LABOR WORK

ITEM QTY UNIT TOTAL COST


DESCRIPTION
COST / DAY UNIT / HOUR NO.OF DAYS NO. OF WORKER LABOR
1.0 EARTHWORKS
1.1 Excavation 96.59 cu.m. 400 0.13 cu.m./hr 39 Days 3 Workmen 46,800

1.2 Grading and Compaction 245.04 sq.m. 400 2.09 sq.m./hr 2 Days 2 Workmen 1,600

1.3 Gravel bedding Compaction 32.90 cu.m. 400 9.46 cu.m./hr 3 Days 3 Workmen 3,600

1.4 Backfilling and Compaction 83.52 cu.m. 400 1.22 cu.m./hr 1 Day 1 Workmen #1 400

1.5 Soil Poisoning 150 sq.m.

2.0 STRUCTURAL WORKS


2.1 Stripping for footing Plywood(4'x8'x1/2'') 500 1.00 hr / pc

2.2 Stripping for column Plywood(4'x8'x1/2) 500 0.85 hr / m2

3.0 CUTTING OF REBAR


3.1 Rebar for footing @1.1m length 400 270 pcs./day

3.2 Rebar for anilyo @ 0.6m & 0.7m length 400 270 pcs./day

3.3 Rebar for column @ 2.8m length 400 270 pcs./day

3.4 Rebar for wall footing @ 6m length 400 270 pcs./day

3.5 Rebar for CHB wall @ 6m length 400 270 pcs./day

3.6 Rebar bending for lateral ties 400 360 pcs./day

4.0 MASONRY WORKS


4.1 CHB 6" for wall @ 0.2m x 0.4m x 0.15m 400 7.0 m2/day

4.2 Tooling (1:4) 213 pcs. bag of cement 400 14 m2/day

4.3 Pouring of column (1:2:3:0.5)=5.4cu.m. 400 0.50cu.m./day

4.4 Pouring of footing (1:2:3:0.5)=9.6cu.m. 400 0.50cu.m./day

4.5 Pouring of WF (1:2:3:0.5)=10.24cu.m. 400 0.50cu.m./day

5.0 TOTAL ESTIMATION

You might also like