DHA-PPC-1 DHA-PPC-1

4" thick brick bellast & 3" thick PCC 1:4:8 including compaction
specfifcations and site leveling dressing, removal of debris complete in all
respects
Cost Breakup

SR Dry
items area volume qty unit rate Amount
No mortar
brick bellast(half
1 1779 750 CFT 97
quantity) 72750
2 cement 1779 524.7 808.038 52 Bags 1150 59800
3 sand 1779 524.7 808.038 249 CFT 18000/250 18000
4 crush 1779 524.7 808.038 497 CFT 162 80514

total material cost 231064

brick bellast cating @


1 17790
10/sft
2 Labor cost @ 37/sft 65823
3 compaction @9/sft 16011

Total cost 330,688

15% overheads and


profit & wastage of 49603.2
material)

Net Payable Amount 380,291