Professional Documents
Culture Documents
Lecture 3 - Time Management - Scheduling PDF
Lecture 3 - Time Management - Scheduling PDF
Management
Scheduling
Lecture 4
Project Scheduling
A C E
3 4 5
D
6
Dr. Ahmad Abbas El-Banna
Critical Path Method (CPM)
• Early Dates:
• ES = Largest EF of preceding activities
• EF = ES + Duration
Predecessor Successor
1 1
Activity
Predecessor Successor
2 1
3 3 6
Project
B Duration
3
6
0 3 3 3 7 9 14
A C 7 E
3 4 9 5
3 9 ES EF
D
3 Name
6 D
Dr. Ahmad Abbas El-Banna
Forward Pass
ES = Early Start
EF = Early Finish
D = Duration of activity
Late Dates:
LF = smallest LS of succeeding activities
LS = LF – Duration
Backward Pass
(-), The Smallest
3 2 1
9 Project
B Duration
6 3 9
6
14
A 5
C 9
E
0 3 3 5 4 9 9 5 14
3
ES EF
D 9 Name
3 6 9 LS D LF
Backward Pass
LS = Late Start
LF = Late Finish
LS = LF – D.
3 6
Project
B Duration
6 3 9
0 3 3 7 9 14
A C E
0 3 3 5 4 9 9 5 14
3 9
ES EF
D
Name
3 6 9 LS D LF
Dr. Ahmad Abbas El-Banna
Total Float
ES LS=LF-d LF
Activity is late d
3 3 3 6
Project
B Duration
6 3 9
0 0 0 3 3 2 2 7 9 0 0 14
A C E
0 3 3 5 4 9 9 5 14
3 0 0 9
ES TF FF EF
Critical D
Activity Name
3 6 9 LS D LF
Dr. Ahmad Abbas El-Banna
Identifying Critical Activities
+
0 3 17 19
14 Lag
Pour Concrete Remove Form
11 3 14 28 2 30
–
+
0 21 -10 11 46
Excavation Lay Pipe Lead
14 21 35 25 35 60
–
Dr. Ahmad Abbas El-Banna
Lags & Leads (SS-relation)
0 3 0 5
Bore Pile Inject Bentonite Zero Lag
5 3 8 5 5 10
12
+
0 21 12 47
Excavation Lay Pipe Lag
13 21 34 25 35 60
–
Lead not recommended for use
Dr. Ahmad Abbas El-Banna
Lags & Leads (FF-relation)
0 3 1 3
Install Cable Tension Cable Zero Lag
7 3 10 8 2 10
+ 15
0 15 10 30
Form work Steel Rebar Lag
30 15 45 40 20 60
–
Lead not recommended for use
Dr. Ahmad Abbas El-Banna
Multiple Activity Relation
0 5 0 10 5
Excavation
5 17
5 10 15 3 15
5 15
7 5 17 5 5 0 17
Pipe Laying
8
10 12 22 9 24
11 23 10 25
10 22 10 5 0 25
4 Backfill
15 15 30
3 3 3 6
B
6 3 9
0 0 0 3 3 2 2 7 9 0 0 14
A C E
0 3 3 5 4 9 9 5 14
3 0 0 9
ES TF FF EF
D
Name
3 6 9 LS D LF
Early Bar Chart
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 days
A
TF = 3
B
TF = 2
C
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 days
TF = 0
B
TF = 0
C
D J
6 7
B
3 E
5 7
H
2 2 10
A F K
2 4 1 1
I
8
C G
6 5
Example 1 Solution
9 4 0 15 15 7 7 22
D J
13 6 19 22 7 29
4 0 0 9 12 0 0 19
B 3 E
4 5 9 12 7 19 19 0 0 29
H
2 2 19 10 29
0 0 0 2 9 4 4 13 29 0 0 30
A F K
0 2 2 13 4 17 29 1 30
1
19 1 1 27
I
2 5 0 8 8 7 6 13 20 8 28
C G
7 6 13 15 5 20
ES TF FF EF
Activity (i)
LS Duration LF
Critical Path: A-B-E-H-K
Example 2
3
C H
4 9
A -1 8
10
I
2 D E 12
28 14
Start
0
B F G
12 10 20
0 0 0 12 12 2 2 22 24 0 0 44
B F G
0 12 12 14 10 24 24 20 44
ES TF FF EF
Activity (i)
Critical Path 1: A-C-D-E-I
LS Duration LF Critical Path 2: B-D-E-G-I
Example 3
For the given precedence diagram, complete the forward and
backward pass calculations. Assume the project starts at T=0, and no
splitting on activities is allowed. Also assume that the project latest
allowable completion time (project duration) is scheduled for 30
working days.
D F
Test & debug SF 12 Decument
program program
FS 0 (D=6) (D=12)
A B
Develop SS 3 Write comp.
system spec. FF 4 program
(D=8) (D=12)
SS 6 C E
Collect FS 0 Run
system data program
(D=4) (D=6)
Example 3 Solution
TF= 3 TF= 3
FF = 0 FF = 0
TF= 3
15 21 15 27
TF= 3 SF 12 TF= 3
FF = 0 D F
FF = 0 FF = 0
FS 0
0 8 3 15 1 6 24 18 12 30 27 27
A SS 3 B 8 END
FF 4
3 8 11 6 12 18 9 13 21 27 30 0 30
SS 6 C E
FS 0
14 4 18 24 6 30
TF= 5 TF= 3
FF = 2 FF = 0
TF=
FF =
ES EF
Activity (i)
LS Duration LF
Example 3 Solution
Computing Slack Time (Float Time)
Activity ES EF LS LF TF Critical
A 0 8 3 11 3 Yes
B 3 15 6 18 3 Yes
C 9 13 14 18 5 No
D 15 21 15 21 3 Yes
E 21 27 24 30 3 Yes
F 15 27 18 30 3 Yes
❑ Critical path is the path with the least total float = The longest
path through the network.
42
Example (4)
43