Contractor to submit the programme of works, cash flow and any
other information reasonably required by the Engineer or the Employer or any
update thereof may result in the withholding of any payments due to the Contractor
until the programme or subject monthly update has been submitted.
"The Contractor shall be solely responsible for each revision of the Contractor's
programme and construction scheduling to be done for the Project and for
completing the Works on or before the Time for Completion. The Engineer's and I
or the Employer's approval of the Contractor's programme from time to time shall
not in any manner relieve the Contractor from any of his responsibilities or
obligations under the Contract."
The programme of works shall be used as the basis for progress reporting and be
updated monthly to reflect current forecasting.
8.4 Extension of Time for In Sub-Clause (a), add “to the extent that the varied works have caused the
Completion Contractor’s delay, if any,” after “Variations”
Delete the following words from sub-paragraph 8.4(e): "or the Employer's other
Contractors on Site".
(i) the Contractor has made reasonable and proper efforts to mitigate
such delay;
(ii) the Contractor shall not be entitled to a separate extension of time for
each one of several causes of delay running concurrently;
15 of 26
(iii) the Contractor has demonstrated, to the reasonable
satisfaction of the Employer (which may include, if requested, a critical
path analysis, as-built schedule, window analysis, and time impact
analysis, to the level of detail specified by the Employer), that the delay
was on the critical path of the programme of the Works;
(iv) the Contractor can demonstrate, to the reasonable satisfaction of the
Employer, that the Contractor has taken all reasonable steps to mitigate
the costs and losses caused by the delay
(v) any such delay which is concurrent with another delay for which the
Contractor is responsible shall not be taken into account; and
(vi) the Contractor has complied with Clause 20.1 [Contractor’s Claims].”
8.5 Delays Caused by In sub-paragraph 8.5(b), insert "such that the Time for Completion is delayed" after
Authorities the words "disrupt the Contractor's work"
8.8 Suspension of Work Delete Sub-clause in its entirety and replace with:
“The Employer may at any time and from time to time, instruct the Contractor to
suspend progress of part or all of the Works, and may at any time after any such
instruction give an instruction to the Contractor to proceed with normal working.
During any such suspension, the Contractor shall protect, store and secure such
part of the works against any deterioration, loss or damage, and (unless otherwise
instructed by the Employer) shall maintain the Contractor’s personnel ready to
resume normal working within seven days after receipt of an instruction from the
Employer to proceed.
The Engineer may also notify the cause for the suspension. If and to the extent that
the cause is notified and is the responsibility of the Contractor, the following sub-
clauses 8.9, 8.10 and 8.11 shall not apply.”
“If the Contractor contravenes health and safety requirements during any construction
activities, the Engineer shall have the right to suspend the Works or any construction
activities in such part or parts affected by the Contractor's default until he provides the
health and safety requirements to the satisfaction of the Engineer. The Contractor
shall not be entitled for any kind of claims whatsoever due to such
suspension.”
16 of 26
8.10 Payment for Plant and Add sub paragraph 8.10 (c)
Materials in Event of “the Plant and Materials are ready to be delivered to the Site”
Suspension
“The Contractor shall operate an "early warning" system whereby the Contractor
shall notify the Employer and the Engineer as soon as it is aware of any matter
adversely affecting or threatening the Works and/or the project and/or a Party's
performance under the Contract and (within the scope of its agreed role, expertise
and responsibilities) shall include in such notification, proposals for avoiding or
remedying such matter. The Engineer shall convene a meeting of the Parties within
seven (7) days from the date of any such notification to discuss with the Parties
and subsequently issue a direction on an appropriate course of action unless the
Parties and the Engineer agree such course of action without a meeting.”
8.14 Meetings “The Contractor will attend weekly progress meetings or any other meeting with the
Employer’s Personnel to be held at a mutually agreed time to review programme,
procurement, outstanding requests for inspection, approvals and report generally
on the progress of the works, encumbrances and difficulties. Where delays are
forecast the Contractor will prepare interim programmes to identify actions to
address delay.
In addition the Contractor will attend and report to a monthly executive meeting
summarizing the progress of the Works, issues of the day and forecast completion.
An agenda for all meetings to be mutually agreed between the Parties.”
10.1 Taking of the Works and Insert the following after the end of the first paragraph of Sub-Clause 10.1:
Sections
"provided however that it shall be a condition precedent to the issue of the
Taking-Over Certificate for the Works that the Contractor shall have:
(a) provided the Employer with the as-built documents, the operation and
maintenance manuals and training which the Contractor is obliged to provide
pursuant to this Contract;
(b) all applicable Laws regarding the use and occupation of the Works or
relevant Section have been complied with and any and all permits and no
objection certificates have been obtained and passed on to the Employer;
(c) all direct agreements requested by the Employer pursuant to the Contract
prior to completion and take over have been executed and provided in favour of
the Employer and/or any third party identified by the Employer;
(d) the Works or relevant Section have passed the Tests on Completion and duly
certified reports of the tests have been forwarded to the Employer and the
Employer or the Engineer have endorsed the
17 of 26
Contractor's test certificate or issued a certificate to the Contractor to that effect in
accordance with Clause 7.4 [Testing];
(e) all costs, expenses and damages payable by the Contractor to the
Employer on the date on which the Employer issues Taking Over
Certificate have been paid in full;
and any and all of the stipulations identified in the Contract as being pre-requisites
of Taking Over have been satisfied.
10.2 Taking Over of Parts of Delete the words “plus reasonable profit” and “and profit” from the fourth paragraph.
the Works
10.3 Interference with Tests on Delete the words “plus reasonable profit” from Sub-Clause (b) in the third paragraph.
Completion
10.5 Access to install Equipment The Contractor shall co-ordinate his activities with the Employer in order
and Fit-out to provide other Employer`s contractors and suppliers
reasonable access to the Site to commence and complete their works by the date(s)
notified by the Employer.
The Contractor acknowledges and agree to coordinate with these Employer's other
contractors and suppliers who may work in the same time with the Contractor in the
same area of works and buildings.
The Contractor shall allow in his programme of works reasonable time allocated for
such contractors. the Employer will provide the Contractor with a list of the contracts
already placed or to be placed with those contractors and suppliers within the time of
programme submission under clause 8.3.
Prior to the issue of a Taking-Over Certificate, the Contractor shall retain control of and
responsibility for the Site and the Works during the time such relevant works are being
undertaken ."
11.1 Completion of Outstanding Delete the last two lines of the Sub-Clause (b) and replace with “Upon the failure of
Work and Remedying any part or component or the appearance of any defect of the Permanent Works during
Defects the Defects Notification Period, the Contractor shall repair or replace such defective
part or component as soon as reasonably practicable after receiving notice from the
Engineer or the Employer.”
11.2 Cost of Remedying Defects Add after the word “Contractor” in the third line the words “who shall also pay all the
costs of the Engineer incurred in the inspection thereof”
18 of 26
apply and the entitlement, if any, of the Contractor to additional payment
thereunder.”
11.6 Further Tests Add the words “or affects” in the first line of the first paragraph after the
words “may affect”.
"After the Performance Certificate has been issued, each Party shall remain liable for
the fulfilment of any obligation which remains unperformed at that time and for on-
going obligations; such on-going obligations at that time include, for the avoidance of
doubt, the provision of collateral warranties under sub-paragraph 11 .12 [Collateral
Warranties] which the Contractor shall procure and provide them to the Employer after
the issue of the Performance Certificate. For the purposes of determining the nature
and extent of unperformed and on- going obligations, the Contract shall be deemed to
remain in force".
Insert the following new Sub-Clauses after Sub-Clause 11.11 "11.12 Collateral
warranties The Contractor shall, within 14 days of the Employer's written request from
time to time to do so, procure one or more collateral warranty agreements in favour of
one or more Beneficiaries in the respective form set out in Annex 6 with only such
amendments as the Engineer shall, acting reasonably, approve. Such collateral
warranties s hall be validly executed by the Contractor, and, in the case of any
collateral warranties to be provided by any Subcontractor, by the Subcontractor as
well. The obligation for the provision of such collateral warranties shall continue
notwithstanding termination of the Contract or of the Contractor's employment under
the Contract for any reason whatsoever including (without limitation) breach by the
Employer. However, any such agreement provided after such termination shall be
amended by the Employer so as to refer to the fact and date of such termination, to
omit any obligations to continue to exercise skill, care and diligence after such
termination, and to omit any provision enabling a third party to assume the position of
the Employer. Without prejudice to any other right or remedy available to the Employer,
the Employer shall be entitled to withhold the sum of ten percent ( I0%) of the Contract
Price from any payment to be certified in a Payment Certificate for each and every
collateral warranty agreement requested but not provided pursuant to this sub-
paragraph. 11.13 Latent defects Notwithstanding the expiry of the Defects Notification
Period or the issue of the Performance Certificate, the Contractor shall remain liable for
any defects in the Works or any failure of the Works to comply with the Contract or with
the Laws for a period of ten years from the date of the relevant Taking-Over
Certificate."
The Contractor shall, within 14 days of the Employer's written request from time to time
to do so, procure one or more collateral warranty agreements in favour of one or more
of Third Parties or of the Employer itself in the respective form set out in Annex F with
only such amendments as the Engineer shall, acting reasonably, approve. Such
collateral warranties shall be validly executed by the Contractor, and, in
the case of any collateral warranties to be provided by any
19 of 26
Subcontractor, by the Subcontractor as well. The obligation for the provision of
such collateral warranties shall continue notwithstanding
termination of the Contract or of the Contractor's employment under the
Contract for any reason.
Notwithstanding the expiry of the Defects Notification Period or the issue of the
Performance Certificate, the Contractor shall remain liable for any defects in the
Works or any failure of the Works to comply with the Contract or with the Laws for
a period of ten years from the date of the relevant Taking-Over Certificate."
13.1 Right to vary Delete ” A Variation shall not comprise the omission of any work which is to be
carried out by others” at the first paragraph.
“To avoid doubt, the Contractor shall not be entitled to claim any extension of
time or additional Costs where it fails to notify the Engineer in accordance with
this Sub-Clause”
13.3 Variation Procedure Add a new paragraph at the end of the Sub-Clause as follows:
20 of 26
13.5 Provisional Sums Add the following paragraph
The Employer may omit in part or in full any Provisional Sum. No claims will
be entertained due to the same.
13.6 Daywork Add to the end of the Sub-Clause the paragraph “An instruction pursuant to
Sub-Clause 13.6 [Daywork] shall not entitle the Contractor to an extension of
the Time for Completion pursuant to Sub-Clause 8.4 [Extension of Time for
Completion].”
13.7 Adjustments for Changes in Add “and which the Contractor could not reasonable have foreseen at the base
Legislation date” in the last part of paragraph 1.
Add “which the Contractor could not reasonably have foreseen at the Base
Date” in paragraph 2.
13.8 Adjustments for Changes in Delete the text of the Sub-Clause and replace with
Cost
"Except only as expressly stated otherwise in this Contract, the Contract Price
is not subject to adjustment, rise, fall or escalation (including for increases in
the cost of goods, labour or materials or any other matters affecting the cost of
the execution of the Works)."
(a) Delete words “and Sub-Clause 13.8 [Adjustments for Changes in Cost]”
14.3 Application for Interim Payment
from sub paragraph (b)
Certificates
21 of 26
Add the following paragraph
14.5 Plant and Materials intended for Add sub paragraph (a) item iii
the Works
“provided a vesting certificate to the Employer for any delivered Plant or
Material. “
14.6 Issue of Interim Payment Add the following text to the end of the first sentence of the first paragraph
Certificates
“or the insurances as specified in the relevant clauses of this Contract
Agreement (to be submitted to the Engineer in original). The approval by the
Engineer/ Employer to be in writing”.
14.7 Payment amend 56 days to be 28 days after the Employer has received the payment
certificate from the Engineer.
15.2 Termination by the Employer Add words after” terminate the Contract” in paragraph 1
“(g) is liable to pay delay damages in excess of the maximum amount stated in
the Appendix to tender”
(h) uses of has used deception or fraud in its transactions with the Employer or
Add “and such Contractor’s equipment and temporary works as he or they may
require” in the last part of paragraph 5.
22 of 26
Contractor without the need for a court order. The termination shall take effect
14 calendar days after the date the Contractor receives the termination notice.
After such termination, the Contractor shall be paid solely for Works performed
up to the time of such termination and for Materials and Plant reasonably and
as per the Contract delivered to the Site. After this termination, the Contractor
shall proceed in accordance with sub-paragraph 16.3 [Cessation of Work and
Removal of Contractor's Equipment]."
15.6 Employer’s Entitlement to Upon termination of the Contract by the Employer for any reason
Complete the Works whatsoever, the Employer may complete the Works himself and/or arrange for
following Termination any other entities to do so. The Employer and these entities may use such
Materials, Plant, Contractor's Documents and other design documents made
by or on behalf of the Contractor and such Temporary Works as he or they may
require. The Contractor shall co-operate fully with the Employer and any such
new contractor(s) for the orderly transfer of the Works.
“the Contractor has lawfully exercised its right to suspend under Sub- Clause
16.1 and such period of suspension has exceeded 60 days;”
16.3 Cessation of Work and Add new Sub-Clause (d) “refrain from taking any action that could hinder or
Removal of Contractor’s prevent the Employer from proceeding with the Works in a timely and cost
Equipment efficient manner.”
“mitigate any loss, cost, expense or damage arising from such termination."
17.2 Contractor’s Care of the Insert as a new final paragraph “If the Contract is terminated in accordance with
Work the provisions of these Conditions, for the purposes of this Sub-Clause, the date
of issue of the Taking-Over Certificate shall be
deemed to be the date of expiry of the Notice of Termination given under
23 of 26
Clause 15 [Termination by Employer] and Clause 16 [Suspension and
Termination by Contractor].”
17.4 Consequences of Employer’s In the first sentence of the first paragraph, replace the word “Goods”
Risks with “Materials, Plant and Temporary Works”.
Delete the sentence “In the case of sub-paragraph (f) and (g) of Sub- Clause
17.3 [Employer’s Risks], reasonable profit on the Cost shall also be included.”
in Sub-Clause (b).
“The Contractor shall, within respective periods stated in the Appendix to tender
(calculated from the commencement date) submit to the Employer”
Add the words “and Sub-Clause 18.4 [Insurance for Contractor’s Personnel] and
Sub-Clause 18.5 [Additional Insurances]” to the end of Sub-Clause 18.1 (b).
18.2 Insurance for Works and In the second line of the first paragraph insert the words “on the Site” after
Contractor’s Equipment “Contractor’s Documents”.
18.4 Insurance for Contractor’s Add the following paragraph to the end of the Sub-Clause:
Personnel
“This Insurance shall be for a limit per occurrence of not less than the amount stated
in the Appendix to Tender, with no limit on the number of occurrences.”
“Notwithstanding anything contained in Clause 18, the Contractor shall effect and
maintain such additional insurances in accordance with the Laws, and with limits not
less than those set forth in the Appendix to Tender, as may be required by the
Employer, such as, but not limited to:
24 of 26
of the United Arab Emirates Civil Code. The Engineer shall be named as a co-
insured under this policy. The policy shall be valid for a period of 10 years measured
from the date of the Taking-Over Certificate. The terms of the policy shall be subject
to the approval of the Engineer, and the costs thereof shall be borne by the
Contractor. The undertaking letter shall be provided to the Engineer within 14 days
of the Commencement Date.”
“In the event that the Contractor has any right or entitlement pursuant to the Contract
or otherwise, the Contractor shall in all cases take such steps (if any) which can
reasonably be taken to eliminate or mitigate any such entitlement, to the extent that
such elimination or mitigation can be achieved without any additional Cost to the
Contractor. In the event that mitigation measures are available to the Contractor but
require the Contractor to incur additional Cost, the Contractor shall consult with the
Engineer and the Engineer shall issue such instructions as the Engineer considers
appropriate and shall proceed in accordance with Sub-Clause
3.5 [Determinations] to agree or determine the entitlement of the Contractor to any
additional cost incurred by the Contractor in complying with such instructions.”
"Upon any termination or suspension of Contractor, the Employer shall not be liable
to the Contractor for any loss of profit or loss of opportunity arising out of or in
connection with such termination or suspension."
20.1B Contractor’s Claims " In no event shall the Contractor have the right to suspend the execution of the
Works due to the submittal of a claim under the Contract."
20.4 Obtaining Dispute Adjudication Delete Sub-Clause 20.4 as well as all references made to it in the general and
Board’s Decision particular conditions.
20.5 Amicable Settlement Delete Sub-Clause 20.5 in its entirety and substitute with the following:
“If a dispute (of any kind whatsoever) or breach thereof arises between the
Parties in connection with, or arising out of, the Contract or the execution of
the Works including any dispute as to any certificate, determination,
instruction or opinion or valuation of the Engineer, both Parties shall
attempt to settle the dispute by notice from the Party alleging the dispute or
difference to the other Party for an amicable settlement before the
commencement
of arbitration.”
25 of 26
20.6 Arbitration Delete Sub-Clause 20.6 in its entirety and substitute with the following:
20.6.1 This Contract is governed by the laws of the Emirate of Abu Dhabi and the
federal laws of the UAE as applied and implemented in the Emirate of Abu Dhabi.
20.6.2 Any dispute or difference arising out of or in connection with this Contract
including, without limitation, any dispute regarding the existence, formation,
performance, interpretation, nullification, termination or invalidation of this
Contract, shall be referred to and finally resolved by the Abu Dhabi Commercial
Conciliation & Arbitration Center (ADCCAC) in accordance with its Rules, which
rules are deemed to be incorporated by reference into this Sub-Clause 20.6. For
the purposes of any arbitration proceedings commenced pursuant to the Rules
15.3:
(c) the language to be used in the arbitral proceedings shall be English; and
(d) the arbitrator shall have the power to issue directions in respect of all
costs.
20.7 Failure to Comply with Dispute Delete Sub-Clause 20.7 as well as all references made to it in the general and
Adjudication Board’s Decisions particular conditions.
20.9 Submissions The Contractor must submit to the Engineer with 21 days from signing the Contract
the following documents:
(a) programme of Works; - except programme required in 7 days
(b) manpower histogram;
(c) list of Plant, Materials, Equipment and Facilities;
(d) the Site visit acknowledgment;
(e) projected cash flow for the Works;
(f) proposed organization chart & CV of key personnel;
(g) quality assurance system;
(h) health and safety management system;
(i) environmental management system;
(j) proposed Subcontractors & Suppliers list;
(k) details of proposed resources; and
(I) schedule for the submittal of shop drawings and samples.
26 of 26
GENERAL CONDITIONS OF CONTRACT
The General Conditions of Contract shall be the FIDIC Conditions of Contract for Construction for
Building and Engineering Works designed by the Employer, First Edition 1999. ISBN 2-88432-022-9
Appendix D
FORM OF TENDER
SPECIMEN
Date:
Dear Sir
(1) Having examined the Tender Documents (as described in Invitation to Tender Conditions of
Contract, Drawings, Specifications, Bill of Quantities but for this purpose also including any document
issued by the Employer or Tenderer and intended to form part of the Tender Documents) for the
execution of the above named Works, we, the undersigned, offer to execute and complete such Works
and remedy any defects therein in conformity with the said Tender Documents for the sum of
U.A.E. Dirhams [ Dhs.......................................]
or such other sum or sums as may be ascertained in accordance with the Agreement included in the
Tender Documents (the “Conditions of Contract”).
3. We have included with our Tender all the required and relevant information and enclosed
herewith all the information requested in the Tender Documents.
5. We undertake, if our Tender is accepted, to commence the Works within 14 days of receipt of
the Employer’s notice to commence issued by the Consultant.
6. We undertake, if our Tender is accepted, to complete and deliver the whole of the Works
comprised in the Agreement within the time stated in the Appendix E of Invitation to Tender.
7. The periods stated include all Fridays, Public Holidays etc., and other non-working days caused
by inclement weather, etc., and shortened working hours during the Holy Month of Ramadan.
8. We agree to abide by this Tender for ninety (90) days from the last date of submission of Tenders
and it shall remain binding upon us and may be accepted at any time before the expiry of the ninety
(90) days.
9. If our Tender is accepted we will provide the Performance Security as described in Clause 4 of
the Standard Terms and Conditions.
10. If our Tender is accepted we shall obtain the insurances as required by the Tender before
commencing the Works.
Page 22 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
11. Unless and until a formal agreement is prepared and executed, this Tender together with the
Employer’s Letter of Acceptance issued by the Consultant shall constitute a binding contract between
us.
12. We understand that you are not bound to accept the lowest or any Tender you may receive.
Signature .................................................................
Name ................................................................
Date ................................................................
Contractor ...........................................................................................
In the presence of
Signature ..........................................................
Name ...........................................................
Date ...........................................................
Page 23 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
Appendix E
COMPONENT PROJECT MASTER PROGRAMME
Page 24 of 28
Date: Septe,ber 2022
ERTH Guest Arrival
Master Programme
ID Task Name Duration Start Finish Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023
J M M J S N J M M J S
1 ERTH Guest Arrival - Programme 31.8 mons Wed 09/02/22 Wed 17/07/24
2 Consultant Appointments 7.65 mons Wed 09/02/22 Fri 09/09/22
6 Design Stage 10.4 mons Thu 10/02/22 Mon 28/11/22
35 Authority Approvals 1.75 mons Wed 16/11/22 Wed 04/01/23
39 Tender 7.95 mons Thu 19/05/22 Wed 28/12/22
51 Construction 20.02 mons Wed 04/01/23 Wed 17/07/24
Appendix F
Summary of Current Commitments
Page 25 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
We hereby confirm the below provides a true and accurate reflection of our current commitments:
Signature .................................................................
Name ................................................................
Date ................................................................
Contractor ...........................................................................................
In the presence of
Signature ..........................................................
Name ...........................................................
Date ...........................................................
Page 26 of 28
Classification: Internal
Erth Hotel Guest Arrival Experience, Refurbishment Works
Invitation to Tender
22 November 2022
Appendix G
BILL OF QUANTITIES
Page 27 of 28
The Armed Forces Officers Club and Hotel
Fit-out Works
Fit-out Works
BILL 1
PRICING PREAMBLES
A Scope of work includes for the construction and completion of the Erth Guest Experience - Fit-out Works Package as shown
in the drawings.
GENERALLY
B The Lump sum amount entered by the Main Contractor in these Bills of Quantities shall constitute the entire claim for
compensation for the work under this contract in accordance with the Conditions of Contract. The works shall not be
remeasured and will be subject to adjustment only as a result of changes in the scope of work through changes in drawings
and/or specifications.
C Upon award of contract, the Bills of Quantities shall be used solely for evaluation of progress payments due to the Main
Contractor, and as a schedule of rates for changes.
D The Bills of Quantities herein, including all notes and instructions, shall form an integral part of the Contract Documents.
However, the descriptions contained in the Bills of Quantities for each item are not necessarily complete. The Main
Contractor is referred to the Conditions of Contract and other Documents, Specifications and Drawings as well as relevant
Standards and Codes of Practice for further information as no claim or variation will be considered on account of the Main
Contractor's failure to do so.
E The Main Contractor is cautioned to familiarize himself with the full content of other Contract Documents including the
Drawings and Specifications (or any other information that can be reasonably inferred from any of them) and all obligations
contained in the documents shall be included in the tender prices and lump sum tender price, even if specific items relating to
them are not listed in the Bills of Quantities.
F Drawings, Specifications, Conditions of Contract and Bills of Quantities and all other Contract documents are complementary
and if any item is included in any of them, it shall be deemed included in all.
G The Main Contractor's bid for the entire work shall provide for supervision of any and all trades that are not intended to be
performed with his own resources. No extra compensation for services, as a General Main Contractor will be paid.
H The Main Contractor is required to provide with his Tender one complete copy of the Bills of Quantities fully priced out in
waterproof ink with summation sheets properly completed.
J Amendment shall not be made to these Bills of Quantities without the authority, in writing, of the Engineer.
K The Main Contractor shall not use these Bills of Quantities as the basis for a construction programme or for the purpose of
ordering materials or arranging Sub-contracts, be they Nominated or otherwise. The references for these activities shall be
the drawings, specifications and instructions issued by the Engineer.
GENERALLY (CONT*D)
A The Bills of Quantities have been prepared in such a manner that the description of each item (which description shall imply
reference to any heading or sub-heading, preamble or other clause or item which shall apply), shall be held to include for all
that is necessary to fulfil the liabilities and obligations arising out of the performance of the Contract, including (but not limited
to) the following:
b) Labour and supervisory labour with all associated payroll additives costs,
c) Materials, goods and all associated costs (including purchasing, conveyancing, delivering, unloading, positioning,
handling, hoisting, lowering, returning packing and the like),
f) Customs duties, port dues, import duties, taxes, charges, insurances and other dues levied by any authority or imposed by
the government,
j) Provision and use of plant, equipment, small tools and maintenance of same,
l) Wastage on materials,
n) Short lengths,
GENERALLY (CONT*D)
o) Safety,
p) Protection,
q) Provision of samples,
r) Consumables,
s) Testing,
t) Establishment charges,
w) Making good,
x) Attendance, coordination and maintaining a permit to work system for items of install only, or supply only or both supply
and install.
z) Transportation
GENERALLY (CONT*D)
Format of Descriptions
B m - Meter
C m2 - Square Meter
D m3 - Cubic Meter
E Nr - Number
F Kg - Kilograms
G KN - Kilo Newton
METHOD OF MEASUREMENT
J The Bills of quantities have been prepared in accordance with the NRM 2: Detailed measurement for building works, as
published by the Royal Institution of Chartered Surveyors. In addition to these preambles any specific departures from the
NRM 2 to suit local custom has been incorporated into the headings and descriptions of scheduled items.
K The following amendments to NRM 2 have been included and are to be read in conjunction with the specifications and the
drawings.
L These preambles form the Appendix to the NRM 2: Detailed measurement for building works, of which Tenderers shall be
deemed to be in possession of their own copies of the NRM 2.
PRICING
A The Main Contractor's unit rates are to be fully inclusive value of the work described and must include all related work,
accessory or consumable materials, incidental labour, supervision, administration, tools, construction equipment, overhead
and profit and all costs and expenses which may be required in and for the completion of the work described together with all
costs and expenses in complying with all general risks, liabilities and obligations set forth or implied in the Drawings,
Specifications and Conditions of Contract.
B The unit rate inserted by the Main Contractor for any item of work shall apply to the completed work as described in the
Contract Documents covering everything necessary including expenses of labour, material and equipment required for
executing that item of work. These general expenses shall include but are not restricted to the following, unless entered as a
separate item in the BOQ:
b) Labour, plant, tools and vehicles and all costs in connection therewith.
c) Costs related to the Contractors site, temporary construction including the provision of all utilities and facilities.
f) Cost of laboratory testing, survey work and assistance to the Engineer as required in the Contract.
C Lump sums shall not be given where unit rates are applicable.
D Where the word "allow" is used, the cost of the items shall be the responsibility of the Main Contractor.
E Where the word "item" is used, the cost of the items shall be the responsibility of the Main Contractor.
PRICING (CONT*D)
A The amounts set against any items of profit shall include for all costs in connection with the letters of credit, bank charges,
interest charges and insurance after the materials come under the control of the Main Contractor.
B No variation will be allowed for any error in the computation of the Tender discovered after date of issue of letter of
acceptance of the tender and award of the Contract.
Definitions
C "Prices also to include"; items under this heading fall into two categories:
(i) Those which are deemed to be included in descriptions and, therefore, in prices.
(ii) Those for which the Main Contractor shall allow for in his prices.
E "Cross Falls", "Cross Slopes", "Cross Weathered": inclination from the horizontal in more than one plane.
Fix Only
F The expression "fix only" used in these Bills of Quantities means that the Main Contractor shall provide the following facilities:
(iii) Giving and marking dimensions and taking responsibility for their accuracy.
(vi) Casing up and protection, including clearing away protection on completion of the works.
PRICING (CONT*D)
(vii) Full cost of replacement of any items which are damaged, broken, lost or stolen after the acceptance of the items from
the supplier or client and until handing over the complete works.
Supply Only
A The expression "supply only" used in these Bills of Quantities means that the Main Contractor is to include for all liabilities
and obligations arising out of the Contract except fixing in position.
B Any Sub-Main Contractors or Suppliers which the Main Contractor proposes to use for the works are subject to the approval
of the Engineer and Employer. Any Sub-Main Contractor or Supplier who has not been approved by the Engineer and
Employer shall not be used in connection with the carrying out of the works.
C The Main Contractor should ascertain from Sub-Main Contractors and Suppliers before the work is put in hand particular of
positions in which chases, holes, mortises and the like will be required to be formed or left. No claim for the extra costs of
cutting away work already built due to the Main Contractor's failure to ascertain these particulars will be admitted.
D The Main Contractor shall allow for any additional costs incurred due to Sub-Main Contractors working different hours from
and extended hours to those worked by the Main Contractor.
Attendances to be provided by the Main Contractor to all Sub-Main Contractors and Nominated Sub-Main Contractors
F The Main Contractor shall be responsible for providing, including but not limited to, the following attendances:
(ii) Use of Main Contractor's mess room, sanitary and welfare facilities.
(iv) Co-ordination and scheduling of all works related to each Sub-contract and Nominated Sub-contract.
PRICING (CONT*D)
(viii) Giving and marking dimensions and taking responsibility for their accuracy.
(ix) Space for Sub-Main Contractor offices and stores be they Domestic or Nominated.
(xi) Offloading all Sub-Main Contractors' or Suppliers' materials and placing in stores be they Domestic or Nominated.
(xii) Clearing away all and any rubbish be it generated by Main Contractor, Nominated or Domestic SubMain Contractors.
(xiii) Other necessary and usual facilities, documentation, general inter-trades attendances, labour and assistance.
A The Sub-Main Contractor or Nominated Sub-Main Contractor shall be responsible for providing, including but not limited to,
the following attendances:
(i) All special scaffolding required by him in the execution of his works.
(ii) Taking from stores, distributing, hoisting and placing in position, all items of plant, equipment and materials required by
him in the execution of his works.
(iii) All labour, plant etc (other than included in Attendances to be provided by the Main Contractor).
PRICING (CONT*D)
(iv) Site offices and stores required by him for the execution of his works.
(v) Obtaining security passes for access of work people to the site.
(vi) Offloading from material delivery vehicles his materials, placing in temporary stores on-site, distributing, hoisting and
placing in position.
Provisional Sums
A For all work executed, or goods, materials, plant or services supplied by any Nominated Sub-Main Contractor or Nominated
Supplier the Main Contractor shall be entitled to:
(i) The actual price paid or due to be paid by the Main Contractor, on the instructions of the Engineer.
(ii) In respect of all other charges, profit and attendance, a sum being a percentage rate of the actual price paid or due to be
paid. The Main Contractor shall insert the percentage or sum as applicable required for all other charges, profit and
attendance against each item in the Bills of Provisional Sums.
(iii) The Main Contractor is responsible for ensuing that the works of the Sub-Main Contractor are complete. No variation by
the Main Contractor or Sub-Main Contractor will be accepted in this regard.
B Provisional Sums included in these Bills of Quantities may be expended totally, in part or not at all and as directed by the
Engineer.
C The Main Contractor will have no entitlement to any claim for loss of profit in the event that any or all Provisional Sums are
omitted in part or in their entirety. Where the Main Contractor has inserted an associated %age (not composite items) for
attendances and builders work these shall also be adjusted for any omission or addition as required under the Conditions of
Contract.
D Percentage or adjustment of Provisional Sums shall not be applicable to any direct payments made by the Employer to a
third party or where no approved sub-contract agreement exists.
PRICING (CONT*D)
A PC rates of Supply Only rates for Nominated Suppliers of materials and equipment shall be deemed to include delivery to site
and exclude the Main Contractor's percentage for overheads and profit as stated in the Preliminaries section of the Bills of
Quantities. At the time the Engineer has approved the actual material to be used in the works, the actual delivered to site
cost plus Main Contractor's overheads and profit percentage as stated in the Bills of Quantities shall be inserted into the Main
Contractor's rate following the deduction of the original PC supply only rate contained in the Main Contractor's rates against
the particular item description in the Bills of Quantities.
B The Main Contractor when pricing items in the Bills of Quantities which contain PC supply only rates shall add to the PC rate
the percentage required to cover for profit and overheads, and fixed prices for the unloading from delivery vehicle to site
store, loading and transporting from site store, hoisting and lowering and distribution to various positions, assembly as
necessary, cutting, fixing, casing up and protecting and finally cleaning down and, where appropriate, oiling and adjusting and
leaving in perfect order, all necessary straight, curved and irregular cutting, wastage and all other allowances required to fully
fix, install or place the particular item in accordance with the specification and the written instructions of the Engineer. These
allowances shall be fixed and will not be adjusted against the final value of the supply rates adopted. Should the item
including PC supply only rates be deleted from the Contract no payment against that item will be made to the Main
Contractor.
C The Employer shall select the Supplier from those listed in the specifications and shall procure the materials and equipment
with assistance from the Engineer. The Employer shall be responsible for obtaining any competitive or negotiated prices from
the Nominated Suppliers with assistance from the Engineer. Once the award for Supply only has been completed by the
Employer, the Engineer shall instruct the Main Contractor and inform him of the details. The Main Contractor shall arrange for
all co-ordination of deliveries be they in part or full loads to suit the Main Contractor's Programme of Works.
Builders Work
D Within the Bills for Provisional Sums the Main Contractor is to allow for all the builders work required in connection with the
various work elements covered by Provisional Sums as noted. To assess the builder's work required, the Main Contractor
may review the drawings related to these Works at the offices of the Engineer.
F All other Charges and Profit includes Profit, Overheads, Builder's works, Facilities, Assistances and Attendances in
connection with the expenditure of Provisional Sums in favour of Sub-Main Contractors.
G The expression General Attendances shall mean, but is not limited to the following:
PRICING (CONT*D)
c) The use of the Main Contractor's facilities, including mess rooms, sanitary accommodation and welfare facilities.
e) Space for SubMain Contractors offices, stores and lay down areas.
f) The clearing away of all rubbish, waste and debris on a regular basis.
h) Unloading, distributing, hoisting or lowering to the respective floor levels, and placing in suitable positions for the SubMain
Contractor all plant, machinery or the like to be installed by the SubMain Contractor.
i) The provision of electrical power by Main Contractor for the SubMain Contractor's works, including all lighting and 3-phase
or heavy supplies, which may be required for purposes of testing and commissioning.
j) The provision of water for the Sub-Main Contractor's works, including the requirements for testing and commissioning and
subsequent removal of water.
k) The provision of all fuel necessary for the testing and commissioning of the Subcontract works.
l) The general co-ordination and integration of all Subcontract works into the general Programme.
m) Ascertaining full details of any work to be executed by other SubMain Contractor's in connection with the Subcontract
works and arranging for such work to be executed at the correct time.
PRICING (CONT*D)
Engineers Overtime
A The Main Contractor will be liable for the payment of "Engineers Overtime" for site supervisory staff required to work beyond
normal site office hours for inspection/supervision of the Works in accordance with clause 6.5 of the Conditions of Contract.
The Main Contractor shall allow for such costs within his tender.
Overtime Fridays
Rates &
Public
Hol
AED / Hr AED /
Hr
PRICING (CONT*D)
Measurement Demarcation
A Building, Substructure measurement demarcation shall include for all works commencing from the excavation surface of the
Enabling Works up to and including structural slab level on the ground floor level. It shall include for such works as level and
compact bottoms of excavation, prepare top of the foundation raft. It shall also include, Works up to and including Concrete
floor slab at ground floor with formation of all holes, inserts, MEP services cast into the ground floor slab and below.
Completion of Substructure, Superstructure and External Works should be shown as separate key milestone dates on the
Main Contractor's Programme of Works.
B Building, Superstructure measurement demarcation is from the ground floor slab level up to and including the uppermost part
of the roof. It shall include for all floor finishes on ground floor level and all works up to and including the Roof level. All works
to be instructed under Provisional Sums will also for part of the works for which the Main Contractor will be responsible.
C External Works measurement demarcation is all works outside the gross external area and footprint of the Building
depending upon the level. It shall include for all hard and soft landscaping at ground floor level up to and including the hard
and soft landscaping and all other External Works at Ground Floor Structural Slab Level. Landscape structures is included in
the external works.
PRICING (CONT*D)
Permitting
A The Employer shall be responsible for paying direct all fees associated with Permitting for the Project be it the Building Permit
or the like. However, should the Employer or Engineer request the Main Contractor or his Nominated or Domestic SubMain
Contractors to collect the approved application and pay the associated Permit Fees to the statutory/governing authority on
behalf of the Employer, then the Main Contractor shall be entitled to a Variation Order to recover these Permit Fees in
accordance with the Conditions of Contract. The Main Contractor should provide all necessary invoices, 'Stamped Paid' and
all documentation associated with the approved application to the Employer and Engineer.
Section 1 Preliminaries
B Payment for the establishment of the items for site office and facilities will be lump sum which will be made only after the
completion of all facilities. A breakdown of all lump sum amounts to be submitted together with the Tender Submission.
C Payment for the maintenance of site office and facilities items will be in monthly instalments.
D Payment for the removal of site office and facilities items will be by lump sum which will be made only after the completion of
their removal. The removal of the Site Office for the Engineer shall be one month after the completion of the Works.
E Payment for Main Contractors supervision and the like - bill items shall be in monthly instalments.
F Instalments can be suspended, reduced or deleted from any Contract Payment, if, in the opinion of the Engineer, the Main
Contractor is not fulfilling his obligations.
G The rate inserted for General Protection of the site shall include for the cost to maintain access to areas adjacent to the work
site.
H The item for Traffic safety and control shall include the cost of all temporary traffic diversions and traffic management
necessary to complete the works. The item shall include for liaison with the Police, the Engineer and Municipality and
conforming to their requirements for safety.
J Temporary works, diversions, site cleaning, etc, and other items not otherwise covered in this preamble or otherwise detailed
in the Bills of Quantities will be cost related items and will be paid as a percentage of work completed to total value of work.
K Payment for the establishment of surveying equipment will be lump sum and it will be made only after the delivery of all the
equipment specified. Payment for items maintained will be in monthly Instalments.
PRICING (CONT*D)
A Payment for assisting Engineer shall be in monthly Instalments and is deemed to cover all costs in providing assistance to
the Engineer by the Main Contractor as stated in the Contract.
B Payment for Project Sign Boards shall include for erection, maintenance, removal within one month of completion and
reinstatement of ground to its original state.
C Payment for progress photographs will be by set of monthly progress photographs as defined in the Specification.
D Payment for conditions of contract will be by monthly Instalments and shall cover all costs and expenses including overhead
and profits incurred by the Main Contractor in carrying out the requirements of the Conditions of Contract not otherwise
included in the Bill of Quantities. Breakdown of all lump sum amounts to be submitted together with the Tender Submission.
E Items for which the measurement unit is in days, such items shall be measured for the actual period for which facilities,
services, etc., are provided in accordance with the construction programme. Measurement will commence only after the
completion of the Mobilization period and on the day as approved by the Engineer in agreement for the facilities, services,
etc., when fully provided.
F These Instalments can be suspended, reduced or deleted from any contract Payment, if in the opinion of the Engineer, the
Main Contractor is not fulfilling his obligations.
G Items which relate to the final completion works will be certified only upon issuance of Taking over certificate for the Works
H The Employer requires that the Contractor will within one (1) month of signing of the Contract review and agree with the
Employer the redistribution of costs within the Preliminaries section of their Bill of Quantities and that these redistributed costs
will reflect a fair and equitable representation of the actual costs incurred by the Contractor during the mobilization, recurring
and de-mobilization stages of the preliminaries works and avoid any possible “front loading”.
Section 3 Demolitions
K Concrete shall be measured in cubic metres (m3) irrespective of reinforcement percentage, slope and ground conditions.
L Form work to sides of foundations and/or bases shall be measured as a single item regardless of the thickness.
PRICING (CONT*D)
A Form work to sides and soffits of beams shall be measured as a single item regardless if it is attached to slabs, attached to
walls or isolated.
C Reinforcement bars are measured as a single item regardless of their horizontal or vertical lengths and regardless if they are
straight, bent or curved.
Section 14 Masonry
D All items as mentioned below shall be measured by area (m²), stating the overall thickness. Battering, tapering and curved
walls shall be measured separately. No deductions are made for void areas equal to or less than 0.10 m2. Brickwork and
block work are measured on the centre line of the materials.
a) Walls
b) Diaphragm walls
c) Isolated piers
d) Isolated casings
E The rates for this work shall be deemed to include for scouring the face; and for plumbing angles and surfaces, all square
cutting, wedging and pinning against columns, beams, slabs, etc. for all waste cutting and wire ties required in tying skins
together.
F Reinforcement, insulation, forming and closing cavities, pointing and jointing is included in the rates for brickwork and block
work.
Section 19 Waterproofing
G Each item mentioned below shall be measured by area (m²) and grouped together under the term ‘generally’ irrespective of
width. No deductions shall be made for void areas equal to or less than 1.00 m2:
PRICING (CONT*D)
A The following items are not measured separately but deemed included in the rates in which they occur.
a)Fair edges
b)Rounded edges
c)Drips
d)Arrises
e)Turning asphalt nibs into grooves
f)Edge trims
B The following items are deemed included in the rates in which they occur.
a)Cleaning and preparing of surfaces to be waterproofed, protection from damage and cleaning down, flood testing, if
required and handing over in an acceptable and guaranteed watertight condition at completion, unless otherwise stated.
b)Dressing, bending, narrow widths, angles, intersections, cutting and waste where applicable, for the extra material
required lapping and for sealing laps as described.
C Unless otherwise stated turning-ups should be provided to all wet areas/rooms and shall be measured by linear metres (m)
stating the height.
D Notwithstanding the Measurement Rules stated in Section 20, proprietary Partitions may be measured and given in square
metres in the Bills of Quantities Irrespective of different heights.
E Items for linings to walls, beams, columns and reveals and soffits of openings and recesses shall be measured in area (m²) in
the Bills of Quantities irrespective of heights and widths.
F The following items shall not be given separately in the bills and shall be deemed to be included in the rates for partitions or
linings in which they occur:
PRICING (CONT*D)
A Raised access floors shall be measured by area (m²) stating the thickness of panel and height of cavity. No deduction shall
be made for voids equal or less than 0.50 m². Raised access floors to ramp areas shall be enumerated, stating the thickness,
length, width and height.
B Skirtings and perimeter edge trims which are executed as part of the raised access floors are not measured separately but
deemed to be included in the rates for raised access floors
C Panel cubicles shall be enumerated per set. Cubicle sets include doors and ironmongery. Framing, stiffening, connecting and
fixing devices, supporting legs and brackets are deemed to be included
D Ceilings shall be measured by area (m²), stating the thickness of linings and method of fixing. No deduction shall be made to
voids equal or less than 0.50m2. The depth of suspension shall not be stated.
F Items for raking and curved cutting shall not be given separately but deemed to be included in the rates for cladding and
covering in which they occur.
G Items for weathering, flashings and fixing members at tops, bottoms and sides where part of the component shall be deemed
to be included in the rates for cladding and covering.
H Curtain walling shall be measured by area (m²). Dimensions shall be included in the description. Flat, sloping and curved
(radii stated) curtain walling shall be measured separately with no deductions made for void areas equal to or less than 1.00
m². Cleats, brackets, bolts and fixings are deemed to be included. Doors shall be enumerated as extra over items to curtain
walling, stating the appropriate dimensions
PRICING (CONT*D)
a)for all short lengths, cutting, waste and fitting at intersections to flashings, aprons, capping, etc
b)bedding washers
c)coating projecting ends of hook bolts and nuts, etc with bitumen after fixing
d)all square notches, square cutting and waste, laps, fitting and drilling. All quantities are measured net and no allowance
has been made for laps
A All items stated below, which are integral parts of the roof coverings and wall cladding sections shall not be measured
separately. These items are only measured if considered to be isolated or known to be installed and constructed by two or
more different Contractors.
B Items for holes and fire stops shall not be measured but deemed to be included in the rates in which they occur.
C Roof and wall coverings shall be measured by area (m²), stating the pitch. No deduction is made for voids area equal to or
less than 1.00 m². Underlay and battens are deemed to be included
PRICING (CONT*D)
A Windows, window shutters, sun shields, roof lights, skylights, lantern lights, screens, shop fronts, louvre and frames shall be
described as overall dimensions and measured as numbers (nr).
B Ironmongery to windows, shop fronts, roof lights, screens, louvers and shutters shall be deemed to be included in the rates.
C Multi-leafed doors shall be described stating overall structural opening or overall size and will be measured as one (1)
number (nr).
D Door frames, linings, stops, fire stops, trims and smoke stops shall be deemed to be included in the rates as identified and
given in door schedule and details.
E Any trims and the like fixed to the set after installation shall be deemed to be included in the rates as identified and given in
door schedule and details.
F Ironmongery shall be measured in number (nr) described in sets as referred in the given schedule and rate shall include all
constituent parts of the units or sets.
G Finishes to door panels/shutters and door frames shall be deemed to be included in the rates as identified and given in door
schedule and details.
H Staircases, loft ladders, ladders, extra over for quarter landings and half landings shall be measured by number (nr) stating
the dimensions and types. Attached balustrades and newel posts are deemed to be included.
J Catwalks, walkways shall be measured by linear metres (m) stating the dimensions, flat / curved and radius.
K Balustrades, handrails, barriers, guard rails and balcony units shall be measured by linear metre (m) or number (nr) stating
the dimensions. These items are measured when not forming an integral part of staircase unit.
PRICING (CONT*D)
A All screed, beds, toppings, raised access floors, finish to roofs, finish to floors, walls, ceilings and staircases shall be
measured by area (m²) regardless of the width unless noted otherwise.
B All plaster, render, finishes to walls, finishes to columns shall be measured by area (m²) regardless of the width unless noted
otherwise.
Section 29 Decoration
C Painting shall be measured by area (m²) to all surfaces shall be identified as follows:
G Trims, fittings, shadow gap battens and associated finishes are deemed to be included in the measurement and rates of
ceiling works.
H Collars integral with the fire barriers are deemed to be included in the measurement and rates of ceiling systems.
PRICING (CONT*D)
B The rates for pipework shall be deemed to include for all the fittings (e.g. bends, tees, junctions and branches, reducers, end
caps, etc.).
a)Preparing drawings
b)Operating manuals and instructions
E The rates for pipework shall be deemed to include for all the fittings (e.g. bends, tees, junctions and branches, reducers, end
caps, etc.).
F The rates for pressure pipes (sump pump discharge pipes) shall be deemed to include for all necessary thrust blocks and
concrete support.
G The rates for manholes, inspection chambers and the like shall be deemed to include for all sundry items such as covers and
frames, step irons, intercepting traps, backdrops, etc. and all necessary earthwork items such as excavation, bedding,
surrounds, backfilling, compacting and disposal of surplus excavated materials
PRICING (CONT*D)
A Unless stated as included, all associated excavation, disposal and filling is measured in accordance with Section 5:
Excavating and filling. No deductions made in superficial items for voids of equal to or less than 1.00 m²
B All of the following items are measured in accordance with rules of Work Section 11: In-Situ concrete works:
a)In-situ concrete
b) Form work
c) Reinforcement
d)Joints
e)Worked finishes
f)Accessories cast in
C All of the following items are measured in linear metre (m) and extra over items measured in (nr):
a)Kerbs
b) Edging
c) Channels
d).
Paving accessories – deemed included
e).Line markings, width of less than 300 mm; width stated
D All of the following items measured in area (m²) if the width is over 300mm, girth and thickness stated, and linear metre (m) if
not exceeding 300mm and extra over items measured in (nr):
a)
Coated macadam and asphalt – thickness and girth on face stated.
b) Gravel, hogging and woodchip
c).Interlocking, brick and blocks, slabs, bricks, blocks, setts and cobbles
d).
Accessories – deemed included
e).Liquid applied surfacing, sheet surfacing, proprietary coloured surfacing and surface dressings
f).Sheet lining to pools, lakes, ponds, waterways and the like, but measured in linear metre (m) if width equal to or less than
500mm
PRICING (CONT*D)
a) Site furniture
b) Letters, figures, and symbols
c) Spot items
B Not used
C The rates for plants shall be deemed to include for all associated excavation, disposal and filling, unless stated as measured
separately.
E The following shall be measured in (nr) and identified in botanical name, supports and ties are deemed included:
a) Trees
b) Young nursery stock trees
c) Shrubs
d) Hedge plants – can measured in linear metre (m), height, spacing, number of rows and layout stated.
e) Plants – can measured in area (m²), size and number per m² stated
f) Bulbs, corns and tubers – can be measured in area (m²), size and weight per m² stated.
F Permanent fencing is measured in accordance with the rules of Work Section 36: Fencing.
PRICING (CONT*D)
A The rates for equipment and pipework ancillaries shall be deemed to include for all necessary insulation and fire rating
enclosure.
B The rates for pipework shall be deemed to include for all the fittings (e.g. bends, tees, junctions and branches, reducers, end
caps, etc.).
a)Preparing drawings
b)Operating manuals and instructions
E Work related to these Sections is classified in accordance with Section 39 and given under an appropriate Work Section
heading:
Primary Equipment
F Switchgear, distribution boards, contractors and starters and motor drives are enumerated (nr) stating the type, size, rated
capacity and method of fixing.
G The rates for switchboards, switchgear, distribution boards, control gear, fittings, equipment and the like shall include for:
a)All identification labels, warning notices, circuit schedules and the like.
b)The completion of the circuit schedules
PRICING (CONT*D)
A The rates for incandescent and fluorescent lighting fittings shall include for boxes, conduit boxes, wood blocks, moulded
patterae, break joint rings, ceiling roses, connector blocks, flexible cords, earth continuity, chokes, capacitors, starters, lamp
holders and the like.
B The rates for all light fittings shall include for all associated lamps, control gear, diffusers, shades and the like.
C The rates for clocks, telephones, fire alarms, burglar alarms, loudspeakers and the like shall include where required for all
boxes, conduit boxes, wooden blocks, moulded patterae, cover plates and the like.
D The rates for all socket outlets shall include for associated plug tops.
E The rates for surface accessories shall include for any necessary backplates and surface mounting boxes.
F The rates for all flush, semi-flush, recessed, semi-recessed and insertion items shall include for any necessary boxes.
Cable Containment
G Containment is enumerated (nr) stating the type, material, finish, section shape, dimensions, number of compartments,
method of jointing, fixings, and background for fixing.
a)Bending, cutting, screwing, jointing and all conduit fittings excluding boxes
b)Clips, saddles and crampets.
c)Forming holes for conduit entry.
d)Draw wires, draw cables, and the like.
PRICING (CONT*D)
A Cable trunking, cable tray, ladders and racks are measured by linear metre (m) and are deemed to include components for
fittings, earth continuity, cutting and jointing to fittings.
Cables
Final Circuits
B Cables in conduit or trunking and cables fixed to trays are measured in linear metre (m) as the net length of the conduit,
trunking or tray. Other cables are measured as fixed without allowance for sag.
D Cable joints and termination glands are deemed to be included in the measurement of cables.
E Cable and conduit in final circuits are measured on an enumerated points basis (nr) where they form part of a domestic or
similar simple installation from distribution boards and the like. The rates shall include conduit boxes, wiring accessories,
fittings, pullwires, clamps, bending, cutting , jointing and the likes.
Busbar
F Busbar is measured by linear metre (m) stating the type, size and rated capacity and any associated fittings are enumerated
(nr).
G Cutting and jointing busbar trunking to fittings, tap off units, feeder units and fire barriers are deemed to be included.
PRICING (CONT*D)
A Pipe duct fittings and accessories shall be deemed to be included in the measurement of pipes.
B Builder’s work shall include all of the below, but it should be noted that this list is not intended to be exhaustive and
everything necessary will be deemed to be included.
(i) Drilling, cutting or leaving of holes for pipes, ducts and the like through walls, floors, partitions, roofs, etc and subsequently
making good.
(ii) Cutting and pinning ends of supports for pipes, equipment, appliances, fittings and the like to walls, floors, partitions,
soffits, etc., and making good.
(iii) Cutting or leaving mortises, sinkings, etc., for holding down bolts, brackets, supports and the like and grouting in.
(iv) Cutting chases for pipes and the like in walls, floors, partitions, etc., and subsequently making good.
(v) Cutting and fitting around, boring holes through and making good of finishings up to pipes, supports, brackets, and the
like.
(vi) The formation of small concrete bases, plinths, etc. for plant, tanks and equipment, including anti-vibration pads as
necessary.
(vii) The painting of exposed pipe work, fittings, equipment, etc.
SERVICES GENERALLY
C The Main Contractor shall be completely responsible for obtaining the requirements for holes, fixings, and any other builder’s
work. He shall coordinate the requirements for builders work between trades and ensure that such information is as shown
on the drawings in accordance with his own and the employer’s requirements. Details of builder’s work which is not shown on
the drawings but which is required by the Main Contractor shall be forwarded to the engineer for his written approval before
the work is put in hand. Any cost of unnecessary work due to the Main Contractor failing to comply with these conditions or
failing to act upon such information given will be borne entirely by the Main Contractor.
D The drilling, cutting or leaving of holes or apertures through structural floors, walls, beams, etc., shall be avoided, but where
this becomes a necessity the Main Contractor must obtain the written approval of the Engineer before such work is put in
hand.
Fit-out Works
BILL 2
PRELIMINARIES
Conditions of Contract
A The Contractor should price here the cost and expense of all the 1 Item
works related to his obligations mentioned in the Conditions of
Contract
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 2 PR/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 2 - PRELIMINARIES & GENERAL CONDITIONS
PRELIMINARIES (CONT*D)
TEMPORARY WORKS
A Access road from nearest asphalted road to the site offices 1 Item
Water
Electricity
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 2 PR/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 2 - PRELIMINARIES & GENERAL CONDITIONS
PRELIMINARIES (CONT*D)
Security
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 2 PR/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 2 - PRELIMINARIES & GENERAL CONDITIONS
PRELIMINARIES (CONT*D)
OTHER COSTS
G Office stationary supplies includes but is not limited to paper for 1 Item
photocopiers (w/paper selection of A4/A3 and letter sizes),
facsimiles and printers, colour and black & white cartridges,
sharpeners, writing pads, pens, pencil, staplers, tape, hole
punchers, files and folders and other supplies
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 2 PR/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 2 - PRELIMINARIES & GENERAL CONDITIONS
PRELIMINARIES (CONT*D)
B Consumables such as coffee various types, tea, sugar, fresh milk, 1 Item
soft drinks, fruit juices, bottled mineral water, biscuits, paper and
plastic products (cups, paper towels serviettes, etc.)
TEMPORARY WORKS
H Provision of lighting and power for the Works and provision of 1 Item
supply/refill of fuel for generators dedicated to site offices and
facilities and generators maintenance
K Provision of sanitation for the Works and sewage disposal and 1 Item
maintenance of site offices and facilities
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 2 PR/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 2 - PRELIMINARIES & GENERAL CONDITIONS
PRELIMINARIES (CONT*D)
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 2 PR/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 2 - PRELIMINARIES & GENERAL CONDITIONS
PRELIMINARIES (CONT*D)
Other costs
B The Contractor shall allow for all other obligations in accordance 1 Item
with the Employer's Requirements, Policies and Guidelines and
other relevant documents of the Contract, not specifically
identified under non-recurring preliminary costs incurred at the
completion of the Works. The Contractor is to detail below any
such obligations, together with the relevant clause, number or
reference as applicable
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 2 PR/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 2 - PRELIMINARIES & GENERAL CONDITIONS
PRELIMINARIES (CONT*D)
COLLECTION
Page : PR/1
Page : PR/2
Page : PR/3
Page : PR/4
Page : PR/5
Page : PR/6
Page : PR/7
BILL SUMMARY
PRELIMINARIES PR/8
Fit-out Works
BILL 3
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
COLLECTION
Page : 3.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SUPERSTRUCTURE (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SUPERSTRUCTURE (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.2/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.2/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 3.2/1
Page : 3.2/2
Page : 3.2/3
Page : 3.2/4
INTERNAL FINISHES
WALL FINISHES
A Type W200 25 m2
B Type W201 13 m2
D Type W204 32 m2
E Type W206 39 m2
F Type W202 31 m2
G Type W501 62 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
A Type W901 13 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
FLOOR FINISHES
Screeds
A To floors 645 m2
Finish to floors
C Type F-102 12 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
CEILING FINISHES
Finish to ceilings
A Type C-201 4 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.3/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
COLLECTION
Page : 3.3/1
Page : 3.3/2
Page : 3.3/3
Page : 3.3/4
Signage
A Type ST01 1 nr
B Type ST03 2 nr
C Type DS01 2 nr
D Type DS02 3 nr
E Type LD01 1 nr
F Type LD02 1 nr
G Type ES02 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
Furnitures
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.4/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
Furnitures (CONT*D)
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.4/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
COLLECTION
Page : 3.4/1
Page : 3.4/2
Page : 3.4/3
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Primary equipment
A DB 1 nr
Final circuits
Socket outlets
D Floor Box 8 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
C Floor Box 8 nr
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
Emergency Lighting
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
39 Electrical services
Final circuits
D Flasher 3 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
B Flasher 3 nr
IT System
Final circuits
G WIFI Ceiling 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
IT System (CONT*D)
C 65" TV 2 nr
D WIFI Ceiling 1 nr
Security System
CCTV
Final circuits
E Dome Camera 12 nr
F Box Camera 3 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
A Dome Camera 12 nr
B Box Camera 3 nr
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 7 nr
D Door with card reader, Electric lock, BGU and exit Push button 7 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
SERVICES (CONT*D)
COLLECTION
Page : 3.5/1
Page : 3.5/2
Page : 3.5/3
Page : 3.5/4
Page : 3.5/5
Page : 3.5/6
Page : 3.5/7
Page : 3.5/8
Page : 3.5/9
Page : 3.5/10
Page : 3.5/11
Page : 3.5/12
EXTERNAL WORKS
35 Site works
Hardscape
A Gravel; 15-25mm dia, 50mm depth, Light beige/ grey color natural 12 m2
finish
Softscape
Shrubs
B Lawsonia-inermis 30 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 3.6/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
COLLECTION
Page : 3.6/1
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 3 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 3 - GF GUEST ENTRANCE + CAFE + ATM NOOKS
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 3.2/5
Services 3.5/13
Fit-out Works
BILL 4
GF CENTRAL CORRIDOR
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
COLLECTION
Page : 4.1/1
SUPERSTRUCTURE
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 4.2/1
INTERNAL FINISHES
WALL FINISHES
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
FLOOR FINISHES
Screeds
A To floors 314 m2
Finish to floors
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
CEILING FINISHES
Finish to ceilings
B Type C-800 10 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
COLLECTION
Page : 4.3/1
Page : 4.3/2
Page : 4.3/3
Signage
A Type DS01 2 nr
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
COLLECTION
Page : 4.4/1
SERVICES
DISPOSAL INSTALLATIONS
Pipework
A 50mm diameter 11 m
B 75mm diameter 11 m
Pipe ancillaries
Clean out
C 50mm diameter 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
WATER INSTALLATIONS
38 Mechanical services
Pipework
A 15mm diameter 23 m
B 22mm diameter 30 m
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
Ductwork
Duct ancillaries
B 200 mm Diameter 38 nr
E Ref. VAV-GE-G-2/3-02 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
ELECTRICAL INSTALLATIONS
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
Lighting Installation
A Lighting points 45 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
39 Electrical services
Final circuits
D Flasher 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
B Flasher 1 nr
IT System
Final circuits
F WIFI Ceiling 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
IT System (CONT*D)
B 65" TV 2 nr
C WIFI Ceiling 2 nr
Security System
CCTV
Final circuits
D Dome Camera 2 nr
E Dome Camera 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 4.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
SERVICES (CONT*D)
COLLECTION
Page : 4.5/1
Page : 4.5/2
Page : 4.5/3
Page : 4.5/4
Page : 4.5/5
Page : 4.5/6
Page : 4.5/7
Page : 4.5/8
Page : 4.5/9
Page : 4.5/10
Page : 4.5/11
Page : 4.5/12
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 4 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 4 - GF CENTRAL CORRIDOR
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 4.2/2
Services 4.5/13
Fit-out Works
BILL 5
GF WEST CIRCULATION 01
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
COLLECTION
Page : 5.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 5.2/1
Page : 5.2/2
INTERNAL FINISHES
WALL FINISHES
B Type W206 84 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
Screeds
A To floors 229 m2
Finish to floors
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
CEILING FINISHES
Finish to ceilings
A Type C-200 65 m2
C Type C-800 5 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
COLLECTION
Page : 5.3/1
Page : 5.3/2
Page : 5.3/3
Signage
A Type ID01 2 nr
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
COLLECTION
Page : 5.4/1
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
B 200 mm Diameter 24 nr
E Ref. VAV-GE-G-2/3-02 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
Lighting Installation
A Lighting points 24 nr
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
Emergency Lighting
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
39 Electrical services
Final circuits
D Flasher 2 nr
E Response Indicator 6 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
B Flasher 2 nr
C Response Indicator 6 nr
IT System
Final circuits
E WIFI Ceiling 1 nr
F WIFI Ceiling 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
Final circuits
A Dome Camera 2 nr
B Dome Camera 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 5.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
SERVICES (CONT*D)
COLLECTION
Page : 5.5/1
Page : 5.5/2
Page : 5.5/3
Page : 5.5/4
Page : 5.5/5
Page : 5.5/6
Page : 5.5/7
Page : 5.5/8
Page : 5.5/9
Page : 5.5/10
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 5 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 5 - GF WEST CIRCULATION 01
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 5.2/3
Services 5.5/11
Fit-out Works
BILL 6
GF WEST CIRCULATION 02
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
COLLECTION
Page : 6.1/1
SUPERSTRUCTURE
INTERNAL DOORS
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 6.2/1
INTERNAL FINISHES
WALL FINISHES
A Type W203 16 m2
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
FLOOR FINISHES
Screeds
A To floors 342 m2
Finish to floors
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
CEILING FINISHES
A Type C-200 65 m2
C Type C-800 5 m2
Suspended Ceilings
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
COLLECTION
Page : 6.3/1
Page : 6.3/2
Page : 6.3/3
Signage
A Type DS01 2 nr
B Type LD03 1 nr
C Type LD04 1 nr
Furnitures
Artwork
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
COLLECTION
Page : 6.4/1
SERVICES
WATER INSTALLATION
38 Mechanical services
Pipework
A 22mm diameter 7 m
Pipe ancillaries
Gate Valve
B 22mm diameter 2 nr
C 22mm diameter 1 nr
D 22mm diameter 1 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
Ductwork
Duct ancillaries
B 200 mm Diameter 42 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Panel boards
Primary equipment
A DB 1 nr
Final circuits
Socket outlets
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
C Floor Box 3 nr
Lighting Installation
Emergency Lighting
Final circuits
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
Emergency Lighting
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
39 Electrical services
Final circuits
D Flasher 3 nr
E Response Indicator 3 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
B Flasher 3 nr
C Response Indicator 3 nr
IT System
Final circuits
E WIFI Ceiling 2 nr
F WIFI Ceiling 2 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
CCTV
Final circuits
A Dome Camera 7 nr
B Dome Camera 7 nr
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 3 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 3 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 6.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
SERVICES (CONT*D)
COLLECTION
Page : 6.5/1
Page : 6.5/2
Page : 6.5/3
Page : 6.5/4
Page : 6.5/5
Page : 6.5/6
Page : 6.5/7
Page : 6.5/8
Page : 6.5/9
Page : 6.5/10
Page : 6.5/11
Page : 6.5/12
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 6 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 6 - GF WEST CIRCULATION 02
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 6.2/2
Services 6.5/13
Fit-out Works
BILL 7
GF WEST CIRCULATION 03
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
COLLECTION
Page : 7.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 7.2/1
Page : 7.2/2
INTERNAL FINISHES
WALL FINISHES
A Type W203 26 m2
B Type W206 16 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
FLOOR FINISHES
Screeds
A To floors 114 m2
Finish to floors
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
CEILING FINISHES
Finish to ceilings
B Type J-900 23 m
C Type C-800 10 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
COLLECTION
Page : 7.3/1
Page : 7.3/2
Page : 7.3/3
Page : 7.3/4
Signage
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
COLLECTION
Page : 7.4/1
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
B 200 mm Diameter 44 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Panel boards
Primary equipment
A DB 1 nr
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
Socket outlets
Lighting Installation
Final circuits
B Lighting points 17 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
39 Electrical services
Final circuits
D Flasher 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
B Flasher 1 nr
IT System
Final circuits
D WIFI Ceiling 1 nr
E WIFI Ceiling 1 nr
Security System
CCTV
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
Final circuits
A Dome Camera 1 nr
B Box Camera 1 nr
C Dome Camera 1 nr
D Box Camera 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 7.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
SERVICES (CONT*D)
COLLECTION
Page : 7.5/1
Page : 7.5/2
Page : 7.5/3
Page : 7.5/4
Page : 7.5/5
Page : 7.5/6
Page : 7.5/7
Page : 7.5/8
Page : 7.5/9
Page : 7.5/10
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 7 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 7 - GF WEST CIRCULATION 03
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 7.2/3
Services 7.5/11
Fit-out Works
BILL 8
GF EAST CIRCULATION 01
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
COLLECTION
Page : 8.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 8.2/1
Page : 8.2/2
INTERNAL FINISHES
WALL FINISHES
B Type W206 80 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
FLOOR FINISHES
Screeds
A To floors 200 m2
Finish to floors
B Type F-300B 23 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
CEILING FINISHES
Finish to ceilings
A Type C-200 79 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
COLLECTION
Page : 8.3/1
Page : 8.3/2
Page : 8.3/3
Signage
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
COLLECTION
Page : 8.4/1
SERVICES
DISPOSAL INSTALLATIONS
38 Mechanical services
Pipework
A 50mm diameter 4 m
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
B 200 mm Diameter 18 nr
E Ref. VAV-GE-G-2/3-01 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
Lighting Installation
Final circuits
A Lighting points 16 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
39 Electrical services
Final circuits
D Flasher 2 nr
E Response Indicator 4 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
C Flasher 2 nr
D Response Indicator 4 nr
IT System
Final circuits
G WIFI Ceiling 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
IT System (CONT*D)
B 65" TV 1 nr
C WIFI Ceiling 1 nr
Security System
CCTV
Final circuits
D Dome Camera 2 nr
E Dome Camera 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 8.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
SERVICES (CONT*D)
COLLECTION
Page : 8.5/1
Page : 8.5/2
Page : 8.5/3
Page : 8.5/4
Page : 8.5/5
Page : 8.5/6
Page : 8.5/7
Page : 8.5/8
Page : 8.5/9
Page : 8.5/10
Page : 8.5/11
Page : 8.5/12
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 8 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 8 - GF EAST CIRCULATION 01
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 8.2/3
Services 8.5/13
Fit-out Works
BILL 9
GF EAST CIRCULATION 02
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
COLLECTION
Page : 9.1/1
SUPERSTRUCTURE
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 9.2/1
INTERNAL FINISHES
WALL FINISHES
B Type W501 80 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
FLOOR FINISHES
Screeds
A To floors 166 m2
Finish to floors
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
CEILING FINISHES
Finish to ceilings
A Type C-200 77 m2
B Type C-202 89 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
COLLECTION
Page : 9.3/1
Page : 9.3/2
Page : 9.3/3
Signage
A Type ID01 1 nr
B Type DS01 1 nr
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
COLLECTION
Page : 9.4/1
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
B 200 mm Diameter 21 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
ELECTRICAL INSTALLATIONS
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
Lighting Installation
A Lighting points 16 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
39 Electrical services
Final circuits
D Flasher 2 nr
E Response Indicator 4 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
C Flasher 2 nr
D Response Indicator 4 nr
IT System
Final circuits
G WIFI Ceiling 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
IT System (CONT*D)
B 65" TV 1 nr
C WIFI Ceiling 1 nr
Security System
CCTV
Final circuits
D Dome Camera 2 nr
E Box Camera 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
B Box Camera 1 nr
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 nr
D Door with card reader, Electric lock, BGU and exit Push button 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 9.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
SERVICES (CONT*D)
COLLECTION
Page : 9.5/1
Page : 9.5/2
Page : 9.5/3
Page : 9.5/4
Page : 9.5/5
Page : 9.5/6
Page : 9.5/7
Page : 9.5/8
Page : 9.5/9
Page : 9.5/10
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 9 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 9 - GF EAST CIRCULATION 02
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 9.2/2
Services 9.5/11
Fit-out Works
BILL 10
GF EAST CIRCULATION 03
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
COLLECTION
Page : 10.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 10.2/1
Page : 10.2/2
INTERNAL FINISHES
WALL FINISHES
B Type W206 7 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
FLOOR FINISHES
Screeds
A To floors 127 m2
Finish to floors
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
CEILING FINISHES
Finish to ceilings
B Type J-900 49 m
C Type C-800 8 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
COLLECTION
Page : 10.3/1
Page : 10.3/2
Page : 10.3/3
Page : 10.3/4
Signage
Furnitures
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
COLLECTION
Page : 10.4/1
SERVICES
DISPOSAL INSTALLATION
38 Mechanical services
Pipe ancillaries
Planter drain
A 50mm diameter 3 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
B 200 mm Diameter 48 nr
D 225x225mm 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
A Ref. VAV-GE-G-6/3-01 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Panel boards
Primary equipment
A DB 1 nr
Final circuits
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
Socket outlets
Lighting Installation
Final circuits
B Lighting points 52 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
39 Electrical services
Final circuits
D Flasher 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
C Flasher 1 nr
IT System
Final circuits
F WIFI Ceiling 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
IT System (CONT*D)
Security System
Final circuits
B Dome Camera 1 nr
C Dome Camera 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.5/14
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
SERVICES (CONT*D)
COLLECTION
Page : 10.5/1
Page : 10.5/2
Page : 10.5/3
Page : 10.5/4
Page : 10.5/5
Page : 10.5/6
Page : 10.5/7
Page : 10.5/8
Page : 10.5/9
Page : 10.5/10
Page : 10.5/11
Page : 10.5/12
Page : 10.5/13
EXTERNAL WORKS
35 Site works
Hardscape
A Gravel; 15-25mm dia, 50mm depth, Light beige/ grey color natural 24 m2
finish
Softscape
Shrubs
B Asparagus sprengeri 46 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 10.6/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
COLLECTION
Page : 10.6/1
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 10 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 10 - GF EAST CIRCULATION 03
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 10.2/3
Services 10.5/14
Fit-out Works
BILL 11
GF RECREATION LOBBY
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
COLLECTION
Page : 11.1/1
SUPERSTRUCTURE
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 11.2/1
INTERNAL FINISHES
WALL FINISHES
B Type W206 29 m2
C Type W501 52 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
FLOOR FINISHES
Screeds
A To floors 586 m2
Finish to floors
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
CEILING FINISHES
Finish to ceilings
B Type C-800 10 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
COLLECTION
Page : 11.3/1
Page : 11.3/2
Page : 11.3/3
Page : 11.3/4
Signage
A Type ID01 3 nr
B Type ID03 1 nr
C Type DS01 1 nr
Furnitures
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.4/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
COLLECTION
Page : 11.4/1
Page : 11.4/2
SERVICES
DISPOSAL INSTALLATION
38 Mechanical services
Pipework
A 50mm diameter 37 m
Pipe ancillaries
Clean out
B 50mm diameter 4 nr
Planter drain
C 50mm diameter 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
B 200 mm Diameter 82 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Panel boards
Primary equipment
A DB 1 nr
Final circuits
Socket outlets
D Floor Box 3 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
Socket outlets
C Floor Box 3 nr
Lighting Installation
Final circuits
D Lighting points 88 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
39 Electrical services
Final circuits
D Flasher 3 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
C Flasher 3 nr
IT System
Final circuits
G WIFI Ceiling 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
IT System (CONT*D)
B 65" TV 1 nr
C WIFI Ceiling 1 nr
Security System
CCTV
Final circuits
D Dome Camera 7 nr
E Dome Camera 7 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
Access Control
Final circuits
A Door with card reader, Electric lock, BGU and exit Push button 2 nr
B Door with card reader, Electric lock, BGU and exit Push button 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.5/14
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
SERVICES (CONT*D)
COLLECTION
Page : 11.5/1
Page : 11.5/2
Page : 11.5/3
Page : 11.5/4
Page : 11.5/5
Page : 11.5/6
Page : 11.5/7
Page : 11.5/8
Page : 11.5/9
Page : 11.5/10
Page : 11.5/11
Page : 11.5/12
Page : 11.5/13
EXTERNAL WORKS
35 Site works
Hardscape
A Gravel; 15-25mm dia, 50mm depth, Light beige/ grey color natural 16 m2
finish
Softscape
Shrubs
D Asparagus sprengeri 26 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 11.6/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
COLLECTION
Page : 11.6/1
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 11 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 11 - GF RECREATION LOBBY
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 11.2/2
Services 11.5/14
Fit-out Works
BILL 12
GF RECREATION RECEPTION
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
COLLECTION
Page : 12.1/1
Signage
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
COLLECTION
Page : 12.2/1
SERVICES
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
SERVICES (CONT*D)
Lighting Installation
Final circuits
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
SERVICES (CONT*D)
Emergency Lighting
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.3/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.3/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.3/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 12.3/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
SERVICES (CONT*D)
COLLECTION
Page : 12.3/1
Page : 12.3/2
Page : 12.3/3
Page : 12.3/4
Page : 12.3/5
Page : 12.3/6
Page : 12.3/7
Page : 12.3/8
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 12 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 12 - GF RECREATION RECEPTION
COLLECTION
Page : D/Add/1
BILL SUMMARY
Services 12.3/9
Fit-out Works
BILL 13
GF AL ROUDHA OASIS
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
COLLECTION
Page : 13.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 13.2/1
Page : 13.2/2
INTERNAL FINISHES
WALL FINISHES
B Type W206 12 m2
C Type W210 32 m2
D Type W212 32 m2
E Type W213 32 m2
H Type W303 82 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
A Type W304 82 m2
D Type W306 82 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
FLOOR FINISHES
Screeds
A To floors 1,024 m2
Finish to floors
C Type F-308 27 m2
D Type F-311 25 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
A Type F-309 21 m2
C Type F-302 22 m2
D Type F-303 28 m2
E Type F-304 31 m2
F Type F-306 46 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
B Type J-900 96 m
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.3/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
CEILING FINISHES
Finish to ceilings
A Type C-202 45 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.3/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
COLLECTION
Page : 13.3/1
Page : 13.3/2
Page : 13.3/3
Page : 13.3/4
Page : 13.3/5
Page : 13.3/6
Signage
A Type ID01 2 nr
B Type DS02 2 nr
Furnitures
D Ref. A12A 1 nr
E Ref. A12B 1 nr
F Ref. A12C 1 nr
H Ref. A14 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
Furnitures (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.4/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
Furnitures (CONT*D)
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.4/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
COLLECTION
Page : 13.4/1
Page : 13.4/2
Page : 13.4/3
SERVICES
DISPOSAL INSTALLATION
38 Mechanical services
Pipework
A 50mm diameter 13 m
B 75mm diameter 49 m
C 100mm diameter 37 m
Pipe ancillaries
End cap
D 50mm diameter 2 nr
E 100mm diameter 2 nr
Floor Drain
F 50mm diameter 12 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
WATER INSTALLATIONS
38 Mechanical services
Pipework
Pipe ancillaries
Isolation Valves
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
B 200 mm Diameter 24 nr
D Ref. VAV-GE-G-6/3-02 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Panel boards
Primary equipment
A DB 1 nr
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
COMMUNICATION, SECURITY AND CONTROL SYSTEMS
39 Electrical services
Final circuits
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
IT System
A WIFI Wall 4 nr
B WIFI Ceiling 1 nr
C WIFI Wall 4 nr
D WIFI Ceiling 1 nr
Security System
CCTV
Final circuits
E Dome Camera 8 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
A Box Camera 2 nr
B Dome Camera 8 nr
C Box Camera 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
SERVICES (CONT*D)
COLLECTION
Page : 13.5/1
Page : 13.5/2
Page : 13.5/3
Page : 13.5/4
Page : 13.5/5
Page : 13.5/6
Page : 13.5/7
Page : 13.5/8
Page : 13.5/9
Page : 13.5/10
Page : 13.5/11
Page : 13.5/12
EXTERNAL WORKS
35 Site works
Hardscape
A Gravel; 15-25mm dia, 50mm depth, Light beige/ grey color natural 497 m2
finish
D Sculptures 4 nr
E Water bodies 49 m2
Softscape
Shrubs
F Lawsonia-inermis 201 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.6/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
Shrubs (CONT*D)
A Aerva javanica 48 nr
Grass
Ground cover
Trees
E Salvadora persica 10 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 13.6/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
COLLECTION
Page : 13.6/1
Page : 13.6/2
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 13 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 13 - GF AL ROUDHA OASIS
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 13.2/3
Services 13.5/13
Fit-out Works
BILL 14
GF PUBLIC BATHROOM
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
Demolish and off site disposal of existing walls, floor finishes, wall
finishes, ceilings and MEP services as per drawings and
specification
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
COLLECTION
Page : 14.1/1
SUPERSTRUCTURE
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 14.2/1
Page : 14.2/2
INTERNAL FINISHES
WALL FINISHES
B To receive paint 35 m2
C Type W203 35 m2
Mosaic Wall tile; including all accessories and works required; all
in accordance with the Specifications
E Type MOS-001 58 m2
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
Screeds
A To floors 62 m2
Finish to floors
Porcelain Floor tile; Matt finish, colour : sand, size : 120x240, laid
on self levelling compound (measured separately) including
preparation and all works required; all in accordance with the
Specifications
B Type F-300B 10 m2
C Type F-003 52 m2
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
CEILING FINISHES
Finish to ceilings
A Type C-202 62 m2
Suspended Ceilings
C 250mm high 11 m
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
COLLECTION
Page : 14.3/1
Page : 14.3/2
Page : 14.3/3
Signage
A Signages 2 nr
Countertop
Artwork
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
COLLECTION
Page : 14.4/1
SERVICES
SANITARY INSTALLATIONS
38 Mechanical services
A Water Closet 9 nr
D Trash bin 9 nr
E Tissue holder 9 nr
F Health Spray 9 nr
H Mirror 10 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
DISPOSAL INSTALLATION
38 Mechanical services
Pipework
A 32mm diameter 8 m
B 50mm diameter 12 m
C 75mm diameter 23 m
D 110mm diameter 26 m
Pipe ancillaries
Clean out
E 75mm diameter 2 nr
F 110mm diameter 2 nr
Floor Trap
G 75mm diameter 13 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
Valve
A 75mm diameter 1 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
WATER INSTALLATION
38 Mechanical services
Pipework
A 15mm diameter 32 m
B 22mm diameter 46 m
Pipe ancillaries
Isolation Valves
C 15mm diameter 2 nr
D 22mm diameter 6 nr
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
Lighting Installation
Emergency Lighting
Final circuits
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
Security System
CCTV
Final circuits
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/14
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 14.5/15
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
SERVICES (CONT*D)
COLLECTION
Page : 14.5/1
Page : 14.5/2
Page : 14.5/3
Page : 14.5/4
Page : 14.5/5
Page : 14.5/6
Page : 14.5/7
Page : 14.5/8
Page : 14.5/9
Page : 14.5/10
Page : 14.5/11
Page : 14.5/12
Page : 14.5/13
Page : 14.5/14
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 14 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 14 - GF PUBLIC BATHROOM
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 14.2/3
Services 14.5/15
Fit-out Works
BILL 15
GF STAIRS
INTERNAL FINISHES
WALL FINISHES
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 15 15.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 15 - GF STAIRS
FLOOR FINISHES
Screeds
A To floors 297 m2
Omani Beige marble Split face, laid on cement and sand screed
(measured separately) including preparation and all works
required; all in accordance with the Specifications
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 15 15.1/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 15 - GF STAIRS
COLLECTION
Page : 15.1/1
Page : 15.1/2
EXTERNAL WORKS
35 Site works
Hardscape
A Gravel; 15-25mm dia, 50mm depth, Light beige/ grey color natural 14 m2
finish
Softscape
Shrubs
B Asparagus sprengeri 52 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 15 15.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 15 - GF STAIRS
COLLECTION
Page : 15.2/1
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 15 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 15 - GF STAIRS
COLLECTION
Page : D/Add/1
BILL 15 - GF Stairs
BILL SUMMARY
Fit-out Works
BILL 16
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
H Allow for making good and treatment of cut concrete surfaces 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
3 Demolitions (CONT*D)
D Demolition of upstand 23 m3
G Allow for making good and treatment of cut concrete surfaces 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.1/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
COLLECTION
Page : 16.1/1
Page : 16.1/2
SUPERSTRUCTURE
UPPER FLOORS
15 Structural metalwork
C Allow for anchor bolt drilling and installation to existing columns 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 16.2/1
Page : 16.2/2
INTERNAL FINISHES
WALL FINISHES
B Type W201 14 m2
D Type W206 75 m2
E Type W202 27 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
A Type W301 22 m2
B Type J400 25 m2
C Type W501 18 m2
D Type W500 41 m
E Type W900 14 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
FLOOR FINISHES
Screeds
A To floors 1,416 m2
Finish to floors
Porcelain Floor tile; Matt finish, colour : sand, size : 120x240, laid
on self levelling compound (measured separately) including
preparation and all works required; all in accordance with the
Specifications
D Type F-101 15 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
A Type F-102 14 m2
C Type J-900 21 m
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
CEILING FINISHES
Finish to ceilings
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.3/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
COLLECTION
Page : 16.3/1
Page : 16.3/2
Page : 16.3/3
Page : 16.3/4
Page : 16.3/5
Signage
A Type ST01 2 nr
B Type ID01 2 nr
C Type DS01 1 nr
D Type DS02 1 nr
E Type LD01 1 nr
F Type LD02 1 nr
G Type ES01 2 nr
H Type ES02 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
Furnitures
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.4/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
Furnitures (CONT*D)
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.4/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
COLLECTION
Page : 16.4/1
Page : 16.4/2
Page : 16.4/3
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
Lighting Installation
Final circuits
A Lighting points 74 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 16.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
SERVICES (CONT*D)
COLLECTION
Page : 16.5/1
Page : 16.5/2
Page : 16.5/3
Page : 16.5/4
Page : 16.5/5
Page : 16.5/6
Page : 16.5/7
Page : 16.5/8
Page : 16.5/9
Page : 16.5/10
Page : 16.5/11
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 16 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 16 - FF VIP ENTRANCE + MAIN CIRCULATION
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 16.2/3
Services 16.5/12
Fit-out Works
BILL 17
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
COLLECTION
Page : 17.1/1
SUPERSTRUCTURE
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 17.2/1
INTERNAL FINISHES
WALL FINISHES
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
FLOOR FINISHES
Screeds
A To floors 1,842 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
CEILING FINISHES
Finish to ceilings
C Type J-900 22 m
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
COLLECTION
Page : 17.3/1
Page : 17.3/2
Page : 17.3/3
Page : 17.3/4
Signage
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
COLLECTION
Page : 17.4/1
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
SERVICES (CONT*D)
COLLECTION
Page : 17.5/1
Page : 17.5/2
Page : 17.5/3
Page : 17.5/4
Page : 17.5/5
Page : 17.5/6
Page : 17.5/7
Page : 17.5/8
Page : 17.5/9
Page : 17.5/10
Page : 17.5/11
EXTERNAL WORKS
35 Site works
Hardscape
A Gravel; 15-25mm dia, 50mm depth, Light beige/ grey color natural 61 m2
finish
Softscape
Shrubs
D Lawsonia-inermis 60 nr
E Leptadenia pyrotechnica 30 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.6/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
Softscape (CONT*D)
Grass
A Pennisetum setaceum 56 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 17.6/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
COLLECTION
Page : 17.6/1
Page : 17.6/2
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 17 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 17 - FF AL MIS'HAB HALL (ABU MOUSA HALL)
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 17.2/2
Services 17.5/12
Fit-out Works
BILL 18
FF PRE FUNCTION
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
COLLECTION
Page : 18.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 18.2/1
Page : 18.2/2
INTERNAL FINISHES
WALL FINISHES
B Type W206 20 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
FLOOR FINISHES
Screeds
A To floors 422 m2
Finish to floors
Porcelain Floor tile; Matt finish, colour : sand, size : 120x240, laid
on self levelling compound (measured separately) including
preparation and all works required; all in accordance with the
Specifications
C Type F-103 52 m2
D Type J-900 33 m
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
CEILING FINISHES
Finish to ceilings
A Type C-202 16 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
COLLECTION
Page : 18.3/1
Page : 18.3/2
Page : 18.3/3
Page : 18.3/4
Signage
Furnitures
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
COLLECTION
Page : 18.4/1
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
Lighting Installation
Final circuits
A Lighting points 12 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
SERVICES (CONT*D)
COLLECTION
Page : 18.5/1
Page : 18.5/2
Page : 18.5/3
Page : 18.5/4
Page : 18.5/5
Page : 18.5/6
Page : 18.5/7
Page : 18.5/8
Page : 18.5/9
Page : 18.5/10
EXTERNAL WORKS
35 Site works
Hardscape
A Gravel; 15-25mm dia, 50mm depth, Light beige/ grey color natural 14 m2
finish
Softscape
Shrubs
D Lawsonia-inermis 29 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 18.6/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
COLLECTION
Page : 18.6/1
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 18 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 18 - FF PRE FUNCTION
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 18.2/3
Services 18.5/11
Fit-out Works
BILL 19
FF WEST CIRCULATION
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
COLLECTION
Page : 19.1/1
SUPERSTRUCTURE
A Glazed partition to retail zones 7, 8, 9, 10, 11 and 12; Type W400 267 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 19.2/1
Page : 19.2/2
INTERNAL FINISHES
WALL FINISHES
B Type W206 94 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
Screeds
A To floors 651 m2
Finish to floors
Porcelain Floor tile; Matt finish, colour : sand, size : 120x240, laid
on self levelling compound (measured separately) including
preparation and all works required; all in accordance with the
Specifications
D J-900 54 m
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
CEILING FINISHES
Finish to ceilings
A Type C-202 13 m2
B Type C-800 25 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
COLLECTION
Page : 19.3/1
Page : 19.3/2
Page : 19.3/3
Page : 19.3/4
Signage
A Type ID03 2 nr
B Type DS01 1 nr
C Type LD03 1 nr
D Type LD04 1 nr
E Type ES02 1 nr
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
COLLECTION
Page : 19.4/1
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
Lighting Installation
Final circuits
A Lighting points 92 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 19.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
SERVICES (CONT*D)
COLLECTION
Page : 19.5/1
Page : 19.5/2
Page : 19.5/3
Page : 19.5/4
Page : 19.5/5
Page : 19.5/6
Page : 19.5/7
Page : 19.5/8
Page : 19.5/9
Page : 19.5/10
Page : 19.5/11
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 19 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 19 - FF WEST CIRCULATION
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 19.2/3
Services 19.5/12
Fit-out Works
BILL 20
FF EAST CIRCULATION
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
COLLECTION
Page : 20.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 20.2/1
Page : 20.2/2
INTERNAL FINISHES
WALL FINISHES
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
FLOOR FINISHES
Screeds
A To floors 928 m2
Porcelain Floor tile; Matt finish, colour : sand, size : 120x240, laid
on self levelling compound (measured separately) including
preparation and all works required; all in accordance with the
Specifications
C Type F-101B 98 m2
D J-900 73 m
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
CEILING FINISHES
Finish to ceilings
B Type C-800 23 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
COLLECTION
Page : 20.3/1
Page : 20.3/2
Page : 20.3/3
Page : 20.3/4
Signage
A Type ID03 1 nr
B Type DS02 1 nr
C Type LD05 1 nr
D Type LD06 1 nr
E Type ES01 2 nr
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
COLLECTION
Page : 20.4/1
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
Lighting Installation
Final circuits
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
Emergency Lighting
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 20.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
SERVICES (CONT*D)
COLLECTION
Page : 20.5/1
Page : 20.5/2
Page : 20.5/3
Page : 20.5/4
Page : 20.5/5
Page : 20.5/6
Page : 20.5/7
Page : 20.5/8
Page : 20.5/9
Page : 20.5/10
Page : 20.5/11
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 20 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 20 - FF EAST CIRCULATION
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 20.2/3
Services 20.5/12
Fit-out Works
BILL 21
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
COLLECTION
Page : 21.1/1
SUPERSTRUCTURE
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 21.2/1
INTERNAL FINISHES
WALL FINISHES
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
FLOOR FINISHES
Screeds
A To floors 374 m2
Finish to floors
Porcelain Floor tile; Matt finish, colour : sand, size : 120x240, laid
on self levelling compound (measured separately) including
preparation and all works required; all in accordance with the
Specifications
C Type F-101 44 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
CEILING FINISHES
Finish to ceilings
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
COLLECTION
Page : 21.3/1
Page : 21.3/2
Page : 21.3/3
Signage
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
COLLECTION
Page : 21.4/1
SERVICES
SPACE HEATING AND AIR CONDITIONING
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
Lighting Installation
Final circuits
A Lighting points 47 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 21.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
SERVICES (CONT*D)
COLLECTION
Page : 21.5/1
Page : 21.5/2
Page : 21.5/3
Page : 21.5/4
Page : 21.5/5
Page : 21.5/6
Page : 21.5/7
Page : 21.5/8
Page : 21.5/9
Page : 21.5/10
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 21 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 21 - FF CONNECTION TO EAST WING
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 21.2/2
Services 21.5/11
Fit-out Works
BILL 22
FF PUBLIC BATHROOM 1
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
Demolish and off site disposal of existing walls, floor finishes, wall
finishes, ceilings, doors and MEP services as per drawings and
specification
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
COLLECTION
Page : 22.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 22.2/1
Page : 22.2/2
INTERNAL FINISHES
WALL FINISHES
Mosaic Wall tile; including all accessories and works required; all
in accordance with the Specifications
D Type MOS-001 48 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
FLOOR FINISHES
Screeds
A To floors 62 m2
Finish to floors
Porcelain Floor tile; Matt finish, colour : sand, size : 120x240, laid
on self levelling compound (measured separately) including
preparation and all works required; all in accordance with the
Specifications
C Type F-003 44 m2
D To toilet floors 44 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
CEILING FINISHES
Finish to ceilings
A Type C-202 61 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
COLLECTION
Page : 22.3/1
Page : 22.3/2
Page : 22.3/3
Page : 22.3/4
Signages
A Toilet sign 2 nr
Countertop
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
COLLECTION
Page : 22.4/1
SERVICES
SANITARY INSTALLATIONS
38 Mechanical services
A Water Closet 7 nr
C Urinals 2 nr
E Trash bin 7 nr
F Tissue holder 7 nr
G Health Spray 7 nr
H Urinal partition 2 nr
K Mirror 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
DISPOSAL INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Clean out
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
Floor Trap
Valve
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
WATER INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Isolation Valves
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
Lighting Installation
A Lighting points 53 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
Security System
CCTV
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/14
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 22.5/15
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
SERVICES (CONT*D)
COLLECTION
Page : 22.5/1
Page : 22.5/2
Page : 22.5/3
Page : 22.5/4
Page : 22.5/5
Page : 22.5/6
Page : 22.5/7
Page : 22.5/8
Page : 22.5/9
Page : 22.5/10
Page : 22.5/11
Page : 22.5/12
Page : 22.5/13
Page : 22.5/14
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 22 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 22 - FF PUBLIC BATHROOM 1
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 22.2/3
Services 22.5/15
Fit-out Works
BILL 23
FF PUBLIC BATHROOM 2
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
Demolish and off site disposal of existing walls, floor finishes, wall
finishes, ceilings, doors and MEP services as per drawings and
specification
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
COLLECTION
Page : 23.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 23.2/1
Page : 23.2/2
INTERNAL FINISHES
WALL FINISHES
B To receive paint 25 m2
Mosaic Wall tile; including all accessories and works required; all
in accordance with the Specifications
D Type MOS-001 78 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
FLOOR FINISHES
Screeds
A To floors 47 m2
Finish to floors
C Type F-003 39 m2
D To toilet floors 39 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
CEILING FINISHES
Finish to ceilings
A Type C-202 45 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
COLLECTION
Page : 23.3/1
Page : 23.3/2
Page : 23.3/3
Page : 23.3/4
Signages
A Toilet sign 2 nr
Countertop
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
COLLECTION
Page : 23.4/1
SERVICES
SANITARY INSTALLATIONS
38 Mechanical services
A Water Closet 7 nr
C Urinals 2 nr
E Trash bin 7 nr
F Tissue holder 7 nr
G Health Spray 7 nr
H Urinal partition 2 nr
K Mirror 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
DISPOSAL INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Clean out
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
Floor Trap
Valve
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
WATER INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Isolation Valves
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
Lighting Installation
A Lighting points 53 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
Security System
CCTV
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/14
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 23.5/15
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
SERVICES (CONT*D)
COLLECTION
Page : 23.5/1
Page : 23.5/2
Page : 23.5/3
Page : 23.5/4
Page : 23.5/5
Page : 23.5/6
Page : 23.5/7
Page : 23.5/8
Page : 23.5/9
Page : 23.5/10
Page : 23.5/11
Page : 23.5/12
Page : 23.5/13
Page : 23.5/14
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 23 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 23 - FF PUBLIC BATHROOM 2
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 23.2/3
Services 23.5/15
Fit-out Works
BILL 24
FF PUBLIC BATHROOM 3
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
Demolish and off site disposal of existing walls, floor finishes, wall
finishes, ceilings, doors and MEP services as per drawings and
specification
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
COLLECTION
Page : 24.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 24.2/1
Page : 24.2/2
INTERNAL FINISHES
WALL FINISHES
B To receive paint 25 m2
Mosaic Wall tile; including all accessories and works required; all
in accordance with the Specifications
D Type MOS-001 81 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
FLOOR FINISHES
Screeds
A To floors 47 m2
Finish to floors
C Type F-003 40 m2
D To toilet floors 40 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
CEILING FINISHES
Finish to ceilings
A Type C-202 46 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
COLLECTION
Page : 24.3/1
Page : 24.3/2
Page : 24.3/3
Page : 24.3/4
Signage
Door Signs
A Type ST02 3 nr
Countertop
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
COLLECTION
Page : 24.4/1
SERVICES
SANITARY INSTALLATIONS
38 Mechanical services
A Water Closet 7 nr
C Urinals 2 nr
E Trash bin 7 nr
F Tissue holder 7 nr
G Health Spray 7 nr
H Urinal partition 2 nr
K Mirror 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
DISPOSAL INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Clean out
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
Floor Trap
Valve
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
WATER INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Isolation Valves
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
Lighting Installation
A Lighting points 53 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
Security System
CCTV
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 24.5/14
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
SERVICES (CONT*D)
COLLECTION
Page : 24.5/1
Page : 24.5/2
Page : 24.5/3
Page : 24.5/4
Page : 24.5/5
Page : 24.5/6
Page : 24.5/7
Page : 24.5/8
Page : 24.5/9
Page : 24.5/10
Page : 24.5/11
Page : 24.5/12
Page : 24.5/13
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 24 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 24 - FF PUBLIC BATHROOM 3
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 24.2/3
Services 24.5/14
Fit-out Works
BILL 25
FF PUBLIC BATHROOM 4
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
Demolish and off site disposal of existing walls, floor finishes, wall
finishes, ceilings, doors and MEP services as per drawings and
specification
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
COLLECTION
Page : 25.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 25.2/1
Page : 25.2/2
INTERNAL FINISHES
WALL FINISHES
Mosaic Wall tile; including all accessories and works required; all
in accordance with the Specifications
B Type MOS-001 26 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
FLOOR FINISHES
Screeds
A To floors 34 m2
Finish to floors
B Type F-003 34 m2
C To toilet floors 34 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
CEILING FINISHES
Finish to ceilings
A Type C-202 45 m2
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
COLLECTION
Page : 25.3/1
Page : 25.3/2
Page : 25.3/3
Signages
A Toilet sign 1 nr
Countertop
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
COLLECTION
Page : 25.4/1
SERVICES
SANITARY INSTALLATIONS
38 Mechanical services
A Water Closet 4 nr
C Trash bin 4 nr
D Tissue holder 4 nr
E Health Spray 4 nr
G Mirror 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
DISPOSAL INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Clean out
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
Floor Trap
Valve
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
WATER INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Isolation Valves
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
Lighting Installation
A Lighting points 15 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
Security System
CCTV
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 25.5/14
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
SERVICES (CONT*D)
COLLECTION
Page : 25.5/1
Page : 25.5/2
Page : 25.5/3
Page : 25.5/4
Page : 25.5/5
Page : 25.5/6
Page : 25.5/7
Page : 25.5/8
Page : 25.5/9
Page : 25.5/10
Page : 25.5/11
Page : 25.5/12
Page : 25.5/13
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 25 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 25 - FF PUBLIC BATHROOM 4
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 25.2/3
Services 25.5/14
Fit-out Works
BILL 26
FF PUBLIC BATHROOM 5
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
Demolish and off site disposal of existing walls, floor finishes, wall
finishes, ceilings, doors and MEP services as per drawings and
specification
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
COLLECTION
Page : 26.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 26.2/1
Page : 26.2/2
INTERNAL FINISHES
WALL FINISHES
Mosaic Wall tile; including all accessories and works required; all
in accordance with the Specifications
B Type MOS-001 26 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
FLOOR FINISHES
Screeds
A To floors 35 m2
Finish to floors
B Type F-003 35 m2
C To toilet floors 35 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
CEILING FINISHES
Finish to ceilings
A Type C-202 50 m2
Suspended Ceilings
C 250mm high 20 m
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
COLLECTION
Page : 26.3/1
Page : 26.3/2
Page : 26.3/3
Signages
A Toilet sign 1 nr
Countertop
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
COLLECTION
Page : 26.4/1
SERVICES
SANITARY INSTALLATIONS
38 Mechanical services
A Water Closet 4 nr
C Trash bin 4 nr
D Tissue holder 4 nr
E Health Spray 4 nr
G Mirror 1 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
DISPOSAL INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Clean out
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
Floor Trap
Valve
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
WATER INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Isolation Valves
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
Lighting Installation
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
Security System
CCTV
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 26.5/14
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
SERVICES (CONT*D)
COLLECTION
Page : 26.5/1
Page : 26.5/2
Page : 26.5/3
Page : 26.5/4
Page : 26.5/5
Page : 26.5/6
Page : 26.5/7
Page : 26.5/8
Page : 26.5/9
Page : 26.5/10
Page : 26.5/11
Page : 26.5/12
Page : 26.5/13
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 26 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 26 - FF PUBLIC BATHROOM 5
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 26.2/3
Services 26.5/14
Fit-out Works
BILL 27
FF PUBLIC BATHROOM 6
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
Demolish and off site disposal of existing walls, floor finishes, wall
finishes, ceilings, doors and MEP services as per drawings and
specification
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
COLLECTION
Page : 27.1/1
SUPERSTRUCTURE
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SUPERSTRUCTURE (CONT*D)
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 27.2/1
Page : 27.2/2
INTERNAL FINISHES
WALL FINISHES
Mosaic Wall tile; including all accessories and works required; all
in accordance with the Specifications
C Type MOS-001 48 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
FLOOR FINISHES
Screeds
A To floors 66 m2
Finish to floors
C Type F-003 46 m2
D To toilet floors 46 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
CEILING FINISHES
Finish to ceilings
A Type C-202 62 m2
Suspended Ceilings
C 250mm high 30 m
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
COLLECTION
Page : 27.3/1
Page : 27.3/2
Page : 27.3/3
Page : 27.3/4
Signages
A Toilet sign 2 nr
Countertop
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
COLLECTION
Page : 27.4/1
SERVICES
SANITARY INSTALLATIONS
38 Mechanical services
A Water Closet 7 nr
C Urinals 2 nr
E Trash bin 7 nr
F Tissue holder 7 nr
G Health Spray 7 nr
H Urinal partition 2 nr
K Mirror 2 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
DISPOSAL INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Clean out
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
Floor Trap
Valve
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
WATER INSTALLATION
38 Mechanical services
Pipework
Pipe ancillaries
Isolation Valves
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
Lighting Installation
A Lighting points 53 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
Security System
CCTV
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/13
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 27.5/14
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
SERVICES (CONT*D)
COLLECTION
Page : 27.5/1
Page : 27.5/2
Page : 27.5/3
Page : 27.5/4
Page : 27.5/5
Page : 27.5/6
Page : 27.5/7
Page : 27.5/8
Page : 27.5/9
Page : 27.5/10
Page : 27.5/11
Page : 27.5/12
Page : 27.5/13
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 27 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 27 - FF PUBLIC BATHROOM 6
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 27.2/3
Services 27.5/14
Fit-out Works
BILL 28
FF THEATER LOBBY
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
COLLECTION
Page : 28.1/1
SUPERSTRUCTURE
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 28.2/1
INTERNAL FINISHES
WALL FINISHES
B Type W206 41 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
FLOOR FINISHES
Screeds
A To floors 395 m2
Finish to floors
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
CEILING FINISHES
Finish to ceilings
C Type J-900 41 m
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
COLLECTION
Page : 28.3/1
Page : 28.3/2
Page : 28.3/3
Page : 28.3/4
Signage
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
COLLECTION
Page : 28.4/1
SERVICES
SPACE HEATING AND AIR CONDITIONING
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
Lighting Installation
Final circuits
A Lighting points 44 nr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 28.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
SERVICES (CONT*D)
COLLECTION
Page : 28.5/1
Page : 28.5/2
Page : 28.5/3
Page : 28.5/4
Page : 28.5/5
Page : 28.5/6
Page : 28.5/7
Page : 28.5/8
Page : 28.5/9
Page : 28.5/10
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 28 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 28 - FF THEATER LOBBY
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 28.2/2
Services 28.5/11
Fit-out Works
BILL 29
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
COLLECTION
Page : 29.1/1
SUPERSTRUCTURE
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 29.2/1
INTERNAL FINISHES
WALL FINISHES
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
FLOOR FINISHES
Screeds
A To floors 810 m2
Finish to floors
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
CEILING FINISHES
Finish to ceilings
C Type J-900 78 m
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
COLLECTION
Page : 29.3/1
Page : 29.3/2
Page : 29.3/3
Page : 29.3/4
Signage
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
COLLECTION
Page : 29.4/1
SERVICES
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
Lighting Installation
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 29.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
SERVICES (CONT*D)
COLLECTION
Page : 29.5/1
Page : 29.5/2
Page : 29.5/3
Page : 29.5/4
Page : 29.5/5
Page : 29.5/6
Page : 29.5/7
Page : 29.5/8
Page : 29.5/9
Page : 29.5/10
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 29 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 29 - FF GREATER TUNB HALL
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 29.2/2
Services 29.5/11
Fit-out Works
BILL 30
FF AL HISN FOYER
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
COLLECTION
Page : 30.1/1
SUPERSTRUCTURE
INTERNAL DOORS
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SUPERSTRUCTURE (CONT*D)
COLLECTION
Page : 30.2/1
INTERNAL FINISHES
WALL FINISHES
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
FLOOR FINISHES
Screeds
A To floors 80 m2
Finish to floors
B Type F-101B 80 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.3/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
CEILING FINISHES
Finish to ceilings
A Type C-205 52 m2
B Type C-202 20 m2
C Type J-900 10 m
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.3/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.3/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
COLLECTION
Page : 30.3/1
Page : 30.3/2
Page : 30.3/3
Page : 30.3/4
Signage
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
COLLECTION
Page : 30.4/1
SERVICES
SPACE HEATING AND AIR CONDITIONING
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
Lighting Installation
Final circuits
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
Emergency Lighting
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 30.5/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
SERVICES (CONT*D)
COLLECTION
Page : 30.5/1
Page : 30.5/2
Page : 30.5/3
Page : 30.5/4
Page : 30.5/5
Page : 30.5/6
Page : 30.5/7
Page : 30.5/8
Page : 30.5/9
Page : 30.5/10
Page : 30.5/11
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 30 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 30 - FF AL HISN FOYER
COLLECTION
Page : D/Add/1
BILL SUMMARY
Superstructure 30.2/2
Services 30.5/12
Fit-out Works
BILL 31
FACILITATING WORKS
DEMOLITION WORKS
3 Demolitions
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
COLLECTION
Page : 31.1/1
INTERNAL FINISHES
WALL FINISHES
A Type W203 95 m2
B Type W206 55 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.2/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
FLOOR FINISHES
Screeds
A To floors 262 m2
Finish to floors
Porcelain Floor tile; Matt finish, colour : sand, size : 120x240, laid
on cement and sand screed (measured separately) including
preparation and all works required; all in accordance with the
Specifications
C Type F-103 79 m2
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.2/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
CEILING FINISHES
Finish to ceilings
Suspended Ceilings
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.2/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
COLLECTION
Page : 31.2/1
Page : 31.2/2
Page : 31.2/3
Signage
Artwork
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.3/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
COLLECTION
Page : 31.3/1
SERVICES
SPACE HEATING AND AIR CONDITIONING
38 Mechanical services
Ductwork
Duct ancillaries
D VAVs 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
ELECTRICAL INSTALLATION
39 Electrical services
Final circuits
Socket outlets
Socket outlets
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
Lighting Installation
Final circuits
Emergency Lighting
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
Emergency Lighting
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
38 Mechanical services
Sprinkler Installations
Pipework
Pipe ancillaries
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
39 Electrical services
Final circuits
B Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
D Flasher 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
A Ceiling void Intelligent optical Smoke Detector with LED remote 1 Item
Indicator
C Flasher 1 Item
IT System
Final circuits
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
Security System
CCTV
Final circuits
Access Control
Final circuits
C Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
A Door with card reader, Electric lock, BGU and exit Push button 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
B Allow for integrating the new MEP services to the existing services 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 31.4/12
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
SERVICES (CONT*D)
COLLECTION
Page : 31.4/1
Page : 31.4/2
Page : 31.4/3
Page : 31.4/4
Page : 31.4/5
Page : 31.4/6
Page : 31.4/7
Page : 31.4/8
Page : 31.4/9
Page : 31.4/10
Page : 31.4/11
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 31 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 31 - FF BANQUET STORE AND EXECUTIVE CAFE
COLLECTION
Page : D/Add/1
BILL SUMMARY
Services 31.4/12
Fit-out Works
BILL 32
SERVICES
SPACE HEATING AND AIR CONDITIONING
38 Mechanical services
B Allow for supply and installation of new AHU units including supply 14 nr
air fan, return air fan, coils, eliminators, panel / bag filters,
manometers, duct connections, motorized dampers / actuators,
mixing boxes, floor mounted all in accordance with the drawings
and specification
E Allow for replacement of kitchen extract fans with ecology units 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 32 32.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 32 - MODIFICATION OF MEP PLANT & EQUIPMENT
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 32 32.1/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 32 - MODIFICATION OF MEP PLANT & EQUIPMENT
SERVICES (CONT*D)
38 Mechanical services
B Allow for provision of workstation for the existing fire alarm system 1 Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 32 32.1/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 32 - MODIFICATION OF MEP PLANT & EQUIPMENT
SERVICES (CONT*D)
COLLECTION
Page : 32.1/1
Page : 32.1/2
Page : 32.1/3
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 32 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 32 - MODIFICATION OF MEP PLANT & EQUIPMENT
COLLECTION
Page : D/Add/1
BILL SUMMARY
Services 32.1/4
Fit-out Works
BILL 33
SERVICES
ELECTRICAL INSTALLATIONS
39 Electrical services
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 33 33.1/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 33 - PROVISION OF POWER AND DATA TO RETAIL SHOP
SERVICES (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 33 33.1/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 33 - PROVISION OF POWER AND DATA TO RETAIL SHOP
SERVICES (CONT*D)
COLLECTION
Page : 33.1/1
Page : 33.1/2
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 33 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 33 - PROVISION OF POWER AND DATA TO RETAIL SHOP
COLLECTION
Page : D/Add/1
BILL SUMMARY
Services 33.1/3
Fit-out Works
BILL 34
DAYWORKS
DAYWORKS
GENERAL NOTES
The Contractor will be paid for Dayworks carried out during the
course of the Works, while other operations are in progress, at the
rates set out in this Schedule. Profit and Overheads are not to be
included in the actual rates but stated as a percentage addition at
the Item provided for same at the end of the Labour, Materials and
Plant sections of the Dayworks Schedule.
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
The Daywork rates quoted for Labour are to be the inclusive net
amounts payable, including wages, bonuses and all allowances
paid to operatives directly engaged on dayworks (including those
operating mechanical plant and equipment).
The Daywork rates shall include for use of hand tools and
consumables, ordinary non-mechanical plant, staging, scaffolding,
tarpaulin, use of electric power, light and water for the works, etc.,
and all special inducements for working in Al Ula.
The rates shall also be deemed to include for the extra cost of
public holidays, other holidays with pay, medical costs, bonuses,
sick leave, termination indemnity pay and the like.
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/3
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/4
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
Plant hire rates shall include for the cost of maintaining in proper
working order, repairs, maintenance, insurance, attendance in
starting up and shutting down, fuel, re-fuelling, power, oils, grease,
cleaning materials, replacement and / or sharpening of tools,
provision of tools and all other ancillary items, including
consumables.
Drivers and Attendants shall be charged for, at the rates set out in
the Schedule of Rates for Labour.
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/5
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/6
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
Generally
A Labourer (unskilled) 1 Hr
B Labourer (skilled) 1 Hr
C Steel fixer 1 Hr
D Bar bender 1 Hr
E Welder; uncoded 1 Hr
F Welder; coded 1 Hr
G Transport driver 1 Hr
H Plant operator 1 Hr
J Mason/Brick/Block layer 1 Hr
K Carpenter/Joiner 1 Hr
L Plumber/Pipe Fitter 1 Hr
M Plasterer/Tile Fixer 1 Hr
N Painter 1 Hr
P Fitter/Mechanic 1 Hr
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/7
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
Generally (CONT*D)
A Electrician 1 Hr
B Electrician's Mate 1 Hr
C Cable Jointer 1 Hr
F Ductwork Fabricator 1 Hr
G Ductwork Erector 1 Hr
H Air-conditioning Fitter 1 Hr
Percentage Addition
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/8
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
Percentage Addition
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/9
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
A Concrete mixer, 7 / 5 1 Hr
E Concrete vibrator 1 Hr
H Welding Machine 1 Hr
J Drilling Machine 1 Hr
K Concrete pump 1 Hr
L Air compressor (250 cubic feet) any type of drive including power, 1 Hr
fuel, water, all consumable stores, spares, hoses and tools
M Air compressor (180 cubic feet) any type of drive including power, 1 Hr
fuel, water, all consumable stores, spares, hoses and tools
N Concrete mixer, closed drum with hopper any type of drive fuel 1 Hr
and consumable stores and spares capacity 10/7
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/10
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
Percentage Addition
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/11
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
DAYWORKS (CONT*D)
COLLECTION
Page : DW/1
Page : DW/2
Page : DW/3
Page : DW/4
Page : DW/5
Page : DW/6
Page : DW/7
Page : DW/8
Page : DW/9
Page : DW/10
ADDITIONAL ITEMS
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 34 DW/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 34 - DAYWORKS
COLLECTION
Page : DW/Add/1
BILL 34 - DAYWORKS
BILL SUMMARY
DAYWORKS DW/11
Fit-out Works
BILL 35
PROVISIONAL SUMS
PROVISIONAL SUMS
Provisional Sum
A TBC item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 35 PS/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 35 - PROVISIONAL SUMS
COLLECTION
Page : PS/1
ADDITIONAL ITEMS
Any items that may not be covered elsewhere in the Bills of
Quantities which the tenderer deemed to be necessary in order to
carry out the works in full compliance with the Drawings,
Specifications and any other items necessary to form a complete
Installations, must be itemised and priced below. The tenderer
may provide additional sheets for this purpose if necessary. All
items under this section must be summarised under a separate
cover.
A Item
B Item
C Item
To Collection AED 0
Issued on: 15/11/2022
CLIENT The Armed Forces Officers Club and Hotel
PROJECT Erth Guest Experience
PACKAGE Fit-out Works BILL 35 D/Add/2
BILL OF QUANTITIES - 50% DETAILED DESIGN
BILL 35 - PROVISIONAL SUMS
COLLECTION
Page : D/Add/1
BILL SUMMARY
GENERAL SUMMARY
GENERAL SUMMARY
GENERAL SUMMARY
Appendix H
Site Restrictions
Page 28 of 28
AFOCH
– Erth
Hotel
Outline Site Restrictions
November 2022
General Requirements
• Delivery Access Hours, night shift and to comply to ERTH security department. (Subject to
Contractor’s methodology)
• Removal of waste during nnight shift and to comply to ERTH security department. (Subject to
Contractor’s methodology)
General Requirements
Work permits, As per UAE safety code and EHS requirements such as but not limited
to method statement, risk assessment, required certificates for staff.
Further Contractor Requirements ▪ Client will support where possible to provide sufficient power and water to
undertake the works. (The Contractor is to verify their power requirements)
▪ All the Contractor’s work areas need to be protected and managed from any guests
entering the space, by use of hoarding. Hoarding to be standard and will require ▪ The Contractor will ensure that the site is managed properly & kept in a clean
gypsum boarding and graphics. Design to come from marketing/branding Erth manner at all times.
Management. ▪ The Contractor will be responsible to provide wild air to their working zones /
areas. Sufficient ventilated area.
▪ The Contractor will need to provide Health, Safety & Environment (HSE) plans to
the Erth, to be signed off, inclusive but not limited to: Lay-down area / Offices
• First Aid ▪ The Contractor will be provided a designated laying down area (offsite).
• Toolbox talks ▪ Lay down are within the site will need to be established throughout, will change
• General site welfare
• Lockout procedures ▪ The Contractor will be provided a site office space. Operational offices will be at the
• Working at heights expense of the contractor.
• Working in confined spaces
• Inductions, etc. ▪ The Contractor is to provide security at site for its materials laydown area.
▪ The Contractor is to fully comply with Abu Dhabi code of Construction Safety ▪ Roads to be kept open at all times by the Contractor.
Practice.
▪ The Contractor will be able to utilise the bathrooms provided by Erth hotel.
Material delivery / labour access and egress
▪ The Contractor will deliver materials through a designated route provided by Erth
management.