Comparison of components with design,

A. Completeness To ensure that the HVAC-


Compliance with technical rules, Cleanliness,
checks (step 2 of the system has been delivered in
Storage on site, Documents necessary for
guidelines) accordance with the design
assembling and operating

1 To ensure that the


B. Installation checks Self-instruction and self-inspection with the use
components are mounted
(step 6 and 7 of the of INSITER tools, Accessibility, Positioning,
according to the
guidelines) Protection, Air- and water tightness
manufacturer's instructions

1
C. Functional checks Verifying the operation of Component settings, Balancing the system,
(partly step 7 and part components and the HVAC Operation of components and system, Putting
of commissioning) system the system into use

D.1 Functional Verifying on a statistical Determine which measurements and recordings


measurements (partly basis that the system are necessary, Extent of functional
step 7 and part of achieves the values measurements, Measurements, Comparing
commissioning) according to the design results with the design

L
D.2 Special In case of doubts concerning Determine which measurements and recordings
measurements the quality of parts of the are necessary, Determine uncertainty of the
(if necessary) system measurements, Measurements

Final check (report)